Power Transmission - The Real Bottleneck
Power Transmission - The Real Bottleneck
Power Transmission - The Real Bottleneck
Knowledge Partner
September, 2013
Contents
1. 2. Executive Summary ..................................................................................................................................1 India Transmission Sector Overview........................................................................................................5 2.1 2.2 3. Current Market Structure .................................................................................................................9 Evolution of Transmission Sector....................................................................................................10
Enormity of the Problem ........................................................................................................................13 3.1 3.2 3.3 Deficiency in Current Transmission Capacity..................................................................................14 Delays in Future Transmission Capacity Addition ...........................................................................15 Future Investments & Adverse Spiral Effect ..................................................................................16
4.
Challenges & Potential Recommendations...........................................................................................19 4.1 Project Planning .............................................................................................................................20 4.1.1 4.1.2 4.2 Issues ...........................................................................................................................21 Recommendations........................................................................................................23
4.3
4.4
Clearances & redressal mechanism for unforeseen events...........................................................34 4.4.1 4.4.2 Issues ...........................................................................................................................34 Recommendations ...................................................................................................... 36
4.5
Level Playing Field between private developers and state owned entities................................... 37 4.6.1 4.6.2 Issues .......................................................................................................................... 37 Recommendations ...................................................................................................... 39
5. 6.
Foreword
India's Power Transmission networks constitute the vital arteries of the entire power value chain. It goes without saying that the growth of power sector is contingent to development of a robust and a non collapsible transmission network. Over the past decades, the total power capacity has witnessed commendable growth, with more than 232 GW of generation capacity currently installed in India. However, India's peak load supply is only 141 GW, and aggravating this situation further is that some of India's power surplus regions do not have adequate power evacuation infrastructure which could alleviate the recurring supply shortages in other parts of the nation. While the issues related to Generation and Distribution sectors, rightfully, got due focus from policy makers to industry stakeholders, Transmission which is the critical link of power supply with no fall back option got downplayed due to multiple reasons. In light of this, FICCI constituted a Task Force on Transmission with participation from various key stakeholders including developers, contractors, reputed consultants, legal firms and regulators with primary intent of sensitizing the policy makers on prevailing problems which are hampering the growth of Transmission sector. The inaugural report Power Transmission: The Real Bottleneck , finalized after extensive discussions with our various industry partners carefully researches and documents the important findings pertaining to the reasons behind the slow growth of this sector. With a planned generation capacity addition estimated at 88 GW in the 12th Plan and improved generation with fuel issues getting sorted out for existing capacity, a corresponding increase in Transmission capacity is needed to ensure that power generated reaches the end consumer. More than 46% of the total investment required (in excess of Rs 2 lakh crore) has to come from private sector. Clearly, successful PPP in transmission would be vital to meet the huge investment & capacity enhancement target in transmission. The report highlights various reasons which currently saddle the pace of private investments in the transmission sector along with measures to address them. We sincerely hope that the issues along with recommendations brought forth in this report will serve to highlight and provide key inputs to stakeholders towards resolving these important issues in an expedited manner.
Executive Summary | 1
1 2 3 4 5 6
Worldbank Data Worldbank Data Central Statistical Organization, India CEA, as per May 31, 2013 CEA, Load Generation Balance Report 2013-14 Economic Survey of India, 2012-13
7 8 9 10 11
Planning Commission CEA, Planning Commission Central Electric Authority PowerGrid Annual Report, 2011-12 The Economic Times - 120 power transmission projects face roadblocks, 2011
India is one of the few countries where Transmission Sector has been opened up for private participation & has garnered significant interest from private players. The bidding framework is fairly comprehensive with provisions for majority of situations which may occur during the term. Introduction of Point of Connection (PoC) regime is a step in the right direction & has been appreciated by lenders and investors alike. Still, the success of other sectors, like generation, is yet to be replicated. Key policy changes which can pave way for robust capacity creation in the sector, based on experiences gained so far, have been highlighted below. Time taken from concept to commissioning11, which is currently 5 to 6 years, is much longer than global standards, and must be optimized. The process needs to be more efficient and the process for award of projects needs to be streamlined. At the same time, incentives must be given to a developer for faster project execution. Currently, even if a developer is able to commission lines before the contractual COD (commercial operation date), revenues are realized from the contractual COD only. To ensure faster execution, it is recommended that provision for early commissioning incentives be made in the Standard Bidding Documents. Also, state owned utilities, such as PGCIL, whose order book (of Rs.1,20,000 crores) has reached saturation point, need to focus on fast track execution of projects during the next 3-4 years, and refrain from accepting new orders. The level of innovation and technology in the industry must be upgraded considerably, thereby upgrading quality, speed and health and safety standards. Currently, no guidelines on use of technology are mandated and the focus is on lowest price for competitive bidding. This doesn't help incentivise developers to innovate and suggest new ways of working as they will be at a disadvantage compared to a cheaper alternative. It is recommended that policies be realigned to focus on output parameters rather than input factors in order to extract maximum results from projects. When new transmission systems are conceptualised by CTU and various standing committees, they must exhaust all possibilities to optimise existing transmission corridors by deploying best available technologies, before embarking on creating green-field lines and substations which occupy scarce agricultural and forest land. Qualification requirements must be critically evaluated and reformed so as to screen out inexperienced players from the bidding process. Due to inadequate pre-bid due diligence by inexperienced players, projects have been awarded at unviable prices. When the developers later realize the actual costs, projects are often stalled. Qualification requirements must be tailored to attract only serious participants, which can be achieved by placing higher emphasis on prior transmission experience. In addition, for projects that have already been awarded, it is recommended that concessionaire should be allowed to completely exit the project at any point in time (before/after COD) by selling equity to an equally qualified substitute concessionaire. Post-commissioning, the projects may even be sold to financial investors who are willing to provide adequate O&M undertaking through third parties.
