04 03 Transportation
04 03 Transportation
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 4.3.2 4.3.1 4.3 TRANSPORTATION AND TRAFFIC Redevelopment, which includes the realignment and extension of Maritime Street, including the Loop Road, would provide benefits, including reducing hazards to bicyclists and pedestrians, providing 105 acres of ancillary maritime support to relieve nearby communities from truck traffic and parking, and reducing delays on Maritime Street south of 7th Street due to the removal of two railroad/highway grade crossings. Redevelopment would also result in less than significant, potentially significant, and significant impacts to the transportation system. With the implementation of measures recommended in this section, most of the potentially significant and significant impacts would be mitigated to a level that is less than significant. No feasible mitigation measures have been identified that would reduce freeway impacts to a level that is less than significant. Study Area The redevelopment project area is located near the hub of the Bay Area freeway system, is well served by local roadways, and has access to public transit and rail service. The project area is located within an important recreation and commercial shipping area. Figure 4.3-1 depicts the study area for the transportation analysis. This area was selected to encompass areas within the regional transportation network that could be potentially affected by traffic generated by redevelopment. The study area also includes local access routes expected to serve at least fifty peak hour trips generated by redevelopment during peak commute hours. The local study area includes freeways, major city arterial roads and local access routes within the cities of Oakland, Emeryville, Berkeley, and Alameda. The study area includes freeways in the East Bay from the Alameda/Contra Costa County line in the north to San Lorenzo and Castro Valley. Those freeways are I-880, I-80, I-580, I-980, I-238, and State Route (SR) 24. Regulatory Setting Federal The Federal Highway Administration. The Federal Highway Administration (FHWA) is the agency of the U.S. Department of Transportation (DOT) responsible for the federally-funded roadway system, including the interstate highway network and portions of the primary state highway network. FHWA funding is provided through the Transportation Equity Act for the 21st Century (TEA-21 Public Law 105-178, as amended by Title IX of Public Law 105-206). This act can be used to fund local transportation improvement projects, such as projects to improve the efficiency of existing roadways, traffic signal coordination, bikeways, and transit system upgrades.
Page 4.3-1
April 2002
Page 4.3-2
April 2002
Page 4.3-4
April 2002
Page 4.3-5
April 2002
provide High Occupancy Vehicle (HOV) lanes and improved ramp connections to I-580 and the Bay Bridge. I-80, north of the OARB, carries approximately 260,000 vehicles daily to San Francisco. I-580 is an eight-lane freeway serving Northern Alameda County, Livermore, Stockton, Marin County north and I-5 south. Access to the redevelopment project area is provided via the West Grand Avenue/I-80 ramps. The City of Oakland has placed a heavy truck (over 4.5 tons) restriction on I-580 between Grand and 106th avenues. Truck traffic to and from the redevelopment project area must use alternative roadways. I-580 carries approximately 194,000 vehicles daily east of I-980. East of I-238, I-580 carries approximately 158,000 vehicles daily. I-980 provides access to the Oakland downtown area. I -980 has six to eight lanes and an average daily traffic volume of 191,000 vehicles. I-980 becomes State Route 24 (SR-24) at the northern end, providing access to Contra Costa County via the Caldecott Tunnel, and provides a direct connection between I-580 and I-880. I-238 is a four-lane freeway that connects I-580 to I-880 through unincorporated San Lorenzo. I238 provides the primary truck link between the redevelopment project area and I -580 east to the Tri-Valley and Central Valley and carries approximately 118,000 vehicles daily. I-238 is planned to be widened to eight lanes. SR-24 is an eight-lane freeway that connects the East Bay area with central and east Contra Costa County. SR-24 extends from I980 to I -680 through the Caldecott tunnel and carries approximately 150,000 vehicles daily just west of the Caldecott Tunnel. The following discussion of regional freeway conditions was taken from the 2000 Level of Service Monitoring Report prepared by the CMA (2000). The CMA monitors congestion on freeways in the region by measuring the average travel speed during the p.m. peak period (4:00 to 6:00 p.m.). Freeway traffic conditions are then described in terms of level of service (LOS), a standard measure for traffic operations defined by the average number of seconds of delay per vehicle, with LOS A representing free-flow conditions and LOS F representing gridlocked conditions.1 According to the CMA, traffic speeds of 49 miles per hour (mph) or higher on the freeway indicate LOS A through C. At LOS D, traffic operating conditions become unstable and speeds can drop as low as 41 mph. At LOS E, there are virtually no usable gaps in the traffic stream and speeds can drop as low as 30 mph. Below 30 mph, at LOS F, stop-and-go traffic operations often occur. As shown on Table 4.3-1, in 2000 during the p.m. peak, traffic congestion occurs on most routes leading away from major employment centers in the study area. I-80 operates at LOS F eastbound from the Bay Bridge to the I-80/I-580 split, and is congested westbound approaching
Appendix 4.3 includes definitions of LOS.
