Tariff Regulation 2014-19 - ICRA

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

CERCsFver MYT Tariff Regulations for FY2015-19 to remain Negative for Thermal Generation Utilities, Marginally Negative for

Transmission Licensees, & to Benefit the Distribution Utilities February 2014


Summary
CERC has vide its order dated February 21, 2014 approved regulations for cost-plus or normative principle based tariff determination for the next control period commencing in April 2014 up to March 2019 (FY 2015-19). These regulations are applicable for power generating companies owned or controlled by the central government, generating companies supplying power to more than one state under a composite scheme and for inter-state transmission licensees. In ICRAs view, the tariff regulations approved by CERC for next tariff control period (FY 2015-19) are expected to benefit the distribution utilities and consumers by way of lower tariffs. However, they are negative for generation utilities & marginally negative for transmission licensees. Tightening of operational efficiency norms: CERC has tightened the normative operating performance norms by lowering the normative station heat rate, secondary fuel consumption norms and auxiliary consumption for existing as well as upcoming coal/lignite/gas based thermal power projects. This is based on the actual operating performance of the thermal generating stations during FY2009 to FY2013. This could result in a reduction in tariff by about 3-4 paisa/unit based on normative principles in case of energy charges applicable for central sector utilities. Also, CERC has introduced sharing of financial gains/losses due to controllable factors with the beneficiaries on monthly basis which will affect the quantum of such gains available with the generation & transmission companies. However, CERC has lowered the normative plant availability factor for recovery of fixed charges for generating stations to 83% from 85% in earlier regulations, in view of the prevailing uncertainty over supply of domestic coal availability. Linking of incentives to actual PLF: The incentives for a generating station are linked to plant load factor (PLF) in the tariff regulations for 2014-19 as against the provision of linking with plant availability factor (PAF) in the earlier tariff regulations which were applicable for the period of FY 2009-14. The incentive is at the rate of Rs. 0.50 per unit for excess energy delivered beyond the normative annual PLF. This is a negative for generating stations as plants may operate at PLFs lower than the availability because of reasons beyond their control. ICRA estimates that this would result in a tariff reduction for thermal plants by about 6 paisa/unit due to lower incentives. Tax payments on actual basis instead of gross-up at applicable tax rates: CERC has modified the existing provision of the pre-tax RoE being grossed up by the applicable tax rate to pre-tax RoE grossed up with actual effective income tax rate, which would be arrived based on estimated advance tax for the respective financial year and subsequently, trued up at the end of the financial year. This would be negative for entities that have been implementing multiple generation assets on the books and thus, have benefitted from tax arbitrage resulting from the lower actual effective tax rate as compared with the applicable tax rate used for grossing of the allowed return on equity. As per ICRAs estimates, the net impact would be at about 7 -8 paisa/unit which would be equivalent to reduction by 3% RoE, in case of entity where the actual effective tax rate is at 24% while the applicable tax rate is at 33.99% for tariff recovery. Lower fuel stock allowed for normative Working Capital: CERC has reduced the provision towards coal/lignite stock from 45 days for pit head stations and 60 days for non-pit head stations to 15 days and 30 days respectively. This modification has been approved based on the actual annual average fuel stock held by generating stations from FY09 to FY13, which was lower than normative days allowed as per the existing tariff regulations for FY 2009-14. This reduction in the primary fuel stock norms would be negative for the generation entities as it would lead to disallowance of about 2 paisa/unit in tariff recovery which would be equivalent to reduction by 0.7% RoE as per ICRAs estimates.

ICRA RESEARCH SERVICES

Contacts:
Sab ya sa ch i M aju md a r +91 1 2 4 4 5 45 30 4 sab y a sach i @i cra in d ia. co m Gi ri sh k u mar Kad a m +9 1 22 6 17 9 63 41 gir i sh ku ma r @i cra in d i a. c om

Vikram V.
vi kra m . v@ ic ra in d ia .c o m +9 1 4 0 40 67 6 51 8

ICRA LIMITED

CERCs tariff regulations would also have a marginally negative impact on transmission licensees given the reduction in escalation rate along-with the allowed O&M expenses and tightening of operating norms for line availability both for recovery of annual fixed capacity charges and incentives. Overall, the tariff norms approved by CERC for FY 2015-19 remain favorable for distribution utilities and in turn for the consumers. This is because the cost of power purchase for the utilities is likely to go down by about 10 paisa/unit in the case of purchases from project SPV and by about 18 paisa/unit in case of the purchase from generation entities having multiple assets on the books, assuming that the additional savings over and above its allowed RoE at 15.5- 16% are curtailed. While some of the generation stations continue to operate at better efficiency norms than the revised levels, ICRA expects overall reduction in the RoE at about 6-7% on equity for generation utility with multiple assets on the books and which in turn, is expected to provide a relief on retail electricity tariff by about ~0.8% (~4 paise/unit) based on average electricity tariff prevailing in the country and also, the current share of generation by large central sector generating entities to meet the electricity demand.

