Substation Pre Commissioning Tests
Substation Pre Commissioning Tests
Substation Pre Commissioning Tests
Insulation checks will be made using a 500V Megger on each bus wire to earth and from each bus wire to all others. These checks should be carried out with all individual fuses, links, miniature Circuit Breakers, etc., open or removed at a) the source of supply and b) all incoming and outgoing circuit panels and Switchgear. www.sayedsaad.com
4- Multi-Core Cables
All multi-core cables will be tested and checked in accordance with the appropriate termination diagrams. The insulation resistance will be measured using a 1000V megger after all the multi-core cables have been connected to the erected equipment. (These tests on the multi-core cables although done at the pre-commissioning stage to sort out any obvious problems will be repeated during the acceptance testing stage). 5 - Batteries and Chargers The batteries and chargers will be checked to see that they have been erected / assembled correctly in accordance with the manufacturers recommended procedures. The tests that are carried out at this stage will be to determine that the batteries and chargers are functioning correctly, within the recommended tolerances, so that their performance can be relied upon during the commissioning of the rest of the substation equipment. The responsibility for carrying out the above will be taken by a SCE. The actual acceptance tests, including the time-consuming discharge tests, to be witnessed by the client, are carried out towards the end of the commissioning programme. www.sayedsaad.com
8- Shunt Reactor
These tests are carried out in accordance with the format of the Works Site Test Report. The tests conducted are:(1) Visual Checks. www.sayedsaad.com (2) Winding Insulation Level. (3) Oil Tests. www.sayedsaad.com (4) Oil / Winding Temperature Gauge Calibration Fan Control Sequence Test. www.sayedsaad.com
test results should be compared with those expected from the schematic diagrams. All CT's will have the dc secondary loop resistance and individual secondary winding resistances measured. The saturation tests will be carried out to prove there are no shorted turns associated with the CT and to establish the knee point voltage of the CT's The magnetization curve will be plotted for each CT or superimposed on the factory curves in order to determine that the correct CT is installed.
2. Local and Remote Indications of above 3. Electrical Interlocks of above 4. Synchronizing Sequence Tests (including secondary injection of voltage selection scheme) (iv) 5. Gas Monitoring Sequence Tests 6. Alarm Sequence Tests 7. Tripping Tests Sequence tests will be carried out to prove all electrical circuits are operating correctly as shown in the schematic diagrams. The control circuits will be tested by the manual operation of all close-trip Switches from all positions, for all Circuit Breakers, disconnecting Switches (line Switches), ground Switches (earth Switches), and other devices in accordance with the schematic diagrams. The operation of all protection circuits will be proved to be in accordance with the protective gear schematic diagrams. The tests will be conducted by manually making every main relay contact or initiating device at source and observing Circuit Breaker tripping, auxiliary relay operation, lock-out relay operation and any others. Tripping initiated by each relay in a protection scheme will be tested with the appropriate trip link in and out to prove that the link is connected and labeled correctly. The annunciator circuits will be proved to be in accordance with the schematic diagrams including alarm buzzer and/or bell, lights and any other means of alerting staff. Operation tests of the alarm circuit will be by operating, at source, each alarm initiating relay, where possible, or otherwise by simulation. Operation of each Circuit Breaker, isolator, earthing Switch or other piece of equipment will be proved to be free or locked according to the interlock condition shown on the schematic diagrams. Synchronizing Sequence Tests will be made by secondary injection of voltage at the "VT test terminals" on the, appropriate panels. Care must be taken to ensure that the VT secondary are isolated from the VT voltage circuits so that no high Voltage is developed at the VT primary circuits.
