The document discusses project execution and control processes including change control, issue management, risk control, project tracking and monitoring. These processes ensure the project progresses according to plan and any changes, issues or risks are properly addressed.
The document discusses project execution and control processes including change control, issue management, risk control, project tracking and monitoring. These processes ensure the project progresses according to plan and any changes, issues or risks are properly addressed.
WHAT HAPPENS DURING PROJECT EXECUTION?....................................................3 MANAGEMENT DURING PROJECT EXECUTION.........................................................3 PROJECT CONTROL PROCESSES..................................................................................................................4 PROJECT CONTROL PROCESS....................................................................................5 CHANGE CONTROL........................................................................................................6 CHANGE CONTROL DURING PROJECT EXECUTION.........................................................................................6 CHANGE CONTROL PROCESS.....................................................................................8 THE CHANGE CONTROL FORM .....................................................................................................................9 WHAT IS ISSUE MANAGEMENT?................................................................................11 ISSUE MANAGEMENT PROCESS................................................................................12 THE ISSUE RESOLUTION FORM...................................................................................................................13 CORRECTIVE ACTIONS DURING PROJECT EXECUTION ........................................15 SOURCES OF PROJECT PROBLEMS ............................................................................................................15 FIXING A PROBLEM WITH A RECOVERY PLAN ..............................................................................................16 THE FORMAL REVIEW PROCESS...............................................................................17 THE INFORMAL REVIEW PROCESS...........................................................................17 THE STATUS REVIEW.................................................................................................................................18 A MODEL MEETING AGENDA......................................................................................................................19 EXECUTIVE STEERING COMMITTEE MEETINGS.............................................................................................20 RISK CONTROL.............................................................................................................20 Project Execution and Control
RISK MONITORING AND MITIGATION DURING PROJECT EXECUTION ..............................................................20 RISK MONITORING IS AN ITERATIVE PROCESS.............................................................................................21 RISK CONTROL CYCLE...............................................................................................................................21 THE ROLE OF THE RISK MANAGER .............................................................................................................22 RISK MEETINGS.........................................................................................................................................22 ON-GOING RISK IDENTIFICATION.................................................................................................................22 RISK RESOLUTION.......................................................................................................23 PROJECT TRACKING AND MONITORING..................................................................24 EXAMPLE - PROJECT TRACKING MATRIX................................................................28 ACTIVITY AND SCHEDULE TRACKING ..........................................................................................................30 PROJECT SCHEDULE UPDATE...................................................................................31 WHAT IS PROJECT MONITORING? ............................................................................31 FINANCIAL METRICS ..................................................................................................................................37 PROJECT TRACKING AND REPORTING PROCESS.........................................................................................41 THE STATUS REPORT PACKAGE.................................................................................................................42 INDEPENDENT REVIEWS .............................................................................................................................42 MANAGING EXTERNAL PROJECT MANAGERS........................................................44 EXTERNAL PM PROCESS...........................................................................................................................45
Once a project reaches the execution process, the Project Plan should have been fine-tuned and baselined, and a Project Team and the necessary resources should be in place to produce the project deliverables. The Project Manager now focuses on working the plan. This process is graphically presented below.
Management during Project Execution BaselinePlan Established Updateto BaselineDone as Needed ChangeControl, Risk Management and Issue Identification Done Project is Executed Project is Tracked, Monitored, and Reviewed
The focus of project management during the execution process is to: Track and monitor project activities to measure actual performance to planned performance Review and communicate status and future actions Monitor and mitigate potential risks Execute a rigorous change management process to control changes to the projects objectives, specifications and overall definition Execute an issue tracking process to ensure that there is a central repository for project issues that are addressed in a timely fashion Project Execution and Control
Have in place a process to document and track plans to correct an issue that impacts the plan and which establishes guidelines for updates. Project Control Processes
The Project Plan serves as the basis for the project's monitoring, controlling and reporting activities. By following the Plan and gathering data for the status meetings and reports, information will be available to accurately identify any concerns or problems.
Once a project has been baselined and project execution starts, then it needs to be controlled. This section deals with the control of the project after start-up. This involves processes that should be in place to ensure that the project progresses according to the Project Plan. During tracking, monitoring and reviewing, the Project Team collects data to assess the status of the project. These activities always include: Reviewing the completed activities and comparing to plan Identifying milestones reached and comparing to plan Identifying deliverables completed comparing to plan Identifying problems or issues.
Project control activities that may be needed include: Addressing issues Reviewing change requests and taking action on them Preparing action plans to deal with planned and unplanned risks Rescheduling as necessary and as approved by the Steering Committee, Sponsor or stakeholders. Reallocating resources to adjust for productivity variances Adding resources and/or equipment to deal with changed scope Updating project schedule and progress information Updating budget and variances.
The next figure presents a graphic view of the project control process.
There are three processes that will significantly increase the chances of project success and will help with the overall management of the project. These processes are collectively referred to as Change Management and include: Change Management Issue Management Version Management
During planning, the management approach for these areas is identified. At start-up, responsibility for these areas should be assigned, and these processes should be in place and working. In many regards, the processes are similar and the purposes are the same -- to help control the project. At times, a requester may not be sure if an item is a change or an issue. In fact, many times an item will start in the issue process and end up in the change process.
The difference between an issue and a change rests in how a project is impacted. Change, as indicated in its name, affects the view of the project and will impact the project scope or product scope, e.g. project definition, and/or specification.
Issues may not have an impact on the defined projects product scope or project scope. Issues are identified in the form of questions, problems or suggestions raised by the Project Team, management, or contractor. If they become a change request, they can often affect the status of tasks or deliverables, which would result in changes to cost and schedule.
Version management or version control is important to ensure a quality product, to minimize errors and to minimize duplication of effort. Version control is a process used to control the release and installation of versions of potentially any deliverable produced by the project team. It is similar to change and issue management because it requires the same level of focus. A project without good version control processes is at high risk of project failure.
You Can't Manage What You Don't Control
As discussed earlier, too much change in a project is one of the major reasons projects fail. This is the area in which Project Managers continually lose control. One reason is a lack of discipline within the Project Team and with the customer to resist changing the stated deliverable of the project. A solution is to establish a critical baseline of the projects deliverable and to document it. These documents are the Project Plan, the product specification, and other development documents that are placed under Change Management. Whenever a question is raised about changing the project or deliverable, the baseline documents are always the reference point. Anything that alters the baseline is a change.
If an individual is not sure if it is a change, then treat it as an issue.
