Cash Flow
Cash Flow
Electrorate
Ruwanwella
Yatiyantota
Road
Mahakanda Road
Mahella Road
Humbaswalana Road
Rattagala road
Kithulgala road
Elugala road
Wilakanda Road
Newsmeyer Road
Doranuwa road
Length
(km)
2.50
1.66
2.60
2.50
3.00
2.50
2.00
3.30
2.00
st
Total
3,338,845.77
0.00
0.00
5,734,262.00
517,820.00
4,800,000.00
3,492,351.00
7,611,200.00
0.00
13,849,092.99
399,400.00
180,500.00
3,589,953.00
5,428,050.00
13,073,916.00
703,950.00
1,570,170.00
0.00
0.00
3,671,496.00
2,842,164.00
3,589,953.00
0.00
0.00
10,464,732.00
0.00
0.00
1,050,663.00 18,238,601.76
4,070,896.00
3,022,664.00
0.00 12,914,168.00
5,945,870.00
17,873,916.00
14,661,033.00
9,181,370.00
1,599,608.00 1,599,608.00
25,494,478.77
38,795,031.99
20,568,345.00
2,650,271.00
SUMMER OF CASH REQUIREMENT FOR ROAD WORKS- RUWANWELLA & YATIYANTOTA ELECTRORATES
Electrorate
Road
Length
Cash requirement for road works
th
st
(km)
16 -31 July
August
September
October
November
Deraniyagala Yatiwala Road
15km
7,005,400.00 13,453,675.00 36,303,111.00 32,380,220.00 6,273,729.00
Optional road
0.00
0.00
Mawatenna Road
11,022,140.00
Welidade road
18,027,540.00
13,453,675.00
36,303,111.00 32,380,220.00
6,273,729.00
Total
95,416,135.00
0.00
11,022,140.00
36,711,486.00
0.00
143,149,761.00
19,935,046.94
4,070,896.00
3,022,664.00
9,324,215.00
5,945,870.00
15,645,969.12
14,661,033.00
9,181,370.00
1,599,608.00
95,416,135.00
0.00
CASH REQUIREMENT FOR THE REMAINING PART OF THE ROAD PROJECT- DERANIYAGALA ELECTRORATE
Optional road
Description
Sub contractor's
payment required to
be made for essential
structure & road
concrete works before
Asphalt paving
Road concrete - sub
contractor
ABC
ABC transport
CSS1
CRS1
Asphalt
Unit
Rate
Qty
Total
Amount
Qty
Qty
August
Amount
Item
m3
Cubes
m3.km
Barrel
Barrel
tons
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
0.00
From
To
28-Jul
31-Jul
28-Jul
31-Jul
28-Jul
31-Jul
5-Aug
8-Aug
5-Aug
8-Aug
5-Aug
8-Aug
0.00
0.00
Mawatenna road
Description
Sub contractor's
payment required to
be made for essential
structure & road
concrete works before
Asphalt paving
Road concrete - sub
contractor
ABC
ABC transport
CSS1
CRS1
Asphalt
Unit
Rate
Total
Amount
Qty
Item
m3
Cubes
m3.km
Barrel
Barrel
tons
13,064.00
5,200.00
27.80
18,050.00
18,600.00
11,649.00
680
40800
18
9
400
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
Qty
August
Amount
1,200,000.00
1,200,000.00
0.00
3,536,000.00
1,134,240.00
324,900.00
167,400.00
4,659,600.00
0.00
3,536,000.00
1,134,240.00
324,900.00
167,400.00
4,659,600.00
0.00
0.00
0.00
0.00
0.00
0.00
11,022,140.00
0.00
11,022,140.00
From
To
1-Aug
5-Aug
1-Aug
5-Aug
1-Aug
5-Aug
10-Aug
13-Aug
10-Aug
13-Aug
10-Aug
13-Aug
Qty
680
40800
18
9
400
Welikade Road
Description
Sub contractor's
