Rules For Classification and Construction VI Additional Rules and Guidelines
Rules For Classification and Construction VI Additional Rules and Guidelines
Edition 2007
Germanischer Lloyd Aktiengesellschaft Head Office Vorsetzen 35, 20459 Hamburg, Germany Phone: +49 40 36149-0 Fax: +49 40 36149-200 [email protected] www.gl-group.com "General Terms and Conditions" of the respective latest edition will be applicable (see Rules for Classification and Construction, I - Ship Technology, Part 0 - Classification and Surveys). Reproduction by printing or photostatic means is only permissible with the consent of Germanischer Lloyd Aktiengesellschaft. Published by: Germanischer Lloyd Aktiengesellschaft, Hamburg Printed by: Gebrder Braasch GmbH, Hamburg
VI - Part 9 GL 2007
Table of Contents
Chapter 2 Page 3
Table of Contents
Section 1 A. B. C. D. E.
General Principles and Requirements Scope .......................................................................................................................................... Other Relevant Standards ........................................................................................................... Requirements for the Manufacturer ............................................................................................ Materials .................................................................................................................................... Welding Consumables and Auxiliary Materials ......................................................................... 111111 1 1 1 1
Section 2 A. B. C. D. E.
Production Fundamentals General ....................................................................................................................................... Forming ...................................................................................................................................... Welding Joints ............................................................................................................................ Welders Qualification Tests ...................................................................................................... Welding Procedure Tests ........................................................................................................... 222221 1 1 1 2
Section 3 A. B. C. D.
Inspection of Welded Pipelines Visual Inspection ........................................................................................................................ Penetrant Inspection ................................................................................................................... Radiographic Inspection ............................................................................................................. Hydrostatic Test ......................................................................................................................... 33331 2 2 7
Section 4
VI - Part 9 GL 2007
Section 1
Chapter 2 Page 11
1. These Guidelines give technical principles regarding the production and inspection of welded pipes made of copper-nickel alloys designed for the use on ships. Concerning other components made of this material these Guidelines could be correspondingly adopted. 2. These Guidelines are meant to be a supplement of the Rules for Classification and Construction I Ship Technology Part 1 Seagoing Ships, Chapter 2 Machinery Installations, Section 11, which have to be definitely observed for the vessels construction under class of Germanischer Lloyd (GL). 3. Germanischer Lloyd reserves the right to modify or to complement these Guidelines according to the technical development and as the case may be to the coming into force of new Rules for Classification and Construction.
D.
Materials
1. The materials have to be appropriate to the intended use. 1.1 For pipe manufacturing, pipes made of copper-nickel-alloy 90/10 acc. to the GL Rules II Materials and Welding, Part 1 Metallic Materials, Chapter 3 Non-Ferrous Metals, Section 2 (CuNi10Fe1Mn acc. EN 12449) are to be used or similar material (CuNi10Fe1,6Mn acc. to WL 2.1972). 1.2 For the use of other alloys, requirements for the properties of welded joints have to be defined separately. Possible restrictions of analysis for pipe material suitable for welding acc. to the standards are to be observed.
B.
1. These Guidelines refer to the standard series DIN 85004 Pipelines of Copper-Nickel-Alloys respectively adopt them accordingly. 2. If there are differences concerning the requirements between these Guidelines and the standards which also apply, the requirements of these Guidelines shall take precedence unless otherwise stipulated.
E.
C.
1. The production works must provide qualified equipments in order to carry out the welding appropriate to these Guidelines. 2. Equipments and installations in external places, e.g. concerning the non-destructive testing, can be taken into account for the evaluation of the shop if the conditions for an appropriate testing are given at that place. 3. The manufacturer has to notify welding supervisors, who verify the welding work with responsibility. Only welders and welding procedures, both approved according to Section 2, D. and E. respectively, are allowed to be used for the work.