Part of controlling a project is to have established change management processes. These processes are established, or at least reviewed, as part of the planning process and kept current until project close-out.
The key elements to these processes are: A central repository for change, issue and version information Summary of information for the processes on either a change request form or issue form Detailed and well understood change management processes Assignment of a responsible person to track change management by the Project Manager, Project Sponsor or Steering Committee The change management process can be managed by either the Project Manager or a member of the Project Team Inclusion of change and issue summary information as part of the standard project status meetings Consistent and ongoing evaluation of change and issue items and development of appropriate resolution/implementation strategies.
To maintain the balance between requirements and the schedule, the project team should use a well-defined Change Management Process. This process allows for change during the project's life cycle, but always puts the change in the context of the latest version of the approved Project Plan. This version is called the current baseline.
The change management process consists of a series of steps that allows changes to be identified, evaluated, priced and tracked through closure. If the change is significant, you should perform a Cost Schedule Impact Analysis (CSIA). A CSIA is a detailed analysis of what the change might cost and what impact it might have on the project schedule. This analysis is performed and approved under the direction of the Project Sponsor and the Steering Committee.
The process defined in the following figure may be too complex for some projects and not complex enough for others. It portrays an overall flow of a change request within a change management framework. In any case, the goal is for projects to implement and use a process that fits the project and the organization.
Stakeholders may submit a change request on any desired change to the planned work or the features or functions of any planned products. An approved change control form should be submitted, and after the related authorization has been completed, changes would be implemented. This might impact project plan and budget.
The change control form is included in Appendix B: Forms.
The form is additive. In other words, additional information is completed on the form as it moves through the process. This process is iterative in that it will keep occurring until the project is complete.
Section 1 - Requester Information
The change control form includes the following:
Identification Block - is completed by the requester and identifies the change request title, which will be used in subsequent communication, the date submitted, and the person and organization submitting the request.
Proposed Change Description and References - describes the change being proposed and clearly identifies whether the change is system, organizational, procedural or product related. Any reference material that will assist the reviewers should be identified and attached.
J ustification - a discussion of why the change is being proposed, including a cost benefit analysis, if already complete. In summary, the requestor should define how the organization will benefit from the change.
Impact Statement - if the change is not implemented, how will it adversely affect the customer and organization?
Alternatives - list at least one alternative (more if possible) to the change you are proposing, and briefly indicate why the proposed change is better.
When complete, submit to the Project Manager or appropriate individual. At that time, a control number will be assigned so it can be tracked to resolution.
Section 2 - Initial Review of the Change Request
All change requests will be reviewed on a regular basis by the Project Manager, Project Sponsor and, if necessary, the Steering Committee. The actual schedule will depend on where the Project Team is in terms of the project life cycle. The Project Manager will drive the schedule based on the number and complexity of change requests.
As part of phase 2 of the change control process, the appropriate person will complete the second part of the form, which includes:
Initial review results and disposition - the Project Manager will review the initial request and determine whether to proceed, reject or defer the request. In moving forward, the request may be assigned to an analyst for further analysis.
Section 3: Initial Impact Analysis
The assigned team members will make an initial assessment of the cost, schedule and resources needed to implement the proposed change. If the requested change is complex, and an initial assessment cannot be made quickly, a Cost/Schedule Impact Analysis (CSIA) should be requested.
The analyst will indicate this and will estimate the cost, schedule and resources needed to perform the CSIA.
The Project Sponsor or Steering Committee will once again review the requested change and either accept, reject or defer the change.
Section 4: Final Review Results and Change Priority
When the analysis has been completed, and if the change is approved by the Project Manager or Project Sponsor, and if it exceeds their approved budget level, the Project Manager will submit the change to the Steering Committee for review.
If approved, the appropriate processes will be followed to update contracts and the baseline documents.
PMBOK defines an issue as a point or matter in question or in dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements. Issue management is a process that provides a mechanism to process and review issues. Issues that develop during the project need a way to be raised by the Project Team and for the Team to know that they will be addressed.
When issues arise, they need to be resolved in a consistent and disciplined manner in order to maintain the quality of the deliverable, as well as to control schedules and cost. The issue management process ensures that the differences, questions and unplanned requests are defined properly, escalated for management attention and resolved quickly and efficiently.
The issue management process should handle technical problems or issues, as well as process, organizational and operational issues. The process considers:
Appropriate procedures for issue escalation Level of management that needs to be involved for escalation Required time for resolution Responsibility for researching or resolving the issue.
The following chart is a generic process for submitting, reviewing and gaining closure on an issue within a project. This is a process that may be too complex for some projects and not complex enough for others. The goal is for projects to implement and use a process that fits the project and the organization. Project Execution and Control
Issue Management Process Business Issue or Technical Issue "Individual" Resolution Resolved ? P roject Status Team Review Conduct Research and Report Results Resolved? Executive Management Review Document Resolution Does Resolution Lead to Change P roblem Closure Go to Change P rocess By P M or Sponsor using Informal P rocesses Y N Y Y N N Project Execution and Control
The issue resolution form gives everyone involved with the project a way to report issues or problems. It provides a template for documenting the issue, assessing the impact of the issue and making recommendations. If it becomes a change request, it provides a mechanism for documenting the Cost and Schedule Impact Analysis.
The issue process is also iterative in that it will keep occurring until the issue is closed or the project is complete.
Section 1 - Requester Information
The issue resolution form is included in Appendix B: Forms.
The issue resolution form is divided into major categories. The first part is completed by the person reporting the issue. Its major categories include:
Identification block - identifies the issue title, which will be used in subsequent communication, the date submitted, and the person and organization submitting the issue.
Issue classification and description - Description of issue Recommendations, if any Impact (if not resolved) Date required and proposed assignee.
Each category should be self-explanatory, but individuals should be directed to the Change Manager for assistance, as needed. Attach any supporting documentation that helps clarify the problem or issue, such as report outputs, customer screens being used, the steps performed leading to the problem, error messages, etc. When complete, submit to the Change Manager. At that time, a control number will be assigned so that the issue can be tracked to completion.
Section 2 - Initial Review of the Issue
All issues should be reviewed on a regular basis at the project team status meetings.
The group will complete the second part of the form which includes:
Reviewer information and initial comments Estimate of additional effort, if appropriate If the issue becomes a change, responsible person and planned completion date Signatures. Project Execution and Control
All items will be tracked until they are resolved either by closure or by moving to the change control process. The Change Manager will report on all open issues at the status meetings. If the list of issues is too long, only the new or key issues should be discussed. At times, it may be advisable to pre-distribute issue information so that the group can review the material before the meeting. Major issues and their resolution should always be reported to the Project Sponsor or Steering Committee.
