CH 05
CH 05
CH 05
Chapter 5
Network Modeling
1.
If supplies are represented by positive numbers and demands are represented numbers, the balance-of-flow
rule would be stated as follows:
For Minimum Cost Network
Apply This Balance-of-Flow Rule
Flow Problems Where:
At Each Node:
Total Supply > Total Demand
Outflow - Inflow Supply or Demand
Total Supply < Total Demand
Outflow - Inflow Supply or Demand
Total Supply = Total Demand
Outflow - Inflow = Supply or Demand
2.
Multiply both sides of the constraint by -1 and reverse the sign of the inequality.
3.
b.
c.
d.
Node
Newspaper
Mixed
Paper
White
Office
Cardboard
Process 1
Process 2
Newsprint
Packaging
Print Stock
Node
Newspaper
Mixed Paper
White Office
Cardboard
Process 1
Process 2
Newsprint
Packaging
Print Stock
Net
Flow
-80.0
Supply/Deman
d
-80
-50.0
-50
-30.0
-40.0
0.0
0.0
60.0
40.0
50.0
-30
-40
0
0
60
40
50
Net
Flow
-80.0
-50.0
-30.0
-25.4
0.0
0.0
60.0
40.0
50.0
Supply/Deman
d
-80
-50
-30
-40
0
0
60
40
50
In part a, if we assume supply is inadequate the demand (when, in fact, it is adequate) we require all
the supply to be used even if it is not all needed. This results in higher than necessary costs. In
part b, assuming supply is adequate to meet demand (when, in fact, it is) resulted in a smaller total
cost as this solution does not require all the supply to be used.
Errata: This question should refer the reader to Figure 5.21 rather than 5.19 and should indicate the
shortage occurs on print stock pulp rather than packaging pulp. The shortage on print stock pulp can
be reduced to 4 units (without sacrificing newspaper or packing paper pulp) at an additional cost of
$307.
4.
Because there is a 10% loss of flow on all arcs going to node 4, a total of 702/0.9 = 780 units must flow
into node 4. Thus, we can simply increase the demand at node 4 to 780 and assume no loss of flow occurs
on arcs leading into this node. Similarly, only 608/1.05 = 579.05 units must flow into node 5. Thus, we
can simply decrease the demand at node 5 to 579.05 and assume no gain of flow occurs on the arcs
leading into this node.
5.
-5
1
6
7
4
+4
+0
+8
8
5
5
-7
6.
2
-8
+5
1
5
+5
+5
4
-7
7.
3
7
The cost on each arc increases by $2,000. The optimal plan under both leasing options is to replace the
equipment at the beginning of years 3 and 5. However, leasing option 2 provides the lowest total cost
($122,965 + $62,000) and is therefore the preferred alternative. See file: Prb5_7.xls
8.
b.
9.
310 feet.
a.
-30
-40
$6.50
Reg1
$7.50
Reg 2
$7.00
Pine Hills
6
$8.00
-25
Reg 3
$8.25
60
$7.25
$6.75
-35
Reg 4
$7.75
Eustis
7
70
$7.00
-33
b.
c.
10. a.
Reg 5
$7.50
$6.75
Sanford
8
40
+410
Beg
Inv
1
$0
lb = 0
+310
+580
+540
+50
D1
$1.50
D2
$1.50
D3
$1.50
$1.50
lb = 50
D4
lb = 50
lb = 50
lb = 50
Fin
Inv
10
-120
$49 lb = 400
$45
lb = 400
$46 lb = 400
P1
P2
P3
-500
-520
-450
$47 lb = 400
P4
8
-550
b.
c.
d.
11. a. Errata: Production costs (per 1000) in January, February, March, April, May and June are $7,100,
$7,700, $7,600, $7,800, $7,900, and $7,400, respectively.
To
Mar
Unit Cost
$7,265
0
0
0
6
10
0
0
0
0
13
0
14
0
0
0
6
0
20
0
0
0
0
26
0
0
0
33
3
0
1
1
1
1
1
2
2
2
2
2
2
3
3
3
3
3
3
4
4
4
4
4
5
5
5
5
6
6
6
Jan
Jan
Jan
Jan
Jan
Feb
Feb
Feb
Feb
Feb
Feb
Mar
Mar
Mar
Mar
Mar
Mar
Apr
Apr
Apr
Apr
Apr
May
May
May
May
Jun
Jun
Jun
14
15
16
17
18
13
14
15
16
17
18
13
14
15
16
17
18
14
15
16
17
18
15
16
17
18
16
17
18
Apr
May
Jun
July
Aug
Mar
Apr
May
Jun
July
Aug
Mar
Apr
May
Jun
July
Aug
Apr
May
Jun
July
Aug
May
Jun
July
Aug
Jun
July
Aug
Total Cost
$7,320
$7,375
$7,430
$7,485
$7,540
$7,810
$7,865
$7,920
$7,975
$8,030
$8,085
$7,600
$7,720
$7,775
$7,830
$7,885
$7,940
$7,800
$7,935
$7,990
$8,045
$8,100
$7,900
$8,050
$8,105
$8,160
$7,400
$7,555
$7,610
$1,006,675
12. a.