Page 4.3-6
April 2002
Source: ACCMA 2000 LOS Monitoring Report. Note: a Missing values (designated with a dash -) were not reported in the reference document.
5 6 7 During the a.m. peak period (7:00 to 9:00 a.m.), bottlenecks occur on many of the freeways leading to the major employment centers in and near the transportation study area. SR-24 is Public Review Draft Page 4.3-7 April 2002
Page 4.3-8
April 2002
Page 4.3-9
April 2002
This version of the Highway Capacity Manual was prepared in 1997 and is commonly referred to as the 1997 Highway Capacity Manual. Worksheets are available for review at 250 Frank Ogawa Plaza, Suite 3330, during normal business hours.
Page 4.3-10
April 2002
Page 4.3-11
April 2002
P.M. Peak Hour LOS C D B B B B B C C C A C A B B A C B C B C C C C B B A C B B C B B C D C Delay 29.6 35.4 10.7 10.3 10.6 11.6 17.0 21.8 23.2 33.3 7.8 30.5 8.7 16.7 11.9 9.5 20.8 10.8 21.1 11.7 27.1 29.1 22.8 29.3 11.8 13.3 8.4 22.4 19.1 15.9 20.4 19.8 17.3 22.4 43.9 30.5
a
30.3 9.6 11.1 10.0 11.4 13.7 23.8 24.2 29.7 5.2 29.2 8.6 14.8 9.0 10.7 15.0 10.5 32.6 10.4 31.5 30.4 19.5 20.9 11.3 13.9 8.5 30.4 15.5 11.8 9.5 18.3 15.8 21.3 25.2 29.9
Page 4.3-12
April 2002
LOS C C C B C C C C C
Delay 22.7 31.8 28.6 12.5 33.7 29.8 20.6 31.5 22.3
LOS C C C D D C C C C
Delay 31.1 34.3 31.6 46.4 48.6 32.2 22.0 28.6 20.7
1 2 3 4 5 6 In 1995, there were 2,044 employees at the OARB (U.S. Army Corps of Engineers [Corps] 2001), 714 more than the 1,330 employees at the end of 2000 (OBRA 2001). The traffic generated by these 714 additional employees were added to existing traffic volumes to develop the alternative baseline for the transportation impact analysis. Additional trips generated by OARB employees in 1995 are shown in Table 4.3-3.
