What Every Engineer Should Know About PM
What Every Engineer Should Know About PM
What Every Engineer Should Know About PM
ENGINEER SHOULD
KNOW ABOUT
PROJECT
MANAGEMENT
WHAT EVERY ENGINEER SHOULD KNOW
A Series
Editor
William H. Middendorf
Department of Elecm'cal and Computer Enginee~ng
UnivemTSIty
of G n a n m '
Cincinnati, Ohio
Arnold M. Ruskin
Partner
Claremont Consulting Group
La Cafiada, California
W. Eugene Estes
Consulting Civil Engineer
Westlake Village, California
rn
MARCEL
Ruskin, Arnold M.
What every engineer should know about project management / Arnold
M. Ruskin, W. Eugene Estes. -- 2nd Ed., rev. and expanded.
pm cm. -- (What every engineer should know ; 33)
Includes bibliographical references and index.
ISBN 0-8247-8953-9 (acid-free paper)
1. Engineering--Management. I. Estes, W. Eugene
11. Title. 111. Series
TA190.RR7 1994 94-39689
658.4'04--dc20 CIP
The publisher offers discounts on this book when ordered in bulk quantities.
For more information, write to Special Sales/Professional Marketing at the
address below.
Neither this book nor any part may be reproduced or transmitted in any form
or by any means, electronic or mechanical, including photocopying, micro-
filming, and recording, or by any information storage and retrieval system,
without permission in writing from the publisher.
Arnold M. Ruskin
W. Eugene Estes
Preface to the First Edition
Arnold M. Ruskin
W. Eugene Estes
Contents
Introduction
1 Anatomy of a Project
I. Project Life Cycles
11. Project Boundaries, Inputs, Outputs,
and Interfaces
3 Planning Techniques
I. Why Plan?
11. Defining Tasks and Work Breakdown
Structures
111. Precedence Charts
IV. Subplans: A Checklist of Major Plan Elements
V. Estimating Techniques
VI. Scheduling Techniques
VII. Budgeting Techniques
VIII. Representating the Plan
4 Control Techniques
I. Principles of Control
11. Task Control
111. Schedule Control
IV. Cost Control
V. Early Warning Signals
5 Risk Management
I. Risk Assessment
11. Risk Reduction
111. Risk Plans
IV. Risk Control
9 Negotiating
I. Elements of Negotiating
11. Preparing for a Negotiation
111. Arrangements for Negotiating
IV. Negotiating Techniques
Epilogue
FIGURES
TABLES
A. Concept Phase
The concept phase begins with the initial notion or "gleam
in the eye" of someone who imagines accomplishing some
objective. The objective may be to provide a bridge, to de-
velop a manufacturing capability, to obtain information, to
make arrangements to accomplish some task or goal, to
build relationships to enable future actions, to win some
number of customers, to train some number of employees,
and so forth. Sometimes the objective is less specific than,
say, to provide a bridge. Perhaps the objective is stated
merely as "to provide a means for 1,500 cars to cross the
river per hour." This approach is just as valid as specifying
a bridge, and it may be more useful because it does not rule
out choices that may be better.
The only absolute restriction on defining an objective is
that one must be able to tell when it has been attained.
Generally, however, the objectives statement can be usefully
rephrased as a succinct set of individual requirements,
which will make the project more manageable. Each require-
ment in a well-formulated set has the following character-
istics, as appropriate:
1. Defines what, but not how, to the maximum extent pos-
sible, to allow the project team to select the most ap-
propriate approach
6 Chapter 1
*If only "shall" statements are used, a wordprocessor can easily find all
the requirements statements. While other forms, e.g., "must," are gram-
matically equivalent, their use opens the door to an unlimited set of alter-
natives and makes identification of all requirements statements uncertain.
"Should" statements indicate desires, not requirements. They are ac-
ceptable, for often they can be accommodated without penalty. Neverthe-
less, their fulfillment is optional with the project team and they are not the
basis for contractual obligations.
Anatomy of a Project 7
*Depending upon the situation, customer may mean (1) the client's rep-
resentative, (2) the client's own customer, (3) a group of people in the
client's organization, (4) the project manager's boss, (5) another individual
in the project manager's own organization, or (6) a group of people in the
project manager's organization.
8 Chapter 1
pensive than the first, but it may take less elapsed time to
reach the ultimate objective.
The project definition produces a plainly written, unam-
biguous description of the project in sufficient detail to sup-
port a proposal or request to the customer to undertake the
overall project. The definition should address
1. How the work will be done
2. How the project will be organized
3. Who the key personnel are
4. A tentative schedule
5. A tentative budget
The aim is to convince the customer that the doers know
what to do and are qualified to do it. At the same time, the
description should not have so much detail that the project
is essentially planned or completed even before it is autho-
rized.* Thus, the project definition phase represents a begin-
ning-to-end thinking-through of the project but does not
accomplish the project in and of itself. It is like a map of a
route rather than the route per se, and it is a coarse map at
that.
If at all possible, key personnel of the would-be project
should be involved in defining the project and preparing the
proposal. Sometimes this ideal arrangement is not possible
for legitimate reasons such as unavailability at the moment.
When key personnel are not significantly involved at this
stage, it is often worth the expense of money and time for
them to review the work of this phase and perhaps modify
E. Performance Phase
The performance, or work accomplishment, phase is the part
of the project that most people think of when they think of
a project. Basically it consists of doing the work and report-
ing the results. Doing the work includes directing and co-
ordinating other people and controlling their accomplish-
ments so that their collective efforts achieve the project's
objectives. These topics warrant entire chapters. Directing
and coordinating work is discussed in Chapters 6 and 7, and
controlling work is discussed in Chapter 4.
F. Post-Accomplishment Phase
It is commonly believed that completing the last task in the
performance or work accomplishment phase concludes the
project, but there is yet a final phase called a post-accom-
plishment phase. This phase consists of
1. Confirming that the customer is satisfied with the work
and performing any small adjustments and answering
any questions necessary to achieve satisfaction
Anatomy of a Project 13
G. Phase-to-Phase Relationships
While Figure 1.1 and the preceding discussion tend to make
the interphase boundaries distinct, the successive phases
often overlap in time. As the project is defined, for example,
second thoughts about the concept may arise, leading to its
revision. Thus, the concept phase is extended so that it over-
laps the project definition phase. Such overlaps are shown
in Figure 1.2.
In addition to phases overlapping, it is likely that some
iteration among, say, the plan validation phase, the concept
phase, and the project definition and planning phases will
occur. Certainly there are cases where the results of plan
validation have caused the entire project to be revamped.
B. Project Inputs
The information, materials, and resources that flow into a
project are called inputs and significantly influence how the
project will be conducted. These items are discussed in this
section.
1. Scope of Work
A scope of work is a statement of project objectives and ma-
jor constraints, including schedule and budget. Sometimes it
is quite detailed; other times it is so poorly stated that the
project cannot proceed until it is refined. In any event, the
scope of work is a major input to the project.
A scope of work may originate with the customer or it
may originate with the organization that will perform the
project. The latter may seem strange, but often the would-
be customer asks a would-be project organization to propose
a project. Although the project organization may have pro-
posed the scope of work to the customer originally, it is only
a proposal at this early stage. When it comes back as a con-
tract, i t is really the customer's. No project manager should
think that the scope of work can be changed without obtain-
16 Chapter 1
2. The Marketer
Some project organizations are part of larger entities that
have marketers who call regularly on their customers. Such
people can be invaluable sources of information about po-
litical and fiscal climates in customer organizations. Project
managers should communicate regularly with their market-
ers in order to keep abreast of changes in customer feelings
long before they surface formally in change orders or sus-
pensions.