Legend: (Cost, Upper Bound)
($20, 50)
C-O
($135, 200)
150
-300
C-N
200
($178, 200)
($156.5, 250)
10
-300
($159.5, 250)
H-N
H-O
1
($20, 50)
DnO
5
150
($171, 200)
DnN
200
($139, 200)
B-O
-400
($20, 50)
150
200
($157.5, 250)
B-N
8
-400
($153.5, 250)
($20, 50)
A-O
A-N
150
b.
c.
($152.5, 250)
DaN
($132, 200)
($173, 200)
11
($160.5, 250)
DaO
($176, 200)
($155.5, 250)
($134, 200)
200
($154.5, 250)
12
From
1 Huntington-O
1 Huntington-O
1 Huntington-O
1 Huntington-O
2 Bakersfield-O
2 Bakersfield-O
2 Bakersfield-O
2 Bakersfield-O
7 Huntington-N
7 Huntington-N
7 Huntington-N
7 Huntington-N
8 Bakersfield-N
8 Bakersfield-N
8 Bakersfield-N
8 Bakersfield-N
3 Dallas-O
4 Chicago-O
5 Denver-O
6 Atlanta-O
To
3
4
5
6
3
4
5
6
9
10
11
12
9
10
11
12
9
10
11
12
Dallas-O
Chicago-O
Denver-O
Atlanta-O
Dallas-O
Chicago-O
Denver-O
Atlanta-O
Dallas-N
Chicago-N
Denver-N
Atlanta-N
Dallas-N
Chicago-N
Denver-N
Atlanta-N
Dallas-N
Chicago-N
Denver-N
Atlanta-N
Total Cost
Cost
$139.00
$135.00
$134.00
$132.00
$176.00
$178.00
$171.00
$173.00
$160.50
$156.50
$155.50
$153.50
$157.50
$159.50
$152.50
$154.50
$20.00
$20.00
$20.00
$20.00
$220,050.00
13. a.
57.429
27.800
37.913
43.7
21.3
30.825
0.0
22.529
23.813
8.000
+1
36.629
-1
37.000
20.125
16.0
17.100
51.613
63.313
50.329
35.4
77.155
Notes: 0-1 = keep current equipment to use during the coming year
0-2 = trade-in current equipment immediately and use new equipment during the coming year
b.
c.
The problem could be made more realistic by considering the tax savings associated with depreciation
on the equipment. Also, the current problem does not consider the time value of money (i.e., we
might attempt to minimize the net present value of the cash flows). Both of these considerations
could be accommodated easily by altering the objective function coefficients.
14. a.
NY
17
Chic.
7
6
+1
18
24
18
95
LA
2
32
50
Denver
27
19
13
25
30
Memp
24
14
14
105
St Lou
35
35
45
San Diego
1
-1
b.
MIN
c.
15. a.
-700
-$24
Sbo
-$23
Clx
Brk -$25
Mln
ub = 600
lb = 300
-$11
16. a.
b.
c.
$50
$44
Sav
-400
$48
Mln $42
Pry -300
$43
-$0.5
b.
c.
Clx
$45
$0.5
-$25.5
-500
ub = 700
lb = 350
-$10
Hvl
-50
Val -450
17. a.
b.
18.
Supply nodes: 1, 2
Demand node: 6
Transshipment nodes: 3, 4 & 5
See file: Prb5_17.xls
The solution is: X13=20, X24=10, X25=30, X36=40, with a minimum total cost of $2,700.
MAX
X71
ST
19. a.
Stores
Warehouses
+20
+25
+30
+35
-30
4
6
5
-30
6
4
4
-30
b.
3
2
MIN
ST
c.
d.
Assign arbitrarily large costs (such as $999) to the arcs representing these flows.
The optimal solution is then: X13 = 30, X21 = 20, X24 = 10, X32 = 5, X34 = 25.
Minimum total cost = $345.
Note that store 2 receives 20 units less than demanded.