1. The welding consumables have to be chosen that way, that the requirements established for the material are also fulfilled by the weld metal and the joint. This is the case if e.g. welding consumables of the type CuNi30 to EN14640 (SG-CuNi30Fe to DIN 1733-1) are used for welding of CuNi10Fe1Mn. 1.1 If possible, welding consumables and auxiliary materials already tested and approved by GL shall be used, see also the GL Rules II Materials and Welding, Part 3 Welding, Chapter 1 General Requirements, Proof of Qualifications, Approvals, Section 5. 1.2 The evidence can also be provided through a welding procedure test acc. to Section 2, E. at the user. This kind of recognition is restricted to the users work and only valid for max. one year, if an annual repeat test is not carried out.
VI - Part 9 GL 2007
Section 2
Production Fundamentals
Chapter 2 Page 21
1. The working place of copper-nickel-materials has to be separated from the working of steel components. 2. Pipes and pipe fittings have to be handled in a proper condition, that means that dirt of each kind, rests of oil and grease as well as sand, cuttings and other are to be removed. 3. Until installation on board, the openings of the pipes and fittings are to be protected against the penetration of dirt.
B.
Forming
1. The procedures of forming (T-Drill process), flanging and reducing of pipes at the manufacturer have to be approved by GL. 2. Cold bending of pipes can be carried out, if the bending diameter is larger than 2 times the external diameter. Occurred bending ripples are to be removed. 3. Pipe branching can be performed by fittings, welded connections or forming (T-Drill process). In the case of forming, the calculated wall thickness has to be observed. If relevant cold works have to be carried out, annealing is required at a temperature of approx. 750 C.
D.
1. Welders qualification tests acc. to EN ISO 9606-3 are required for all welders executing welding by hand guided welding apparatus (e.g. TIG, manual arc welding). 2. The qualification of the operating staff for automatic welding machine (e.g. orbital welding) is to be proved by welded test pieces acc. to EN 1481/ISO 14732, e.g. as part of the procedure test. 3. The welder or operator having successfully passed the welding procedure test in accordance with E. is qualified for the corresponding scope acc. to EN ISO 9606-3 and EN 1418 / ISO 14732 respectively, provided that the decisive test requirements are fulfilled. 4. Apart from the specifications and requirements of the a.m. standards, the requirements of the GL Rules II Materials and Welding, Part 3 Welding, Chapter 1 General Requirements, Proof of Qualifications, Approvals, Section 3 are to be observed.
C.
Welding Joints
1. The welding has to be preferably carried out with the tungsten inert gas arc welding process (141) under argon shielding gas, also for root side. 2. In case of multilayer welding of pipes with wall thickness more than 6 mm, manual arc welding (111) with basic covered rod electrodes can be used for the fill and final pass. The root pass must be welded by TIG-process. 3. Other procedures can also be approved on request, if sufficient quality properties are proved by a welding procedure test.
Chapter 2 Page 22
Section 2
Production Fundamentals
VI - Part 9 GL 2007
E.
1. Before starting the fabrication, it must be proved by means of a welding procedure test that pipe joints acc. to the required quality properties can be manufactured in the workshop. 2. The welding supervisor has to indicate all details in a manufacturers welding procedure specification (WPS) how to carry out the welding works. The welding of test pieces is made upon this preliminary welding procedure specification. 3. Concerning the TIG-welding with preparation of the square butt joint, a welder must weld a piece each with a diameter d1 = 150 up to 200 mm and a wall thickness s = 2,5 up to 3 mm in a horizontal pipe axis (pos. PA, PF, PE) and in a vertical pipe axis (pos. PC), see Fig. 2.1. 4. If multilayer welding is applied, another set of test pieces with corresponding wall thickness has to be welded. If the welding is restricted to the flat position (PA), e.g. welding on rotating device, the welder can only weld the test pieces in that position.