Section 4: Final Review Results and Change Priority
When the issue or problem has been resolved, verified and documented the issue is closed.
If the issue does become a change, the process is to transfer the issue to the change control process and track it as a change request.
When a project encounters problems, they need to be evaluated and decisions made on corrective actions. If the project is off schedule or over budget, steps should be taken to determine the following:
Is the project still meeting its original objectives? Are the issues so great that the project must be adjusted? Can the project meet the documented organizations business needs?
The corrective action process can go hand-in-hand with the change control process; however, the change control process is not intended to solve problems that need to be addressed in an urgent manner or where there is a question on the stability of the project.
Generally, problems that fall into the category of needing corrective action require immediate action by the Project Management Team and the Steering Committee. Sources of Project Problems
Situations that normally require corrective actions fall into the following categories:
Internal Examples: A task or group of tasks is significantly behind schedule or over budget, and it impacts the overall Project Plan A major milestone is missed The functionality of the project deliverables are not meeting project objectives Critical path dates are being missed.
External Examples: A major problem may have surfaced, and the resolution to the problem does not allow the project to be developed as specified The organization environment has changed, and the current IT project is not part of the solution for meeting the defined business needs Regulatory changes have occurred Funding has been withdrawn or modified.
All of the internal situations identified above represent increasing severity for the Project Team. They span a wide range of possible solutions ranging from simple additional attention at the status meeting to developing complete and detailed corrective plans or actually stopping the project.
A key part of project management is providing immediate action to identified problems and developing successful corrective plans. Corrective action plans can take the form of updates, reallocating resources or changing the way the project is coordinated or organized.
Corrective action that was planned as a result of risk planning is referred to as contingency actions. Corrective action that was unplanned is referred to as a workaround.
The corrective actions available revolve around balancing the cost, schedule and technical performance parameters of the project. However, stakeholders and executive managers should also be involved at an early point in the process. They have the ability to impact the corrective action process by shifting business priorities, reaffirming their support for the project and showing commitment to having it updated. If they are not brought in early, their support may be more difficult to obtain.
Fixing a Problem with a Recovery Plan
An effective control process doesnt just track, monitor and review, but it also re-directs the project if a major problem occurs. The first rule is to try and protect the overall integrity of the project charter and the project schedule by developing a Recovery Plan. The goals of the Recovery Plan are to:
Fix the problem quickly Limit the damage.
Detailed recovery plans should be put in place if a problem will cause harm to cost, schedule or quality of the project. The Recovery Plan should:
Identify the owner of the Recovery Plan Identify the sequence of activities that must occur to complete the resolution Determine the dates when each activity of the Plan will be started and completed, and identify the dependencies of each activity Ensure that the appropriate people approve the Recovery Plan Reflect the outcome, if the Recovery Plan is successful, in terms of schedule, activities modification and cost.
All recovery plans should be tracked following the reporting guidelines covered in the Tracking and Monitoring section of this chapter.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 17
The Formal Review Process
J ust as tracking and monitoring are critical to controlling a project, so too is reviewing. One of the major causes of a project getting off schedule is the lack of attention to:
Formal and consistent project reviews Setting up and using informal assessment methods.
The focus of project reviews is to ensure that information is being shared, communicated and evaluated. Where tracking and monitoring focused on the process of measuring actual project performance to the baseline, reviewing focuses on sharing that data and other related information with the project stakeholders.
As in all other areas of project management, the review process needs to be tailored to the specific project. However, there are some minimum review activities that should be performed. All of these should be in the Project Plan:
Detailed design reviews, design walkthroughs and peer reviews Status meetings should be conducted by project team leaders as needed Executive reviews - as needed Quality assurance audits - as needed; will depend on the size of the project and the risk. However, each organization is encouraged to develop its own schedules and standards for quality reviews.
The Informal Review Process
The informal reviews are the processes that the Project Manager and key project staff set up to measure the atmosphere of the project. This is sometimes referred to as Management By Walking Around (MBWA).
This information can be gathered by: Walking the halls Visiting team work areas Sitting in on some team status meetings
The purpose of informal reviews is to get input from all parties on issues beyond what is presented in the formal reviews. Formal reviews often limit the open exchange of information. By talking with one team member, it might be discovered that a key technical staff member is very unhappy about some decisions on the project. This unhappiness might escalate to the point where a person would leave the project, and/or it could develop into a major problem.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 18
Part of the Project Managers strategy includes collecting information and interjecting it into the formal processes where it can then be analyzed to determine if actions are required.
Lastly, the way a project is organized will drive the way the project is reviewed. Each key project activity needs to be tracked and reviewed as such, and the person or group responsible for the activities will need to provide input to the control process.
The Status Review
The cornerstone of the project review process is the project status meeting with the key team members. The Project Team should know that this meeting is not optional. For this reason, it is recommended that status meetings occur regularly and consistently throughout the project life cycle. Meeting too often is disruptive and does not allow the Project Team to focus on other tasks. Not meeting enough will allow issues to go unresolved.
Some projects set up the project status meeting on the same day, at the same time and at the same place. Another consideration is that the meeting time should be on Tuesday, Wednesday or Thursday to avoid Mondays and Fridays, due to scheduling conflicts. By providing a consistent schedule, a routine can be established. Consistent meetings also drive a discipline into the project organization.
The purpose of the project status meeting is to coordinate the schedule, resource and financial needs of the project. The objective will be to share and receive data and to make group decisions critical to the Project Plan. Areas of prime interest are the financial, schedule, quality and technical issues of each group and how they work together within the overall project structure. Another objective of the status meetings is to gather information that will eventually go into the project status report.
The first project status meeting serves as a training session for the participants. The training session covers how future meetings will be conducted and what each participants roles and responsibilities will be during and after the meeting. Preparation for this meeting is critical and should lead to the generation of the project status report.
The following topics should be covered in the first meeting: What is the baseline Project Plan? How are risks to be managed and reported? How will changes and issues be tracked and reviewed? Who will keep the schedule and cost information, and how will it be updated for review? What are key lessons learned from other projects? Who will be the reporter or scribe for the team meetings? When will expected meetings take place? How will quality be evaluated and measured? How will behavior and performance guidelines be created?
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 19
After the initial orientation meetings, attendees serving on a large project might be specifically selected and the numbers limited. They should consist of individuals who can provide status information and contribute to issues, risks and general status discussions.