Table 4.3-3 OARB Trip Generation, 1995 and 2001 Trips G e n e r a t e d Year 1995 2001 Land Use Category Employees Daily Warehousing Warehousing 2,044 1,330 714 5,378 3,896 1,482 AM Peak Hour In Out Total 590 229 819 397 192 155 75 552 267 PM Peak Hour In Out Total 334 620 954 224 109 417 203 641 313
7 8 9 10 11 12 13 14 15 16 The additional trips generated by employees that were on the base in 1995 were added to existing traffic volumes based on the distribution of traffic derived from the Alameda County Congestion Management Agency Countywide Transportation Model. The Countywide Model incorporates a representation of land use and demographic characteristics of the nine-county Bay Area, which allows it to produce travel demand forecasts that incorporate influences of regional travel demand on the transportation network in Alameda County. The distribution of OARB trips is shown in Table 4.3-4. The analysis showed that about half of the trips attributed to the OARB alternative baseline would be to or from the area outside the local study area and half would be within the local study area. Public Review Draft Page 4.3-13 April 2002
6
Table 4.3-5 a Intersection Operations for Baseline Conditions , 1995 A.M. Peak Hour Intersection West West West West West West Grand Grand Grand Grand Grand Grand Avenue/Maritime Street Avenue/I-880 Frontage Road Avenue/Mandela Parkway Avenue/Adeline Street Avenue/Market Street Avenue/San Pablo Avenue LOS D C A B A B Delay 37.1 30.7 9.6 11.5 9.9 11.5
b
P.M. Peak Hour LOS C D B B B B Delay 32.6 37.3 10.6 10.6 10.6 11.6
b
Page 4.3-14
April 2002
LOS B C C C A C A B A B B B C B C C B C B B A C B B A B B C C C C C C B C C C C C
Delay 13.7 23.9 24.2 30.4 5.2 29.3 8.5 14.8 9.0 10.7 15.0 10.5 33.6 10.4 31.5 30.4 19.5 20.9 11.3 13.9 8.5 30.4 15.5 11.8 9.5 18.4 15.8 21.3 25.2 29.9 22.7 31.8 28.6 12.5 33.7 29.8 20.6 31.5 22.3
LOS B C C C A C A B B A C B C B C C C C B B A C B B C B B C D C C C C D D C C C C
Delay 16.9 21.8 23.3 33.6 7.5 30.6 8.7 16.7 11.9 9.5 20.8 10.8 21.3 11.7 27.2 29.1 22.8 29.4 11.8 13.3 8.4 22.4 19.1 15.9 20.5 19.9 17.3 22.4 44.1 30.5 31.1 34.4 31.6 46.4 48.6 32.3 21.9 28.6 20.7
Source: Dowling Associates 2002. Notes: a Baseline conditions reflect 2001 traffic levels, adjusted to account for 1995 Traffic Generation at the OARB. b Delay in seconds per vehicle c Defined as a downtown intersection.
Page 4.3-15
April 2002
Vehicle Types. Traffic in and near the project area consists of two primary components: passenger car traffic generated by commuters and local residents, and heavy trucks. Heavy trucks have a substantially greater proportional influence on traffic operations than passenger cars. To determine the relative number of passenger cars and trucks in the redevelopment project area, vehicle classification counts were conducted at three locations: Maritime Street south of West Grand Avenue; 7th Street west of I-880; and Middle Harbor Road south of 3rd Street.
These locations show traffic conditions, respectively, at the northern, central, and southern areas of the Port. Variations in auto, truck, and total traffic volumes throughout the weekday for the three locations listed above are shown in Figure 4.3-4. The figure shows that automobile traffic in the redevelopment project area peaks between 7:00 and 8:00 a.m., at the noon hour, and between 3:00 and 4:00 p.m. Truck traffic peaks between 11:00 a.m. and 12:00 noon. Railroads. Burlington Northern Santa Fe (BNSF) has its major Northern California railyard in Richmond but also has rail access to the Oakland Outer Harbor area. BNSF has an agreement to use the UP rail line between Richmond and Oakland, where BNSF maintains a small yard facility near 34th and Wood streets. Oversize and heavy loads (like earthmoving equipment on railroad flatcars) can be routed from Richmond to the Wood Street Yard via the UP mainline and then interchanged with the Oakland Terminal Railroad (OTR) for the final movement to marine terminals in the Port. The JIT was recently constructed by the Port in the area bounded by 7th Street, Maritime Street, and Middle Harbor Road in order to expand the existing intermodal cargo handling capabilities at the Port and to allow the BNSF to operate effectively at the Port. From the Bay Area, most of BNSFs priority freight is shipped east to other points in the United States via Stockton, California, and Flagstaff, Arizona. UP serves the Bay Area on trackage to the east via Stockton and the Sierra Nevada to Salt Lake City, Utah, and points east. UP currently operates an intermodal terminal along Inner Harbor, providing a direct transfer point for containers moving between ships and trains. Currently, most of the Oakland-related UP train traffic travels via Salt Lake City, where UPs primary lines to Southern California, the Pacific Northwest, and the Midwest converge. In 1996, UP purchased SP. In this acquisition, UP acquired three routes for moving freight to and from the Bay Area and the former SP West Oakland Intermodal Railyard on the northeastern side of the Port. The northern route has two tracks and crosses the Carquinez Strait at Benicia en route to the Sacramento area for connections to the Pacific Northwest, Midwest, and Gulf of Mexico. OTR is an offshoot of the East Bays former interurban Key Line Transit system that is jointly owned by UP and BNSF. OTR is a local switching railroad that shuttles rail cars between the UP, BNSF, and the Port of Oakland marine terminals. In addition to these interchange Public Review Draft Page 4.3-16 April 2002
Page 4.3-17
April 2002
The methodology for determining the impacts of redevelopment was based on the analytical procedures described in the previous section. The analysis of traffic operations at intersections was performed using the 1997 Highway Capacity Manual methodologies. For freeways, the Public Review Draft Page 4.3-19 April 2002
Amount
376 577 444 50 600 29 15 300
Daily
3,670 5,099 3,214 349 5,255 232 561 1,453 19,832e
Port Area
Marine Terminals Proposed Employment Approved Employment New Employment New Intermodal Trucks f New Off-site Trucks f Rail Terminalg Proposed New Intermodal Facility
4
192 151 41 34 31 14
All trips discussed in this document are reported as the equivalent number of passenger car trips. Each truck trip generated by redevelopment is considered as the equivalent of two passenger car trips. The total number of daily truck trips generated by redevelopment would be 3,029 the equivalent of 6,058 automobile trips.