5. In the case that the measurements of the pipes used during the fabrication are differing too much from the a.m. dimensions of the test piece, an adjusted test program has to be agreed with GL. 6. Prior to sectioning, the welded test pieces are to be examined over the entire length of the seam by non-destructive testing in order to find external or internal welding failures by visual, penetrant and radiographic examination (VT, PT, RT). The evaluation of the imperfections will be assessed according Section 3, Table 3.1, 3.2 and 3.4. 7. The sectioning of the test pieces and the dimensions of the specimens concerning the mechanical-technological testing are described in Figure 2.2 and Fig. 2.3. One test set shall be made up of the following specimens if not agreed otherwise: 2 transverse tensile test specimens (Z) per welding position 2 transverse bend test specimens per welding position, one is to be bent with the final pass (FBB) and one with the root pass (RBB) in tension 1 macrographic (M) per welding position
d1 PA s
= ca. 300
PE
Pipe fixed (Pos. PA, PF, PE) Pipe axis horizontal or Pipe rotating (PA) Pipe axis horizontal
PF
Z M
Pipe axis vertical, Pipe fixed (resp. horizontal, if welded with rotating device)
Fig. 2.2 Positions and preparation of specimens for welding procedure tests
ca. 300
PF
PF
PC
d1
VI - Part 9 GL 2007
Section 2
Production Fundamentals
Chapter 2 Page 23
L0
R35
LS LC
Fig. 2.3 Dimensions of tensile and bend test specimens Table 2.1 Requirements for the welded joints
Type of test Tensile test transversal to weld (Z) Requirements Tensile strength Rm as stipulated for the base material at least 290 N/mm2. The minimum elongation A 15 % shall be checked with an initial gauge length of L0 = 5,56 S0 . Bending angle 180 with a mandrel diameter of 3 times the wall thickness. Minor open defects up to a maximum length of 3 mm may be tolerated. Imperfections are to be within the specified limits of Table 3.1, 3.2 and 3.4.
8. In welding procedure and production tests on copper-nickel-alloy 90/10, the butt weld specimens must meet the minimum requirements shown in Table 2.1. 9. A successfully passed welding procedure test is valid for the examinated welding process, for the used copper-nickel-alloy, for the used welding consumable type and for the tested welding position(s).
The scope of the wall thickness and the diameter is determined according to the welders qualification test acc. to EN ISO 9606-3. 10. Depending upon the pipe class, the validity of a welding procedure is determined in Chapter 1 General Requirements, Proof of Qualifications, Approvals, Section 3 and Chapter 3 Welding in the Various Fields of Application, Section 4 of the GL Rules II Materials and Welding, Part 3 Welding.
20
(Tension side)
R2
VI - Part 9 GL 2007
Section 3
Chapter 2 Page 31
1. The external condition of all weld seams are to be inspected, even the root sides of the seams, as far as accessible. 2. Unevenness of the weld seams inside the pipelines, e.g. welding beads or sagging drops of weld, has to be removed, but the minimum wall thickness has to be respected. 3. The root reinforcement shall not exceed the values given in Table 3.1. The misalignment of the inside does not exceed the half of the wall thickness or 2 mm max. The sum of root reinforcement and the inside misalignment has not to be more than the values described in Table 3.1.
Table 3.2
According to EN ISO 6520-1 Designation Gas pore Clustered porosity Linear porosity Worm-hole Tungsten inclusion Lack of fusion Lack of penetration Undercut, continuous Undercut, intermittent Shrinkage groove Crack Irregular bead appearance Poor restart
2 Pores up to 0,3 mm are not evaluated. 3 Tungsten inclusions up to 0,5 mm are ignored for wall thickness of 2 mm and above; tungsten inclusions up to 0,3 mm are not evaluated.
Classification number 2011 2013 2014 2016 3041 401 402 5011 5012 5013 100 514 517
Symbol Aa Ab H C D F F E
Remark see Table 3.4 not permissible 1,2 not permissible 2 not permissible not permissible 3 not permissible not permissible not permissible conditionally permissible not permissible not permissible permissible not permissible
Chapter 2 Page 32
Section 3
VI - Part 9 GL 2007
B.