As a guideline, if the Project Team is small (12 or less), then the full Project Team may attend. If the Project Team numbers over 12, then only lead team members (planning, development, test, quality, etc.) should attend.
The bottom line is that the persons attending the meeting communicate the status of the project activities and action items for their assigned area of responsibility. However, the number of attendees should be controlled so that the group is not too large to be productive.
A location should be selected that will provide the fewest disruptions. It should not be in someones office or in a public area. A conference room where telephones can be controlled is a good location. Disruptions cause the meeting to appear disorganized and cause the length to extend. This results in people not wanting to attend because it is viewed as a waste of time.
A Model Meeting Agenda
All meetings should have an agenda. Since a large percentage of project time is spent in meetings of one form or another, a set of rules should be applied to each meeting type. These rules follow standard meeting management principles: Start and end on time Come prepared Bring handouts; information should not just be in the attendee's head Summarize information; do not read it Bring minutes from the last meeting. A list of action items and resolutions should be the by-products from the meeting. The action items and discussion topics should be written up and disseminated. If a project action item, change request, issue or new risk element is mentioned, then the support person responsible for distributing the status meeting information should ensure that the responsible Project Team member is informed.
Since a Project Manager is responsible for reporting on the projects status to other levels of the organization, written materials are needed to complete the necessary reports.
If significant tasks are not on schedule, then the responsible person should address: Why the task completion is late or early What other areas might become impacted What actions need to be taken?
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 20
Executive Steering Committee Meetings If appropriate for your project, conduct a monthly or quarterly meeting with executives who are not on the Steering Committee, but have a large vested interest in the success of the project. The timing of this meeting should be built into the Project Plan.
Risk Control
Risk Monitoring and Mitigation during Project Execution
Risk monitoring and mitigation are key processes needed to successfully complete a project. Part of controlling a project during the execution process is to have an established risk management process that is relevant to the size, type and risk of the project. This process begins as part of project planning and is kept current until project close-out. The key elements to this process are: Creating a central repository for risk information and associated documentation of risk items and resolution strategies Documenting risk information on a risk analysis worksheet Including a risk summary report in the regular status meetings Providing a consistent and ongoing evaluation of risk items and development of risk strategies: Identify the risk Evaluate the risk and assess its potential impact Define a resolution strategy Implement the strategy Track and monitor the risk.
The risk control process begins in project planning, is baselined at project startup and is fully maintained during project execution. The key is not the format of the data but that the Risk Management Plan is kept current during the execution process.
Remember, risks are not events that have occurred but events that might occur that would adversely impact the project. Events that have occurred and are impacting the project are addressed in the change management, issue management or exception reporting process.
As the project evolves through the project life cycle, the ability to define and specify the risk items increases. This is attributable to the fact that more is known about the project and the associated issues. This allows for the development of realistic contingency plans, including specific action plans. These actions are then tracked. The Risk Management Plan should reflect these activities.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 21
Risk Monitoring is an Iterative Process
Risk analysis is an iterative process that is performed throughout the project. Risk analysis examines the risk and its potential impact on the project. Risk planning defines actions to eliminate or to mitigate the impact of that risk should it occur. The process starts with the risks identified in the Project Plan and the first definition of resolution strategies. There are typically three types of resolution strategies: eliminating, reducing or accepting. The risk management process, as defined in Chapter 3, includes five overlapping steps: Risk identification Risk assessment and prioritization or risk analysis Risk reduction and contingency planning Risk management plan execution Risk tracking and reviewing or risk monitoring
The balance of this section of the chapter further addresses the risk control cycle. The risk control cycle is shown below.
Risk Control Cycle
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 22
The Role of the Risk Manager
The risk control role is assigned in the planning process and is documented in the Project Plan as the Risk Manager. The Risk Manager is responsible for ensuring that risk management is performed throughout the project execution. This person may be the Project Manager, although in most large projects this is not advisable due to the associated workload. The Risk Manager should: Be senior enough in the project organization structure that they would have the ability to request that specific risk contingency plans be assigned and staffed Attend the Project Team status meetings Have an understanding of the overall project.
The identity of the Risk Manager should be publicly announced and should also be reflected in the project organization chart. In most cases, the Risk Manager will also be fulfilling another management or technical role on the Project Team. The notation can be in the form of an asterisk or sub-heading. A risk management box may be assigned, and names will be repeated for different functions.
Risk Meetings
Risk management, of which risk control is part, is a process that involves all members of the Project Team and occurs throughout the project life cycle. Risk meetings contribute to the process of identifying risks and developing ways to approach the risks.
Risk Identification Meetings. It is during this process that the current risk list is reviewed and updated. Steering Committee Meetings. A risk summary report of the top risk items for the project should be included in the project status report. Ideally, this should be not more than one page. It should list the risk, state the recommended resolution and indicate the current status. Project Team Status Meetings. The Risk Manager should report to the project status group on the current status of project risks. There should be a written summary, preferably using the actual risk management worksheet.
On-going Risk Identification
The initial list of risks from the planning process will evolve over time. To ensure that new risks are added and resolved risks are eliminated, risk identification meetings should be held. How often this should occur is based on the size of the project and the perception of the Project Team and key stakeholders as to the degree of risk that exists for the project. For most projects, monthly risk identification meetings are adequate. Risk is normally updated by using the status report form and documenting any concerns with risk in the appropriate areas.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 23
The format for these meetings should be open and interactive to facilitate a wide consideration of risk areas. The starting point for this meeting is the previous risk list. The group should be given some ground rules in terms of the degree of risks that will be tracked and ways to eliminate or include risk items.
Current problems are not to be considered, as these are issues for other processes. The meeting will require a facilitator and note taker.
This group assists in the process of prioritizing the new risks or updates by determining the probability of their occurrence and the impact the risk could have on the project.
Focus on Key Risks
Risks must be prioritized to ensure that the key risks are addressed. Be careful to focus on high priority risks and not to identify so many minor risks that major risks are buried. The basic ground rules for prioritization are: There should generally be about 5 to 10 risks being worked at any one time. These should be the risks with the highest probability of occurring and the potential impact. However, for very large projects, each major activity may be tracking this number of risk items. The list of actively monitored risks should generally be no longer than a single sheet. Keep a separate list of lower priority risks so that they can be reviewed at future risk identification meetings. Focus on the risk items that have the greatest possible impact on cost and/or schedule. The prioritization process starts with the group that identified the risk, but also includes the Project Manager and related stakeholders.
Risk Resolution
For the top risk items, mitigation/resolution strategies must be developed. From the steps above, a view of the risk is developed that includes: where, when and to what extent the risk will impact the project.