payment required to
be made for essential
structure & road
concrete works before
Asphalt paving
Road concrete - sub
contractor
ABC
ABC transport
CSS1
CRS1
Asphalt
Unit
Rate
Qty
Item
m3
Cubes
m3.km
Barrel
Barrel
tons
Qty
Qty
August
Amount
2,250,000.00
13,064.00
5,200.00
27.80
18,050.00
18,600.00
11,649.00
2394
143640
60
30
1406
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
Total
Amount
0.00
12,448,800.00
3,993,192.00
1,083,000.00
558,000.00
16,378,494.00
36,711,486.00
From
To
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
CASH REQUIREMENT FOR THE REMAINING PART OF THE ROAD PROJECT- DERANIYAGALA ELECTRORATE
Yatiwala road (Chainage 4-12km)
Description
Unit
Sub contractor's
payment required to
be made for essential
structure & road
concrete works before
Asphalt paving
Item
Road concrete - sub contractor
m3
ABC
Cubes
ABC transport
m3.km
CSS1
Barrel
CRS1
Barrel
Asphalt
tons
Rate
Qty
Qty
3,800,000.00
3,800,000.00
13,064.00
0.00
0.00
5,200.00
5735 29,822,000.00
440 2,288,000.00 1765
27.80 430125 11,957,475.00 33000 917,400.00 132375
18,050.00
165 2,978,250.00
0.00
33
18,600.00
83 1,543,800.00
0.00
11,649.00
3890 45,314,610.00
0.00
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
Total
Amount
95,416,135.00
From
To
26-Jul
26-Jul
26-Jul
7,005,400.00
From To
6-Aug
6-Aug
6-Aug
4-Sep
4-Sep
4-Sep
19-Oct
19-Oct
19-Oct
11-Nov
11-Nov
11-Nov
August
Amount
Qty
September
Amount
Qty
October
Amount
November
Qty
0.00
0.00
0.00
9,178,000.00
1765 9,178,000.00
1765 9,178,000.00
3,680,025.00 132375 3,680,025.00 132375 3,680,025.00
595,650.00
88 1,588,400.00
44
794,200.00
0.00
39
725,400.00
33
613,800.00 11
0.00
1814 21,131,286.00
1555 18,114,195.00 521
13,453,675.00
36,303,111.00
32,380,220.00
November
Amount
0.00
0.00
0.00
0.00
204,600.00
6,069,129.00
6,273,729.00
5735
430125
165
83
3890
0
0
95416135
CASH REQUIREMENT FOR THE REMAINING PART OF THE ROAD PROJECT- RUWANWELLA ELECTRORATE
Raththagala Road -2.5km
Description
Unit
Sub contractor's
payment required to
be made for essential
structure & road
concrete works before
Asphalt paving
Item
Road concrete - sub contractor
m3
ABC
Cubes
ABC transport
m3.km
CSS1 (for 100m)
Barrel
CRS1 (for 1030m)
Barrel
Asphalt (for 1030km) tons
Rate
Total
Amount
Qty
13,064.00
5,200.00
27.80
18,050.00
18,600.00
11,649.00
33
10
447
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
3,500,000.00
431,112.00
0.00
0.00
0.00
186,000.00
5,207,103.00
9,324,215.00
From
To
19-Aug
19-Aug
19-Aug
Qty
1st-15th August
Amount
33
3
150
16th-31st August
Qty
Amount
3,500,000.00
431,112.00
0.00
0.00
0.00
55,800.00
1,747,350.00
0.00
0.00
0.00
0.00
7 130,200.00
297 3,459,753.00
5,734,262.00
3,589,953.00
1st-15th September
Qty
1st-15th September