Penetrant Inspection
to test class A, but the minimum of the optical density has to be increased up to 2.5. 1.4 When taking radiographs with gamma rays, one has to make specimen radiographs because of the loss of sensitivity with regard to the source-filmdistance according to test class B and A respectively. 1.5 Exposure time and film systems are to be chosen that way that the optical density according to 3. is achieved. 2. Film systems and intensifying screens
1. A penetrant testing of weld seams of the pipelines of pipe class I and II are to be carried out in a spot check way. 2. The GL Rules II Materials and Welding, Part 3 Welding, Chapter 2 Design, Fabrication and Inspection of Welded Joints, Section 4, N. specifies the requirements for the execution of the penetrant inspection. 3. The evaluation of the imperfections has to be executed according to Table 3.2.
C. 1.
2.1 Class C3 and C4 films according to EN 584-1 are to be used. With regard to the tube voltage Ur 150 kV C3 films and Ur 150 kV respectively with Ir192 and Se75 C4 films are to be used. 2.2 Intensifying screens are to be chosen according to EN 444 in case of front intensifying screens (VF) or rear intensifying screen (HF). In case of tube voltage Ur 150 kV, 0.02 mm front intensifying screens (VF) and rear intensifying screens (HF) are preferably to be used. 2.3 One has to make sure that the films are very close to the screens (vacuum packaging). 3. Optical density, image quality and image quality indicator Optical density
1.1 The radiographic examination upon welded pipe lines of copper-nickel-alloys has to be carried out according DIN 85004-9. X-rays is the preferable source for the radiographic examination upon the a.m. pipe lines. Test class B according to EN 444 is the basis. The maximum of the tube voltage can be increased by 50 kV, see Fig. 3.1.
500 400 300 200 copper
3.1
steel titanium aluminium
Limit energy in kV
100 70 60 50 40 30 20
Following EN 444, an optical density of 2.0 and in case of gamma rays of 2.3 is required within the scope of radiographic images. When using gamma ray sources acc. to test class A, the minimum of the optical density is 2,5. 3.2 Image quality indicator
10
4 5 6 7 8 9 10
20
30 40 50 60 mm 100
The image quality has to be checked with image quality indicators (copper) acc. to EN 462-1 and be proven acc. to EN 462-3. 3.3 Stepped photometric absorption wedge
Radiographed thickness w in mm
Fig. 3.1
1.2 In the case of repair where already installed pipes cannot be tested by x-rays because of access problems, the examination with gamma rays (e.g. Ir192 or Se75) according to test class B acc. to EN 444 is admissible. If the penetrated wall thickness is smaller than 10 mm, only Se75 is to be used. 1.3 If a further distance reduction is necessary because of access problems or for a central radiograph, one can examine the pipe with Se75 according
For evaluation of the radiographic films with regard to determine the excessive root respectively cover pass reinforcement the stepped photometric absorption wedge according to Fig. 3.2 has to be used. Depending upon different test arrangements, flat and bend step wedges are to be used. The bend step wedge is to be arranged far from the film; the flat step wedge is to be arranged near the film (Fig. 3.3). Step wedge (position 1 in Fig. 3.3) can also be arranged parallel to the weld seam, if it is additionally indicated by a lead letter F (F = near the film).
VI - Part 9 GL 2007
Section 3
Chapter 2 Page 33
Dimensions in millimeters
2,5
0,5
1,5
3,5
Stepped heights
0,5
1,5
2,5
3,5
6 8 x 6 = 48 Material: CuNi10Fe1,6Mn or copper Tolerances for holediameters and step heights 0,1 mm
4.
6.
Evaluation of radiographs
The test arrangement has to follow the pictures I IV (Fig. 3.4). Central radiographs for pipe nominal diameter from DN 100 are admissible. The respective FFDs depending upon the used focus shows Fig.3.5. The film-focus distance for other test arrangements shall be taken from EN 444.
The radiographs are to be evaluated according the following criteria: Assessment of the radiographic images: Image quality acc. to EN 444 and EN 462-3, test class B respectively A Optical density (blackness) acc. to DIN 85004-9 Is the used film in line with the required film system class acc. to EN 584-1 respectively the GL Rules II Materials and Welding, Part 3, - Welding, Chapter 2 Design, Fabrication and Inspection of Welded Joints, Annex C. Positioning of the step wedges Evaluation of the imperfections in the welded joints: Admissible internal root reinforcement acc. to Table 3.1 Imperfections of the weld seam acc. to Table 3.2 and Table 3.4 The evaluation of CuNiFe-radiographs regarding the permissible internal root reinforcement and existing weld imperfections may only be performed by trained persons with adequate practical experience. GL may require appropriate documentary proof of such training and experience.