Some of the following is review from Chapter 3, but is included here to consider when identifying new risks during execution. The following options should be considered:
Eliminating or avoiding the specific threat, usually by eliminating the cause. The Project Team can never eliminate all risk, but specific risk events can often be avoided. Eliminating a risk usually involves taking specific action to change a planned event in the project. That is, if a risk is identified that will occur if the project continues on its current course, the option is to change the course. Risk elimination depends on the extent of change that would be required to the overall Project Plan, considering the cost to make the change and the calculated severity of the risk
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 24
should it occur. As a general rule, elimination should be pursued when the risk cannot be managed away or it will be costly to the project.
Reducing the impact to the budget from a risk through mitigation. In some ways it can be seen as insurance. The area of reducing risk is the most familiar resolution approach used during the planning process. Risk mitigation often involves developing risk contingency reserves. It is defined as a set aside of project dollars and/or schedule to be used to cover the problems that a risk event would cause. The contingency reserve is a calculated figure based on the cumulative risk hours documented on the risk management worksheet.
Accepting that a risk will occur and developing contingency plans to be executed should the risk event occur. A risk contingency plan can be developed for the project that defines the actions to be taken, the resource plans and the factor(s) that trigger an action, should a given risk occur. Contingency plans are pre-defined action steps to be taken if an identified risk event should occur.
Historical Record of Project Risks
A record of the risks that were planned and those that actually occurred should be stored in your project archive and will be maintained over time. This history can be used as lessons learned, and the Project Team can benefit from reviewing past risks and occurrences.
Project Tracking and Monitoring
The Project Plan as the Road Map
To begin the tracking process, use the Project Plan as the roadmap. The tracking activities contained in this document serve as the minimum set of planned events that are to be tracked and monitored over the lifetime of the project.
It should be noted that part of planning was to acknowledge which events were to be tracked and how often they were to be tracked. The planning process, in conjunction with the tracking process, provides a practical, workable method to evaluate where a project stands at a given point in time with regard to the initial baselined plan.
The concept of a perfect Project Plan is an illusion. Plans are living documents that change as the environment of the project changes. Success is dependent on strategies, project resources and people. The focus should be on monitoring and directing these dynamic elements and not on hard-and-fast precepts.
The Project Plan as the Baseline
The key elements that are needed for tracking include:
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 25
Scope of Work including project objectives and success factors Functional specifications or product scope description Work Breakdown Structure (WBS) -- activity list and activity network Work packages Budgets and estimates along with the assumptions on which they were based Master and supporting schedules Financial and funding plans Quality and Change Management Plans Staffing Plan Spending Plan.
Even very large projects can be controlled well if adequate time is spent planning, tracking and monitoring.
Why Tracking and Monitoring?
The management functions of tracking and monitoring are indispensable to the effective and efficient control of the project. In this methodology, tracking is defined as the fact-finding processes, and monitoring is the analysis of these facts. Both are needed for the management of the project.
Control processes are established not to determine what has happened but rather to predict and manage what may happen in the future.
Tracking Monitoring Prediction of Likely Events Effective Management Fact-Finding Analysis
Information generated during the tracking and monitoring processes forms the basis for reaching a judgment about the project status and whether corrective action is required. It also allows the Project Team to answer these specific questions:
General Where is the project on schedule, cost, performance, quality, objectives and goals? What is the status of activities that were to be completed? How does this status impact future project activities? What is going right on the project?
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 26
What is going wrong? What opportunities are emerging? Are the project stakeholders comfortable with the results of the project?
Organization Is the Project Team an effective and suitable organization? Does the Project Manager have adequate control and authority? Have key roles been defined in the project? Are the Project Team personnel innovative and creative by suggesting improvements? Does the Project Team get together on a regular basis to see how things are progressing? Does the project have an efficient method for handling change requests? Does the Project Team seek the advice of stakeholders on matters of mutual concern?
Tracking at the Right Level of Detail?
A key management issue in every project is to develop processes that provide critical information without becoming a burden. Many think this is only an issue in large projects, but small projects share equally in the problem because they typically lack the necessary resources to do many of the management functions.
The Project Manager should focus on putting in place the most critical parts of tracking and monitoring and then add additional items to track as necessary, based on the complexity of the project.
Tracking and monitoring means focusing on the following kinds of information:
Status current activities and planned activities
Comparing the planned schedule to the actual progress and determining the current position. This analysis should be done at the top levels of the Work Breakdown Schedule for reporting, but should also be done at the actual task level for determining work activities. Key items are: Tasks planned and actual start/finish dates Impact of actuals on Project Plan
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 27
Comparing the planned budget with the actual expenditure. The tracking and monitoring processes should generate: Actual expenditures to date Estimate to Complete (ETC) Estimated Cost at Completion (EAC) Adjusted baseline after replanning, if necessary.
Performance and quality indicators from each stage of the project.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 28
The frequency of the various tracking and monitoring activities will vary with the specific element and the amount of detail needed and should complement the various reviewing processes of the project. The frequency of tracking activities should be noted in a project tracking matrix. A sample matrix is provided:
Example - Project Tracking Matrix
Tracking Activity Recommended Frequency Possible Automated Tools** Remarks Updated Project Milestone Schedule Status Report Qtrly, Milestone, or Phase Completion Reviews MS Project Timeline FastTrack GANTT chart preferred Save copy of previous month's chart Updated Work Product Identification Status Report Qtrly, Milestone, or Phase Completion Review As deliverable dates change Automated Project Database
Provide updates to Database Manager Updated Estimate at Completion (EAC) Status Reports As required when ahead or behind schedule Qtrly, Milestone, or Phase Completion Reviews MS Project (Estimating add-in) Excel Lotus Get task leaders to cost out subtasks Include project costs to date Updated Detailed Financial Status Status Report For Qtrly, Milestone, or Phase Completion Reviews As required when ahead or behind schedule MS Excel MS Word Labor hours awarded vs. labor hours expended Dollars awarded vs. dollars expended Updated Planned vs. Actual Spending Profile Status Reports Excel Lotus Provide Dashboard Report for Mgmt Updated Staffing Profile Status Report For Qtrly, Milestone, or Phase Completion Reviews As work product deliverable dates change MS Project
Are there unacceptable peaks and valleys? Updated Resource Loading Status Report Qtrly, Milestone, or Phase Completion Reviews As deliverable dates change Excel Validate need for resources
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 29
Updated Risk Identification Status Report
MS Word Automated project database Update risk matrix Is risk mitigation required? Has a risk materialized? Updated Work Packages As required when work package is rescheduled, or changed MS Word Automated project database When requirements change Change control list for details Updated Project Requirements As required when requirements have been approved for change MS Word Automated project database Contract modification Change control list for details Updated Quality Project Plan As required Quarterly For Qtrly, Milestone, or Phase Completion Reviews MS Word MS Project
Use baselined plan
Updated Change Management Plan As required when ahead or behind schedule Status Report MS Word MS Project
Use baselined plan
Updated Action Items As required For weekly/ bi-weekly status meetings MS Word Automated project database Tracked until resolved Issue Resolution List for details Updated Corrective Action Items As required Status Report MS Word Automated project database Tracked until resolved
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 30
Activity and Schedule Tracking
A large part of the tracking and monitoring process is knowing the projects status. The only way to determine this is to: Review what activities were planned Determine that the work has been done to complete these activities Analyze whether the level of work is consistent with the level of effort that had been planned Compare this to the planned start and finish dates Determine if adjustments are needed for this activity Analyze if any required adjustments impact other tasks.
