Mass Concrete Thermal Control

Download as pdf or txt
Download as pdf or txt
You are on page 1of 33

Mass Concrete Thermal Control

2009 Structures Design Construction Quality Workshop

Ahmad Abu-Hawash, Iowa DOT Dan Timmons, Jensen Construction

April 1, 2009

What is Mass Concrete?


ACI: any volume of concrete with

dimensions large enough to require that measures be taken to cope with generation of heat from hydration of the cement and attendant volume change to minimize cracking Intentionally vague

Page 2

2009 Structures Design Construction Quality Workshop

April 1, 2009

Factors Affecting Mass Concrete


Concrete mix design: components Environmental condition: Ambient temperature Concrete mix temperature Differential temperature Structural design: steel reinforcement Application: bridge elements Least dimension: 3, 4, or 5?
Page 3 2009 Structures Design Construction Quality Workshop April 1, 2009

Mass Concrete Hydration


Significant heat is generated in the first few

days after placement Expected to reach maximum temperature within 1 to 3 days after placement Heat is trapped and can not escape quickly resulting in:
Thermal Cracking

Significant temperature difference: interior of concrete is much hotter than its surface (>35F) Concrete mix getting too hot (>160F)
Delayed Ettringite Formation (DEF)
Page 4 2009 Structures Design Construction Quality Workshop April 1, 2009

Thermal Cracking
Thermal cracking develops when the tensile stress

exceeds the tensile strength of concrete:

Random map cracks in large foundation A series of vertical cracks in walls (widest near the base) Uniformly spaced cracks in beams (perpendicular to the longest dimension)

Mostly, a durability issue: easy pathways for air and

water In some severe cases, it may affect the structural capacity

Page 5

2009 Structures Design Construction Quality Workshop

April 1, 2009

Delayed Ettringite Formation (DEF)


Development of unstable hydration Long-term effect that may not show for

months or years after construction Can cause significant cracking

Page 6

2009 Structures Design Construction Quality Workshop

April 1, 2009

Thermal Control
Objective: Eliminate thermal cracking

by controlling temperature differential and mix temperature (prior to, during and after concrete placement) Control measures should be evaluated for costs vs. benefits

Page 7

2009 Structures Design Construction Quality Workshop

April 1, 2009

Thermal Control Measures


Optimal concrete mix design Insulation Concrete cooling before placement Concrete cooling after placement Use of smaller placements

Page 8

2009 Structures Design Construction Quality Workshop

April 1, 2009

Optimal Concrete Mix Design


Use low-heat cement such as Type II Use Class F fly ash and/or slag as a substitute

for a portion of the cement Use low water-to-cementitious materials ratio Minimize the amount of cementitious materials in the mix Use Larger and better graded aggregates Limestone aggregates are better suited for mass concrete
2009 Structures Design Construction Quality Workshop April 1, 2009

Page 9

Insulation
To control temperature differential: core

vs. surface Has no significant effect on maximum concrete temperature for placements of 5 or greater Typical R-value recommended: 2 to 4 hr.ft.F/Btu
Page 10 2009 Structures Design Construction Quality Workshop April 1, 2009

Concrete Cooling before Placement


Each 1F of precooling is expected to reduce

the concrete temperature (after placement) by about the same amount Chilled water: about 5F (100% subs.) temperature reduction Chipped or shaved ice: about 15F to 20F (75% subs.) temperature reduction Liquid nitrogen (LN2): as low as 35F reduction. Very effective but the most expensive option
Page 11 2009 Structures Design Construction Quality Workshop

April 1, 2009

Concrete Cooling after Placement


Cooling pipes: Non-corrosive piping embedded prior to concrete placement Uniformly distributed: typically 1 pipes @ 2 to 4 on center Removes heat from placed concrete by circulating cool water from a nearby source

Page 12

2009 Structures Design Construction Quality Workshop

April 1, 2009

Smaller Placements
Multiple lifts Result in schedule delays and increased

cost due to additional effort for multiple thermal control, and horizontal joint preparation

Page 13

2009 Structures Design Construction Quality Workshop

April 1, 2009

Case Study: I-80 over Missouri River

Page 14

2009 Structures Design Construction Quality Workshop

April 1, 2009

Iowa Mass Concrete Specifications


Special Provision for Mass Concrete Control of

Heat of Hydration
Mix design

Cement: Type II, IP, or IS min. 560 lbs Slag and Class F fly ash substitution Maximum water to cementitious ratio = 0.45

Thermal Control Plan (per 207.4R-05 ACI)



Page 15

Concrete temperature at placement: 40F-70F Max. Concrete temperature after placement: 160F Temperature differential: 35F Temperature sensing and recording
2009 Structures Design Construction Quality Workshop April 1, 2009

I-80 over Missouri River Thermal Control Plan


Value engineering proposal by Jensen

Construction to modify project specifications Proposed a thermal control plan based on thermal modeling by CTL

Page 16

2009 Structures Design Construction Quality Workshop

April 1, 2009

Thermal Control Plan


Concrete Mix Maximum Concrete Temperature Temperature Difference Limit Cooling System Insulation Temperature Monitoring & Reporting

Page 17

2009 Structures Design Construction Quality Workshop

April 1, 2009

Concrete Mix
As developed by the supplier per

project specifications

Type IP-F Cement: 420 lbs Slag: 207 lbs W/C ratio: 0.42 Class V sand-gravel: 1586 lbs Limestone: 1322 lbs Air content: 6.5%
Page 18 2009 Structures Design Construction Quality Workshop April 1, 2009

