Presentation On Commissioning of CFBC Boiler
Presentation On Commissioning of CFBC Boiler
Presentation On Commissioning of CFBC Boiler
Chemical Cleaning
Boiler Safety Protection Checking
ACTIVITIES OF COMMISSIONING
Steam Dumping
Synchronization
ACTIVITIES OF COMMISSIONING
Pressure parts
approximately 7 - 8ksc
The purpose of air leak test of air, gas ducting & ESP
is to ensure leakage proof in ducts, welding joints, flange joints to ensure efficient operation of fans, boiler
Hydro Test All the pressure parts of the boiler, which are
subjected
to
high
operating
pressure
during
operation, should be checked to ensure that they withstand the high pressure so hydraulic test is conducted
Commissioning Checkpoints
Checklist have to be prepared for all equipments and all activities. After completion of equipments erection, check points to be made and the trial run of equipments
shall commence
Fuel feeders
Chemical Cleaning During the process of erection, there might be entrainment of unwanted material like rust, dirt, mill
scale etc.
The internal surfaces of a boiler where demineralized water of high purity is to be evaporated, should be maintained free of all material which come in the way of efficient heat transfer and thus effect generation.
The
The
Boiler Safety Protection Checking Check the following equipments are having
interlocks
Boiler Safety Protection Checking Check the following equipments are having
interlocks
Boiler Safety Protection Checking Check the following equipments are having
interlocks
Grid Air pressure Drop Study Grid air pressure drop study is nothing but finding out the pressure drop across grid nozzle at different
air flows
The pressure drop values measured in grid pressure drop study are used to find out the bed height when the boiler is in running condition. i.e. at a particular air flow
Steam Blowing
The objective of steam blowing is to remove dirts, loose
Failure to remove the debris may result in damage to turbine blades, valves etc
Steam Dumping Steam dumping is nothing but allowing steam from re-heater through MSL and by by-passing the HP turbine the steam is send to re-heater via HRH line
Steam Dumping Till achieving purity, the steam can be allowed to drain from CEP O/L to open drain. After achieving purity it can be taken to close circuit.
Synchronization After completion of all activities synchronization of the unit shall commence Synchronization is nothing but matching the
Reliable test Run Reliability run is Seven (7) days of Continuous Power Plant operation at various loads in which 72
For For
of the boiler,
any trouble shooting of the boiler for
performance deviations