3. Contract Terms
Contract terms are also project inputs. They may be either
innocuous or consequential, depending upon how well they
describe how the project must proceed and the mutual re-
sponsibilities of the customer and project organization. Of-
ten they are written in a standard format by the customer
and applied indiscriminately. Sometimes standard terms are
unfair or unsatisfactory to the project organization because
of the project's nature. In these cases, they should be revised
or removed through negotiation before the contract is signed.
Also, certain projects need contract terms that are nonstand-
ard and that will appear in the contract only if the project
manager sees that they do. Project managers should study
Anatomy of a Project 17
4. organization Policies
Organization policies are important inputs in most projects
because they guide the way work is performed. For ex-
ample, they may mandate certain types of reviews and ap-
provals before work proceeds from one stage to the next.
They may specify how subcontracts are handled; how sup-
port services, e.g., typing and accounting, are provided;
how personnel are assigned; and how all-important client
contacts or other relationships are maintained. Sometimes
they are written down; often they are not. They are never-
theless important influences on project managers' behavior,
and they need to know how to succeed in their presence.
Anatomy of a Project
5. Project Personnel
Among the most important inputs for project managers are
the personnel who are assigned to their projects. They bring
technical knowledge and skills, interests, aptitudes, and tem-
peraments. Most projects need a mix of these characteristics,
as described in Chapter 6. The project manager should try
first to identify the kinds of talents needed and then to se-
cure them, not just tell the personnel department that the
project needs two X-ologists, one Y-ologist, and four Z-
ologists.
6. Material Resources
Material resources comprise the facilities and equipment that
can or must be applied to the project. Often they limit how
the project can be achieved. Or, if they have unusual capa-
bilities or versatility, they may enable particularly effective
or efficient approaches which are not always used. In either
case, project managers should understand how the material
resources available to them are likely to affect or facilitate
their projects. They should be identified as to
a. What the customer shall furnish
b. What can be obtained from within the project manager's
own organization
c. What shall have to be obtained elsewhere, including
likely sources
7. Information
Available information is a project input and influences how
a project is planned and executed. Information may be tech-
nical, economic, political, sociological, environmental, and
so forth. It can come from other members of the organiza-
tion, from customers, from subcontractors and vendors,
from third parties such as governmental agencies, and of
course from both open and restricted literature.
The quality and quantity of information which the
project organization obtains) either on its own initiative or
24 Chapter 1
2. Internal Information
Internal information consists of the increased knowledge
base that the project staff generate as a result of doing the
project. This information can be invaluable to the organiza-
tion in a future project, whether for the existing customer
or another customer. Above all else, it includes the actual
durations and resource costs of the individual pieces of the
project, which can be used in estimating durations and costs
on future projects. Internal information may also be about
the customer, about subcontractors, about production con-
ditions, and about the environment as well as about the
project itself. The information may be in the form of memo-
randa, report drafts, project instructions, project standards,
check prints, and so forth.
Since the project is not required to deliver such internal
information, it is often neglected. Astute project managers,
however, will retain such information whenever they can in
order to build their knowledge base for future assignments.
3. Experienced Personnel
A major output of every project is experienced personnel.
Whether the experience is in fact beneficial or harmful de-
pends of course on how well the project is conducted. If it
is conducted satisfactorily or even outstandingly, project
staff will grow and develop and generally enjoy their expe-
rience. They will be both more skillful and willing to work
with the project manager in the future, which is a plus for
the project manager. On the other hand, if the project is con-
ducted poorly, project staff will probably not enjoy their
experience even if they do grow and develop. The odds in
such circumstances are that the staff will prefer not to work
with the project manager if they can avoid it, which limits
the manager's options, if not his or her effectiveness, in the
future.
26 Chapter 1
4. Working Relationships
Another project output is the set of working relationships
that the project manager develops with other internal depart-
ments a n d with external organizations. Like the quality of
the project staffs experience, these relationships may be ei-
ther positive or negative and they will bode either well or
ill for the future. Project managers should take care to de-
28 Chapter 1
D. Project Interfaces
A typical project has literally dozens of interfaces across
which information and deliverables flow. These interfaces
are with various departments and offices in the project's
own organization, various functional elements in the client's
organization, different elements in subcontractor and ven-
dor organizations, and third parties, such as regulatory agen-
cies, auditors, and so forth.
A major duty of every project manager is to ensure that
all project interfaces function so that necessary information
and materials are properly transmitted. The first step in
managing these many interfaces is simply to list them and
to assign each one to a project staff member who will keep
it functioning. To help in this regard, Table 1.1 lists repre-
sentative interfaces for reference.
The next step is for all project staff members to estab-
lish face-to-face or telephone contacts with their interface
counterparts and to make their existence known. They
should exchange (or at least begin to exchange) information
with each of them on their respective needs, wants, and
expectations. Each staff member should report back to the
project manager the agreements that they and their counter-
parts have made about the nature, form, and frequency of
their future exchanges. The work implied by these future ex-
changes should then be factored into their project plans,
which are discussed in Chapter 3.
As information and deliverables begin to flow across the
interfaces, the interface-keepers should verify that they are
serving their intended purposes. This responsibility may
require some deliberate follow-up activity, for recipients
may not report whether the items satisfy their needs and ex-
pectations and whether additional work or information
would be helpful.
Roles and Responsibilities
of the Project Manager
A project does not run itself. Someone must direct and con-
trol it, and that someone is the project manager. The project
manager is responsible for directing and controlling all the
day-to-day activities that are necessary to accomplish the
project.
This responsibility does not mean that project managers
cannot delegate the direction or control of specific activities
to others. On the contrary, they may indeed delegate, but
the responsibility for the direction and control is still theirs.
If the delegates do not perform adequately, the project man-
agers are responsible for the inadequate outcomes and for
repairing any damage done.
Good project managers arrange matters so that their
teams avoid troubles and have appropriate back-up plans
and resources for risky situations. By their foresight, their
projects run more or less smoothly. The more successful they
are in this regard, the less likely anyone 'will be aware of
their effectiveness. As a result, they may not be fully
32 Chapter 2
I. WHY PLAN?
+
AACS Technical Administrative
I documentation reports
&,
Design
I
Operations Contract
.
Progress
I
Figure 3.1. The beginning of a work breakdown structure for a spacecraft attitude and articulation
control subsystem's project products.
Animde and Articulation
Control Subsystem (AACS)
I
I
I I
posa'brl
I
Motion Propulsion MCS AACS Power Remote Gmund BBnrh
finder d e l e element bus flight eonverier input- support lest
cornpuler units ougul equip- equip-
. I I I ,--l-
Sun Stellar Inertial Acoeler- Reactii Engine Propulsion 1
sensor reference reference ometer wheel gimbal vatve I 1
assembly unit unit assembly actuator drive L---_I
assembly assembly electronics
Figure 3.2. A portion of a work breakdown structure for a spacecraft attitude and articulation con-
trol subsystem.
48 Chapter 3
Figure 3.3a. The planning segment of a precedence chart for the development of a spacecraft attitude
and articulation control subsystem.
5'
In
I
m
0
5
2.
n
C
m
V)
@
inkial
liin Of RS*
sources @
supplemenl
list of Rs
sources _- Collecl Rs
8 'shoulds'
conflicting Rs
8 'shoulds'
Gattmr
as necessary
Dummy activii
------------ +
* Requiremenls are abbreviated as 'Rs' (Zem Moon aand duratii)
Figure 3.3b. The requirements segment of a precedence chart for the development of a
spacecraft attitude and articulation control subsystem.
/ Place long-
' lead orders
,
Develop ,
,
validation Legend:
pbn
Real atiiity
b
- -----------*
Dinnmy a t i i
.... M were identified in the preferred oplion and are shown in Figure 3.2
Subproducts # I . 2.3, (Zem effort and duralion)
Figure 3 . 3 ~ . The design segment of a precedence chart for the development of a spacecraft attitude and
articulation control subsystem.