ST
The solution is: X13 = 5, X14 = 10, X23 = 5, X25 = 10, X34 = 10
Minimum total cost = $455
See file: Prb5_20.xls
21. a.
Dallas
-1
San Diego
$750
3/2
$487.5
3/6
+1
3/12
+1
3/20
+1
$487.5
$412.5
-1
$562.5
$750
$487.5
3/9
$487.5
$487.5
-1
3/17
$562.5
$750
$562.5
$487.5
-1
3/23
$487.5
$562.5
$750
3/25 +1
Note: each arc represents a possible round trip ticket departing from nodes with the earliest dates (e.g., we
could buy a round trip ticket departing San Diego on March 6, returning to San Diego March 23).
b.
c.
22. a.
L.B. = 7.5
($0, 999)
-30
($1.20, 999)
+6
Toulon
+15
Tanke
r
Doha
0
Rotter
dam
($1.40, 999)
($1.35, 999)
($0.35, 22.5)
($0.25, 999)
6
+0
($0.20, 999)
Damietta
4
($0.15, 999)
($0.16, 15)
+0
Suez
2
($0.27, 999)
($0.28, 999)
($0.20, 999)
+0
b.
c.
P.
Said
3
Palerm
o
($0.19, 999)
L.B
.
0
7.5
0
0
0
0
0
0
0
0
0
0
0
U.B
.
22.5
999
999
999
999
999
15
999
999
999
999
999
999
From
0 Doha
0 Doha
1 Tanker
1 Tanker
1 Tanker
2 Suez
2 Suez
3 Port Said
3 Port Said
3 Port Said
4 Damietta
4 Damietta
4 Damietta
To
2
1
5
6
7
3
4
5
6
7
5
6
7
+9
Suez
Tanker
Rotterdam
Toulon
Palermo
Port Said
Damietta
Rotterdam
Toulon
Palermo
Rotterdam
Toulon
Palermo
($1,000,000s)
$0.35
$0.00
$1.20
$1.40
$1.35
$0.20
$0.16
$0.27
$0.28
$0.19
$0.25
$0.20
$0.15
23. a.
Atlanta
Los Angeles
-1
+1
-1
+1
-1
+1
-1
+1
-1
+1
-1
+1
-1
+1
Note: each arc represents a possible round trip flight assignment departing from nodes with the earliest
times. See spreadsheet for arc costs.
b.
c.
24. a.
b.
c.
d.
25. a.
A1
1.012
A2
1.012
A3
1.012
A4
1.012
1.012
1.012
A5
1.035
1.012
1.035
B5
A6
1.035
B1
BB
B3
1.035
1.012
1.035
1.012
1.035
P3
-9999
+50
C1
+50
1.11
D1
b.
c.
Minimize the total flow from BB (beginning balance) to A1, B1, C1 and D1.
See file: Prb5_25.xls
Flow
From
To
$94.985 1 BB 3 B1
$178.673 1 BB 4 C1
$46.676 3 B1 8 B3
$48.309 3 B1 9 P3
$178.673 4 C1 11 C4
$48.309 8 B3 14 P5
$189.036 11 C4 16 EB
Total cash required = $273,658
1.035
P5
C4
1.058
1.012
1.058
EB
+200
26. a.
700
Denver
5
Chicago
2
900
750
800
725
Kansas City
4
San Fran
6
650
Wash, DC
1
625
725
700
Dallas
3
999999
b.
c.
27. a.
35
15
Cincinnati
5
Boston
1
25
Chicago
7
20
Pittsburgh
3
30
15
20
Memphis
6
15
15
Baltimore
2
25
30
10
Atlanta
4
10
Dallas
8
999
b.
c.
28. a.
b.
29. a.
L.B = 150
-400
P1
out
P1
17
U.B = 500
18
W1
in
L.B = 150
-300
W1
out
19
L.B = 150
-600
b.
P3
P3
out
17
c.
Ship
250
150
600
0
250
0
150
500
100
500
500
0
500
0
300
100
100
From
1 Plant 1
2 Plant 2
3 Plant 3
4 Plant 1 out
4 Plant 1 out
5 Plant 2 out
5 Plant 2 out
6 Plant 3 out
6 Plant 3 out
7 Whse 1 in
8 Whse 2 in
9 Whse 1 out
9 Whse 1 out
9 Whse 1 out
10 Whse 2 out
10 Whse 2 out
10 Whse 2 out
To
4 Plant 1 out
5 Plant 2 out
6 Plant 3 out
7 Whse 1 in
8 Whse 2 in
7 Whse 1 in
8 Whse 2 in
7 Whse 1 in
8 Whse 2 in
9 Whse 1 out
10 Whse 2 out
11 Dist. 1
12 Dist. 2
13 Dist. 3
11 Dist. 1
12 Dist. 2
13 Dist. 3
600
D3
100
W2
out
15
D2
U.B = 500
W2
in
300
21
P2
out
P2
D1
30.