There are numerous ways to collect, analyze and present this information. Two methods are presented here: activity tracking table and updated project schedule. For large, complex projects that have an involved activity network, additional levels of analysis and mathematical models would be needed. These tools should be used first to generate the project schedule during planning and should then continue to be used to track the schedule. Activity Tracking Table
WBS Activity Description Depend Planned Schedule Actual Schedule Target Schedule
Once the activity tracking table is completed, the Project Manager can prepare a graphical presentation of this information. If an automated tool is being used, this graphic will be automatically generated. In most cases, the Project Manager has a choice in the graphical representation. At a minimum, it should be shown as a Gantt chart, as illustrated in the next figure. For this example, planned dates and duration are still shown on the schedule, even though the task has been completed.
The objective of tracking and monitoring is to preserve the original schedule (baseline) for comparison. In the above sample, the actual schedule is reflected for all those tasks completed. For tasks still open and ones that have not been completed, the new target schedule is reflected.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 31
ID TaskName Duration Work 1 1 Plan Net wor k Infr as t r uct ur e 45 d 40 d 2 1.1 Determine Current Environment 9 d 9 d 3 1.2 Establish General Req's 20 d 20 d 4 1.3 Create Conceptual Diagramof Network 16 d 11 d 5 2 Ins t all LAN in Admin 55 d 41.5 d 6 2.1 Get Bids on Wiring and Equipment 1 d 1 d 7 2.2 Order Wiring, Hub, PCs, Servers, etc. 1 d 1 d 8 2.3 Install Wiring 26 d 22 d 9 2.4 Receive and Store Equipment 2 d 0.5 d 10 2.5 Install Equipment 1 d 1 d 11 2.6 Setup and Install NetworkSoftware 1 d 4 d 12 2.7 Setup Individual Workstations for Network Access 3 d 12 d 13 3 Tr ain Us er s 58 d 123 d 14 3.1 Define Training Requirements 2 d 10 d 15 3.2 Develop Training Plan 4 d 10 d 16 3.3 Develop Training Materials 26 d 40 d 17 3.4 Conduct Training Sessions 3 d 63 d 100% 1/14 100% 2/11 7% 3/5 100% 2/12 100% 2/15 8% 3/23 0% 3/25 0% 4/1 0% 4/26 0% 4/29 100% 2/15 100% 2/19 10% 3/29 0% 5/4 12/13 12/20 12/27 1/3 1/10 1/17 1/24 1/31 2/7 2/14 2/21 2/28 3/7 3/14 3/21 3/28 4/4 4/11 4/18 4/25 5/2 5/9 5/16 5/23 D J F M A M Project Schedule Update What is Project Monitoring?
As is graphically presented below, the project monitoring process is an interactive part of tracking and is firmly tied to project planning. Project monitoring takes the outputs of tracking and uses them to determine planned versus actual.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 32
Project Monitoring Related Activity
Fact-finding
Analysis
Issue Research Contingency Plans Workaround Change Orders
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 33
Planned Versus Actual Costs
The basic consideration underlying all the elements of monitoring is planned versus actual. When the Project Manager completes this comparison, he/she then evaluates whether the existing plan can continue to be used, whether the activities can get back on plan or whether the project (in whole or in part) has deviated significantly from the plan.
Cases where actual progress and projected progress differ significantly suggest the need for adjusting which would include updated project budgets. To determine what significant deviation from the plan is, a number of standards can be used. Standards or project indicators can be set by the Project Team, Project Sponsor, or the customer. These standards should be clearly defined and measurable.
Determining Costs
The way to measure progress is through estimation and completion of tasks, deliverables and milestones. First, tasks should be monitored frequently for percent completion and budget expended. Budget updates and ETCs, e.g. the Estimates to Complete, are obtained from the people responsible for doing and managing the work efforts. Second, deliverables and milestones should be used as signposts to show progress.
Cost of performing a task is directly related to the labor assigned to the task, the duration of the task and the cost of any non-labor items required. To develop updated costs and to account for actuals, the Project Manager needs to review labor costs including labor cost burden and all related non-labor costs. Burdened cost typically refers to the overhead and general expenses that are beyond strict salary associated with an employee. Non-labor charges include such items as material costs, reproduction, travel, capital costs (if leasing equipment), computer center charges and equipment costs.
Estimating the ETC still remains the single most difficult part of deriving updated cost estimates.
Updating Project Costs
Actual labor and non-labor cost information is compared to the numbers used to develop the plan. Spreadsheets work well for projects of small to medium scope. For large projects, a project management tool is typically preferred for cost estimation.
Within the project, costs are assigned and estimates updated at the lowest level WBS work package task. These costs are then combined to determine a sub-task cost, and in turn, are combined to determine the overall task cost, which can be summed to find the total project cost.
Document Assumptions
It is essential to document all assumptions made while planning and updating the project budget. Not only can it greatly impact the later success of the project, but also the lack of such documentation can jeopardize the successful tracking of the project.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 34
If, for example, a budget assumed that a staff member would be available at a defined rate, but only substantially higher paid employees are available to perform the task, there will be a budget problem.
Detailed documentation may not always solve the problem, but it is invaluable in helping explain the problem and in helping define solutions.
Tracking and Monitoring Costs
Many projects can obtain useful financial status by generating a spending profile, a planned vs. actual spending profile graphic. This method is particularly useful for presentations to upper management because of its visual impact. The spending profile, as shown on the following page, can show in a glance what is happening with the project's costs.