Page 4.3-20
April 2002
Amount
208 -20 75 15
Daily
959 -92 1,383 561 10,168
16 /Wood Area
North Subareah Officec 1,426 KSF 10,216 1,364 186 1,550 285 Live Work 252 Units 1,428 18 88 106 88 Light Industrial 120 KSF 836 97 13 110 14 Park 1 Acre 8 0 0 0 0 South Subarea Live/Work 123 Units 776 10 50 60 49 Light Industrial 185 KSF 1,289 150 20 170 22 Subtotal 16th/Wood Area 14,554 1,640 358 1,998 459 Total 44,554 4,603 1,178 5,781 1,102 Sources: Institute of Transportation Engineers 1997 and Port of Oakland 1998 Notes: a KSF = thousand square feet; Emp. = employees b Office, R&D was treated as general office for the purpose of trip generation. c Office supporting ancillary retail space was included as office space. d JATC was treated as light industrial space for the purpose of trip generation. e In addition to the trucks associated with Maritime Support, the trip generation rates for Gateway development area and 16th/Wood area include an approximately 1% and 0.6% component of heavy duty trucks, respectively, as assumed in the traffic model. f Truck trips are reported as the equivalent number of passenger cars (1 truck = 2 cars). g No new non-intermodal traffic would be generated due to changes in the size of rail terminal facilities. h Negligible peak hour traffic is expected to result from development of 11,000 sq. ft. of event and common space at the Amtrak Station, and that space is not included in the 16th/Wood land use amounts. Separate components of redevelopment were treated as separate land uses for the purpose of trip generation. 1,393 44 103 1 24 160 1,724 4,376 1,678 132 118 1 73 181 2,182 5,478
th
1 2 3 4 5 6 7 8 9 For the purpose of determining the number of trips that would be generated by redevelopment, the office/R&D land use category described for the Gateway development area was considered as office space. Office development typically generates a slightly higher number of trips than R&D development, so the treatment of the combined category as office space would result in a conservative assessment of traffic impacts. The ancillary retail spaces located in the Gateway development area and the 16th/Wood area were treated as office space because the retail would serve the offices. The ITE trip generation rates for offices include office buildings with a variety of tenant services including service retail facilities.
