CIVE 601 Project Management: Repetitive (Linear) Scheduling
CIVE 601 Project Management: Repetitive (Linear) Scheduling
time, without showing number of units completed within any period of duration (nor variations in rate of progress of a given activity)
Each activity has 2 predecessors: 1. Technological predecessor based on sequence of construction e.g. drive piles must be complete before construct pile caps can begin.
sufficiently ahead to permit subbase work to be performed continuously alternatively, progress rate slowed of subbase to avoid interference or interruption
= 0.83 sections/wk
Delayed 2 days
Cap in 10 days or (b) increase days worked per week for pile cap to 6, so that Production = 2 crews 5 days/week = 1 section/wk 10 days/section or, Production = 2 crews 6 days/week = 1 section/wk 12 days/section