Ismail Hamza-Saudi Grid Code

Download as pdf or txt
Download as pdf or txt
You are on page 1of 35

Saudi Grid Code requirements for IPP, Industries and PV solar plant interconnection to Grid

Presenter: Ismail Hamza

Grid Code
The Grid Code is designed to indicate the procedures for both planning and operational purposes and covers both normal and exceptional circumstances.

The Grid Code has been developed to define the rules and regulations for various Participants for accessing and using the Transmission Grid of the Saudi Electricity Company.
The objective is to establish the obligations of the Transmission Service Provider (TSP) and other Grid UsersGenerators, Distribution Entities, and Directlyconnected Customersfor accessing and using the Grid. Defining of technical, design, and operational criteria for Grid access Planning for Grid development and reinforcement, System operation criteria and standards Scheduling and Dispatch of supply and demand resources Exchange of data and information, and metering policies and systems to account for the Power and Energy transactions in the Grid.
Saudi Grid Code 2

Grid Code
General Conditions Connection Code Planning Code Operating Code Schedule and Dispatch Code Data and Information Exchange Code Metering Code

Saudi Grid Code

General Conditions
The specific objectives of General Conditions are the following: clarify on the legal and regulatory framework for implementing and enforcing of the Grid Code specify the purpose, functions, and composition of the Grid Code Supervisory Committee (GCSC)

describe the framework for making amendments to the Grid Code and for seeking Derogations from its provisions
define general rules regarding the communication between the TSP and Users and exchange of data and information between them

specify the general rules for interpreting the provisions of the Grid Code.

Saudi Grid Code

General Conditions
The Grid Code applies to the TSP and to all Users of the Grid, which are The Transmission Service Provider (TSP)

Generators
Distribution Entities Directly-connected Customers. The provisions under this Code apply to Users seeking new Connection, or modification of an existing Connection, to the Transmission System.

Saudi Grid Code

General Conditions
Grid Code Implementation and Enforcement The TSP shall be responsible for the Grid Code implementation and enforcement.

For the above purposes, the TSP may need access to the services and facilities of Users or to issue instructions to Users in order to implement and enforce the Grid Code (for example, to isolate or disconnect Plant or Apparatus, etc.).
All Users, therefore, are required not only to abide by the letter and spirit of the Grid Code, but also to provide the TSP with such rights of access, services and facilities.

Saudi Grid Code

Connection code
Connection Code specifies certain principles and establishes a set of minimum technical, design, and operational conditions for the Users for connecting to and using the Transmission System.
The purpose is to protect the TSP facilities as well as the Plant and Apparatus of the Users, and to ensure safe, stable, and secure operation of the System. Objectives To provide a set of fair and non-discriminatory basic rules and standards for accessing and using the Transmission System which must be complied with by all Users To specify the normal Transmission System performance standards at the Connection Point To specify the technical design and operational criteria at the Connection Point

To clearly define the technical function, operational criteria, and ownership of the Equipment connected to the Transmission System in accordance with the relevant Site Responsibility Schedule.
Saudi Grid Code 7

Connection code
Grid Connection Procedure A User seeking a new, or modification of an existing, Connection, to the Grid shall secure a proper Connection Agreement with the TSP by following some procedures, prior to the actual connection to the grid. All Plant and Apparatus at the Connection Point shall comply with the relevant TSP standards, or in their absence, other IEC, ANSI, or IEEE standards, unless modified by any provision in the applicable Connection Agreement.

Saudi Grid Code

Connection code
Frequency Variations
The Transmission System shall have a nominal frequency of 60 Hz and R-Y-B counter-clock-wise phase rotation. The TSP shall maintain it within the limits of 59.9 and 60.1 Hz during normal Grid operation. The System frequency could rise to 62.5 Hz or fall to 57.0 Hz in exceptional circumstances. To enable the TSP to maintain the frequency within the limits The design of Generators Plant and Apparatus must enable operation of that Plant and Apparatus in accordance with the following: Below Normal Frequency (Hz) 58.8 60.0 Above Normal Frequency (Hz) 60.0 60.5 Operation Requirement

