Mass Concrete Thermal Control
Mass Concrete Thermal Control
Mass Concrete Thermal Control
April 1, 2009
dimensions large enough to require that measures be taken to cope with generation of heat from hydration of the cement and attendant volume change to minimize cracking Intentionally vague
Page 2
April 1, 2009
days after placement Expected to reach maximum temperature within 1 to 3 days after placement Heat is trapped and can not escape quickly resulting in:
Thermal Cracking
Significant temperature difference: interior of concrete is much hotter than its surface (>35F) Concrete mix getting too hot (>160F)
Delayed Ettringite Formation (DEF)
Page 4 2009 Structures Design Construction Quality Workshop April 1, 2009
Thermal Cracking
Thermal cracking develops when the tensile stress
Random map cracks in large foundation A series of vertical cracks in walls (widest near the base) Uniformly spaced cracks in beams (perpendicular to the longest dimension)
Page 5
April 1, 2009
Page 6
April 1, 2009
Thermal Control
Objective: Eliminate thermal cracking
by controlling temperature differential and mix temperature (prior to, during and after concrete placement) Control measures should be evaluated for costs vs. benefits
Page 7
April 1, 2009
Page 8
April 1, 2009
for a portion of the cement Use low water-to-cementitious materials ratio Minimize the amount of cementitious materials in the mix Use Larger and better graded aggregates Limestone aggregates are better suited for mass concrete
2009 Structures Design Construction Quality Workshop April 1, 2009
Page 9
Insulation
To control temperature differential: core
vs. surface Has no significant effect on maximum concrete temperature for placements of 5 or greater Typical R-value recommended: 2 to 4 hr.ft.F/Btu
Page 10 2009 Structures Design Construction Quality Workshop April 1, 2009
the concrete temperature (after placement) by about the same amount Chilled water: about 5F (100% subs.) temperature reduction Chipped or shaved ice: about 15F to 20F (75% subs.) temperature reduction Liquid nitrogen (LN2): as low as 35F reduction. Very effective but the most expensive option
Page 11 2009 Structures Design Construction Quality Workshop
April 1, 2009
Page 12
April 1, 2009
Smaller Placements
Multiple lifts Result in schedule delays and increased
cost due to additional effort for multiple thermal control, and horizontal joint preparation
Page 13
April 1, 2009
Page 14
April 1, 2009
Heat of Hydration
Mix design
Cement: Type II, IP, or IS min. 560 lbs Slag and Class F fly ash substitution Maximum water to cementitious ratio = 0.45
Concrete temperature at placement: 40F-70F Max. Concrete temperature after placement: 160F Temperature differential: 35F Temperature sensing and recording
2009 Structures Design Construction Quality Workshop April 1, 2009
Construction to modify project specifications Proposed a thermal control plan based on thermal modeling by CTL
Page 16
April 1, 2009
Page 17
April 1, 2009
Concrete Mix
As developed by the supplier per
project specifications
Type IP-F Cement: 420 lbs Slag: 207 lbs W/C ratio: 0.42 Class V sand-gravel: 1586 lbs Limestone: 1322 lbs Air content: 6.5%
Page 18 2009 Structures Design Construction Quality Workshop April 1, 2009
several-truck rolling average: maximum of 85F instead of 70F Concrete temperature after placement: maximum of 160F as per specifications
Page 19
April 1, 2009
limit and the performance-based limit Included a variable factor of safety More conservative in the early age but less conservative at the design strength Calculated specifically for the project mix design
Page 20 2009 Structures Design Construction Quality Workshop April 1, 2009
40
* Maximum allowable temperature difference between the temperature sensor locations shown on Drawing Nos. 3 and 4. ** Actual compressive strength of the in-place concrete at the surface, not the design strength.
10
6000
0 7000
Page 21
Cooling System
Cooling piping system layout was developed
for each component (footing, stem, cap,) River water was continuously circulated through the cooling pipes until the insulation is removed Flow rate must be sufficiently high so that the water does not heat by more than 2F to 3F
Page 22
April 1, 2009
Page 23
April 1, 2009
Page 24
April 1, 2009
Insulation
Used on top surfaces, over side forms and to
cover protruding reinforcing steel R-values in accordance with the Thermal Control Plan To remain in place throughout the monitoring period but may be temporarily removed to prepare for additional placements
Page 25
April 1, 2009
Page 26
April 1, 2009
temperatures at critical locations (center, surface,) Two temperature sensors (a primary and backup) at each location Data is recorded on an hourly basis Report of temperature data (max. and differential) is issued
Page 27 2009 Structures Design Construction Quality Workshop April 1, 2009
Page 28
April 1, 2009
170 160 150 Temperature or Temperature Difference, F 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 0 50 100 150 Hours
Page 29 2009 Structures Design Construction Quality Workshop
Air Temperature, Center Temperature, Top Surface Temperature, Corner Temperature, Side Surface Temperature, Measured Temperature Difference, F TCP1b Temperature Difference Limit, F
200
250
300
350
April 1, 2009
1/22/2009 10/30/2008
No No
2/20/2009
No
3/6/2009
No
Page 30
April 1, 2009
begun to cool from its maximum temperature Concrete has reached and begun to cool from its maximum temperature difference At least 3 days has elapsed Difference between the hottest portion of concrete and the average air temperature is < current difference limit
Page 31
April 1, 2009
Summary
The implementation of the Thermal
Control Plan saved money and kept the project on schedule No thermal cracking in concrete was reported
Page 32
April 1, 2009
References
Iowa DOT Standard Specifications and
Special Provisions Engineering Mass Concrete Structures, November 2006 PCA by J. Gajda and E. Alsamsam ACI 207.4R-05 I-80 over Missouri River Thermal Control Plan by CTL
Page 33 2009 Structures Design Construction Quality Workshop April 1, 2009