Complaint Affidavit Graft Case Vs Senate President Drilon Et Al Over Anomalous Esplanade II Project in Iloilo City.
Complaint Affidavit Graft Case Vs Senate President Drilon Et Al Over Anomalous Esplanade II Project in Iloilo City.
Complaint Affidavit Graft Case Vs Senate President Drilon Et Al Over Anomalous Esplanade II Project in Iloilo City.
crTY oF
X----
rl-o[o
) s.s.
-------X
COMPLAINT-AFF'IDAVIT
I, MANUEL P. MEJORADA, Filipino, of legal age, married, and
in accordance with law, do hereby depose and state:
a resident
ofNo. 2
Kasoy St., Block 11, Villa San Lorenzo Subd., Lapaz,5000 Iloilo City, after being sworn
1.
a. b.
City; and
(BAC),
CR
2.
The afore-named public offrcials, conspiring and confederating with each ottrer,
with intent to defraud'the government, violated Republic ActNo. 9184 (or the
Govemment Procurement Reform Act), Republic Act No. 3019 (or the Anti-Graft
and Comrpt Practices Act, particularly'Section 3, paragraphs [e] and tg]) and other
"Construction qf Slope Protection Works Alone Iloilo River Sta. 5 + 700-IR to Sta.
6 + 420k-IR (Right Bank)" in
3.
The same public officials also committed dishonesty, grave misconduct, malversation of public funds and other such offenses as may be determined by this Honorable Offrce based on the facts and circumstances drawn from evidence.
BACKGROUf{p
4.
The project was advertised in an Invitation to Bid (ITB) on the website of the
A copy (print out from PhiIGEPS archives) of the Bid Notice Abstract for the
to Bid was
P33,950,000. The scope of work was for the'oconstruction of 720 (meters) long
slope protection work (earth dike with concrete blocks on side slopes) including 3m
wide asphalt pavement on 4.0m dike road". The contract duration was for 240
calendar days. The public bidding was:scheduled on June 26, 2012.
6.
The Department of Public Works and Highways (DPWH) Region VI, represented by respondent EDILBERTO TAYAO as Regional Director, is the procuring entity
Notice Abstract
a"
P33,908,791"50;
b.
t2G00026;
c.
d.
8.
Notice to proceed was issued on Jahuary 2,2CI13 with the contract end date on August 11,2013.
The said "Award Notice Abstract" was published on May 16, 2013. Under the heading "Date Created", the date indioated is 16-May-201'3'
The project is better known in Iloilo City as "ESPLANADE II", a pet undertaking
ACCELERATION PROGRAM (DAP) of the Aquino administration upon the initiative of respondent DRILON. While the project proponent is DPWH, for all
intents and purposes, this is a project of respondent DRILON. He is the architect this project and beneficiary from pecuniary gains derived from the anomalous implementation of the same.
of
THE CONTRACT VIOLATES REPUBLIC ACT NO.9184 AI[D ITS REVISED IMPLEMENTING RULES AND REGULATIONS (RIRR).
9.
The project was not included in the Annual Procurement Plan (APP) of the procuring entrty which violates Section 7.2 of the zuRR which mandates that "No procurement shall be undertaken unless it is in accordance with the approved APP
in
No' 9184 the App of a procuring entity. Section 7.1 of the RIRR of Republic Act
considered crucial to the efficient discharge of governmental functions shall be included in the APP."
a. There is nothing about the project that would make it o'crucial" to the
delivery of govemment services as it is an opulent, wasteful, extravagant
'obeautification" project that makes no contribution to tourism or improved
public service.
11. The Invitation to
a newspaper
of
(Annex o'B"), the respondent Bids and Awards Committee also violated the
a.
t\
Section 37.t.6 which provides: "The BAC, through the Secretariat,, shall
post, within three (3) calendar days from its issuance, the Notice of Award
in the PhilGEPS, the website of the procuring entity, if any, and any
conspicuous place of the procuring entity."
RS
d.
b.