Amount
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.15
0.2
3.6
3.5
80
100
16
26
0.05
3.5
3.5
3.5
350
350
1030
7
3
447
2.43
15
15
31
41
447
CASH REQUIREMENT FOR THE REMAINING PART OF THE ROAD PROJECT- YATIYANTHOTA ELECTRORATE
Kithulgala Malwatta Road- 3km
Description
Sub contractor's
payment required to
be made for essential
structure & road
concrete works
before Asphalt paving
ABC for rectification
ABC transport-95km
CSS1 (for 1km)
CRS1 (for 1.05km)
Asphalt (for 1.05km)
Unit
Rate
Qty
Item
Cubes
5,200.00
m3.km
27.80
Barrel 18,050.00
Barrel 18,600.00
tons
11,649.00
20
1900
20
10
450
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
Total
Amount
0.00
104,000.00
52,820.00
361,000.00
186,000.00
5,242,050.00
5,945,870.00
From
13-Aug
13-Aug
27-Aug
27-Aug
27-Aug
To
17-Aug
17-Aug
29-Aug
29-Aug
29-Aug
1st-15th August
Qty
Amount
20
1900
20
104,000.00
52,820.00
361,000.00
0.00
0.00
517,820.00
16th-31st August
Qty Amount
10
450
0.00
0.00
0.00
186,000.00
5,242,050.00
0.00
0.00
0.00
0.00
0.00
5,428,050.00
0.00
Unit
Rate
Qty
Total
Amount
1st-15th August
Qty
Amount
Item
1,600,000.00
Cubes
5,200.00
156
811,200.00
156
m3.km
27.80 1890.4
52,553.12 3573612
Barrel 18,050.00
6
108,300.00
Barrel 18,600.00
24
446,400.00
tons
11,649.00
1084 12,627,516.00
Total
Machinery Requirement
Motor grader
10 ton roller
Water bowser
Asphalt paver
Static roller
PTR
15,645,969.12
From
To
10-Aug
10-Aug
17-Aug 22-Aug
17-Aug 22-Aug
17-Aug 22-Aug
16th-31st August
Qty Amount
1,600,000.00
1,600,000.00
1,600,000.00
0.00
24
446,400.00
0.00 1084 12,627,516.00
4,800,000.00
13,073,916.00
0.00
0.00
0.00
Unit
Sub contractor's
payment required to
be made for essential
structure & road
concrete works
before Asphalt paving
Road concretingABC (for600m)
ABC transport-60km
CSS1 (for 300m)
CRS1 (for 300m)
Asphalt (for 300m)
Item
Cubes
Cubes
m3.km
Barrel
Barrel
tons
Rate
Total
Amount
Qty
13,200.00
5,200.00
27.80
18,050.00
18,600.00
11,649.00
516
3
130
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
Galapatha -wilakanda - 2 km
800,000.00
6,811,200.00
0.00
0.00
0.00
55,800.00
1,514,370.00
9,181,370.00
From
To
30-Aug 30-Aug
30-Aug 30-Aug
30-Aug 30-Aug
1st-15th August
Qty
Amount
516.00
800,000.00
6,811,200.00
0.00
0.00
0.00
0.00
0.00
7,611,200.00
16th-31st August
Qty Amount
3
130
0.00
0.00
0.00
0.00
55,800.00
1,514,370.00
0.00
0.00
0.00
0.00
0.00
0.00
1,570,170.00
0.00
Description
Sub contractor's
payment required to
be made for essential
structure & road
concrete works
before Asphalt paving
ABC
ABC transport
CSS1
CRS1 (for 2km)
Asphalt (for 2km)
Unit
Rate
Item
Cubes
5,200.00
m3.km
27.80
Barrel 18,050.00
Barrel 18,600.00
tons
11,649.00
Qty
519 2,698,800.00
28545
793,551.00
39
703,950.00
19
353,400.00