0
Review and refine subpmduct Plan subproduct development Implement subproduct (per Figure 3 . 3 ~32-45;
. 5
@ Rs* (per Figure 3.3b. 1432) @ (per Flgure 3.3a. 2-19) Rgure 3.3e. 49-63: and Figure 3.3f. 64-72) z.
/ (D
/ rn
/
/
/
Negotiate interfaces /
/ implementalbnwith /
/
/ sibling subpmducts /
@
Legend:
Real actMty
*
* Requirements are abbreviated "Rs"
Dummy aclivity
------------ +
Figure 3.3d. The sub-subsystem implementation segment of a precedence chart for the de-
velopment of a spacecraft attitude and articulation control subsystem.
Receive
Receive
subproducl W2
\ condua
\
Review and adiust Condud Integrate inlegration
integration plai \\ integration and and Deliver
and verification readmess verify verificalion product for
requiremenls Develop verification capabilily review Fix flaws validation
63 Nvetop
/
lacilly
' /
/ Reverify
evel lap ,
inlegralim
tooling
@ Legend:
Real a t i i l y
t
Dummy a d i
------------+
(Zero efforl and ducalion)
Figure 3.3e. The integration segment of a precedence chart for the development of a spacecraft atti-
tude and articulation control subsystem.
. -9
Review and adjwl
\
Receive integraled
produd for validation
Perfcfm validation
exercises and Analyze dala and
Conduct
validation
Deliver
product to
validation plan Deve!q validation equipment acquire data prepare report review
-- customer
0 I
I 0
I
1
I
1
@ Legend:
Real adivily --
Dummy dvily
------------ t
(Zero effort and duration)
Figure 3.3f. The validation segment of a precedence chart for the development of a spacecraft attitude
and articulation control subsystem.
60 Chapter 3
deed the central part of any plan, but it is seldom the whole
plan. The entire list of subplans is
1. Performance or accomplishment plans
2. Staffing plans
3. Quality control plans
4. Equipment and material plans
5. Work authorization plans
6. Cost control plans
7. Schedule control plans
8. Reporting plans
9. Risk plans
Subplans 2 through 9 are discussed in turn. All subplans that
apply should be included in the project plan.
A. Staffing Plans
The staffing plan tells who will be responsible for each part
of the WBS. This plan is easily represented by attaching a
personal name to each element in the WBS, thereby creat-
ing the basic project organization chart. Basic charts may be
augmented to include staff positions for selected basic po-
sitions, for example, an administrator or secretary as staff
to the project manager.
The project organization chart shows reporting relation-
ships for the project and should not be confused with the
company's or department's organization chart. Also, the
project organization chart is not a status chart. Thus a se-
nior individual who is responsible for a detailed portion of
the project may report on the project to a junior person who
integrates the senior person's work with the work of others.
Nor is the project organization chart a device for aggre-
gating the work to be done by individuals. Thus, the chart
should not gather together different responsibilities for a
single individual in order to have the individual's name
appear just once on the chart. To do so would obliterate the
project's hierarchical relationships, which are exactly what
it is intended to show.
62 Chapter 3
G. Reporting Plans
Every project manager will want to know what is going on-
all the time. And the customer will want to know on a pe-
riodic basis. Thus every project needs a reporting plan that
identifies who reports to whom, what is reported, how of-
ten reports are made, and how widely the information is
distributed.
In order to make overall project reporting as efficient as
possible, internal reports (i.e., for those who work on the
project) should be coordinated with reports to the customer.
Information should be detailed and organized to serve mul-
tiple users without recalculation ,or reformatting whenever
possible. Since satisfying customer needs is paramount, their
reporting needs should be determined before establishing
internal reporting requirements.
As in the case of the other subplans, time and resources
must be provided for reporting in the overall project plan.
Specific reporting techniques are discussed in Chapter 8.
H. Risk Plans
To plan for risk is to consciously search out potentially im-
portant adverse occurrences and then determine how they
can be (1) accommodated as is if they should happen, (2)
first reduced and then acommodated, or (3) eliminated or
avoided altogether. Thus, risk planning goes beyond merely
having overall contingency allowances in case something
goes wrong. Rather, risk planning involves detailed consid-
eration of possible adverse occurrences and an action plan
that promises the best cost/benefit results given the re-
sources available.
Risk planning is also known as risk management and is
discussed in Chapter 5.
Planning Techniques
V. ESTIMATING TECHNIQUES
A. Top-Down Estimating
One estimating technique is called top-down estimating. In
this approach, large blocks of effort are estimated by com-
paring these blocks to those with which one has had expe-
rience. The large blocks are typically the major pieces of
work identified in the work breakdown structure. The es-
timates for the large pieces are then added together to ob-
tain estimates for the entire projec't.
The top-down approach naturally works best when the
blocks in the current project closely resemble those in ear-
lier projects and when accurate records of time and expense
exist for the earlier efforts. It works hardly at all when one
has no earlier experience to refer to. Its greatest virtues are
that it is quickly applied and that it provides for necessary
interactions, even if they are obscure.
6. Bottom-Up Estimating
An alternative to top-down estimating is the bottom-up
approach. In this technique, small tasks are estimated indi-
vidually and then summed to arrive at the total project time
and expense. The small tasks are typically the items in the
precedence chart, which is described in Section 111 of this
chapter.
68 Chapter 3
D. Historical Relationships
Other useful adjuncts to top-down and bottom-up estimat-
ing are the historical relationships that may exist among
different parts of similar projects. The efforts spent on docu-
mentation, quality control, accounting, supervision, and
other indirect functions often have rather stable ratios to the
expenses for direct labor. Similarly, the costs for piping,
instrumentation, insurance, architectural services, etc. may
have stable relationships in certain circumstances with the
costs of major pieces of equipment such as boilers, heat ex-
changers, fractionating columns, and so forth.
A special version of the concept of historical relation-
ships is the empirical fact that equipment costs typically
vary as a function of capacity or size by a power law of the
form
cost, -[capacity,
--
Cost, Capacity,
)"
where the value of n varies with economies or diseconomies
of scale. If n is 1.0, then neither economies nor diseconomies
exist. If n is greater than 1.0, then diseconomies exist, for
example, in the case of large-diameter front-surface optical
mirrors. If n is less than 1.0, then economies exist, for ex-
ample, in the case of microwave antennas that operate at a
given frequency. Values of n when it is less than 1.0 are
commonly in the range 0.6 to 0.7.
The power law is useful in extrapolating data from one
or two cases where costs are known or can be easily ob-
tained (e.g., from recent quotations or bids) to cases where
they must be estimated. It assumes, of course, that there are
neither'physical limitations to making the item being esti-
mated nor any step-function changes in the design or manu-
facturing approach between the item whose cost is known
and the item whose cost is being estimated.
70 Chapter 3
E. Simpson's Rule
The actual time or cost of a piece of work may be different
from nominal or most likely time or cost. Also, the actual
time and actual cost are unlikely to exceed some maximum
value and unlikely (or unable) to be less than some mini-
mum value. These facts give rise to an estimating technique
called Simpson's Rule, which uses nominal, minimum, and
maximum values to calculate the expected value of a param-
eter:
where
XeXp= the expected value of x
,X = the minimum possible value of x
Xn,, = the nominal or most likely value of x
X,,, = the maximum value of x
Simpson's Rule can be used to calculate expected times
and costs for each activity in the precedence chart. As de-
scribed in Section VI, the expected and nominal times for
the activities can be used together to determine the project's
overall duration, due dates for individual activities, and the
Planning Techniques 71
F. Documenting Estimates
As will be seen in Chapter 4, the estimates used to prepare
the project schedule and budget will provide the basis for
controlling the project. It pays, therefore, for the project
manager to ensure that all the assumptions surrounding the
estimates are documented. Otherwise, it will be impossible
to tell whether the schedules and budgets based on the es-
timates are still valid if actual performance does not corre-
spond to the schedules and budgets.