Page 4.3-21
April 2002
Page 4.3-22
April 2002
Origin or Destination Within Local Study Area Oakland/San Leandro SR 24 I-580 East I-880 South Grand E. of I-80 th 7 Street MacArthur Blvd Emeryville/Berkeley I-80 Frontage Road San Pablo Avenue Ashby Avenue Powell Street Alameda Constitution Way Webster Street Total
Sources:
5% 8% 6% 6% 4% 2% 1% 1% 1% 1% 2% 2% 100%
2% 8% 10% 3% 2%
3% 6% 5% 16% 9% 2% 1% 1% 1% 1% 2% 2% 100%
100%
1 2 3 4 5 6 7 8 9 10 11 Public Review Draft Page 4.3-23 April 2002 Significance Criteria Redevelopment would have a significant effect on the environment if it would: Cause an increase in traffic which is substantial in relation to the existing or future baseline traffic load and capacity of the street system (i.e., result in a substantial increase in either the number of vehicle trips, the volume to capacity ratio on roads, or congestion at intersections), or change the condition of an existing street (i.e., street closures, changing direction of travel) in a manner that would substantially impact access or traffic load and capacity of the street system. Specifically, redevelopment would have a significant effect on the environment if it would:
Figure 4.3-5 2
Page 4.3-24
April 2002
Figure 4.3-6 2
Page 4.3-25
April 2002
Cause a roadway segment on the Metropolitan Transportation System (MTS) to operate at LOS F or increase the V/C ratio by more than three (3) percent for a roadway segment that would operate at LOS F without redevelopment6;
Downtown is defined in the Land Use Transportation Element of the General Plan (page 67) as the area generally bounded by West Grand Avenue to the north, Lake Merritt and Channel Park to the east, the Oakland Estuary to the south and I-980/Brush Street to the west. LOS and delay are based on the Highway Capacity Manual, Transportation Research Board, National Research Council, 1985, as required by the Alameda County CMA.
Page 4.3-26
April 2002
Not all criteria listed above apply to proposed redevelopment. Redevelopment would not result in a change in air traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks. Impacts Benefits Redevelopment would substantially reduce hazards to bicyclists and pedestrians in the redevelopment project area. Redevelopment and implementation of Caltrans public access Public Review Draft Page 4.3-27 April 2002
Significant West Grand Avenue/Maritime Street. As part of the design for the realignment of Maritime Street, the Port shall also provide modifications to the West Grand Avenue/Maritime Street intersection. West Grand Avenue/I-880 Frontage Road. Project area developers shall fund, on a fair-share basis, modifications to the West Grand Avenue/I-880 Frontage Road intersection. 7th/Maritime Street. As part of the design for the realignment of Maritime Street, the Port shall also provide modifications to the 7th/Maritime Street intersection.
Mitigation 4.3-2:
Mitigation 4.3-3:
Residual Significance: Less than significant Redevelopment would generate 5,800 trips during the a.m. peak hour and 5,500 trips during the p.m. peak hour. Redevelopment traffic would cause the level of service to degrade to worse Public Review Draft Page 4.3-28 April 2002
than LOS D at the three intersections listed above. The impact is considered to be significant. With implementation of Mitigation Measures 4.3-1, 4.3-2, and 4.3-3 the impact would be substantially reduced, and the residual impact would be less than significant. The impact of redevelopment on study area intersections is summarized in Table 4.3-8. The reduction of those impacts by the proposed mitigation measures is shown in Table 4.3-9.
Page 4.3-29
April 2002
Powell Street/I-80 Frontage Road Powell Street/I-80 NB Ramps Powell Street/Christie Street Powell Street/Hollis Street Powell Street/San Pablo Av Stanford Avenue/Market Street Stanford Avenue/MLK Jr. Way Ashby Avenue/7 th Street Ashby Avenue/San Pablo Av Marina Village/Constitution Way Atlantic Avenue/Webster Street Atlantic Avenue/Constitution Way Loop Road/GDA Spine Road Source: Dowling Associates 2002. Notes: Significant impacts of redevelopment are shown in Boldface Italics. a Delay in seconds per vehicle. b Defined as a downtown intersection.
1
Table 4.3-9 Operations at Impacted Intersections After Mitigation Existing Plus Redevelopment Peak Hour Intersection
West Grand Avenue/Maritime Street West Grand Avenue/I-880 Frontage Road 7th Street/Maritime Street LOS F E F A.M. Delaya 298.1 79.6 126.8 LOS F F E P.M. Delaya 262.6 171.1 78.5
Source: Dowling Associates 2002. Notes: Significant impacts of redevelopment are shown in Boldface Italics. a Delay in seconds per vehicle. b Defined as a downtown intersection. c Significant impacts at unsignalized intersections are based on signal warrants not delay.