Continuous

57.5 58.7

60.6 61.5

For a period of 30 minutes

57.0 57.4

61.6 62.5

For a period of 30 seconds

Saudi Grid Code

Connection code
Voltage Variations
The voltage at any point on the TSP system will normally remain within the nominal values as stated in the table below, unless abnormal conditions prevail. Under exceptional circumstances, the maximum over voltage limits stated below should not be exceeded for more than thirty (30 ) minutes Nominal Normal Range Voltage (kV) 110 kV 115 kV 132 kV 230 kV 380 kV 5% 5% 5% 5% 5% 30-Minute Over Voltage + 10 % + 10 % + 10 % + 10 % + 10 %

Saudi Grid Code

10

Connection code
Harmonic Distortion All Plant and Apparatus connected to the Transmission System shall be capable of withstanding the levels of Harmonic distortion expected to be present on the Transmission System. Plant and Apparatus connected to the Transmission System shall not impose voltage Harmonics on the Transmission System which exceed the limits specified in the relevant Connection Agreement, or when no such limits are specified there, a Total Harmonic Distortion of 1.5% with no individual Harmonic greater than 1%. Plant and Apparatus connected to the Transmission System shall not impose current Harmonics on the Transmission System which exceed the limits specified in the relevant Connection Agreement, or when no such limits are specified there, the limits specified in IEEE Standard 519-1992: Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems

Saudi Grid Code

11

Connection code
Voltage Unbalance The User facility shall not cause the phase-to-phase unbalance of the System, as measured with no load and with balanced three-phase loading, to exceed by more than one (1) % at the Connection Point. Voltage Fluctuation and Flicker Severity The voltage fluctuation at any Connection Point with a fluctuating Demand shall not exceed one (1)% of the nominal voltage level for step changes which may occur repetitively. Any large voltage excursions other than step changes may be allowed up to a level of three (3)% providing that this does not pose a risk to the Transmission System or to the System of any other User. The Flicker Severity at any Connection Point in the Transmission shall not exceed the limits of Pst =0.8 and Plt=0.6, both 95th percentile values measured over a period of one week. Transient Voltage Variations The User Systems shall be designed and operated to include the devices that will mitigate the effects of transient over voltages and transient voltage dips on the Grid and the User System. The User shall take into account the effect of electrical transients when specifying the insulation of their electrical Equipment.
12

Saudi Grid Code

Connection code
Protection Equipment/Schemes
Users shall comply with the following requirements for Fault clearance times (from Fault inception to circuit breaker arc extinction) by primary Protection not exceeding: Network Category 110 kV 115 kV Fault Clearance Times

120 millisecond 120 millisecond

132 kV
230 kV 380 kV

100 millisecond
100 millisecond 80 millisecond

Saudi Grid Code

13

Connection code
System Services The relevant Connection Agreement or Power Supply or Purchase Agreement will contain requirements for the capability for certain System Services from the following list which may be needed for proper System operation:

Voltage Control and Reactive Power Support (when used exclusively for such purpose)
Primary Control of Generating Units Secondary Control of Generating Units Black Start Capability Operating Margin (Operating/Contingency Reserve) Interruptible Load

Saudi Grid Code

14

Planning code
This chapter provides a framework for enabling the TSP and Users to interact with each other in relation to planning and development of the Transmission System. All Users, existing as well as prospective, will be bound by the planning conditions prior to generating, transmitting, distributing, or consuming electricity. Grid Planning Responsibility The TSP shall have the primary and lead responsibility for planning the Grid development.

Grid Planning Process Users, existing as well as prospective, will be able to assess conditions for connecting to, and using of, the Grid. TSP to properly plan for Grid development, Users will be required to submit to the TSP all data that the TSP may require from them for this purpose. Any User proposing to close, retire, withdraw from service, or otherwise cease to maintain and keep available for Dispatch any generator greater than ten (10) MW in aggregate shall give the TSP at least twenty-four (24) calendar months notice of such action.
Saudi Grid Code 15

Planning code
Submission of Grid Planning Data For the TSP to undertake planning and development of the Grid, the TSP will require the Users to provide data and information before Connection, and also afterwards at regular intervals. Grid Planning Studies The Grid planning studies may include studies (as the situation or case may demand) such as load flow studies, short-circuit studies, transient Stability studies, steady state Stability studies, voltage Stability studies, electromagnetic transient studies, and Reliability studies, etc. Standard Planning Data Historical Energy and Demand Energy and Demand Forecast Generating Unit/Station Data User System Data
Saudi Grid Code 16