Also, astute project managers, and indeed astute organi-
zations, recognize the value of saving both time and cost es-
timates and actual time and cost data for future reference.
In the final analysis, no better way exists to estimate the
next project than to use data and insight developed on re-
lated or similar previous projects.
Figure 3.6. The aitical path for the precedence chart shown in Figures 3 . 3 ~
and 3.4.
Legend:
Real a c t i i
b
Dummy adivity
------------ C
(Zem effortand duratiin)
Critical path
*
Figure 3.7. A time-scaled version of the critical path shown in Figure 3.6.
80 Chapter 3
Flgure 3.9. A Gantt chart representation of the precedence chart shown in Figures 3 . 3 ~
and 3.4. Ba-
" sis: earliest possible starting times.
Control Techniques
I. PRINCIPLES OF CONTROL
Control implies
1. Expectations of what should happen
2. Measurements of what has happened
3. Comparisons between expectations and what has hap-
pened
88 Chapter 4
con, $
\Contingency cost
Note: "Nominal project cost' refers l o the estimated pmlect cost without pmvismns
for monitoring or conlingency.
Cost. 0
Note: 'Nominal project cost" refers to the estimated project cost without provisions
for monitoring or contingency.
B. Quality lnspectlons
Inspections of work quality are an important aspect of task
control and go hand in hand with detailed functional objec-
tives. Each work increment, no matter how simple, needs
to be checked at some level to assure that it is satisfactory.
Project managers dare not find that a trivial item, such as
late delivery, wrong specifications, inadequate access, incor-
rect size, faulty instrument, lack of suitable personnel, and
so forth, is precluding a successful project. And, certainly,
no major task can go unchecked. Thus, project managers
must arrange for timely and appropriate reviews or inspec-
tions to confirm either that the work is being done accord-
ing to plan or that a deficiency exists that must either be
corrected or accommodated by changing the plan.
C. Work Orders
Another element in task control is the use of work orders
to authorize work increments or packages. By using work
orders, the project manager can force personnel working on
related parts of the project to coordinate their efforts: they
may not proceed until authorized and the authorization will
be given only when the project manager is satisfied that
their interactions are properly reflected in their respective
efforts. This approach minimizes the chance of having to
redo a portion of the work because of overlooking interac-
tions of related activities.
Work orders also preserve flexibility for major revisions
which may be necessary if contingency allowances are fully
Chapter 4
C. Impossible Schedules
Project managers should not agree to schedules they know
are impossible to meet. If, however, they agree to schedules
which they originally thought possible to meet but later dis-
cover are not possible, then they need to renegotiate their
commitments or schedules as soon as they detect the diffi-
96 Chapter 4
A. Budgets
1. Direct Labor Budgets
Expenditures for direct labor occur in relatively small units,
perhaps as small as a fraction of an hour, and may be
spread over a large number of people who are directly or
indirectly responsible to the project manager. The expendi-
tures are typically not coordinated at the level where they
are incurred, so the project manager must establish indi-
vidual budgets for the various work elements in order to be
sure that their total does not exceed the total budget avail-
able for this work. Otherwise, minor overages for each in-
dividual element will accumulate to a major overage for the
project manager, one that exceeds any reasonable contin-
gency allowance that might exist.
B. Expenditure Reports
Once budgets have been suitably prepared for the various
components of the project, expenditures should be reported
against them periodically. In the case of purchased services,
materials, and equipment, the figures reported should be
funds committed rather than invoices received. To wait for
an invoice is to harbor a false impression about how much
money is left to accomplish the remaining work.
C. Expenditure Audits
Expenditures should be audited to verify (1) that they re-
fer to legitimate charges to the project and (2) that the work
to which they refer was in fact done. Strange as it may
seem, project budgets are occasionally charged for work that
should have been charged to another project and for work
which is yet to be done. The first type of false charge may
be simply an error. Both types could be the result of chica-
nery on the part of an unscrupulous staff member. A project
manager cannot afford to have the project budget pilfered
by either type of false charge. Expenditure auditing will help
curb these abuses.
E. Overspending
When cumulative expenditures exceed the upper danger
line, the project manager may have a serious problem to re-
solve: A significant portion of the contingency allowance
may be depleted before the project is finished. This requires
the project manager to reprogram the remainder of the
project in order to conclude it without overrunning the to-
tal budget.
F. Underspending
So far, one might have assumed that an excess of cumula-
tive expenditures over budget is more serious than a defi-
ciency. However, a deficiency, especially in the early or
middle phases of a project, can indicate significant trouble:
if the budget is not being spent, then some work is prob-
ably not being done. Not only does this endanger comple-
tion of the project on time, but it also threatens the budget
because a compressed work schedule almost always entails
inefficiencies and increased costs.
A. Periodic Assessments
Three straightforward project metrics are
1. The ratio of (a) the percent of the schedule and budget-
ary contingency allowances remaining to (b) the percent
of project or project segment remaining versus time
2. The ratio of (a) the cumulative number of substantially
equal-sized work packages scheduled for completion by
104 Chapter 4
B. Reviews
Reviews are typically held at critical junctures in the course
of a project, for example, upon conclusion of requirements
definition, upon conclusion of preliminary design, and so
106 Chapter 4
*The insurance industry uses the term risk management to mean pooling
or sharing risks so that one entity does not bear the full consequences of
specified adverse events. We are not addressing this use of the term here.
Later, however, we refer to transferring risk from one person or entity
to another, which is the essence of insurance.
109
110 Chapter 5
I. RISK ASSESSMENT
A. Uncertainty Reduction
Reducing a risk's uncertainty may have either of two effects.
It may convert the risk to a certainty, to be dealt with ac-
cordingly. Or, it may merely reduce the probability of an
adverse outcome.
Uncertainty may be reduced by the following methods:
1. Prototyping, simulating, and modeling. These three meth-
ods share the notion of using a representation to inves-
tigate selected aspects of requirements, a design, or a
plan in order to be more certain about their suitability.
Ii prototype is a mock-up or representation of (only)
the areas of investigation in order to test its acceptance,
for example, a colored, scaled drawing of a proposed
comlputer display. A simulation is an imitation of the
functioning or behavior of one system by means of the
functioning or behavior of another, for example, a com-
puter or algorithmic simulation of a complex industrial
process. A model is a miniature representation of physi-
cal relationships, for example, a scale model of complex
piping to test spatial relationships.
2. Planning in detail. Detailed planning means detailed es-
timating, budgeting, and scheduling, including resource
schetluling, so that it will be clearer in advance whether
or not the project can be accomplished as contemplated
overall.
3. Parallel alternative developments. A parallel alternative
development is essentially a concurrent backup. How-
ever, unlike a backup that is pursued only after an ad-
verse outcome has occurred and whose cost might be
avoided, a parallel development represents costs that will
necessarily be incurred. It can be worthwhile, though,
especially when time is more important than cost.
This reduction in uncertainty is really a reduction in
the likelihood of failure. The combined or joint probabil-
ity of all alternatives failing is the product of the indi-
vidual alternatives' likelihood of failure. Thus, since each
Risk Management 113
B. Consequence Reduction
A risk's consequences can be reduced by the following meth-
ods:
1. Decoupling related items. Decoupling refers to removing
dependencies. For example, if one person is to work on
two tasks in series, then lateness in completing the first
task can cause lateness in completing the second task. If
the assignments are decoupled and each task is assigned
to a different person, then lateness in completing the first
task does not ips0 facto cause lateness in completing the
second.
Decoupling can often be used to reduce risk conse-
quences when resources are scheduled, when information
or technology are shared, and when two items are de-
rived from a common process.