2 3 4 5 6 7 8 Impact 4.3-2:
Redevelopment would cause some roadway segments on the MTS to operate at LOS F and increase the V/C ratio by more than three percent on segments that would operate at LOS F without redevelopment. Significant Page 4.3-30 April 2002
Residual Significance: Significant and unavoidable Redevelopment would add substantial traffic to roadway segments on the MTS. Redevelopment would cause the following freeway segments on the MTS to operate at LOS F or increase the V/C ratio by more than three (3) percent for segments that would operate at LOS F without redevelopment: I-80 east of the I-80/I-580 split I-880 connector to I-80 east I-880 from 7th Street to the segment south of I-238 I-580 east and west of I-980/SR-24 SR-24 east of I-580
The impact is considered significant. Implementation of Mitigation Measure 4.3-4 would reduce traffic demand on the MTS, but the residual impact to existing congested freeway segments would remain significant, and the impact is considered unavoidable. Mitigation Measure 4.4-5, intended to primarily mitigate air quality impacts, would also reduce traffic impacts, but not to a level that is less than significant. No feasible mitigation measures have been identified that would reduce freeway impacts to a level that is less than significant. Increasing freeway capacity by adding lanes would not be feasible because of high cost, negative impacts to air quality, and other factors. Moreover, adding lanes is inconsistent with the policies of the responsible regional agencies. Other roadway segments on the MTS were evaluated as part of the CMP analysis prepared to satisfy requirements of the Alameda County CMA. No roadway segments were shown to be significantly impacted in that analysis. The CMP analysis showed that the Posey-Webster Tubes would operate at LOS F during the a.m. and p.m. peak hours with or without redevelopment. Traffic from redevelopment would represent 1.1 percent of total traffic at the Posey-Webster Tubes during the a.m. peak hour and less than 1 percent during the p.m. peak hour. Analysis tables for freeway segments and the CMP analysis are included in Appendix 4.3.
A major developer is defined as a City, Port, or private developer of more than 20,000 square feet of employmentgenerating space, or facilities generating more than 100 jobs.
Page 4.3-31
April 2002
Mitigation 4.3-6:
Mitigation 4.3-7:
Residual Significance: Less than significant The redevelopment project area will have a variety of land uses that would attract a range of travelers, including bicyclists and pedestrians accessing the park land along the waterfront, commuter vehicles traveling to and from employment centers within the project area, and Portrelated trucks. This mix of unlike travel modes combined with increased traffic could increase hazards. Because occurrence of this impact depends on site-specific design not currently defined, the impact is considered potentially significant. With implementation of Mitigation Measures 4.3-5, 4.3-6, and 4.3-7, the impact would be minimized, and the residual impact would be less than significant. Due to site constraints, it may not be possible to provide two emergency access routes to the western portion of the Gateway development area, which w ould be in excess of 1,000 feet from the nearest major arterial. Potentially significant Construct an emergency vehicle access to the western portion of the Gateway development area or provide an emergency service program and emergency evacuation plan using waterborne vessels.
Page 4.3-32
April 2002
Mitigation:
Residual Significance: Less than significant Final site plans for the redevelopment project area have not been developed, and it is not known if redevelopment would conflict with adopted policies, plans, or programs supporting alternative transportation. Because occurrence of this impact depends on site-specific designs not currently defined, the impact is considered potentially significant. With implementation of Mitigation Measures 4.3-4 and 4.3-9, the impact would be minimized, and the residual impact would be less than significant. Redevelopment could result in an inadequate parking supply at the Gateway development area, the 16th/Wood sub-district, or for trucks serving the Port of Oakland. Potentially significant The number of parking spaces provided in the project area shall comply with City code or Port requirements and/or with recommendations of a developer funded parking demand analysis. During both construction and operation, the Port shall provide truck parking within the Port development area or Maritime sub-district, at a reasonable cost to truck operators and provide advance information to operators where the parking is located. Page 4.3-33 April 2002
Mitigation 4.3-11:
Significance: Mitigation:
Redevelopment would increase transit ridership on existing AC transit routes serving the redevelopment project area. The demand for transit service would be highly directional predominantly toward the redevelopment project area during the morning peak hour and away from the development project area during the evening peak hour. A summary of transit ridership is shown in Table 4.3-10. Although redevelopment would essentially double the AC Transit ridership between the redevelopment project area and downtown, there is enough capacity on the AC Transit routes to accommodate the additional demand. Because the average load factor with redevelopment in place would not exceed 125 percent over a 30-minute period, the impact is considered less than significant.