Detailed Planning Data Generating Unit/Station Data User System Data

Operating code
Operating code covers: 1) Operational Demand Forecasts

2) Outage Planning
3) System Services 4) Operational Liaison 5) Operational Communication 6) Contingency Planning 7) Operational Testing 8) Testing to Monitor, Investigate, and Verify Performance 9) Cross-boundary Safety Assurance

Saudi Grid Code

17

Operational demand forecast


The requirements for Grid Users to provide Demand and Generating Plant output data to the TSP to enable it to plan and maintain sufficient level of Generation Capacity and Operating Margin in the System to meet Demand Specifies conditions, requirements, and procedures that the TSP and Users shall follow to match Generation Capacity with Forecast Demand on the Transmission System The planning, coordination, and approval of scheduled and un scheduled Outages of the Generating Unit and the Transmission System The Generators to inform the TSP of any other proposed maintenance of a Generating Unit or any associated Power Station Plant or Apparatus, which can affect the availability of System Services from that Generating Unit.

Saudi Grid Code

18

Outage Planning
Notified Unplanned Outages A Generator must, if it considers that a Generating Unit will require an Outage which cannot reasonably be deferred to become a Planned Outage or a STPM but of which it has some advance warning, give the TSP as much notice as is reasonably possible. The TSP may request the Generator to advance or defer the Outage. If the Generator agrees to such a request, the Generator shall send the TSP a written notice confirming this agreement. The TSP will acknowledge this notice. The Generator must then (subject to any intervening Outage) take the Outage in accordance with that agreement. Forced Outages In the event that a Generating Unit suffers a Forced Outage, the Generator shall inform the TSP within ten (10) minutes of the commencement of the Outage. In such an event, the TSP shall have the right to inspect the Generating Unit and all relevant records on any Business Day and at a reasonable time. The Generator shall fully cooperate with the TSP during any such inspection.

Saudi Grid Code

19

System Services
These are essential to the proper functioning of the Transmission System, and which also determine the Quality of supply.

This section specifically deals with the following System Services: Frequency Control
Voltage Control System Control Operating Margin Black Start

Saudi Grid Code

20

Operation Liaison
Procedure for Notification of Operations, Events, and Significant Incidents Timing and Form of Notification Significant Incidents Amber Alert Significant Incident Reporting Procedure

Saudi Grid Code

21

Operational Communication between the TSP and Users


Contact Locations and their Adequacy Timing and Form of Notification

Communication Systems and Equipment


Conditions of Monitoring and Recording Equipment SCADA Systems

Saudi Grid Code

22

Contingency Planning
Terms and Conditions Demand Control System Restoration Restoration Plan

Saudi Grid Code

23

Contingency Planning
Demand Control Amber Alert May be issued when a single Event would give rise to a reasonable possibility of failure to meet the Power System Demand, or of frequency or voltage departing significantly from normal, or if multiple Events are probable due to prevailing weather conditions. Red Alert May be issued when the Contingency Reserve is zero, a Generation deficiency exists, or there is a Critical Loading or imminent overloading of the Transmission lines or Equipment. Red Alert may be issued by 15:00 hours, a day ahead. The Red Alert Warning shall specify the amount and the period during which the Demand reduction will be required due to anticipated frequency or voltage deviation significantly from normal. Blue Alert May be issued when either a Partial or a Total Shutdown of the Power System has taken place.

Saudi Grid Code

24

Operational Testing
Operational Test Request Establishing of the Test Group Operational Test Program Operational Test Report

Saudi Grid Code

25

Testing to Monitor, Investigate, and Verify Performance


Monitoring

Investigation
Testing to verify Performance Generating Unit Capability Tests

Saudi Grid Code

26

Cross-boundary Safety Assurance


The safety Rules Safety at the connection point Logs of cross boundary safety precautions Forms for Cross-Boundary Safety Precautions Approval of local safety Instructions Safety Representatives Coordination on safety matters

Saudi Grid Code

27

Cross-boundary Safety Assurance


Agreement on Safety Precautions Agreement on Isolation Agreement on Grounding In the event of disagreement Implementation of Isolation and Grounding Authorization of Testing affecting other Safety Representatives System Cancellation of safety Precautions