114 Chapter 5
C. Risk Avoidance
Some risks can be avoided by reducing requirements or de-
fining them more completely, increasing the budget, or ex-
tending the schedule. Budget increases and schedule exten-
sions may not be available overall, but they can sometimes
become available locally by changing scope elsewhere in the
project or by accomplishing preceding or succeeding tasks in
less time. Adjusting preceding and succeeding tasks may
require more resources, more intensive use of resources,
reductions in requirements, or a combination.
D. Risk Transfer
A risk can s0metim.e~be reduced for the element at hand
by transferring it to another entity that can better bear it.
Two methods of transferring risk are the use of insurance
and the alignment of responsibility and authority.
116 Chapter 5
A risk plan shows what risks will be reduced, and how, for
given total levels of expenditure. The plan starts with risks
Risk Management 117
B. Risk Reassessment
When a project element's ratio of percentage of margin or
reserve consumed to percentage of work successfully accom-
118 Chapter 5
(Assertive-Nurturing) $&
b.3~
3"
Analytic-
Autonomizing
Analytic-
Autonomizing
enjoy each other and work well together (unless they are
competing with each other). However, a team's strength
comes from having all perceiving and judging preferences
present at least to some degree. Thus, the project team is
better off with some overlap of preferences as well as some
differences. While two people, one sensing-feeling and one
intuitive-thinking, for example, have all the perceiving and
judging traits together, they have little in common. An in-
tuitive-feeling person and a sensing-thinking person are also
needed if the group is have much harmony and succeed in
its work.
138 Chapter 6
Process orientation
Organizing Systematic
Procedures Step-by-step
Planning Logical
Facts Factual
Controlling Verbose
Analysis Unemotional
Trying out Cautious
Testing
Observations
Proof
Details
People orienfation
Self-development Subjective
Feelings Emotional
Awareness Perceptive
Sensitivity Sensitive
(continued)
Coordinatlng and Directing Techniques, Part I
I. COMMUNICATION
11. CRITICISM
B. Meeting Process
Meeting process refers to the way the participants behave and
interact at the meeting. A meeting's objectives are not met
simply because the attendees assemble in a room. Rather,
certain activities must occur, such as initiating the discus-
sion, obtaining information, and achieving agreement, if
there is to be any progress toward the goal.
Key process activities are
1. Initiating. The chair is responsible for starting the meet-
ing and initiating discussion, but all of the participants
can raise issues or introduce new topics when appropri-
ate, and they should raise important items that are be-
ing overlooked.
2. Information and opinion providing. All meeting partici-
pants have a responsibility to share relevant informa-
tion and opinions, whether or not they have been di-
rectly asked. After all, they were invited to the meeting
for the contribution they can make toward its goals.
152 Chapter 7
1. Agendas
In simple terms, an agenda is a list of things to be done.
Often printed agendas, especially those distributed publicly,
Coordinating and Directing Techniques, Part II 157
2. Minutes
Minutes, that is, a record of the important aspects of a meet-
ing, should be made of every meeting. Their form and for-
mality may vary, depending on the circumstances.
All minutes should include the following information:
1. The time and place of the meeting
2. The attendees, including part-time attendees and guests
3. A copy of the agenda (as an attachment)
4. A brief preamble on the purpose of the meeting
5. Notes on issues discussed, including concerns, assump-
tions, decisions made, and open issues
6. Action assignments (see Section 1II.B)
7. When and where the next meeting will be, if known
If formal minutes are called for, they should be orga-
nized, edited for clarity and accuracy, typed, and distributed
within a few days of the meeting. The attendees should re-
ceive the minutes while their memories are still fresh. This
will enable them to review the minutes meaningfully and
identify any errors of omission or commission. If minutes
158 Chapter 7
A. Purposes of Conversations
Conversations are two-way exchanges and are best used
where it is important to know how well one is communi-
cating while proceeding or where one of the parties needs
some response before proceeding. Thus, conversations can
be effectively used for the following purposes:
1. To give information and instructions
2. To obtain information
3. To coach
4. To seek cooperation
5. To keep in touch
Information and instructions can be given by written
communication, as discussed below, but there are times
when a conversation is better. Whenever the information or
instruction is subject to partial or alternative interpretation,
depending on the background and understanding of the re-
cipient, it is helpful to communicate orally. This way, the
sender can check periodically to verify that the receiver has
grasped the information or instructions as they were in-
tended. The sender can observe vocals and nonvocals as well
as ask the receiver to paraphrase to ascertain understanding.
Once understanding has been achieved, it can be confirmed
in writing for the record if necessary.
Likewise, information can sometimes be obtained most
readily through a conversation. This is particularly true
where the request is subject to being misinterpreted or
where the scope needs to be developed by the requester and
the responder together before the request can be addressed.
160 Chapter 7
V. WRITTEN COMMUNICATIONS
B. Style
Style is an important aspect of effective writing. The ulti-
mate measure of style is whether or not it helps the reader
understand the writer's message. Styles that detract from
understanding are bad and styles that help are good. Thus,
the preferred style depends partly on the readers and their
ability to understand from the style used. Nevertheless, a
general axiom or two will serve all writers well.
Perhaps the most important advice is to put first things
first. The subject and its importance to the readers should
be stated at the outset. Project personnel are busy and will
not wade through a memorandum or letter to determine if
Coordinatlng and Directing Techniques, Part II 165
*Suggesting that the most important material be placed first assumes that
all potential readers have similar priorities. If they do not, then they may
need different versions or at least a guide in the introduction to tell them
where they will find what most interests them.
166 Chapter 7
A. Matrix Structures
The essential structural feature of a matrix organization is
that some people have two or more bosses or project cus-
tomers. People with more than one boss are called
multibossed individuals, and their bosses and customers are
called multiple bosses. Somewhere in the organizational hi-
erarchy above the multiple bosses is a common boss, who
resolves conflicts between multiple bosses when the latter
Coordinatlng and Directing Techniques, Part II 171
Common
Boss
. Common
Boso-
Depenment
Manaoer
~ultibossed
Individual
Division
Vice President
Section
Manager.1
Multibossed Mullibossed
Group Gmup
Supervisor-t Supewlsor-2
I. PROJECT RECORDS
A. Organization
Project records originate throughout the project, but they
should be organized and maintained as if they formed a
single collection or database. This does not mean that they
must be kept in a single location. As desirable as this might
be, it is not always possible, especially in cases of very large
projects or projects that involve different organizations that
manage their own information. In these situations, the col-
lection or database may be physically dispersed provided it
is treated as a virtual single entity. Importantly, only one
official copy of information should exist. All other versions
184 Chapter 8
6. Contents
Project records should contain at least the following infor-
mation:
1. Table of contents, with a guide to their locations
2. Current version of the statement of work or product
specification
3. Previous versions of the statement of work or product
specification
4. Documentation of assumptions and their rationales
5. Correspondence and notes regarding agreements and
understandings with functional managers
6. Correspondence and notes regarding interactions with
the customer
7. Correspondence and notes regarding interactions with
project staff
8. Meeting agendas and minutes
9. Action item lists
10. Current resource budgets and schedules and backup
materials, e-g., estimates, calculations, quotations, etc.
11. Previous resource budgets
- and schedules and backup
materials
12. Progress and status reports
13. Milestone review presentation materials, action item
materials, and summary reports
14. Change proposals, impact appraisals, and decisions
15. Reports
Project Records and Reports
B. Reporting Mechanisms
Six ways a project can report its work are:
1. Formal written reports
2. Informal reports and letters
3. Presentations
4. Guided tours
5. Informal meetings
6. Conversations
3. Presentations
A presentation is, in effect, the oral equivalent of a formal
written report. It is more than just a meeting to discuss
project status, although such a discussion may follow the
presentation (see Section II.B.5). The purpose of a presen-
tation is to take advantage of face-to-face interactions (Chap-
ter 7) while transmitting the significant aspects of a major
work unit.