Table 4.3-10 AC Transit Riders Existin g AM PM 47 18 27 19 15 40 21 37 Redevelopment Total with Load Factor with a,b (New Riders) Redevelopment Redevelopment AM PM AM PM AM PM 9 54 56 72 60% 77% 58 37 8 11 10 39 85 56 23 51 31 76 91% 59% 24% 55% 33% 80%
Sources: AC Transit 1998 Boarding & Alighting Survey 1998 and Alameda Countywide Model 2002. Notes: a The table includes AC Transit riders between the redevelopment project area and downtown during peak 30minute periods. b Approximately 4.5 percent of redevelopment trips would use AC Transit.
Significance: Mitigation:
The number of BART riders during both the morning and evening peak commute hour is approximately 19,500 at the West Oakland BART station. Redevelopment would add about 410 peak hour trips to BART during the peak hours 2.1 percent of existing ridership. BART is currently studying system-wide capacity issues and will be adjusting service to match demand. A preliminary assessment by BART staff suggests that the capacity impact of redevelopment would be minimal (BART 2002). Because redevelopment would not increase peak hour average ridership three percent on BART, the impact is considered less than significant. Redevelopment would increase the peak hour average ridership at the West Oakland BART station by 3 percent where average waiting time at fare gates could exceed 1 minute. Potentially significant The City and Port shall provide detailed information regarding redevelopment to BART to enable BART to conduct a comprehensive fare gate capacity assessment at the West Oakland BART station. Pending the results of this assessment, the City and the Port may need to participate in funding the cost of adding one or more fare gates at the West Oakland BART station.
Residual Significance: Less than significant Approximately 1,010 BART riders enter or exit the West Oakland BART station during both the morning and evening peak commute hour. Redevelopment would add about 410 peak hour riders to the West Oakland BART station during the peak hours 41 percent of existing ridership. Most of the BART users added by redevelopment would exit the station during the morning peak and enter the station during the evening peak commuter period in the opposite direction of the current peak demand, as shown in Table 4.3-11. There are five fare gates at the station two for entering, two for exiting passengers, and one reversible gate that serves the peak direction of passenger flow. BART staff has indicated that delays are sometimes a problem for the peak direction at the station. Redevelopment would increase demand for the peak direction of flow at the fare gates by about seven percent. Because it is possible redevelopment could result in an average waiting time exceeding one minute at the West Public Review Draft Page 4.3-35 April 2002
Source: BART Data Acquisition System 2002. Note: a Approximately 8 percent of redevelopment trips would use BART.
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Impact 4.3-11: Impact 4.3-10: Construction of New Berth 21 could cause minor delays to commercial vessels plying their trade. Less than significant Mitigation is not warranted.
Significance: Mitigation:
Dredging equipment would be present in Outer Harbor for a short period of time. The equipment would operate along the east bank of the Outer Harbor channel at its far end out of the way of most vessel traffic. Dredging equipment would be highly visible, and would be well marked in accordance with U.S. Coast Guard regulations. It is estimated that the vast majority of the fill material required for construction of New Berth 21 would arrive by barge, probably from maintenance dredging or from the Bay Bridge reconstruction project. There is a potential for very minor delays to commercial vessels because ferries, work-boats, and other vessels generating powerful wakes would have to slow when passing barges or dredges being transported to and from the work site. However, the delays would not be frequent and would be within normally accepted practices for a busy port complex. The construction of New Berth 21 would not cause unreasonable delays to commercial vehicles plying their trade, and the impact would be less than significant. Remediation, demolition/deconstruction, and construction activities within the redevelopment project area would utilize a significant number of trucks and could cause significant circulation impacts on the street system. Page 4.3-36 April 2002
Potentially significant Prior to commencing hazardous materials or hazardous waste remediation, demolition, or construction activities, a Traffic Control Plan (TCP) shall be implemented to control peak hours trips to the extent feasible, assure the safety on the street system and assure that transportation activities are protective of human health, safety, and the environment. Less than significant
Residual Significance:
Construction and/or remediation would generate haul, delivery, and employee trips. Construction and remediation generally involve large diesel transport trucks. For traffic impacts, transport trucks are considered equivalent to two passenger cars. Remediation vehicles include those transporting both hazardous materials and hazardous waste. These trips may substantially degrade LOS on area roadways and the impact is considered potentially significant. Because occurrence of this impact depends on details of construction/remediation timing and the exact amount and location of related traffic not currently developed, the impact is considered potentially significant. With implementation of Mitigation Measure 4.3-13, the impact would be substantially reduced, and the residual impact would be less than significant.