Maximum Concrete Temperature


Initial concrete temperature based on

several-truck rolling average: maximum of 85F instead of 70F Concrete temperature after placement: maximum of 160F as per specifications

Page 19

2009 Structures Design Construction Quality Workshop

April 1, 2009

Temperature Difference Limit


A compromise between the constant

limit and the performance-based limit Included a variable factor of safety More conservative in the early age but less conservative at the design strength Calculated specifically for the project mix design
Page 20 2009 Structures Design Construction Quality Workshop April 1, 2009

Temperature Difference Graph


100 90 Temperature Difference Limit*, F 80 70 60 30 50 40 20 30 20 10 0 0 1000 2000 3000 4000 5000 Compressive Strength**, psi
2009 Structures Design Construction Quality Workshop

50 Temperature Difference Limit*, C


April 1, 2009

40

* Maximum allowable temperature difference between the temperature sensor locations shown on Drawing Nos. 3 and 4. ** Actual compressive strength of the in-place concrete at the surface, not the design strength.

10

6000

0 7000

Page 21

Cooling System
Cooling piping system layout was developed

for each component (footing, stem, cap,) River water was continuously circulated through the cooling pipes until the insulation is removed Flow rate must be sufficiently high so that the water does not heat by more than 2F to 3F

Page 22

2009 Structures Design Construction Quality Workshop

April 1, 2009

Typical Cooling System - Footing

Page 23

2009 Structures Design Construction Quality Workshop

April 1, 2009

Typical Cooling System - Stem

Page 24

2009 Structures Design Construction Quality Workshop

April 1, 2009

Insulation
Used on top surfaces, over side forms and to

cover protruding reinforcing steel R-values in accordance with the Thermal Control Plan To remain in place throughout the monitoring period but may be temporarily removed to prepare for additional placements

Page 25

2009 Structures Design Construction Quality Workshop

April 1, 2009

Typical Insulation Blanket

Page 26

2009 Structures Design Construction Quality Workshop

April 1, 2009

Temperature Monitoring & Reporting


To measure and report concrete

temperatures at critical locations (center, surface,) Two temperature sensors (a primary and backup) at each location Data is recorded on an hourly basis Report of temperature data (max. and differential) is issued
Page 27 2009 Structures Design Construction Quality Workshop April 1, 2009

Typical Temperature Sensors

Page 28

2009 Structures Design Construction Quality Workshop

April 1, 2009

Typical Thermal Control Graph


TCP1b Footing #: Pier 7 Column final temps Time/Date of Hour 0 :

170 160 150 Temperature or Temperature Difference, F 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 0 50 100 150 Hours
Page 29 2009 Structures Design Construction Quality Workshop

Air Temperature, Center Temperature, Top Surface Temperature, Corner Temperature, Side Surface Temperature, Measured Temperature Difference, F TCP1b Temperature Difference Limit, F

200

250

300

350

April 1, 2009

Thermal Control Plan Elements


Footing Pier 1 2 3 4 5 6 7 8 9 10 11 Size* 43' x 12' x 4'-6 43' x 15' x 5' 43' x 27' x 7'-3 43' x 15' x 5' 43' x 19' x 6'-6 46' x 18' x 5'-9 43' x 25'-6 x 9' 77' x 39'-7 x 10'-6 77' x 39'-7 x 10'-6 43' x 19' x 5'-3 43' x 17' x 5'-9 Date Cast 10/20/2008 11/19/2008 10/30/2008 11/4/2008 2/3/2009 11/4/2008 8/5/2008 12/30/2008 3/5/2009 1/20/2009 Cooling Pipes No No No No No No Yes Yes No No Size* 39' x 4' x 7' 38' x 5' x 19' 38' x 6' x 16' 38' x 5' x 18' 38' x 5' x 20' 38' x 8'-4 x 37' 38' x 7' x 35' 46' x 9' x 41' 46' x 9' x 34' 38' x 8'-4 x 7' 38' x 5' x 5' Stem Date Cast 12/4/2008 1/9/2009 11/21/2008 12/10/2008 2/17/2009 11/19/2008 9/3/2008 2/12/2009 3/13/2009 1/28/2009 Cooling Least Pipes Dim. No 4' No 5' No 6' No 5' No 5' 8'-4 Yes 7' Yes 9' 9' No 8'-4 5' Columns Date Cast 12/4/2008 2/18/2009 1/23/2009 3/5/2009 1/6/2009 10/15/2008 Cooling Pipes No No No No No Yes Least Dim. 4' 5' 6' 5' 5' 8'-4 7' 9' 9' 8'-4 5' Cap Date Cast 1/23/2009 3/20/2009 2/25/2009 Cooling Pipes No No No

1/22/2009 10/30/2008

No No

2/20/2009

No

3/6/2009

No

Page 30

2009 Structures Design Construction Quality Workshop

April 1, 2009

Completion of Thermal Control


Hottest portion of concrete has reached and

begun to cool from its maximum temperature Concrete has reached and begun to cool from its maximum temperature difference At least 3 days has elapsed Difference between the hottest portion of concrete and the average air temperature is < current difference limit

Page 31

2009 Structures Design Construction Quality Workshop

April 1, 2009

Summary
The implementation of the Thermal

Control Plan saved money and kept the project on schedule No thermal cracking in concrete was reported

Page 32

2009 Structures Design Construction Quality Workshop

April 1, 2009

References
Iowa DOT Standard Specifications and

Special Provisions Engineering Mass Concrete Structures, November 2006 PCA by J. Gajda and E. Alsamsam ACI 207.4R-05 I-80 over Missouri River Thermal Control Plan by CTL
Page 33 2009 Structures Design Construction Quality Workshop April 1, 2009

You might also like