The virtues of a presentation are:
1. An astute presenter can adjust his or her delivery while
proceeding in order to reach the audience appropriately.
2. Because a presentation is "live" and not "frozen" as is a
written report, it provides an opportunity to try out al-
ternative ways of conveying information and ideas.
3. The captive nature of an audience at a presentation may
result in some people paying attention to the project who
would otherwise not do so.
4. A presentation affords an opportunity for many differ-
ent people to discuss a project who otherwise would not
be current on its status and take the time to do so.
5. An audience may understand information to be con-
veyed by a graph, table, or chart better when it is pre-
sented than when it is written.
Liabilities of a presentation are:
1. The presenter must be able to retain poise when ques-
tioned by members of the audience.
2. If the presenter is not expert in all facets of the work
being reported, it may be necessary to have several ex-
perts attend the presentation.
190 Chapter 8
4. Guided Tours
A guided tour refers to taking customers to the project site
in order to familiarize them with the work. Sometimes there
is no good substitute for a first hand examination of the
project situation. Yet many a customer has never visited its
project site. Accordingly, such a customer has little appre-
ciation of the project manager's situation. In these cases, the
project manager will do both the project and the customer
a favor by organizing a site visit.
Virtues of site visits or guided tours are:
1. They develop insight on the part of the customers which
may be difficult if not impossible to develop any other
way.
2. They tend to be informal, which makes it easier for the
participants to get to know each other and thereby de-
velop trust.
3. They tend to be absorbing, which means that the custom-
ers' attention will less likely be divided.
4. They tend to take a fair amount of time, which provides
multiple opportunities to communicate.
Project Records end Reports
5. Informal Meetings
Informal meetings are often the most productive way to
report to a customer. While overall they may not satisfy
contractual stipulations, they are more likely to produce a
two-way report, that is, from the customer as well as to the
customer. As mentioned in Chapter 2, information from the
customer constitutes a vital input for the project manager.
Informal meetings may either follow a presentation or be
held separately. Their virtues are:
1. They are in fact informal, so that the formalities that
accompany a presentation are usually missing. This en-
ables the attendees to use their time to good advantage
if they practice good meeting principles (Chapter 7).
2. The participants may be but a subset of those who might
attend a presentation, so that the discussion can be lim-
ited to the needs of a limited group.
3. They generally provide a more inviting atmosphere than
a presentation, so all the attendees feel able to partici-
pate, not just a few key people.
192 Chapter 8
6. Conversations
Conversations have the same advantages in reporting to the
customer that they have within the project organization
(Chapter 7). They are, however, hardly ever recognized as
an official vehicle for the project to report to its customer.
They are simply too casual to satisfy interorganizational re-
sponsibilities. This does not mean that they cannot or should
not be used.
Rather, conversations should be used between the project
and its customer to establish understandings. Once these
understandings have been reached, they should be con-
firmed by an informal report or a letter (see Section II.B.2).
Project Records and Reports 193
E. Obtaining Feedback
It pays project managers to obtain feedback from those who
receive their reports and presentations. Feedback enables
project managers to determine if their materials were under-
stood and provides an opportunity to correct misunderstand-
ings if they are detected. Feedback often includes informa-
tion that is helpful for future action and enhances project
managers' abilities to satisfy their customers. And request-
ing feedback helps project managers show that they care
whether or not their audiences understand.
Feedback can be obtained by interviewing, by question-
naire, or both. If interviews are used, the project manager
can talk with members of the audience "cold or can tell
them that he or she will phone or visit at a particular time
to discuss their reaction to the report. The latter may also
defuse any tendency that members of the audience may
have to send an angry letter.
A questionnaire enables the project manager to reach a
larger audience, but it requires very careful preparation if
it is to elicit useful information and also not offend the re-
spondents. In fact, most questionnaires need to be "dry
run," perhaps several times, to make them unambiguous,
efficient, and helpful. They are generally used therefore
when so many people must be surveyed that the cost of
preparing a suitable questionnaire is less than the cost that
would be incurred if the same people were to be inter-
viewed.
When a questionnaire is in order, it may also be supple-
mented by interviews of selected individuals to learn about
their special reactions and needs. These individuals may be
people who have a special relationship to the project or
people who raise special points in their replies to the ques-
tionnaire. The latter, of course, may be detected only if the
questionnaire solicits comments in addition to asking the
respondents to choose from predetermined answers.
198 Chapter 8
I. ELEMENTS OF NEGOTIATING
A. Cooperation
Negotiating is a cooperative enterprise in which two people
or parties search for an arrangement that leaves both of
them better off than they were when they started. Essen-
tially, each party makes concessions in such a way that the
concessions that it receives are worth more to it than the
concessions it gives up. The aim is to find a win-win ar-
rangement and to avoid win-lose arrangements. Searching
for a win-win arrangement indeed requires cooperation, and
negotiating is thus a cooperative, not a competitive process.
D. Common Interests
Negotiating involves seeking common interests. The two
parties need to identify together what each wants and what
each can give up. It is best if such information is traded in
small amounts; this approach helps keep a cooperative spirit
going until agreement is reached. Also, trading information
in small amounts helps each party avoid offering a substan-
tial concession without receiving a commensurate concession
in return.
E. A Behavioral Process
Negotiating involves trading information and concessions in
a somewhat formal way. It is a little like a minuet, with
each party behaving in a way that is understood by the
other. This behavior enables both parties to estimate about
how much information or concession to offer at any moment
and liow much to expect in return. Each party thus feels that
the concessions that they are exchanging approximately bal-
ance. Each is therefore willing to continue the negotiation
until both are satisfied with their overall situations.
A. Determine Objectives
The project manager should determine the objectives for the
negotiation and should know which aspects of the desired
results are absolutely essential and which are merely nice to
have.
Some assessment should also be made about the difficul-
ties to be expected in trying to obtain the various objectives.
This assessment will be useful in establishing an agenda for
the negotiation (see Section 1I.D).
them all. It merely means that the entire team should know
who is going to do each type.
Those who are not carrying an active role at the moment
should observe the other party's negotiators. The aim is to
determine from spoken remarks and from body language
who is responding favorably, neutrally, or unfavorably to
the concessions and commitments being proposed. This in-
formation can then be exchanged among the team members
during caucuses in order to devise successful strategies. Each
person of the other party should have a designated observer
from one's own team. Some team members may of course
have to observe more than one person.
A team member should also be designated as note-taker
for the team in order to capture details that may otherwise
escape recall. The note-taker needs to understand the essence
and nuances of the negotiation in order to pick u p key
points. It also helps if he or she can glean essential infor-
mation from simultaneous conversations in the event more
than one person talks at once. Observational notes and other
ideas should also be jotted down by the other team mem-
bers as they occur so that they can be referred to and dis-
cussed in caucuses.
Finally, assignment of roles includes instructing the team
members on how to behave when they are and are not the
lead negotiator at the moment. The lead negotiator needs not
only to conduct the discussion at the time, but also to be on
the lookout for signs from team members that they need to
communicate with the leader before proceeding. The leader
should not go so fast so as to preclude receiving their inputs
or force them to interrupt in order to steer the discussion
away from unattractive areas.
By the same token, the other team members need to in-
dicate when they have an input to make, first to the team
leader and then perhaps to the entire group. They might do
this by a signal of the hand or eye, or they might pass a
Negotiating 209
H. Practice
Practice is recommended before a serious negotiation for two
reasons:
1. It helps identify the difficulties that will be faced in the
negotiation so that alternative approaches can be devel-
oped and evaluated.
2. It permits the would-be negotiators to rehearse their roles
and develop some skill in exercising them.
Obviously, the more skillful and knowledgeable the nego-
tiators, the less practice they need. But even the most expe-
rienced negotiators generally profit from at least one dry
run. This allows them to heighten their awareness of the
issues and, if it is a team negotiation, to improve their co-
ordination and ability to work together.