868 10,111,332.00
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
Total
Amount
14,661,033.00
From
19-Aug
19-Aug
19-Aug
2-Sep
2-Sep
2-Sep
To
30-Aug
30-Aug
30-Aug
6-Sep
6-Sep
6-Sep
1st-15th August
Qty
Amount
519
28545
2,698,800.00
793,551.00
0.00
0.00
0.00
3,492,351.00
16th-31st August
Qty Amount
39
0.00
0.00
703,950.00
0.00
0.00
0.00
0.00
0.00
19
353,400.00
868 10,111,332.00
703,950.00
10,464,732.00
Description
Sub contractor's
payment required to
be made for essential
structure & road
concrete works
before Asphalt paving
ABC (for220m)
ABC transport -55km
CSS1 (for 220m)
CRS1 (for 220m)
Asphalt (for 220m)
Unit
Rate
Item
Cubes
5,200.00
m3.km
27.80
Barrel 18,050.00
Barrel 18,600.00
tons
11,649.00
Qty
57
3135
4
2
95
Total
Machinery Requirement
JCB
Tipper
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
From
2-Sep
2-Sep
2-Sep
2-Sep
2-Sep
21-Sep
21-Sep
21-Sep
To
14-Sep
12-Sep
14-Sep
14-Sep
14-Sep
21-Sep
21-Sep
21-Sep
Total
Amount
1st-15th August
Qty
Amount
1st-15th August
Qty Amount
16th-31st August
Qty Amount
0.00
296,400.00
87,153.00
72,200.00
37,200.00
1,106,655.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,599,608.00
0.00
0.00
0.00
1st-15th September
Qty
57
3135
4
2
95
16th-30th September
Amount
0.00
0.00
0.00
0.00
0.00
0.00
3.5
200
3.5
3.5
3.5
200
1330
1330
4
13
0
2.43
15
15
16th-30th September
Amount
0.00
0.00
0.00
3.5
3.5
2500
2500
2.43
24
0
16th-30th September
Amount
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3.5
3.5
800
800
0
0
3.5
3.5
3.5
300
300
300
6
3
0
2.43
-64
-64
-64
-64
16th-30th September
Amount
0.20
0.00
0.00
0.00
3.5
3.5
2000
2000
519
39
3.5
3.5
2000
2000
19
0
2.43
519
1st-15th September
Amount
296,400.00
87,153.00
72,200.00
37,200.00
1,106,655.00
0.20
3.5
220
57
3.5
3.5
3.5
220
220
220
4
2
2.43 ########
1,599,608.00
516
15
72
########
CASH REQUIREMENT FOR THE REMAINING PART OF THE ROAD PROJECT- RUWANWELLA ELECTRORATE
Mahakanda Road - 2.5km
Description
Sub contractor's
payment required to
be made for
essential structure &
road concrete works
before Asphalt
paving
Retainingwall(H3.9m)
Road concrete
ABC (for 1km)
ABC transport
CSS1 (for 1.6km)
CRS1 (for2.5km)
Asphalt (for 2.5km)
Unit
Rate
Total
Amount
Qty
Item
m
m3
Cubes
m3.km
Barrel
Barrel
tons
1,846,149.00
59,707.87
13,064.44
5,200.00
27.80
18,050.00
18,600.00
11,649.00
2,985,393.54
50
110
1437088.4
5
26,000.00
250
6,950.00
31
559,550.00
24
446,400.00
1084 12,627,516.00
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
1st-15th August
Qty
Amount
5-Aug
5-Aug
5-Aug
21-Aug
21-Aug
21-Aug
To
13-Aug
13-Aug
13-Aug
29-Aug
29-Aug
29-Aug
1,846,149.00
25.00 1,492,696.77 25.00
110
5.00
250
31
0.00
22
0.00 997
1,492,696.77
333143.22
0.00
0.00
0.00
409,200.00
11,614,053.00