Another financial tracking tool is an updated estimated cost at completion (EAC) report.
Each project creates an EAC in the planning process to identify the costs associated with each of the project's high level WBS elements, thereby developing an overall budget for the project. The EAC report generated in execution process shows the variation from the original plan. The EAC always shows the actual projected total cost of the projects.
Another financial tracking method is to maintain financial metrics. Though it may be somewhat more complex than other tracking techniques, financial metrics is a good tool for tracking the amount of the budget or schedule that has actually been earned. This tool can be extremely valuable for paying vendors on partial work. This technique is defined in more detail later in this chapter.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 35
Estimated Cost at Completion (EAC) Report
An EAC periodically determines the expected total cost of the project at project completion. The EAC provides: A historical baseline of the budget A disciplined process for obtaining inputs A means of allocating and tracking budgets to manageable sizes A library of metrics that can be updated with actuals throughout the life of the project for use on similar projects.
The EAC is a summary assessment of the total effort required to complete each task. It estimates the amount of effort required to complete each WBS element and adds that estimate to the costs incurred to date to derive the anticipated cost of each WBS element at project completion. A possible process for budget updates is detailed below:
Start with the original EAC document from your Project Plan Calculate the estimated remaining cost Update costs incurred to date Sum the remaining estimates and the costs to date to derive an EAC for each WBS element Sum the EACs for each WBS element to derive an EAC for the overall project Determine the actual amount of funds available to the project Compare the EAC to total funds available to the project If the total available funds are less than the estimated total cost, then options include: o Eliminate unneeded or excessive requirements until the remaining estimated cost is within the bounds of the remaining funds, or o Advise the Steering Committee that current estimated scope of work for the project is greater than initially estimated. A full EAC should be done for each status report and for all major contractual changes.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 36
Sample Estimated Cost at Completion Summary
Analysis in Hours Analysis in Dollars WB S No. Activity Description Budg et Hour s Actual Hours Est. to Compl ete Est. @ Com plete Varian ce (+ = More) Budget $ Actua l $ Est. to Com plete Est. @ Com plete Varia nce (+ = More ) 1.0 Define Requirements 430 600 0 600 170 17,780 26,00 0 0 26,00 0 8,220 2.0 Prepare RFP 572 500 50 550 (22) 22,880 17,00 0 1,900 18,90 0 (3,98 0) 3.0 Issue RFP and Evaluate Vendors 433 100 433 533 100 17,320 4,300 14,20 0 18,50 0 1,180 4.0 Close-Out 72 0 72 72 0 2,880 0 2,880 2,880 0 TOTAL 1,507 1200 555 1,755 248 60,860 47,30 0 18,98 0 66,28 0 5,420
The financial information included in an EAC provides most of the budget information needed by the Steering Committee. But, without good tools, it is somewhat difficult to determine the effort and cost associated with tasks that are in the process of being completed. Three techniques of developing these numbers are described below:
EAC =Actuals to date plus the remaining project budget modified by the performance factor, often the cost performance index (CPI) developed as part of an earned value method of estimating. See the following section on financial metrics.
EAC =Actuals to date plus a new estimate for all remaining work.
EAC =Actual to date plus the remaining budget. This approach is most often used when current variances are seen as atypical and the Project Management Teams expectations are that similar variances will not occur in the future.
Beware of the trap to report more progress than has been achieved!
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 37
Financial Metrics
The following steps provide additional financial metrics that can further assist in determining if the project is really on schedule. This financial data, however, should not be used in isolation. Variance and earned value calculations are recommended to supplement other information. In general, the information only has value as it is tracked over time or cumulative statistics. Single statistics can be misleading, but are often useful as problem indicators that require investigation.
Budgeted Cost for Work Scheduled (BCWS), the budgeted cost for work scheduled to be accomplished, plus the planned effort or apportioned effort scheduled to be accomplished in a given period and the level of effort budgeted to be performed. In other words, BCWS represents the plan that is to be followed. BCWS, as well as BCWP and ACWP can be calculated for any time period. However, cumulative totals tend to balance out single period swings. This may also be called planned value (PV).
Budgeted Cost of Work Performed (BCWP), the budgeted amount of cost for completed work, plus budgeted cost for level-ofeffort, plus apportioned cost for work that is currently in process. This is sometimes referred to as earned value (EV) and is a measure of work accomplished during a given period. Think always of BCWP as what you got for the effort expended. Tasks may be classified either as discrete or level of effort. If discrete, no credit is given for completing a task until it is done. If a task is level of effort, BCWP =BCWS.
Actual Cost for Work Performed (ACWP), the amount of cost actually expended in completing the work accomplished within a time period, plus the apportioned cost for level of effort activities. This is also known as actual cost (AC).
Calculate the Cost Variance (CV) by subtracting ACWP from the BCWP. A negative cost variance means that the project is spending more than it should. A positive variance means you are earning more than planned for the dollars expended. CV =BCWP ACWP or CV =EV - AC
Calculate the Schedule Variance (SV) by subtracting BCWS from BCWP. A negative schedule variance means the project is behind schedule. A positive number means the project is ahead of schedule. SV =BCWP BCWS or SV =EV - PV
Calculate the Cost Performance Index (CPI) by dividing BCWP by ACWP. The CPI is the cost efficiency factor representing the efficiency of work performed. The remaining budget of the project divided by the cumulative CPI is one approach to calculate the revised EAC total. CPI =BCWP/ACWP or CPI =EV/AC Calculate the Schedule Performance Index (SPI) by dividing BCWP by BCWS. The SPI represents the schedule efficiency of work performed.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 38
SPI =BCWP/BCWS or SPI =EV/PV
Calculate the Critical Ratio by multiplying the CPI by the SPI. If the Critical Ratio is between .9 and 1.2, the task or group of task being analyzed is probably OK. Critical Ratio =CPI X SPI
These variances should be plotted graphically and over time to show how the Project Team is doing. Cumulative statistics are best used for predicting future behavior. Current statistics or those calculated using only the most recent time period are best used for problem identification and analysis.
Resource Loading Updates Updating the Project Resource Plan is an important tracking event since shifts in this plan can cause major performance, cost and schedule problems. The resource loading profile, showing the number of FTE by type or role required on the project, was developed as part of the planning process. As part of tracking, this information is compared regularly to the actual project staffing. Periodically, the Project Manager also validates whether these planned resources are still sufficient to complete the task on schedule and within budget given changing conditions.