An effective way to practice is to have personnel who
will not be part of the negotiating effort roleplay the other
party in a mock negotiation. If an experienced negotiator can
be enlisted as a critic and coach during the mock negotia-
tion, so much the better.
210 Chapter 9
B. Place
The selection of the place for a negotiation involves such
factors as freedom from interruptions; psychological advan-
tage; and access to personnel, equipment, files, and services.
The first factor is self-explanatory, but the latter two war-
rant some discussion.
Some psychological advantage generally accrues to the
party that negotiates on its own premises. For this reason,
most negotiators like to work at their own place of work or
business. Since this is true of both parties, they may choose
to favor neither party and instead hold the negotiation at a
neutral site.
There are times when the negotiator should offer to ne-
gotiate at the other party's place of work or business. For
example, if the other party would be less defensive and
more cooperative if it felt more at home, then it might pay
to offer to negotiate at its place. And if it would serve to
build goodwill by meeting at the other party's place, then
the negotiator may offer to do so. In either case, however,
a negotiator should not make such an offer if doing so
would create a serious disadvantage.
Sometimes it is helpful if a negotiator can control access
to other personnel and files during the negotiation. One may
not want to have certain experts or information readily
available if finessing the issues would give an advantage.
There are times when the other party will not pursue an
unattractive element if it is not available or will give the
benefit of the doubt if the facts cannot be easily obtained.
212 Chapter 9
C. Schedule
Schedule refers to the pacing of the negotiation. Generally,
whenever a party feels some urgency about concluding the
negotiation, it is likely to make concessions more readily
than it otherwise would. It pays therefore not to be the
party with the earlier deadline for concluding the negotia-
tion.
Sometimes a party would like very much to conclude a
negotiation by a particular date or time. However, it should
not reveal this fact. While it can indicate its hopes if asked,
it should make very clear that it is able to take as long as
necessary to work out a mutually satisfactory agreement.
Otherwise, the other, more relaxed party may stall until the
deadline approaches. As the deadline nears, the more anx-
ious party may lose patience and become unwilling to work
for what it wants. It can end up giving concessions more
easily and demanding less in return than it would if it were
not so anxious.
Even when one party does not press the other against a
deadline, the negotiation may need to be concluded
promptly for the result to be timely. When this happens,
one party (or both) may be unable to strike the bargain that
it would like to have. It should not be disappointed, how-
ever. When half a loaf is better than none, the correct com-
parison is between something and nothing, not between
something and everything.
Negotiating 213
"difficult list" and defer its consideration until after the other
issues have been resolved. Perhaps the second party will
change its mind if everything else goes well. Even if it does
not change its mind, it can wait until the issue is about to
be actively discussed to declare that it is non-negotiable.
C. Buildlng Goodwill
Goodwill facilitates the negotiating process. At some point,
one of the parties has to offer a concession in order to in-
duce the other to give one in return. There is no assurance,
however, that the offer will not be rejected. The very pros-
pect of rejection can inhibit the first party from making the
Negotiating 215
G. Securing Commitments
Both parties to a negotiation need to confirm in writing
what they have agreed to. This agreement should be done
on the spot at least session by session, if not issue by issue.
These written agreements prevent reneging on and argu-
ments about the results of earlier discussions. They thus
facilitate forward progress of the negotiation.
Negotiating
I. The Plan
Figure A.3b is a WBS of the plan. This figure shows not
only the components per se of the plan but also the staging
needed to develop the plan, using short dashed vertical lines
to separate the stages. Using a convention of time increas-
ing from left to right, the chronologic relationships at the
first level of decomposition are as follows:
a. Initial objectives and constraints is the left-most element at
the first level of decomposition and is the first element
at this level to be prepared.
I I I I I
I I I I 1
I I I
I I
I I
I I
The plan
I
Require-
menls
I
The design
I
Subsystem
1
.. Subsystem'
n
I
Integrated
system
I
VaEdaled
system
,a,
Proposal
I
Negotiated
anangernerds
Staffing
plan
Material
plan'
I
Work
aulhorization
I
Conlrd
plans
Risk
managernerd
Reporting
plan.
C MY) plan* plan*
I
Oualii Schedule Cost
mnlrol mnlrol control
plan. plan* plan*
Figure A.3b. The project plan portion of a system development project's work breakdown structure.
Work Breakdown Structure Paradigms and Processes 225
I
I
Ra *** R, Functional
I
Performance
I
.lLty"
I
Inlerlace Resource Schedule
II
Validation
RS RS Rs Rs Rs Rs Rs
I
Budgelary Other
Rs Rs
Figure A.3c. The requirements portion of a system development project's work.breakdown structure.
Work Breakdown Structure Paradigms and Processes 227
3. The Design
Figure A.3d is a WBS of the design. This figure can be best
described after briefly describing designs and the design
process.
A design has five types of information:
a. A list of the subsystems that will be integrated to form
the system
b. Statements of each subsystem's requirements
c. Statements of the interfaces between the subsystems
d. A description of how the subsystems are to be assembled
or integrated
e. A statement of the verification requirements that will be
used to confirm that the subsystems have been assembled
or integrated correctly
To arrive at this information, members of the project
team need to consider alternatives or options that appear
capable of meeting the project's requirements. Options may
include make versus buy and a single delivery versus incremen-
tal or phased deliveries as well as technical alternatives. In-
cremental deliveries are particularly useful when custom-
ers are unable to articulate requirements without seeing a
physical example.
Of the options that indeed meet the requirements, one
must be selected as preferred, i.e., superior to or at least as
good as a11 others. Selecting a preferred option requires both
The Deslgn
I
I I I
Decision
w o n option
crileria demiptions t&
Figure A.3d. The design portion of a system development project's work breakdown structure.
Work Breakdown Structure Paradigms and Processes 231
4. Subsystem i
Figure A.3e is a W B S for a typical subsystem. Each sub-
system is identified in the design, as described in the pre-
vious section. Comparison of Figures A.3a and A.3e shows
that each subsystem has the same array of WBS elements as
the system itsklf. That is, each subsystem can be treated as
a system, with its own plan, requirements, design, and so
forth. Their WBSs are the same as the corresponding WBSs
for the system except that an additional sub prefix is added
to all systems and subsystems (i.e., subsystem instead of sys-
tem, and sub-subsystem instead of subsystem).
Subsystem i
Figure A.3e. The work breakdown structure for a typical subsystem in a system development project.
Work Breakdown Structure Paradigms and Processes 233
Flgure A.3f. The integrated system portion of a system development project's work breakdown structure.
The Validated Syslem
I
I I I I I
I I I I I
Validation
I
i
Validaim
I
I
Validation Validation Validatian
I
Validation
I
I
Validation
I
I
Validation
I
I
Validation
requiremenls plan equipment facilities persmel article data reporl review
resuhs
I I
.Approach Equipmenl Facilities Slafling Schedule Budget
and method plan plan plan
deseriptinn
Figure A.39. The validated system portion of a system development project's work breakdown structure.
236 Appendix A
lima -+ lime -+
Legend:
' indcatesthat something to the left of the dashed fine
I precedes somethingto lhe rigM of the line
lime -
--- representsa dummy adMIy (no durationand no M o d )
Figure 6.1. Transformation of a work breakdown structure into a precedence chart.
Transforming a WBS into a Precedence Chart 239
The cost versus time profile of most, but not all, projects
follows an S-curve, such as the one in Figure C-1. The vari-
ous parts of the curve are identified by number and have
the following characteristics:
Stage I. Stage 1 is the start-up portion of the project, while
the project manager plans, negotiates for staff, and gen-
erally sets things up. Costs accumulate slowly during this
time unless expensive equipment is purchased.
Stage 2. Stage 2 represents a rapid expenditure of funds as
work proceeds at a fast clip. A cost control system that
cannot keep up with the expenditures at this time leaves
the project manager vulnerable to missed objectives with
inadequate resources to recoup.