11
The Economic Times - 120 power transmission projects face roadblocks, 2011
Another crucial factor is clearance process and redressal mechanisms. Current clearance and redressal policies have not been able to get private players to actively participate in the power transmission sector. The Planning Commission Transmission Services Agreement (TSA) and the TSA specified by the Ministry of Power have different clauses with respect to force majeure events.The TSA, as notified by the Ministry of Power has a clause which restricts consideration of any revocation or refusal to renew consents, clearances and permits as a force majeure event. The additional clause mandates approval of force majeure claims by a competent court of law. Dealing with the judiciary system in India makes the process time consuming and deters private players from participating. Considering the number of risks assumed by a developer during project execution, robust redressal mechanisms should be available to developers in case of unforeseen events. It is recommended that a material adverse effect clause be inserted allowing parties to seek relief, as opposed to electing to terminate the agreement. In addition, an independent nodal body should be formulated to facilitate clearances, address grievances, track project status and enforce quality standards. In order to promote greater private participation in the power transmission sector, it is important that private players be given a level playing field along with state owned players such as PGCIL. PGCIL currently plays a dual role - transmission planning (as CTU) and execution of interstate transmission projects - and is thereby privy to commercially sensitive information. In the course of discharging its duties, as a CTU & as a member of EC, PGCIL is privy to certain material non-public & cost-sensitive information apart from having rights to influence decision making in EC. It is therefore recommended that CTU be hived off from PGCIL & in order to ensure fairness in the bidding process, an independent and impartial Empowered Committee without any representation from PGCIL should decide whether projects should be done by tariff based bidding or under the cost-plus route. State entities and private players should be treated at par with similar norms & processes for securing forest clearance. Immediate policy action is required from the MoP and CEA for reinvigorating the transmission sector. There is an urgent need to synchronise the policy framework with a new reality of wider participation by private players under competitive bidding regime. Earlier rules were designed to only cater to government companies under the cost plus regime. PPPs are a much needed catalyst in reviving this sector and in order to make this successful, policy reforms are necessary. Once PPPs are able to thrive successfully, we will be able to achieve the common objective of building the grid, meeting demand requirements and optimally utilizing generation capacity.
Growing industrialization.
100%
200001
200304 Agriculture
200607 Industry
200910 Services
201213
12
24
Rapid urbanization.
Population in Millions 2,000 1,500 1,000 500 0 1990 2000 2010 Urban Population 2020 2030 2040 2050 2060
Total Population
+33% 105 86 69 43
132
6th
7th
8th
9th
10th
11th
Transmission Line Network Strength In 000 Circuit Kilometers , As per 5 Year plans
+27% 243
146
6th
13
7th
8th
9th
10th
11th
Planning Commission
Private / PPP (Develops transmission lines on BOO model and charges for wheeling electricity within the tarrifs specified by CERC/SERC)
State Transmission Utility (STU) (Ensures development of an efficient, coordinated and economical system of intra-State transmission lines and undertakes intra-state transmission)
The country has been demarcated into five transmission regions viz. Northern, Eastern, Western, Southern and North Eastern. The Northern, Eastern, Western and North Eastern regions have been synchronously interconnected and operate as a single grid National Grid. The Southern region is asynchronously connected to the National Grid through HVDC links. By January 2014, the southern grid is also expected to be connected to the existing national link synchronously. Each of these five regions has a Regional Load Despatch Centre (RLDC), which is the apex body, as per the Electricity Act 2003, to ensure integrated operation of the power system in the concerned region. In addition, there is an apex body at the national level called the National Load Despatch Centre (NLDC) to ensure integrated power system operation in the country. The NLDC and RLDCs together form a part of the Power System Operation Corporation Limited (POSOCO),
which is a wholly owned subsidiary of Power Grid Corporation of India Limited (PGCIL). As a major move, a committee14 was constituted in August 2008 by the Ministry of Power had recommended that ring-fencing of Load Despatch Centres must be done. The objective was to ensure that Load Despatch Centres have functional autonomy, independent and sustainable revenue streams, and are adequately staffed with people having the right skills, equipment, and incentives to deliver. However, even after concrete recommendations by the committee, five years have passed and no concrete action has been taken on this front. The transmission system has to meet the firm transmission needs as well as the Open Access requirements. The Long term access gives the transmission system flexibility to cater to generation capacity additions in future. The Short Term Open Access facilitates real-time trading in electricity and leads to market determined generation dispatches.
14 15
Chaired by Addl. Secretary, MoP , Shri Gireesh B. Pradhan, (vide order no. 6/2/2008) CEA - Status of implementation of progress of reforms under National Tariff Policy 2006
Electricity Laws (Amendment) Act Private participation allowed in generation Up to 100% foreign ownership allowed Operators and SEBs entered into power purchase agreements (PPAs) SEBs to be responsible for transmission and distribution of power
Electricity Laws (Amendment) Act Private participation enabled in transmission CTU and STUs set up Electricity Regulatory Commissions Act CERC & SERCs formed Regulator to protect & promote consumer interest, fair competition, transparency Provide a levelplaying-field for all players
The Electricity Act Replaced the earlier laws, aiming to enable reforms & restructure power sector National Electricity Policy brought out, mandatory creation of SERCs, emphasis on rural electrification, open access in transmission and distribution Introduced a nondiscriminatory open access in the transmission
National Tariff Policy Mandatory competitive bidding of all transmission projects after Jan 2011 Framework for determining tariffs and rate of return for projects under generation, transmission as well as distribution
National Tariff Policy (Amendment) Exemption to intra-state transmission sector from mandatory competitive bidding up to 5th Jan 2013 Exemption of select experimental works/ urgent/ compressed time schedule work from tariff based competitive bidding
Currently, the Indian transmission sector is in the early stages of globalization compared to other sectors like ITES, Telecom etc. (Figure 5). Many private players, ranging from power generation companies like Adani, GMR, etc. to EPC and infrastructure companies like KEC, Isolux, etc. are entering the sector. However, progress in the sector is hampered by various challenges.
Power Generation
Number of years of government support / reforms are needed to drive maturity / stability
16 17 18 19 20
CEA, as per May 31, 2013 The Financial Express - Infra woes trip transmission despite power-surplus oases, 2013 The Financial Express - Infra woes trip transmission despite power-surplus oases 2013 CEA Load Generation Balance Report 2013-14 IBEF Report 2013
Even within a state boundary, choked transmission networks are leading to underutilization of generation capacity. For example, in 2011-12, wind energy generation sites in Tirunelveli and Udumalpet, Tamil Nadu, with cumulative installed capacity of 6,943 MW, ran below capacity, as the transmission capacity available was only 4,997 MW. This under-utilization of the sites meant an annual opportunity loss of 559.03 MU. In addition, the state had a net deficit of electricity and had to purchase power from costlier sources21. Going forward, the demand side capacity is expected to further increase with the industry moving towards Open Access. Open access will allow every end-user of electricity in the country to choose from all available transmission lines, thereby increasing transmission load across the country. If India's transmission capacity is not timely augmented, this problem is expected to further aggravate.