3. Vector Group Test 4. Cooling System Control Sequence Test 5. Local/Remote Tap Change Operations (Mech. and Elec.) 6. Operation of Protective Devices Load drop compensation and winding temperature CTs mounted in the trans-former should be proved to be in the correct phase and have the correct ratio where practicable. Buchholz relays: the alarm and trip initiation shall be proved by means of the test button, if provided, or by shorting the appropriate terminals at the relay. Winding temperature tripping and alarms shall be proved by operating the appropriate initiating Switches. The cooler control ON and OFF shall be proved when three phase 'A.C.' supplies are available by operating the ON/OFF Switch and the appropriate temperature indicating initiating Switches. The direction of the fan rotation must be checked in accordance with the mark. Tap-changer position indicator should be proved to indicate the correct tap position. The limit Switch must function properly to prevent the tap-changer from further movement beyond the two extreme tap positions. Tap-changing shall be tested for every step ensuring stepping relay functions correctly. Measurement of audible noise level on site will be carried out under the following conditions using a sound level meter (IEC Pub 551 type 1 or equivalent): 1. The background noise level at all measuring points shall not exceed 45dBA in accordance with ANSI standard. 2. Only the Transformer under test shall be energized and shall have been on soak for at least 24 hours prior to measurement. The tests shall be carried out at rated voltage with all normal fans running at no load conditions. 3. The audible sound level of each Transformer in turn will be measured at a number of points 30 meters from the substation. 4. The average value of the noise measurements for each Transformer shall be taken and this value checked to ensure it does not exceed 50dBA.
Previous Next
conducted are:a) Winding Insulation Level b) Ratio Test www.sayedsaad.com c) Vector Group
11 - 11kV CT Tests
The tests carried out will be: a) Insulation Test. www.sayedsaad.com b) Flick Test. www.sayedsaad.com c) Resistance Test d) Saturation Test
Where more than one CT is in each phase of a circuit, tests where practical will be carried out to prove the CT's are positioned correctly so that arranged overlap of zones of protection is correct This may be carried out by a) a visual inspection b) a continuity test. Flick tests will be done on all CT's in a group to prove that they are connected to the protection in the same polarity. These tests will also be done on CT's mounted in Transformer bushings. The flick test results should be compared with those expected from the schematic diagrams. All CT's will have the dc secondary loop resistance and individual secondary winding resistances measured. www.sayedsaad.com The saturation tests will be carried out to prove there are no shorted turns associated with the CT and to establish the knee point voltage of the CT's The magnetization curve will be plotted for each CT or superimposed on the factory curves in order to determine that the correct CT is installed.
Secondary injection tests will consist of 'a.c.' injection into the relay coils to prove that the relay calibration is correct A record of the relay type, serial number, and its setting range shall be recorded. The secondary current injection shall take place from the point at which the primary injection checks were made on the CTs. For inverse time relays, the minimum starting current for which the relay will close its contacts with a maximum time dial setting shall be recorded. The resetting time of the disc shall b_ recorded, and the time of operation for a current injection of twice, five times and ten times setting current. These results should be carried out on the relays service setting (or nominal setting if service not known). The results should be compared with the relay curve supplied by the manufacturer. Also the time setting multiplier characteristics will be checked at 2 points (setting point +1 other point). For all relays fitted with a mechanical flag, the flag should operate just before the contacts make and the flag mechanism should not interfere with the operation of the relay. The calibration of all instruments and transducers will be checked at scale and full scale by current and/or voltage injection as appropriate.
schematic diagrams. The tests will be conducted by manually making every main relay contact and observing Circuit Breaker tripping, auxiliary relay operation, lock-out relay operation and any others. Tripping initiated by each relay in a protection scheme will be tested with the appropriate trip link in and out to prove that the link is connected and labeled correctly. www.sayedsaad.com The annunciator circuits will be proved to be in accordance with the schematic diagrams including alarm buzzer and/or bell, lights and any other means of alerting staff. Operation tests of the alarm circuit will be by operating, at source, each alarm initiating relay contact, where possible,-or otherwise by simulation. Operation of each Circuit Breaker disconnect Switch and earthing Switch will be proved to be free or locked according to the interlock condition shown on the schematic diagrams. www.sayedsaad.com
Previous Next