Stage 3. Stage 3 corresponds to the time when most of the
work is complete and attention is devoted to report writ-
ing, tying up loose ends, etc. Expenditures are made at
a lower rate again.
Stage 4. Stage 4 (or point 4) refers to the time when all ex-
plicit commitments have been met. Expenditures to this
date should not equal the total budget because there are
Percent of Time
1. Percent Complete
Percent complete is the ratio of work done to [work done + work
to be done] expressed as a percentage. The following steps
lead to acceptably small increments for percent complete as-
sessments:
a. If we use milestones to refer to substantial pieces of
work, we can use inch-pebbles to refer to small pieces
or increments of work, with many inch-pebbles needed
to make a milestone. The inch-pebbles should all be
about the same size, regardless of the milestones to
which they pertain.
b. We can use a 0-100 rule for considering an inch-pebble
as done. An inch-pebbleis counted at 100% if it is com-
246 Appendix D
2. Earned Value
the basis for payments from the customer to the project or-
ganization.*
The following steps lead to determining acceptably sized
increments:
a. Again, we can use milestones to refer to substantial
pieces of work and inch-pebbles to refer to small pieces
or increments of work, with many inch-pebbles needed
to make a milestone. The inch-pebbles within a billing
period should all be about the same size, regardless of
the milestones to which they pertain.
b. BCWPs work best when the 0-100 rule (step 1.b) is used.
A fractional rule such as the 50-50 rule (step 1.c) is sub-
ject to abuse, e.g., by barely starting a lot of inch-pebbles
just to collect half of their BCWP.
c. If we assume inch-pebbles of a given size and have a
schedule for their accomplishment within a billing pe-
riod, we can determine two numbers: (1) the number of
inch-pebbles that should be finished within the billing
period, and (2) the number of inch-pebbles whose start
and finish dates straddle the last day of the billing pe-
riod. Call the first of these numbers C and the second D.
d. Half of D/C indicates the plus and minus error band on
BCWP or earned value; it can be expressed as a percent-
age.
1. Planning Phase
a. Is the management plan workable?
b. Are the strawman requirements and design defined
sufficiently to permit cost and schedule estimation
and project planning?
c. Are the cost and schedule estimates appropriate to
the maturity of the requirements and the design?
d. Is the design compatible with the requirements, bud-
get, and schedule?
e. Can the WBS and account structure accommodate a
suitable range of plausible designs?
f . Have arrangements been made for the participation
of all personnel who are needed to do concurrent en-
gineering?
g. Has a quality control plan been included in the over-
all plan?
249
250 Appendix E
[Communication] [Control]
Casse style, 138 expenditure, 98
face-to-face conversations, principles of, 87
28, 158 quality, 93
style, 164 schedule, 94
telephone conversations, task, 92
28, 158 techniques, 87
written, 164, 186 Conversations
Comparison of expenditures conducting, 161
against budgets, 98 with customer, 192
Comparisons, 87 face-to-face, 144, 158
Complacency, 70 preparing for, 161
Compliments, 122 purposes of, 158
Compressed work schedule, telephone, 158
102 Cooperation in negotiation,
Compromises, 219 200
Computer, use of, 81 Coordinating techniques, 119-
Concept phase, 4, 5, 7, 14 182
Conclusions about individual Copyrightable materials, 19
motivation, 139 Corrective actions, 88
Conditions, impossible, 220 Cost
Conferences, 148 control, 96
Confidence, levels of, 90-92 control plan, 65
Configuration control, 106 Cost estimates
Conflict and opposition, 126 bottom-up, 68
Conflicting objectives, 24 documenting, 71
Conflicting pressures, 219 historical relationships, 69
Consensus testing, 152 Simpson's rule, 70
Consequence reduction, 113 standard costs and times,
Contingency allowance, 8, 68
77, 80, 88, 94, 102, 114 top-down, 67
Contingency versus monitor- Costs
ing, 90, 91 allowable, 17
Contracts, 30 control of, 65, 96
changes, 17 historical relationships, 69
terms, 16 standard, 68
Control versus time profiles, 241-
budget, 96 243
cost, 96 CPM, 77, 78, 79, 81, 83
266 Index
[Requirements] [Schedules]
project, 4, 30, 44, 225-229 impossible, 95
reporting, 44 negotiating, 212
subsidiary, 44 . project, 72, 89
Reserves Schedule slippage
provision of, 114 causes; 94
monitoring, 117 preventing, 95
Resource Schedule techniques, 71
commitments, 36 scope
material, 23, 96 changes, 44, 220
Responsibility, aligning with of meetings, 150
authority, 116 of work, 10, 15, 185, 186
Reviews, 105 Security requirements, 18
Revolting developments, 32 Seeking higher authority, 215
Rewards, 200 Selecting project staff, 130
Risk Self-actualization, 201
assessment, 110 Sensing preference, 132, 134-
avoidance, 115 135
consequence estimates, 111 Sequence responses, 154
control, 117
Setting priorities, 177
item identification, 110
Sharing strong feelings, 154
managing, 82, 109
plan, 66, 116 Sibling relationship, 51, 52
reassessment, 117 Sidetracking, 156
reduction, 111 Simpson's rule, 70, 80, 82
reduction replanning, 118 Simulating, 112
transfer, 115 Slack, 74, 77, 88
versus change, 118 Slippage, schedule, 94
Robustness, 48 Staffing plan, 61
Roles and responsibilities Standard costs and times, 68
project manager's, 29 Standardization, 50
project staff, 167 Standards, 39
in negotiating, 206 Statement of work, 30, 35
Stopping work, 34
Satisfying needs, 200 Straight talk, 122
Schedule control, 94 Strokes
Schedule control plan, 65 being, 120
Schedules blurred, 121
compressed, 102 conditional, 120
Index 273
[Strokes]
crooked, 121 earliest possible starting,
doing, 120 72, 74
negative, 121 estimates, 73, 75
nonstrokes, 121 keeping, 153
positive, 120 latest permissible comple-
unconditional, 120 tion, 72, 74, 77
Subcontracts, 18 latest permissible starting,
Subdividing tasks, 95 72, 74
Subdividing the project, 37 -and-materials, 96
Subgrouping, 155 Times, standard, 68
Subplans, 60 Timing, good, 154
Subproducts, 45 Top-down estimates, 67
Subprojects, 8, 37 Tough negotiator, 205
self-sufficiencv, 50 Trading information, 61
Summarizing, in meetings,
153 Uncertainty reduction, 112
Suppliers, 97 Unattractive lines of pursuit,
Support services, 96
216
Surprises, 39
Unconditional strokes, 120
Underspending, 102
Task
orientation, 168 Upper management, 24
structure, 168
Techniques Validatability, 48
budgeting, 81 Validation
scheduling, 71 phase questions, 252
visual aid, 196 in a precedence chart, 73
Telephone conversations, 26, Vendor approvals, 18
158 Verbals, 145, 155
Termination Verifiability, 48
of negotiations, 200 Visual aids, 196
of projects, 21 Vocals, 143, 159
of the relationship, 31
Terms, contract, 16 Warranty requirements, 17
Thinking preference, 132, Warnings, early, 39, 94, 103
134, 136 WBS, 38, 44-47, 81, 92, 110,
Time 221-235, 237-239
earliest possible comple- Win-lose arrangement, 200
tion, 72, 74 Win-win arrangement, 200
Withdrawing, 155 Work authorization plan, 64
Work Work breakdown structure
element, 96 (WBS), 38, 44-47, 81,
increments, 92 92, 110, 221-235, 237-239
orders, 93 Working relationships, 27
packages, 104 Written communications, 164
units, 187 Written reports, 186
Work accomplishment phase,
12 Yielding, in negotiations, 203
About the Authors