201 167
9% 3% 2%
18%
150 100 50 0
9%
22%
66%
68%
2011
Nuclear
2012
Renewable Energy Source
2017
Hydro
2022
Thermal
21 22
The New Indian Express - Power transmission losses dip during 2011-12 Booz & Company analysis
Though the Electricity Act, 2003 empowers the licensee with the Right of Way (ROW) under the Telegraphic Act 1885, it is rarity for a transmission project to be executed without any delays in land acquisition or getting the ROW. In 2011, Central Electricity Authority (CEA) estimated that more than 12023 transmission projects faced delays because of the developer's inability to get ROW or acquire land and get timely clearances from the host of stake-holders like forest department, aviation department, defense, and PTCC (Power and Telecommunication Coordination Committee). In the same year, PGCIL had challenges in spending its planned Rs.6000 Crores24 in capital expenditure, for the construction of the inter-state transmission lines, primarily because of the hurdles in land acquisition & ROW problems. At times, transmission lines are forced to take a different route altogether, leading to the whole project plan to go astray. For example, Kerala government is planning to take an alternative route on the Edamon - Pallikkara stretch for the 310-km-long transmission corridor to evacuate power from the Koodankulam Nuclear Power Project (KKNPP). Currently the 170 km stretch on the corridor is stalled because of lack of ROW clearances. This is expected to seriously delay project & also result in unforeseen increase in project cost25. Recently, protest by one land owner delayed crucial India-Bangladesh transmission link by more than four (4) months26. Ministry of Power acknowledges ROW as a critical issue and emphasizes its importance in developing a national grid27. In addition, planning guidelines issued by CEA for the transmission sector also emphasize on ROW being a major impediment in setting up new lines.
3.3
Despite USD 75 Billion28 worth of investments being planned for the next two Five Year Plans (12th and 13th), the investments in the transmission sector are still not adequate. For every dollar invested in power generation, at least 50 cents should be invested in power transmission. In India, this ratio stands at 30%29. To make up for this investment deficit, India needs to invest more than 0.5 times of the future investments made in generation into transmission. Also, as per the 12th Five Year Plan, the investment required in the power transmission sector is about USD 35 billion30, out of which about USD 19 billion31 is planned to come from Power Grid Corporation of India Limited. The remaining USD 16 billion (~46% of the total investments) would have to be secured from private players. Over and above these planned numbers for the 12th Five Year Plan, in order to ensure true open access in the future, the investment required may increase manifold32. This makes it extremely important to ensure PPP projects in the power transmission sector are successful in the long run. In spite of taking significant steps to
The Economic Times - 120 power transmission projects face roadblocks, 2011 MoneyControl - Power Grid seeks Telegraph Act amendment to ease land buy, 2012 25 The New Indian express - Kerala yet to fill gap to claim share of KKNPP power, 2013 26 The Indian Express - One tower standing in way, PowerGrid quietly sealed Bangla deal 27 Ministry of Power - Annual Report (2009 10) 28 Booz & Company Analysis 29 The Financial Express - Infra woes trip transmission despite power-surplus oases, 2013 30 Ministry of Power, CEA 31 Power Grid Corporation of India Limited Annual Report 2011-12 32 IPPA: National Power Beltway
24 23
encourage private players to invest in the sector, the response has been relatively lackluster. Projects have faced various implementation challenges with tariff setting and adjustments, regulatory disputes, ambiguous contracts, hasty allotment of contracts leading to renegotiations, and unequal risk sharing. It is therefore, the need of the hour to learn from other sectors & countries and reform policies so as to ensure greater private participation in the power transmission sector. Additionally, the installed transmission capacity in India is depleting, therefore necessitating strengthening and upgradation of installed infrastructure. India suffered the world's biggest-ever power outage in July 2012 as transmission networks serving areas inhabited by 680 million people collapsed. The grid failure affected 18 states and two union territories in north and eastern India, bringing trains across large stretches of the country to a halt, forcing thousands of hospitals and factories to operate on generators, stranding hundreds of coal miners underground and causing losses to businesses estimated in the hundreds of millions of dollars33. Apart from upping the investment levels, project execution and completion is another area of concern. The 11th Five Year Plan (2007-12) had the target of increasing inter-regional transmission capacity of 32.6 GW. Only about 85% (27 .8 GW) of it could be achieved by 201234. The Ministry of Power has set an ambitious target of building the world's largest transmission network spanning across 140,000 ckm by 2017 from the current capacity of 100,000 ckm35. In the first quarter of 2012-13, only 70% of the targeted 4551 ckm could be achieved36. Without serious & timely reforms in the transmission sector, the country runs the risk of an adverse spiral effect on rest of the power sector and the economy. Current level of power shortages is estimated to account for a loss of US$3.4 billion in generation capacity, which is equal to a GDP loss of US$68 billion (0.4% of GDP) 37. This may hamper the private investment inflow into the sector. Growth in agriculture, manufacturing and services sector will also be impacted. This stagnation in growth can have serious implications on the country's socioeconomic stability. As a first step towards these reforms, it is important to identify the current challenges in the sector and develop suitable solutions for the same.
33 34 35 36 37
Wall Street Journal, 'India's Power Network Breaks Down' IEA Understanding Energy Challenges in India - 2012 Pg. 38 Mint - Govt aims to build world's largest transmission grid by 2017 Renew India - India Power Sector review, 2012 Economic Survey of India, 2012-13
O&M
No impetus on technology & innovation Limited O&M capabilities
Project Exit
Failure to attract FDI Discouraging holding requirements
Under-utilization of Difficulty in resources / obtaining ROW/ technology during forest clearances planning No requirements on No impetus on technology & Lengthy technology & innovation, HSE in conceptualization & innovation the bid document award phase Lack of transparent Overburdening of redressal PSUs with projects (unforeseen) mechanisms No incentives for early commissioning
To successfully accelerate the development of transmission sector, project planning needs to be lean and optimal. However, there are major issues related to the slow pace of project commissioning and sub-optimal utilization of critical resources like land and Right of Way that have slackened the growth in transmission capacity.
4.1.1 Issues
4.1.1.1 Concept to Commissioning (C2C) time is significantly high
An important factor for this slower rate of growth is the long process time for concept to commissioning (C2C). In the current system, average time for C2C is about 60 months39 (Figure 10).
3 months
8 months
9 months
40 months
Almost one-third (20 months) of this 5 year period is taken in the process of awarding the projects to the developer. It takes 3 months for a project approved in Standing Committee (SC) to come to Empowered Committee (EC). Then, post approval in EC it takes 8 months in finalization of the structure of the project, formation of SPV by Bid Process Coordinator (BPC), appointment of a consultant and publishing of RFQ. Following this, Bid Process Coordinator (BPC) carries out a survey, evaluates technical bids, and publishes RFP & invites financial bids. BPC takes ~9 months in this step. Then, a developer is awarded the project and the execution takes about 40 months. There is significant scope to compress the planning process and reduce redundant steps, cutting short the commissioning time.
Besides this, the current incentives for a developer are not aligned to the objective of faster execution of the project. If a developer is able to commission lines before the contractual COD (commercial operation date) revenues can flow in from the contractual COD only. This leaves the developer with little motivation to speed up the development phase of the transmission line, which ultimately results in delays.
39
Even though the execution capacity of PGCIL is constrained, it continues to add projects to its order book. The projects added are a combination of urgent projects granted on a cost plus basis, projects won under tariff based competitive bidding and projects secured on JV basis from the states. During FY13 itself, PGCIL has added projects worth Rs.5,000 crores won under competitive bidding and Rs.8,800 crores secured under JV basis to its order book. The project execution timeframe, though fixed by the grid planners as 3 years, might eventually end up extending to over 6 years as PGCIL's execution capability has already reached saturation point.