Section 37.4.2 which mandates that "The procuring entity, through the
e-{
BAC Secretariat, shall post a copy of the Notice to Proceed and the
approved contract in the PhilGEPS or the website of the procuring entity, any, within fifteen (15) calendar days &om the issuance of the Notice to Proceed."
if
c.
Section 38.1 which provides that "The procurement process from the opening of bids up to the award of contract shall not exceed three (3) months, or a shorter period to be determined by the procuring entity concerned."
December
27
, 2012. The Notice to Proceed was issued on January 2, 20L3 . But the
contract had started to be implemented. In fact, it was past midway of the contract duration.
14. The opening of bids for the contract was held on June 26,2012. The Notice to
Proceed was issued on January 2,2013. The entire procurement process took more
than SIX (6) months, contrary to what is provided under Section 38.1 of the zuRR
ofRA
9184.
actions betray complete disregard and disrespect for the fundamental principles for
which RA 9184 was enacted, particularly TRANSPARENCY and COMPETITIVENESS in the procurem.ent of contracts.
17. Such actions were taken because of pressure from respondent DRILON who was
THE CONTRACT IS GROSSLY DISADVANITAGEOUS TO THE GOYERNMENT AND WAS AWARDED TO A *FAVORED" CONTRACTOR OF RESPONDENT SENATE PRESIDENT FRANKIN M. DRILON, CAUSING T]NDUE INJT]RY TO THE GOVERNMENT Ah[D TAXPAYERS.
18. The contract was awarded to ROPRIM CONSTRUCTION which submiued a
bid
(:<<
of P33,908,79t.50.
A
\
o,i
a. b.
The winning bid is only P41,208.50 below the approved budget for the contract of
P3
3,950,000.00.
Even on its face, the award of this contract already smacks of a rigged
i.
of work involves largely back-filling with earth materials for a length of 720|inear
meters and a 4-meter wide dike with concrete blocks on the embarkment, with a 3meter wide asphalted surface over it.
a.
About 70% of the contract involves back-filling using earth materials for
the "slope protection works".
i. ii.
iii.
iv.
evaluation by this Honorable Office with assistance from independent engineers, the component for back-filling is overpriced
by at least P15,000,000!
b"
For the installation of concrete trlocks and the provision for an asphalt pavement (3 meters wide), it is estimated that these components would only
cost P4-5 million, and there is an overprice of about P5,000,000 on the
same.
PESOS
a.
This contractor is the same entity that was awarded the contracts for the
=s
7<
\
as "Esplanade
i.
Esplanade
Molo. It
a.
Three years ago, Senate President Drilon ordered the Land Management
Bureau of the DENR to conduct a technical survey along the Iloilo River to determine its old boundaries and find out whether private individuals or
business establishments have etcroached into its waterways.
b.
Iloilo River.
c.
of
in the
Mayor Jed Pahick E. Mabilog, whose house and lot property sits on the
bank of the Iloilo River along No. 4 Tap-oc St., Molo, Iloilo City, for allegedly back-filling on the waterway and illegally encroaching on the
same
i. ii.
e.
Iloilo
There is a strong likelihood that the Esplanade II project encroaches on the waterway of the Iloilo River in violation of the water code of the Philippines.
G\
\-
f.
i.
ii.
Director Ramos also referred my letter request for city Mayor Jed
Patrick E. Mabilog for the possible supply of a cop of the survey to me as per his letter dated August 7 (Annex ,.D,,).
,2013
I wrote
city Mayor Mabilog on August 22,2013 asking for a copy of the same. i. A copy of my letter to Mayor Mabilog and the return card are
attached as Annexes o'E" and'oF', respectively.
h. until
Mayor Mabilog.
i.
i.
ii.
Such neglect of responsible public officials in enforcing the law has caused untold suffering of our people and damage to their properties.
In witness thereto, I hereby affix my signature tt tt City, Philippines for Cebu City.
&
EJORADA
Lae-
ryr'
Fab
-1To tzlog