ICRA LIMITED

TABLE OF CONTENTS
Impact Assessment of CERC Tariff Regulations for the period 01-04-2014 to 31-03-2019 Background Analysis of CERCs Regulations for Determination of Tariff for FY 2015-19 & Comparison of the same with the Existing Tariff Regulations Capital Cost & Filing of Tariff & True-up Petition Impact on tariff determination for Thermal Power Projects Fixed Capacity Charges Energy Charges Illustrative Assessment for impact on Levellised Cost Components of Generation and RoE for coal based project Impact on tariff determination for Hydro Power Projects Energy Charges Fixed Capacity Charges Impact on tariff determination for Transmission Licensee Fixed Capacity Charges

ICRA LIMITED

Please contact ICRA to get a copy of the full report


CORPORATE OFFICE Building No. 8, 2nd Floor, Tower A, DLF Cyber City, Phase II, Gurgaon 122002 Ph: +91-124-4545300, 4545800 Fax; +91-124-4545350 REGISTERED OFFICE th 1105, Kailash Building, 11 Floor, 26, Kasturba Gandhi Marg, New Delhi 110 001 Tel: +91-11-23357940-50 Fax: +91-11-23357014 MUMBAI Mr. L. Shivakumar Mobile: 9821086490 3rd Floor, Electric Mansion, Appasaheb Marathe Marg, Prabhadevi, Mumbai - 400 025 Ph : +91-22-30470000, 24331046/53/62/74/86/87 Fax : +91-22-2433 1390 E-mail: [email protected] GURGAON Mr. Vivek Mathur Mobile: 9871221122 Building No. 8, 2nd Floor, Tower A, DLF Cyber City, Phase II, Gurgaon 122002 Ph: +91-124-4545300, 4545800 Fax; +91-124-4545350 E-mail: [email protected] CHENNAI Mr. Jayanta Chatterjee Mobile: 9845022459 Mr. Leander Rayen Mobile: 9940648006 5th Floor, Karumuttu Centre, 498 Anna Salai, Nandanam, Chennai-600035. Tel: +91-44-45964300, 24340043/9659/8080 Fax: 91-44-24343663 E-mail: [email protected] HYDERABAD Mr. M.S.K. Aditya Mobile: 9963253777 301, CONCOURSE, 3rd Floor, No. 7-1-58, Ameerpet, Hyderabad 500 016. Tel: +91-40-23735061, 23737251 Fax: +91-40- 2373 5152 E-mail: [email protected]

[email protected]
KOLKATA Ms. Vinita Baid Mobile: 9007884229 A-10 & 11, 3rd Floor, FMC Fortuna, 234/ 3A, A.J.C. Bose Road, Kolkata-700020. Tel: +91-33-22876617/ 8839, 22800008, 22831411 Fax: +91-33-2287 0728 E-mail: [email protected] AHMEDABAD Mr. Animesh Bhabhalia Mobile: 9824029432 907 & 908 Sakar -II, Ellisbridge, Ahmedabad- 380006 Tel: +91-79-26585049/2008/5494, Fax:+91-79- 2648 4924 E-mail: [email protected] PUNE Mr. Amit Khare Mobile: 9763200633 5A, 5th Floor, Symphony, S. No. 210, CTS 3202, Range Hills Road, Shivajinagar, Pune-411 020 Tel : +91- 20- 25561194, 25560195/196, Fax : +91- 20- 2553 9231 E-mail: [email protected] BANGALORE Mr. Jayanta Chatterjee Mobile: 9845022459 'The Millenia', Tower B, Unit No. 1004, 10th Floor, Level 2, 12-14, 1 & 2, Murphy Road, Bangalore - 560 008 Tel: +91-80-43326400, Fax: +91-80-43326409 E-mail: [email protected]

ICRA LIMITED

ICRA Limited An Associate of Moody's Investors Service CORPORATE OFFICE Building No. 8, 2 Floor, Tower A; DLF Cyber City, Phase II; Gurgaon 122 002 Tel: +91 124 4545300; Fax: +91 124 4545350 Email: [email protected], Website: www.icra.in
nd

REGISTERED OFFICE th 1105, Kailash Building, 11 Floor; 26 Kasturba Gandhi Marg; New Delhi 110001 Tel: +91 11 23357940-50; Fax: +91 11 23357014 Branches: Mumbai: Tel.: + (91 22) 24331046/53/62/74/86/87, Fax: + (91 22) 2433 1390 Chennai: Tel + (91 44) 2434 0043/9659/8080, 2433 0724/ 3293/3294, Fax + (91 44) 2434 3663 Kolkata: Tel + (91 33) 2287 8839 /2287 6617/ 2283 1411/ 2280 0008, Fax + (91 33) 2287 0728 Bangalore: Tel + (91 80) 2559 7401/4049 Fax + (91 80) 559 4065 Ahmedabad: Tel + (91 79) 2658 4924/5049/2008, Fax + (91 79) 2658 4924 Hyderabad: Tel +(91 40) 2373 5061/7251, Fax + (91 40) 2373 5152 Pune: Tel + (91 20) 2552 0194/95/96, Fax + (91 20) 553 9231 Copyright, 2014 ICRA Limited. All Rights Reserved. Contents may be used freely with due acknowledgement to ICRA. All information contained herein has been obtained by ICRA from sources believed by it to be accurate and reliable. Although reasonable care has been taken to ensure that the information herein is true, such information is provided 'as is' without any warranty of any kind, and ICRA in particular, makes no representation or warranty, express or implied, as to the accuracy, timeliness or completeness of any such information. All information contained herein must be construed solely as statements of opinion, and ICRA shall not be liable for any losses incurred by users from any use of this publication or its contents.

ICRA LIMITED

You might also like