4.1.1.3 Sub-optimal planning is leading to under-utilization of resources 4.1.1.3.1 Lack of targeted planning for short, medium & long term transactions At present, the transmission planning process takes into account only long term access (LTA) commitments with no capacity plans for medium term or short term transactions. Moreover, the bidding process is becoming highly prescriptive in lieu of the shift from Case 1 to Case 2 bidding and being based on long term objectives, does not take market realities into account. This coupled with the increase in short & medium term transactions post the Electricity Act of 2003 results in inadequate transmission capacity leading to stranded generation on one hand and unserved loads on other. Lack of differentiation between short and long term objectives extends to similar treatment of long term and short term access applicants. Under present regulations, a Generator with Long Term Access (LTA) but lacking long term PPA is treated at par with short term access applicants leading to a delay in obtaining transmission rights. This results in stranding of generated power despite regular payment of LTA charges by the Generator.
22 Power Transmission The Real Bottleneck
Further, in case if a contract with a Generator is frustrated despite possession of a long term PPA with ISTS having been developed in accordance with the same, the Generator is unlikely to be able to supply power to third party customer because of transmission constraints. 4.1.1.3.2 Insufficient focus on up gradation of existing transmission lines Transmission lines utilize many natural resources, like land and forest cover, as they traverse across the country. Presence of a transmission line reduces the commercial value of the land to almost nil as it can't be put for any alternative commercial use, often leading to protests from the land owners. It also affects the nearby eco-system, more so while passing through the forest cover. Land and forests are scarce resources of prime importance for the nation and expanding the transmission network will only demand more of them. For implementing the transmission lines / sub-stations identified under the 12th Plan, the overall land affected would be about 1.440, million acres - Equivalent to area of state of Sikkim. Since acquiring new land is complex and usually marred with delays and uncertainties, it is extremely important to utilize the existing land, forest cover, and RoW optimally. Hence, a better alternative to laying out new lines (in many cases) could be to upgrade the existing corridors to higher voltage or to re-conductoring the lines to higher capacity conductors. However, due consideration is not given to them before planning a new corridor under the current guidelines.
4.1.2 Recommendations
4.1.2.1 Prune the Concept to Commissioning time to ~40 months
There is potential to reduce the conceptualization-to-award process from ~21 months to ~5-6 months under the competitive bidding framework. Additionally, the Ministry of Power can save ~5-6 months from the project development time by acquiring some key clearances in parallel to the project bidding phase. Following changes can be enforced across the process chain to expedite the commissioning of the project CEA/Empowered Committee (EC) should ask BPC to release RFQ within 1 month of approval by EC. Most of the bid documents are already standardized and significant time (~7 months) can be saved in this step Pre-qualification process should be held annually, rather than on the project to project basis. Up to 3 months can be saved by cutting down the redundancy of evaluating the same technical bid by a developer for different project, differently each time. NHAI also conducts qualification bids on annual basis and has saved significant time in awarding of
40
12th plan envisages building 1,00,000 ckm of transmission lines. Average span (width) assumed at 70 m.
the projects Bids should be awarded within 3 months of approval by EC. Currently, this process takes about 17 months Route surveys should not be conducted by BPC. As all the developers conduct their own surveys, citing data quality issues in the BPC's surveys, this exercise can be avoided altogether. This will avoid ~3 months lost in carrying out the survey. Pre-approvals should be awarded to the SPV by the Ministry of Power (MoP). Currently, the developer has to apply separately for section 164 and other statutory approvals to the MoP . Allowing these approvals to be obtained in parallel to the bidding process and can save 3-6 months, as already done to some extent for Ultra Mega Power Plants (UMPP)
With these changes, time for commissioning of the project could be reduced by one-third, from ~61 months to ~40 months and even lesser (18-24 months) for urgent projects. This recommendation should be implemented within next quarter with high priority with support from CERC, Ministry of Power, CEA, and Bid Process Coordinators (REC/PFC).
gets incentives for early commissioning of its' projects. These norms should be made part of the Standard Bidding Documents (SBD) by the SBD Modification Committee (comprised of MoP , PFC, REC), possibly within the next 3 months. 4.1.2.4 Focused planning for short and medium term transactions The planning process needs to account for market realities so as to provide flexibility to buyers and sellers. Instead of being based on just the LTA applications, transmission system should be planned based on potential generation areas and load projections such that transmission highways creation leads generation. 4.1.2.5 Differentiation between long term and short/medium term applicants Regulations need to be clarified/ modified so that Generators applying for long term applications are given preference over short and medium term applicants. In case a Generator has taken long term transmission access but does not have a long term PPA, transmission access should be given ahead of medium term and short term access applicants. 4.1.2.6 Use of High Performance Conductors in Existing & New Lines Use of High Performance Conductors (HTLS: High Temperature Low Sag) needs to be taken up to increase power transfer intensity. In 2012, a leading Indian conductor manufacturer collaborated with CTC Cable Corporation to re-conductor an existing 132 kV line in Ahmedabad41. The new line with ACCC (Aluminium Conductor Composite Core) conductor doubled the capacity of the existing transmission line, without modifying or reinforcing the existing lattice towers42. Israel Electric Corp (IEC) also upgraded a major part of its transmission network to HTLS (High Temperature Low Sag) conductors, increasing the circuit capacity by an additional 40% to 50%43. Possibility of upgrading an existing power transmission corridor on the same route should be mandatorily explored before conceptualizing a new line. Upgradation and re-conductoring of existing lines can save valuable time, cost, RoW, and forest cover. This would also mean lesser delays, and faster commissioning at a much lower cost to the nation. Re-conductoring takes much lesser time (~6 months), as compared to creating a new parallel corridor (~4-5 years). It also increases the power intensity without utilizing any incremental land. PGCIL upgraded the 220kV D/C Kishenpur-Kishtwar line in Jammu and Kashmir to 400 kV, resulting in significant increase of power transfer capacity with about only 5.7% increase in the ROW44 (from 35m to 37m).