Saudi Grid Code

28

Scheduling and Dispatch Code


The TSP to Schedule and Dispatch adequate Generation resources to meet electricity Demand at all times at minimum cost while ensuring the integrity of the System, as well as the requisite levels of supply Quality and Reliability. Special Actions The Generation Schedule may be followed by a list of Special Actions (either pre-Fault or post-Fault) that the TSP may request a Generator to take in respect of a procedure to be followed by a Generating Unit For a Generator, such Actions may involve a load change or a change of required Notice to Synchronize, in a specific timescale on individual or groups of Generating Units basis. For Distribution Entities and Directly-connected Customers, these Special Actions may involve load transfers between the TSP Connection Points or arrangements for Demand Control by manual or automatic means. These Special Actions will be discussed and agreed with the concerned Generators, Distribution Entities, or Directly-connected Customers. The actual implementation of these Special Actions will be part of the Dispatch procedure.
Saudi Grid Code 29

Scheduling and Dispatch Code


Issuance of Generation Schedule Negative Minimum Demand Regulation (NMDR) Generation Synchronizing and Desynchronizing Times Dispatch of Active Power Dispatch of Reactive Power

Saudi Grid Code

30

Scheduling and Dispatch Code


Additional Dispatch Instructions In addition to Dispatch Instructions relating to Dispatch of Active Power and Reactive Power, Dispatch Instruction may also include those relating to the following: Reserve: Details of the reserve to be carried by each Generating Unit/ Station including specification of the timescale in which that reserve may be transferable into increased Generating Unit/Station output. System Services: An instruction for a User to provide System Services. Secondary Control Mode: A requirement for change to or from Secondary Control Mode for each Generating Unit. Tests: An instruction to carry out tests as per Operating Code.
System Emergency Conditions In order to maintain Transmission System integrity under System Emergency Conditions, the TSP may issue Dispatch Instructions to Generators to operate outside the limits implied by the then current Declarations. Excitation Control System Mode of Operation Each Generator shall operate its Generating Units with automatic voltage regulator (AVR), var limiters, and Power System Stabilizers (PSS), as required under their respective Connection Agreement, in service at all times unless released from this obligation by the TSP.
Saudi Grid Code 31

Scheduling and Dispatch Code


Power System Stabilizer (PSS)

Type of PSS PSS Structure Speed Input

Saudi Grid Code

32

Data and Information Exchange Code


The proper and timely exchange of data and information between the TSP and Users is critical for ensuring non-discriminatory access to the Transmission System and the safe and reliable provision of Transmission services.
Standard Planning Data: Each User shall provide to the TSP the standard data of the Equipment connected to the Transmission System for planning purposes. Detailed Planning Data: Each User shall provide to the TSP the detailed data for the Equipment connected to the Transmission System for planning purposes. Operational Data: Each User shall provide to the TSP the operational parameters of the Equipment connected to the Transmission System for the safe and reliable operation of the system.

Saudi Grid Code

33

Data and Information Exchange Code


Data and Information to be Registered The following Schedules shall be supplied by Users (Generation, Distribution Entities, and Directly-connected Customers) to the TSP and will cover the required data for each User: Schedule 1: Generating Unit Technical Data This shall comprise Generating Unit/Station fixed parameters. Schedule 2: Generating Unit/Station Outage Data. This shall comprise Generating Unit/Station Equipment Outage Planning Data. Schedule 3: Generation Operation Schedule Data. This shall comprise data required for the preparation of the Generation Schedule. Schedule 4: Generation Operational Planning Data. This shall comprise Generating Unit/Station parameters required for Operational Planning. Schedule 5: User System Data This shall comprise electrical parameters relating to Plant and Apparatus connected to the Transmission System. Schedule 6: Connection Point Data. This shall comprise data related to Demand and Demand transfer capability. Schedule 7: Demand Control Data. This shall comprise data relating to Demand Control. Schedule 8: Scheduling and Dispatch Data. This shall comprise parameters required for Scheduling and Dispatch of Generating Unit/Station.
Saudi Grid Code 34

Data and Information Exchange Code


Schedule 9: Load Characteristics Data. This shall comprise estimated parameters of loads in respect of Harmonic content, sensitivity, etc. Schedule 10: Fault In feed Data. This shall comprise data related to short circuit in feed of User Equipment to the Transmission System. Schedule 11: User Demand Profiles and Active Energy Data. This shall comprise data related to Demand profiles. Schedule 12: Data Supplied by the TSP to all Users. This shall comprise data supplied by the TSP to Users. Applicability of these Schedules to each category od users is indicated in the following table
Schedule Number Users Generators Distribution Entities Directly-Connected Customers

10

11

12

Saudi Grid Code

35

You might also like