MAX
ST
X71 + X81
+X71 +X81 -X12 - X13 - X15 = 0
+X12 -X24 - X25 = 0
+X13 -X35 -X36 = 0
+X24 +X54 -X45 -X47 = 0
+X15 +X25 +X35 +X45 +X65 -X54 -X56-X57-X58= 0
+X36 +X56 -X65 -X68 = 0
+X47 +X57 -X71 = 0
+X58 +X68 -X81 = 0
0 X12 100
0 X13 100
0 X15 200
0 X24 100
0 X25 150
0 X35 150
0 X36 150
0 X45 100
0 X47 150
0 X54 100
0 X56 100
0 X57 100
0 X58 100
0 X65 100
0 X68 150
0 X71
0 X81
b. The optimal solution is: X15 = 200, X24 = 100, X25 = 50, X36 = 150, X47 = 150, X54 = 50, X57 = 100,
X58 = 100, X68 = 150, X81 = 200, X72 = 100, X82 = 50, X73 = 150.
Maximum flow = 500 bags per minute.
See file: Prb5_30.xls
31. a.
Albany
3
2
4
Savannah
Macon
2
Atlanta
2
2
Athens
4
b.
MAX
ST
X51
+X51 -X12 = 0
+X12 - X23 -X24 - X25 = 0
+X23 -X35 = 0
+X24 -X45 = 0
+X25 +X35 +X45 -X51= 0
0 X12 5
0 X23 4
0 X24 2
0 X25 2
0 X35 2
0 X45 2
0 X51
c.
The optimal solution is: X12 = 5, X23 = 2, X24 = 2, X25 = 1, X35 = 2, X45 = 2, X51 = 5
Maximum flow = 5 sets of connecting flight plans.
See file: Prb5_31.xls
Cost
$0
$85
$20
$25
$30
$20
$30
$35
9
Total Cost
$25
$270
34. a.
Beg. Inv.
0
$1
(0,500)
$0
(0, 500)
$1
(0,500)
DC Tuesday
7
$0
(300, 500)
Monday
1
(400, 500)
$0
$0
(0, 500)
Tuesday
2
(0,200)
$0
(0, 500)
$2
(0,200)
DC Monday
6
$0
(400, 500)
$2
Wednesday
3
(250, 500)
$0
(0,500)
$1
DC Thus
9
$0
(0, 500)
(0,200)
DC Wed.
8
Thursday
4
$2
(0,500)
$1
(0,200)
$0
(0, 500)
$2
Friday
5
This is a generalized network flow model. The exchange rates and transaction costs comprise the
coefficients that appear on each arc (and are calculated in the spreadsheet). The key is to realize that
you want to maximize the amount that makes it into the bank in US currency.
b.
c.
d.
e.
1.
F1
-999
D1
UB=31
LB=21
$0.92
Loss=2.20+0.60*G4
-999
F4
UB=31
LB=16
T1
T4
Loss=3.2+0.45*G1
$1.02
D4
Loss=1.80+0.35*G3
D2
UB=20
LB=7
T3
UB=31
LB=18
$0.85
F2
-999
T2
D3
Loss=2.25+0.65*G2
$0.87
F3
-999
Di = departure point i
Fi = fuel depot at departure point i
Ti = take off from departure point i
Gi = fuel on board when taking off from departure point I
2.
3.
Hong Kong
Factory
1
$375
(20,30)
$2
(5,20)
Hong Kong
Dock
4
-40
Korea
Factory
2
(25,40)
$1.8
(10,30)
San Fran
Dock
7
(20,65)
$1.0
(5,15)
Korea
Dock
5
Singapore
Factory
3
Singapore
Dock
6
$1.2
(10,18)
$1.0
(5,14)
+20
Baltimore
13
+30
Houston
14
+25
$1.2
(4,6)
San Diego
Dock
8
$2.4
(5,25)
-30
Denver
12
$0.85
(6,12)
San Fran
Warehouse
9
(10,30)
$2.1
$365
(15,30)
+10
$1.1
(3,7)
(5,20)
$2.3
$390
Pittsburgh
11
(5,15)
$2.2
(30,70)
San Diego
Warehouse
10
$1.1
(5,20)
$0.9
(10,20)