Press Release - http://www.ctcglobal.com/news/new-transmission-line-energized-in-india Torrent Power LTD energizes CTC Global's first ACCC transmission line in India 43 T&D World Magazine - Less Sag, More Power: Israel Refurbishes Transmission Lines, 2013 44 PGCIL - Transmission and Distribution in India Report, Booz & Co. Analysis
42
41
400 kV NC*
15
~3X
42.4%
400 KV HPC**
52
0%
An analysis of POSOCO data reveals details of 28 transmission lines aggregating around 2,900 ckms (across 220 KV and 400 KV) which are severely over-loaded and for which alternatives (in terms of capacity enhancement) are urgently required. Upgrading these lines with HPC can provide immediate solutions to the problems of over-capacity within a relatively short period of time without any major changes in the transmission network. The details of the 28 lines are as provided in Annexure II. Both, upgradation or re-conductoring of existing lines, are technically and economically viable alternatives to setting up new lines. They also ensure minimum environmental impact and efficient utilization of national resource (Land, RoW, and Forest), while reducing timelines and remaining compliant to the international design standards. Team from CTU and CEA needs to ensure that an exercise which explores the possibility of reconductoring/upgradation of existing lines is mandatorily carried out before new projects are being planned and approved. The transmission planning criteria needs to be changed to this effect. This recommendation needs to be implemented with priority within the next 3 months.
and effort. The processes and methods being used in India take up considerably more time and money than the best in class practices available globally. While the average time for commissioning is lesser in other western countries like US, UK, etc., it takes ~4-5 years in India to develop a project following the acquisition of the SPV. Even comparable developing nations like Brazil, China take considerably lesser time in developing a project. This low level of mechanization not only considerably slows down the processes, but also has serious implications on quality, speed, and safety of the workers. However, issues like micromanaging specifications and not giving developers a free hand on the innovation affect the usage of technological methods in transmission in India. Four key areas where technology can be used while implementing projects are: I. Survey
II. Tower design III. Selection of Conductor IV. Mechanized construction methods Standard bidding documents currently allows flexibility with respect to Survey and tower design; while provisions of bidding document restrict flexibility with respect to Conductor selection and no specific incentives exist to promote mechanized construction methods. The following section describes these four areas in greater detail:
I. Survey
There is considerable amount of technology already in use by private players while undertaking survey for projects. Transmission Line route optimization through LiDar survey is one of the advanced technologies adopted globally. Light detection and ranging technology is deployed to conduct topographic mapping and functions well in cloudy conditions and can penetrate through dense vegetation as shown in figure given below. To overcome the limitations of manual survey, for the first time in India, a leading private sector developer used the LiDAR survey for transmission line optimization for two of its BOOM projects i.e. BhopalDhule Transmission Company Ltd. (BDTCL) and Jabalpur Transmission Company Limited (JTCL). LiDAR survey clubbed with PLS CADD allowed the transmission line engineers to evaluate several alignment options, including the cost of construction which eventually helped in finalising an alternative, which was both cost-effective and time efficient.
LiDAR is a very effective process. Its usage offers more benefits in terms of resource saving (both time and money). One of the key principles of line optimization is to increase the span by using extensions as per accurate terrain condition and minimum ground clearance requirement. It can also provide solutions for real time RoW problems on the ground
As seen in the above table, the private sector developer's type tested towers have been able to achieve a lower carbon footprint (on an average by 15-20%) as compared to the similar towers made as per industry normative weights for the same technical specifications.
Case Study:
Given below is a comparative case study for building a new line with conventional ACSR conductor and with HPC conductor. This is for a 100 kms 400 kV D/C Quad.
Items
Tower cost Conductor cost Erection & Foundation Other costs Total cost (100 KM Line) Transfer Capacity Cost in Rs. / MW / KM
100% -15%
It can be seen that though the cost of building a line with high capacity conductor is higher, but on a per MW/km basis, it is actually 15% cheaper. Also, if a re-conductoring exercise is undertaken for an existing ACSR line, the cost of the project would be equivalent to the cost of building a new ACSR line (with significant time benefits) and with no further wastage of land / forest resources.
most of the sites in difficult terrains do not have proper approach roads, these methods easily help to save 40-50% of the total time required for tower erection & stringing.
4.2.1 Issues
4.2.1.1 No freedom given to the developer to innovate
As a part of the process for awarding projects under competitive bidding, the empowered committee approves a project, whereas the Bid Process Coordinator (BPC) releases guidelines for the project in the Standard Bidding Documents (including RFP and TSA). As mentioned earlier, the restrictions are more prominent in areas of selection of conductor and selection of material towers. Thereby there has been very low level of technology innovation in these areas. For example, SBD quotes The Tower shall be fully galvanized using mild steel or/and high tensile steel sections. Bolts and nuts with spring washer are to be used for connection . This micro-management seriously restricts the choices given to a developer leaving them tied to the stated guidelines only, leaving no scope for innovation in the methods or the technology used. This focus on the input factors also acts a major de-motivator for major global players, who play on technology and innovation to minimize the cost over the life-cycle of the project. Specifying the methods and techniques strongly limits their ability and reduces them to the role of a contractor, than being a partner to the project. Quicker, better implementation are neither rewarded nor demanded. Only delivering within the stated quality parameters and on the agreed timeline is accepted.
4.2.2 Recommendations
4.2.2.1 Promote technology & give freedom to developers to innovate
BOOM model, by definition, implies that it is in the developer's best interest to build a line that is able to withstand the test of time without tripping or breakdown, since the developer has to maintain and operate the line for 35 years. But the policies continue to be impervious to this. Policy guidelines should be realigned to focus on output factors like performance, capacity, quality, timeliness and rewards or penalties for achieving or not achieving them. While the grid is integrated & hence window of specification is necessary in certain areas like conductor selection; policies need promote use of High Capacity Conductors which use less RoW & transfer higher power. The same can be mandated in bid documents. Similarly, mechanized construction methods including aerial technology of construction can be promoted and specified in certain cases. Suitable facilitations for use of these technologies need to be made by CEA & MOP . Adoption of these technologies will benefit the environment, save forests, and promote health & safety and will also deliver a higher capacity system in lesser time & cost.
The required changes in the technical norms as specified in the SBD are as mentioned in Annexure 6.
4.3.1 Issues
4.3.1.1 Participation from inexperienced players
Developers bidding for transmission projects face high uncertainty from a number of factors that increase the project costs and risks, such as wind zones, soil conditions, route assessment, RoW issues, river crossings, difficult terrains etc. This makes it necessary for adequate pre-bid due diligence to be done by bidders to arrive at realistic project cost prior to bidding. However, many participants, without appropriate pre-bid due diligence, submit aggressive and unviable bids. Later, on better understanding of the issues they either stall or abandon the project, resulting in decade long litigations & crippling of transmission system. Out of the 10 projects awarded till July 2013, only 5 have managed to take off and are under execution45. The other 5 have been stuck in litigation for various reasons. This leads to additional and unplanned costs of dealing with such issues. The reason why inexperienced players are being allowed into the process is that prior transmission experience is not a mandatory requirement.
45
Since this dampens any opportunity for asset churning once the project is completed, this is a major disincentive for the foreign capital and private equity investments in transmission sector.
4.3.2 Recommendations
4.3.2.1 Stringent QRs to filter out the inexperienced participants Qualification requirements should be tailored to keep inexperienced participants filtered out of the process. In this regard, transmission sector can borrow from the recommendations that planning commission has made for ports and highways Minimum technical experience for a bidder should be two times the project cost. Out of this total technical experience, at least 25% of the experience has to come from relevant sector. Credit should be given for pure infrastructure experience only. Standard Bidding Document (SBD), currently, qualifies capex even for projects that do not relate to infrastructure such as factory buildings. Technical experience of the affiliates should be allowed to be used by the bidder only when it demonstrates control of these affiliates through majority ownership.