W. Grand Ave
Maritime St
Before Mitigation
After Mitigation
a. 1 left turn lane b. 1 combination left-through lane c. 2 right turn lanes with overlap signal phasing (green arrow) Public Review Draft Page 4.3-37
April 2002
Maritime St
2. Revise southbound Maritime Street (formerly Wake Avenue) lanes to provide: a. 1 left turn lane b. 1 combination through-right lane c. 1 right-turn lane 3. Revise eastbound West Grand Avenue exit ramp to provide: a. 1 left turn lane b. 2 through lanes c. 1 right turn lane with a receiving third southbound lane south of the intersection (free right) 4. Revise westbound West Grand Avenue to provide: a. 1 left turn lane b. 1 combination left-through lane c. 1 combination through-right lane 5. Provide split signal phasing for east and westbound traffic movements on West Grand Avenue 6. Increase the traffic signal cycle length to 124 seconds. Mitigation 4.3-2: West Grand Avenue/I-880 Frontage Road. Project area developers shall fund, on a fair share basis, modifications to the West Grand Avenue/I-880 Frontage Road intersection. This measure applies to Impact 4.3-1 and Cumulative Impact 5.3-1.
Split Phase
W. Grand Ave
W. Grand Ave
I-880 Frontage Rd
Split Phase
The following modifications shall be made at the West Grand Avenue/I-880 Frontage Road intersection:
After Mitigation
1. Revise the northbound Frontage Road lanes to provide: a. 1 left-turn lane b. 1 combination left-through lane c. 1 combination through-right lane Public Review Draft Page 4.3-38
April 2002
I-880 Frontage Rd
5. Increase the traffic signal cycle length to 124 seconds. Mitigation 4.3-3: 7th/Maritime Street. As part of the design for realignment of Maritime Street, the Port shall also provide modifications to the 7th/Maritime Street intersection. This measure applies to Impact 4.3-1 and Cumulative Impact 5.3-1. The following modifications shall be made at the 7th /Maritime Street intersection: 1. Revise the southbound Maritime Street lanes to provide: a. 1 left-turn lane b. 1 combination left-through lane c. 1 combination through-right lane
Maritime St
7th St
After Mitigation
2. Revise the westbound 7th Street lanes to provide: a. 2 left-turn lanes Public Review Draft Page 4.3-39 April 2002
Maritime St
The plan shall include strategies designed to promote transit use and increase availability of transit opportunities within the project area, including, but not limited to the following: Coordination with AC Transit to provide expanded bus service with no greater than 30 minute peak commute hour headways to major employment centers. Coordination with BART to provide shuttle service with no greater than 15 minute peak commute hour headways between the West Oakland BART station and major employment centers Provision of employer incentives to use alternative transit modes, such as Flash passes or transit reimbursements
These measures shall be coordinated with BAAQMD and CAP Transportation Control Measures (TCMs) implemented under Mitigation Measure 4.4-5. The Transit Access Plan shall be funded at a level that would enable the goal of a 15 percent reduction in single-occupancy, peak hour ridership. Mitigation 4.3-5: Redevelopment elements shall be designed in accordance with standard design practice and shall be subject to review and approval of the City or Port design engineer. This measure applies to Impact 4.3-3 and Cumulative Impact 5.3-3. Through design review, the City and/or Port, as applicable, shall ensure the design of roadways, bicycle and pedestrian facilities, parking lots, and other transportation features comply with design standards and disallow design proposals that likely to result in traffic hazards. Any mitigation or redevelopment features that may directly affect Caltrans facilities shall be submitted for review by that agency. Mitigation 4.3-6: The Port shall fund signage designating through transport truck prohibitions through the interior of the Gateway development area. This measure applies to Impact 4.3-3.
Page 4.3-41
April 2002
Page 4.3-45
April 2002