5.
Scope of tests
Prior to sectioning, each butt weld test piece for welders and welding procedure qualification tests shall undergo a radiographic inspection over the entire length. Butt welds at pipelines of the pipe class I are to be examined to 100%, those by pipelines of the pipe class II to 10%. The details are settled on GL Rules II Materials and Welding, Part 3 Welding, Chapter 3 Welding in the Various Fields of Application, Section 4. The tests of the welding seams on CuNiFe-pipelines for German navy ships are to be carried out according to a spot check inspection plan, see Table 3.3.
12,5
Chapter 2 Page 34
Section 3
VI - Part 9 GL 2007
Table 3.3
N 1
7.
Digital radiography
If the weld seams of CuNiFe-pipelines shall be examined via the digital radiography and the use of memory foil or of detector, a GL approval is needed based on specially manufactured test specimens in order to validate the examination system.
1 Batch volume (number of the weld seams being presented at the same time) 2 Sample test volume (number of the weld seams being selected for the test). 3 Acceptance number (permissible number of the faulty weld seams).
Table 3.4
Nominal wall thickness s mm
Permissible porosity
Weld joint thickness mm min. Acceptable number of pores per 50 mm joint length for pore size 1 in mm over 0,3 over 0,5 over 1 up to 0,5 up to 1 up to 1,5 Nominal wall thickness s mm Weld joint thickness mm min. over 0,3 up to 0,5 Acceptable number of pores per 50 mm joint length for pore size 1 in mm over 0,5 up to 1 over 1 up to 1,5
4
2
0 2 2 0 2 0 3 1 4 2 0 5 3 0
0 0 0 1 0 1 0 1 0 1 2 0 1 2 8 8,8
6
1 2
6,6
10
11
12
13,2
7 5 2 0 8 6 4 2 0 10 7 5 3 1
0 1 2 3 0 1 2 3 4 0 1 2 3 4
The pore size is the maximum size of a pore detectable (projected) in the radiographic film. Pore size up to 0,5 mm is ignored for wall thickness of 2 mm and above; pores up to 0,3 mm are not evaluated.
VI - Part 9 GL 2007
Section 3
Chapter 2 Page 35
Test arrangement A
Taking arrangement B 2
FFD
even stepped photometric absorption wedge 2 bend stepped photometric absorption wedge FFD film-focus-distance
Film
Film
B 2
1 Film B
Filmposition A
2 Filmposition C Filmposition B
Fig. 3.3 Test arrangements of image quality indicator and stepped photometric absorption wedge
Chapter 2 Page 36
Section 3
VI - Part 9 GL 2007
DN 80
800 < FFD < 2600 IV A D B C DN 250 Note: In the application case IV instead of 2 irradiations (elliptic radiation), 4 individual radiographs are to be set up.
Test arrangement and film-focus distance (FFD) depending upon pipe's nominal diameters (DN)
2
b FFD
f s
FFD
Film
Film
Fig. 3.4 Test arrangement and film-focus distances (FFD) depending upon the pipes nominal diameters (DN) and test arrangement for central radiographics
VI - Part 9 GL 2007
Section 3
Chapter 2 Page 37
Fig. 3.5 Film-focus distance (FFD) depending upon the pipes nominal diameters (DN) and upon the used focus D. Hydrostatic Test nology, Part 1 Seagoing Ships, Chapter 2 Machinery Installations, Section 11. Generally, the test pressure is 1.5-fold of the design pressure. It is to be assured that the 0,2 % proof stress (Rp0.2) of the material is not exceeded during the test.
In presence of the Surveyor, finished pipe sections of pipe class I and II are to be subjected to a hydraulic pressure test according to GL Rules I Ship Tech-
FFD
VI - Part 9 GL 2007
Section 4
Chapter 2 Page 41