The above norms have been implemented in sectors such as highways & ports and have been successful in keeping large credible private players engaged in the bidding process while keeping the inexeperienced participants out of the process. New players would be able to gain entry & experience by partnering with experienced players from around the world. Ministry of Power and CEA can implement the above suggestions in the short term by rationalizing the qualification requirements in the Standard Bidding Documents. 4.3.2.2 Simplified exit norms to allow for asset churning The Concessionaire should be allowed to completely exit the project at any point in time before or after COD. In case of exit before COD, transfer of equity should be allowed to an equally qualified (technically and financially) substitute concessionaire as at this stage there are substantial construction risks like RoW, BOQ increase, or other factors which can impact project cost & time of delivering the project. As these risks exist in an under-construction project, hence only an equal or more capable developer be allowed to take over such projects. After COD, the projects may even be sold to financial investors who are willing to provide adequate O&M undertaking through third parties. Relaxing the exit norms gives an opportunity to the investment companies that have resources to acquire projects, but are unwilling to take up the construction risks. It also provides the concessionaire an opportunity to exit from the investment they had not been able to manage. This significantly reduces the business risk associated with the project, making the sector more investment worthy. In other emerging countries like Brazil, complete exit is allowed by the regulators to asset churning.
Ministry of Power and CEA should act on this recommendation with a medium term outlook (within next six months).
4.4.1 Issues
4.1.1.1 Delay in approvals / clearances as a ground for force majeure & relief Delays in granting of statutory and Government approvals/ consents are usually on account of administrative and procedural delays. The Planning Commission Transmission Services Agreement (TSA), which is applicable to STUs, allows any unlawful or un-authorized refusal to renew or grant a clearance, consent or permit without valid cause to be considered as a force majeure event. However, the TSA, as notified by the Ministry of Power, restricts consideration of any such revocation or refusal to renew any consents, clearances and permits as a force majeure event. It specifies an additional mandate that approval would be granted only if certified by a competent court of law. This becomes a big hassle since the judicial process in India is time consuming and is also subject to different interpretations by different courts. As transmission projects are time bound and crucial for the country, these projects should be insulated from any matter that is litigious and hence time consuming. Also, the additional requirement to get such determination by a court of law defeats the purpose of treating it as force majeure. Also, there are specific issues pertaining to obtaining approvals and clearances. 4.4.1.1.1 Grant of an authorization under section 164 Authorization under Section 164 of the Telegraph Act confers authority to a developer to erect a transmission line on someone's land in lieu of compensation as per stipulated norms. In the absence of this approval, land owners can question the developing authority resulting in litigation and disputes. This is often used as a tool for extortion by land owners. For example, in the JTCL project being done by a leading private sector developer, even after 27 months of project award, authorization under Section 164 has not been granted. Due to this, there is severe resistance from land owners for erecting towers, extortion where land owners demand compensation of up to 15-20 times the actual stipulated compensation for RoW, numerous litigations by land owners being piled up against the developer, which would require significant time, investment and legal resources, the cost of which would exceed Rs.20-30 Crores46. Currently, the developer is responsible for obtaining this clearance from the Ministry of Power and no tentative timeline is given for granting the same. This has resulted in significant delays where projects have not been provided clearances even 30 months after awarding the project47.
46 47
4.4.1.1.2 Central Projects Status for Forest Clearance In the event of the project being awarded to a private developer, the developer mandatorily needs to acquire compensatory land for afforestation. This is a pre-requisite for receiving the forest clearance which is applicable only to private players. Central Government bodies, on the other hand, need to pay twice the compensation for afforestation without the need for acquiring compensatory land. Land acquisition poses a major hurdle for private developers and has significant delays associated with it. 4.4.1.2 Redressal mechanism for unforeseen events The tariff for a transmission project remains fixed during operation, but there are significant risks assumed by a private developer during project execution. This has the potential to adversely affect project economics and render it economically unviable for the developer. In such cases, the developer has no redressal mechanism available and therefore, slows down or abandons the project. In a recent case, Reliance had filed a petition in CERC for compensation in lieu of delays caused in Section 164. After a long time elapsed, costs increased multiple fold post the financial bid. As the project became unviable and no redressal was provided, Reliance abandoned two of its projects, one in North Karanpura and the other in Talcher, both of which were crucial for the northern and eastern grid. These projects were awarded in 2009 & were supposed to be commissioned by now; however there is little progress on the ground. Due to absence of transparent redressal mechanism both these projects are under dispute while fate of power plants dependent on these lines hangs in balance. When a developer abandons an operational project, the power flow in the region being served is severely affected. This poses significant risks to the nation's grid. A similar case has happened in Uttar Pradesh where 900 MW worth of power units, namely Reliance Power's Rosa and Lanco's Anpara, have become non-operational following disputes with UP Power Corporation Limited (UPPCL). Both Rosa and Lanco have shown their unwillingness to run their power units, lest they are paid their dues or have their charges revised by the state government. An acute power crisis is being faced by the state forcing it to draw from the National Grid48. Currently, there is no guideline to deal with abandoned projects & past experience in power and other sectors show that such projects create dead-lock thereby hurting all the stakeholders and finally the consumer. Some examples of events that adversely impact project economics at the time of operation which could not be predicted at the time of financial bidding are as follows: Abnormal fluctuations in commodity prices/interest rates/foreign currency Revenue loss/increases in project cost due to delay in crucial clearances, Force Majeure events, Difficult Right of Way/land acquisition process. Change in any laws post project bid
48
'UP staring at Power crisis as Rosa, Anpara plants shut 900 MW units'- Times of India
Currently, the Advance Loss of Profit (ALOP) insurance policies cover only the interest component for certain delays in project commissioning and no compensation is provided for project losses due to delay in RoW/clearances/Force Majeure events. There have been some cases where certain compensation was given. However, clear relief clauses still do not exist in the SBD and is subject to the interpretation of developers and the adjudicating body (CERC). This creates uncertainty for private investment, thereby lowering investor confidence. For example, recently, the effect of depreciation of rupee and consequential increase in the project cost (due to higher cost of construction) has been challenged by Sasan Power Ltd. in a petition before the CERC. The order of the CERC in this matter will provide clarity on the position of the Commission on the effect of the fiscal regime on the feasibility of projects. Another case is that of Adani Power Limited and Coastal Gujarat Power Limited. CERC, in its recent orders in the cases of Adani Power Limited and Coastal Gujarat Power Limited, acknowledged the hardships faced by developers whose plants were based on imported fuel and allowed for a compensation package (which would be over and above the tariff). The CERC in these orders, while concluding that increase in costs of imported fuel did not tantamount to force majeure or change in law, however, allowed relief to the petitioners even after the tariffs were discovered through competitive bidding. Relief has been provided in cases where tariff was determined by the Commission (as opposed to being adopted) for instance in the matter of PGCIL v. MPPTCL, in which CERC allowed an increase in the capital cost due to foreign exchange rate variation as additional capital expenditure incurred by PGCIL as it was on account of unavoidable circumstances not attributable to it and agreed to factor the same in the tariff.