Updating projected resource loading and staffing profiles, as shown below, helps the Project Manager adjust to these changing conditions by refining the estimated effort to complete the project, validating the continuing need for resources and identifying staffing problems. By identifying and analyzing discrepancies, the Project Team can determine if adequate resources are being applied to the project and can get early indications that the project is falling behind schedule or is more complex than initially estimated. FTE Resource Loading
This same information can be graphically presented on a timeline with actuals compared to planned. This graph is referred to as a staffing profile.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 39
Staffing Profile 0 1 2 3 4 5 6 7 8 9 10 01 02 03 04 05 06 07 08 09 10 11 12 Weeks N u m b e r
o f
F T E ' s PLANNE D ACTUAL
This information can also be represented in a bar chart as shown in the next table so that actuals can be tracked as opposed to trends. This form of the Staffing Plan is sometimes referred to as a histogram. Staffing Profile 0 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 WEEK PLANNED ACTUAL
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 40
Reporting to the Project Steering Committee
A standard requirement of all projects is to provide status reports to the Steering Committee, the Project Team and others, as required. At a minimum, the frequency of the reports should correspond with the meetings that are scheduled.
The information shared in the status report should be in a consistent format throughout the project. The types of reports that a particular agency uses will vary. A general rule of thumb is that the detail should be kept to what can be explained during a Steering Committee meeting. If more details are needed to clarify issues, then these should be provided as supplementary data.
Status reports are produced by key Project Team members. Status reporting is an integral part of the project management processes. It is the means by which the stakeholders stay informed about the progress and key activities required to successfully complete the project. The purpose of the status report, like the status meetings, is to develop a standard format for the formal exchange of information on the progress of the project. The status reporting process is graphically represented on the following page:
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 41
Project Tracking and Reporting Process
G a t h e r P r o j e c t D a t a A s s e m b l e S t a t u s R e p o r t s P r o j e c t T e a m S t a t u s M e e t i n g S t e e r i n g C o m m i t t e e I s s u e s ? E x c e p t i o n R e p o r t i n g P r o j e c t E n d s N Y E n d o f P r o j e c t ? Y N
The status report package should be prepared by the Project Management Team detailing activities, accomplishments, milestones, identified issues and problems. Some level of recovery plans should be prepared for activities that are not on schedule and prevention plans prepared for anticipated problems.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 42
The Status Report Package
The standard status report package includes the following: Status report form which includes significant accomplishments for the period and scheduled activities. The status report form is included in Appendix B. Updated GANTT charts Recovery plans for activities not on schedule defined by the Project Team as being late, (e.g. slippage in the critical path activities) Updated risk management worksheet Updated issue status including those recently resolved Updated WPI (work product identification) Updated estimated cost at completion Updated Staffing Plan Updated activity tracking table Change requests Financial metrics Exception reports addressing plan variations, e.g. crashing tasks, explaining cost overruns.
Independent Reviews
An important part of project evaluation is done by conducting an independent quality assurance review, sometimes referred to as project oversight. For medium to large projects, project oversight or QA reviews should be done on a schedule consistent with the size and risk of the project.
Many state organizations are moving to the process of QA or oversight reviews to augment their standard tracking process. These reviews provide the opportunity to have an independent appraisal of where the project stands and the efficiency and effectiveness with which the project is being managed. The independent reviewers are interested in the projects processes rather than the project products. The purpose of the audit procedure is to ensure that the Project Plan is being adhered to and that any identified problems or deficiencies are resolved in a timely manner.
A sample independent review process is defined below.
Review the project as required for conformance to the applicable Project Plan. This review includes the CM and data management process, the use of methodologies and tools identified in the Project Plan, the peer review process and the walk through process. Provide a summary report of each visit to the Project Manager. This report should clearly identify any deficiencies or problems encountered during the visit.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 43
For projects with problems or deficiencies, work with the Project Manager to ensure that a plan is implemented to resolve the problems/deficiencies and schedule a follow-up review to make sure that the problems/deficiencies have been resolved. If appropriate, the oversight report should be shared with the Project Sponsor or Steering Committee. This decision will be made at the state agency level. Independent reviews work only if follow-up actions are taken to resolve any problems or deficiencies identified.
Periodic Updates
As shown in the tracking matrix earlier in this chapter, other tracking and monitoring activities may occur on a different frequency than the financial, budget and status activities. Some of the periodic tracking processes are listed here.
Updating a Project's Work Assignments Each project identifies a series of work assignments for specific work to be accomplished. Work assignments are generally created to cover a specific task within the WBS. They should be updated as project requirements change or as additional requirements are developed. It should be noted that work assignments are tracked until completion. The Project Team should update the following areas each time a work assignment is rescheduled, or changed: Work assignment description Person responsible for the work package Start date End date Dependencies Updated requirements.
Updating Project Requirements
In the planning process, each project must identify the high-level or general requirements that the project intends to satisfy. Like the work package, once identified, project requirements are tracked until completion.
Based on the change control processes, project requirements only change as a result of thorough review and written notification. Hence, project requirements will be updated as part of the change control process.
Updating the Quality Project Plan
A quality activities matrix that lists project specific quality-related activities is required for each project. This matrix is initially developed in the planning process and is updated as project requirements change or as additional requirements are developed. The Project Team shall update the quality activities milestone schedule, as necessary, by:
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 44
Adding or deleting quality activities Providing actual or revised quality activity completion dates as the project progresses.
Updating the Change Management Plan
A change management activities matrix that lists project specific CM-related activities is included in the Project Plan. This matrix is initially developed in the planning process and is updated as project requirements change or as additional requirements are developed. The Project Manager shall update the CM activities schedule, as necessary, by: Adding or deleting CM Activities Providing actual or revised CM activity completion dates as the project progresses.
Managing External Project Managers
As the project progresses, the internal Project Manager must continue to ask questions of the external Project Manager, i.e. contracted company, to determine the current status of the work. They should have regular status meetings, but there should be a formal quality assurance audit at the end of every major phase within a project. The types of questions you would ask at that time include: Have the scheduled deliverables as specified in the project schedule and WPI been completed up to this point? Have the deliverables been agreed to and approved by the Steering Committee or their designate? If the vendor has met expectations up to this point, should interim payments be made? Can the vendor clearly explain where the project is verses where it should be at this time? Will all the future deliverables specified in the project definition be completed as planned? Are issues being resolved in a timely manner? Are scope change requests being managed according to agreed to policy? Are risks being identified and managed successfully? Should the contract or project definition be updated to reflect any major changes to the project.
Project Execution and Control Project Management Best Practices Release: 4.1 Chapter 5 - Page 45