3,338,845.77
13,849,092.99
19,935,046.94
From
16th-31st August
Qty Amount
From
24-Sep
24-Sep
24-Sep
To
24-Sep
24-Sep
24-Sep
0
0.00
0.00
0.00
0.00
0.00
0.00
2
87
Unit
Rate
Item
Cubes
m3.km
Barrel
Barrel
tons
5,200.00
27.80
18,050.00
18,600.00
11,649.00
Total
Amount
Qty
25
1250
13
7
304
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
From
To
13-Aug 14-Aug
13-Aug 14-Aug
13-Aug 14-Aug
4-Sep
6-Sep
4-Sep
6-Sep
4-Sep
6-Sep
1st-15th August
Qty
Amount
16th-31st August
Qty Amount
130,000.00
34,750.00
234,650.00
130,200.00
3,541,296.00
0.00
25
0.00 1250
0.00
13
0.00
0.00
130,000.00
0.00
34,750.00
0.00
234,650.00
0.00
0.00
7
130,200.00
0.00 304 3,541,296.00
4,070,896.00
0.00
399,400.00
3,671,496.00
Unit
Rate
Item
Cubes
m3.km
Barrel
Barrel
tons
5,200.00
27.80
18,050.00
18,600.00
11,649.00
Total
Amount
Qty
0
10
5
236
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
From
To
15-Aug 16-Aug
15-Aug 16-Aug
15-Aug 16-Aug
10-Sep 12-Sep
10-Sep 12-Sep
10-Sep 12-Sep
1st-15th August
Qty
Amount
0.00
0.00
180,500.00
93,000.00
2,749,164.00
0.00
0.00
0.00
0.00
0.00
3,022,664.00
0.00
16th-31st August
Qty Amount
0
10
0.00
0.00
0.00
0.00
180,500.00
0.00
0.00
5
93,000.00
0.00 236 2,749,164.00
180,500.00
2,842,164.00
Unit
Rate
Qty
Item
Cubes
m3.km
Barrel
Barrel
tons
Sub contract
Sub contract
Sub contract
Sub contract
Sub contract
Total
Amount
st
th
1 -15 August
Qty
Amount
Total
Machinery Requirement
Motor grader
10 ton roler
Water bowser
Asphalt paver
Static roler
PTR
From
To
19-Jul
19-Jul
20-Jul
20-Jul
20-Jul
From
28-Jul
28-Jul
27-Jul
27-Jul
27-Jul
11-Aug
11-Aug
20-Aug
20-Aug
20-Aug
To
25-Aug
25-Aug
9-Feb
9-Feb
9-Feb
th
st
16 -31 August
Qty Amount
st
th
th
th
16th-30th September
Amount
0
0.00
0.00
0.00
37,200.00
1,013,463.00
1,050,663.00
0
3.5
0
1000
3.5
3.5
3.5
1600
200
200
0
0
31
2
2.43 ########
0
15
0
15
########
607
16th-30th September
Amount
0.00
0.00
0.00
0.00
0.00
0.00
3.5
540
3.5
3.5
3.5
660
700
700
13
7
0
2.43
15
15
16th-30th September
Amount
0.00
0.00
0.00
0.00
0.00
0.00
3.5
260
3.5
3.5
3.5
545
545
545
10
5
0
2.43
15
15
th
th
16 -30 September
Amount
3.5
540
3.5
3.5
3.5
660
700
700
13
7
0
2.43
15
15
MACHINERY REQUIREMENT
Machine
18-Jul
JCB
Tiper
Motor Grader
Water bowser
10 ton oller
Asphalt paver
Static roller
PTR
25-Jul
1-Aug
8-Aug
Required Period
15-Aug
22-Aug
29-Aug
5-Sep
12-Sep
Electrorate
Ruwanwella
Yatiyantota
Deraniyagala
Road
Mahakanda Road
Mahella Road
Humbaswalana Road
Rattagala road
Kithulgala road
Elugala road
Wilakanda Road
Newsmeyer Road
Doranuwa road
Yatiwala Road
Optional road
Mawatenna Road
Welidade road
Noriya Basnagala Road
Demada road
Date of joint
measurement
Date of sent
Date of
Date of sent to
submited to
Ratnapura
Amount
22,235,534.00
Remarks