4.4.2 Recommendations
4.1.2.1 Key clearances & authorizations to be in place before financial bid It is recommended that Authorization under Section 164 & Section 68 should be obtained by SPV prior to award of a project. Provisional Authorization under section 164 can be obtained by SPV prior to award while final Authorization within 6 months can be given on submission of final route by developer. This decision, once taken by the MoP and CEA can be implemented in the short term. 4.4.2.2 Adequate redressal for unforeseen events A specific clause for material adverse effect should be inserted which allows the parties to seek relief, as opposed to the parties electing to terminate the agreement. Material adverse effects could include those events which restrict the ability of either party to perform its obligations or which cause a material financial burden on the party. As a further safeguard to prevent misuse, the Transmission Service Agreement (TSA) should provide relief/compensation for a material
adverse effect will be subject to the discretion of the appropriate commission. By introducing this provision, the appropriate commission will have the right to adjudicate on the issue and decide an appropriate relief/compensation. In addition, it should be noted that the Planning Commission TSA allows extension of the period to achieve financial close, the time set forth in the Project Completion Schedule and extension of the Concession Period, as the case may be, depending upon the time when a particular force majeure event occurs. Additionally, as regards monetary relief allowed in that TSA, Force Majeure Costs includes interest payments on debt, loss of revenues, O&M Expenses, any increase in the cost of Construction Works on account of inflation and all other costs directly attributable to the Force Majeure Event. Similar provisions should be introduced in the MoP TSA which currently does not provide much clarity on the force majeure costs and time extensions that can be sought by the affected party. CERC is the body that should be empowered to provide relief (in terms of tariff increase) for events unforeseeable at the time of bidding with a clear mechanism for the same specified in the SBD, to reduce subjectivity. This recommendation once approved by the MOP and CEA could be implemented in the medium term.
4.5
Level Playing Field between private developers and state owned entities
In the Power Transmission Sector, a competitive bidding process was mandated for all future projects w.e.f. 5th January 2011. Although private players have participated in 15 project bids since then, there are inherent disadvantages that the private players face as compared to their public sector counterpart i.e. PGCIL in the bidding process.
4.5.1 Issues
4.5.1.1 Differential treatment for award of forest clearances and Section 164 authorisation Acquiring land in order to attain forest clearances is one of the most time consuming and tedious processes in executing projects. The forest clearance process is very different in the case of private players and PGCIL. Private developers are required to acquire the compensatory land for afforestation in the same state and hand it over to the Forest Department as prerequisite to getting Stage I clearance. This is in complete contrast to PGCIL which only has to pay double the afforestation compensation for getting the clearance. Clearly for private players, the process is very cumbersome and as a result, several private projects are currently stalled or extensively delayed. Similarly, for securing authorization under Section 164, PGCIL is not required to secure separate authorizations for each project whereas in the case of private players, project wise authorizations are mandatory.
4.5.1.2 Preferential Access to Confidential Information and ability to influence bidding decisions Being a part of the Empowered Committee (EC), PGCIL (as CTU) is privy to sensitive information and have the ability to influence critical bidding related decisions. Private players, on the other hand, have no representation in the Empowered Committee and hence, don't get these benefits. Being a part of the EC, PGCIL has know-how of the entire project pipeline along with preliminary cost estimates. This, in turn, helps PGCIL in its internal bid planning process. In addition, PGCIL can influence bid decisions so as to suit its commercial interests, such as: Technology selection: These include decisions on multiple technology parameters, e.g. voltage of the line, HVDC or AC, new corridor or Upgradation etc. Awarding Process: This entails deciding the process for awarding projects, e.g. project being placed in Tariff Based Competitive Bidding vs. giving on nomination basis Project Structuring: PGCIL, being a beneficiary of cost plus is also a participant in TBCB. PGCIL (as CTU) has the potential to influence decisions in its favor. These decisions pertain to project timing, project size, project prioritization, project consolidation/clubbing etc. PGCIL has the unfair advantage to align key project parameters with its ongoing projects in order to extract greater commercial benefits.
4.5.1.3 Unfair Commercial Advantages for PGCIL When bidding for projects, PGCIL, which is Central Public Sector Enterprise is entitled to various duty benefits, such as customs duty benefits of around 3%49 and other benefits. These benefits are not available to the Private Developers. In February 2012, PGCIL won two projects under TBCB regime. Industry sources & analyst reports suggest PGCIL had quoted very low unviable tariffs. However, PGCIL (as CTU) knew everything about planning & need of corridors post bid as well. This knowledge was used by PGCIL to file a petition with CERC to enable itself to withdraw from the Projects. Hence, PGCIL, which itself, had approved the projects being the planner and later as member of EC revisited the decision. This unfair practice helped PGCIL gain unlawfully from acting as CTU. Therefore, CTU being a member of EC is privy to significant amount of material non-public & cost-sensitive information in addition to having the right to influence critical decision making in the EC. Due to the non-existence of a Chinese wall between PGCIL & CTU, PGCIL is significantly benefited and private players are heavily disadvantaged.
49
Custom notification chapter 98 & 84; 12/2012 dated 17th March 2012
One of the other advantages to PGCIL being a PSU with sovereign backing is very low cost of capital which puts private sector at a substantial disadvantage. Cost of debt for PGCIL is as low as 8% while for private sector same stands at more than 12%.
4.5.2 Recommendations
4.5.2.1 Similar treatment in land acquisition for Compensatory Afforestation All Inter-State Transmission Projects, whether cost-plus or TBCB, whether executed by private players or by PSUs, are clearly central projects. Therefore, as per statute same norm of double compensation should be applicable for forest clearance. This would ensure greater enthusiasm from private players and also reduce the reluctance of financial organizations in lending to private transmission players. The relevant stakeholders for this recommendation are the MoP and MoEF. The recommendation can be implemented in next 3 to 6 months. 4.5.2.2 CTU to be made an independent body & creation of an unbiased Empowered Committee (without PGCIL representation) It is recommended to separate CTU from PGCIL and also make the Empowered Committee independent of PGCIL. This would remove the conflict of interest of PGCIL as the planner, proposer and commercial bidder. In addition, this would eliminate all unfair commercial advantages available to PGCIL by having CTU as one of its functions. The process of separating the CTU from PGCIL and removal of PGCIL's representation in the Empowered Committee would require the involvement of MoP , CEA and CTU and can be implemented in the short term.
Greater investment and active participation from the private sector is a much-needed catalyst to achieve the objective of building the grid, meeting demand requirements, and optimally utilizing generation capacity. Summary of recommendations to implemented by CEA & MoP towards achieving these objectives is reproduced below :
Area Planning Order 1 2 3 4 Technology & Innovation Qualification / Bid Document requirements Clearances & redressal mechanism Level Playing Field 5 6 7 8 9 10 11 Simplified exit norms to allow for asset churning Key clearances & authorizations to be in place before financial bid Adequate redressal for unforeseen events Identical norms & processes for granting forest clearance to public and private sector CTU to be made an independent body & creation of an unbiased Empowered Committee (without PGCIL representation) Recommendation Prune the Concept to Commissioning time to ~40 months Reduce concentration of projects with PSUs Incentivize early commissioning and speedier execution Use of High Performance Conductors in New & Existing Lines Promote technology & give freedom to developers to innovate
Annexures |6
6. Annexures Annexure I
Reference
Schedule 2, Specific requirement for Lines, point 2
Current Clause
IS Steel section of tested quality in conformity with IS 2062:2006, grade E 250 (Designated Yield Strength 250 Mpa) and/or grade 350 (Designated Yield Strength 350 Mpa) are to be used in towers, extensions, gantry structures and stub setting templates. The contractor can use other equivalent grade of structural steel angle sections and plates conforming to latest International Standards. However, use of steel grade having designated yield strength more than that of EN 10025 grade S355 JR/JO (designated yield strength 355 Mpa) is not permitted. The steel used for fabrication of towers shall be manufactured by primary steel producers only.
Suggested Changes
1) Globally accepted quality standards to be mentioned here without limiting grade to E250 to 350. Higher grades need to be allowed. 2) Yield strength of more than of EN 10025 grade S355 JR/JO (designated yield strength 355 Mpa) to be allowed. Simply because, in other countries which have much extreme weather, this steel has been used successfully. 3) Secondary steel, other than from primary steel producerswith adequate provision for controlling quality of steel, be allowed in building tower. The same is being currently used in transmission grids across North America, Europe and China. 1) Other type of towers like guyed type towers be allowed. These type of towers while having similar or higher strength affect lesser amount of land & are also lesser in weight by 15%. These towers have been successfully used world over The selection of conductors in bundled position, needs to be flexible, subject to its meeting the carr ying capacit y and performance parameters under Corona and RIV. The TSP shall give the RLDC(s), CTU/ STU, as the case may be, the Long Term Transmission Customers and any other agencies as required at least sixty (60) days advance written notice of the date on which it intends to connect an Element of the Project, which date shall be not be earlier than 6 months prior to Scheduled COD or 6 months prior to Schedule COD extended as per Article 4.4.1 of this Agreement, unless the Lead Long Term Transmission Customer otherwise agrees. In case of line getting commissioned prior to Scheduled COD, the Long Term Transmission Customers will be obliged to pay TSP monthly Tariff (equal to Levellised Tariff) for each month of early commissioning.
The Tower shall be fully galvanized using mild steel or/and high tensile steel sections. Bolts and nuts with spring washer are to be used for connection.
The conductor configuration shall be hexagonal ACSR Zebra or hexagonal AAAC (equivalent to ACSR Zebra) for [Name of Line] and Quad ACSR Moose or Quad AAAC (equivalent to ACSR Moose) for [Name of line] The TSP shall give the RLDC(s), CTU/ STU, as the case may be, the Long Term Transmission Customers and any other agencies as required at least sixty (60) days advance written notice of the date on which it intends to connect an Element of the Project, which date shall be not earlier than its Scheduled COD or Schedule COD extended as per Article 4.4.1 of this Agreement, unless the Lead Long Term Transmission Customer otherwise agrees.
Annexure II
List of 28 Lines which are severely overloaded & require immediate attention
S. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Name of Line Kawas - Ichchapur Gunadala-Nunna-1 Vijayawada T.P .S.-Nunna-1 Tadikonda-Vijayawada T.P .S.-1 Ballabhgarh-Badarpur-1 Ballabhgarh-Badarpur-2 Chinakampalli-Rajampet-1 Vijayawada T.P .S.-Narasaraopet-1 Chinakampalli-Kalikiri-1 Tarkera-Budhipadar-1 Tarkera-Budhipadar-2 Kadakola-Kaniyampet-1 Chinakampalli-Renigunta-1 Vijayawada T.P .S.-Podili-1 Btps -Jindal -I Deepalpur-Bawana Singrauli - Anpara Ballabgarh - Gurgaon Unnao-Panki-I Bhiwani(PG)-Mahindergarh HVDC Khammam -Ktps Khammam -Ktps Nellore - Almahy-I Nellore - Almahy-II Gooty - Neelamangala Gooty-Somanahalli-I Vijayawada - Nellore-I Vijayawada - Nellore-II Total Source: POSOCO -I -II Voltage Level(kV) 220 220 220 220 220 220 220 220 220 220 220 220 220 220 400 400 400 400 400 400 400 400 400 400 400 400 400 400 Line Length (Ckt. Kms.) 3 5 17 25 25 25 56 68 84 109 109 119 130 147 8 18 25 43 49 50 68 68 194 194 256 301 341 341 2,879 Coductor Type ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Snowbird ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose ACSR Moose
3.
4.
5.
6.
Mr. S.K. Bhan General Manager Projects Power Finance Corporation Limited
7.
Mr. Rajat Misra Senior Vice President SBI Capital Markets Limited
8.
Mr. Ajay Bhardwaj COO & Business Head Sterlite Grid Limited
9.
10. Mr. Vivek Pandit Senior Director & Head Energy / Defence & Aerospace FICCI
Transmission investments have not kept pace with generation in 10th and 11th plan resulting in lack of sufficient transmission capacity. India has installed capacity of 225 GW, yet we are able to meet peak demand of only 123 GW one of the key reasons being lack of transmission lines. India, sadly, has coexistence of power surplus and deficit region. Despite severe need of having robust capacity, there are certain challenges restricting quicker project delivery. More than 46% of the total investment required (in excess of Rs 2 lac crore) in 12th Plan needs to come from Private Sector. Clearly, Successful PPP in transmission would be vital to meet the enormous investment & capacit y enhancement target in transmission. The report Transmission: The Real Bottleneck , intensively dwells on the ch a l l e n g e s a c r o s s l i fe c y c l e o f Tr a n s m i s s i o n p r o j e c t b a s e d o n experiences gained so far in the sector & benchmarking against other infrastructure sectors. Further, the report makes specific recommendations to overcome these challenges.
Federation of Indian Chambers of Commerce & Industry Federation House, Tansen Marg, New Delhi 110 001 Email: [email protected] Web: www.ficci.com
Booz & Company (India) Pvt. Ltd. Level 11, Building No. 9, Tower B, DLF Cyber City Phase 3, Gurgaon, Haryana Email: [email protected] Web: www.booz.com/in