Changes to ISO/TS 16949 Rules 4th Edition

What They Mean for Your Organization


The Rules for Achieving and Maintaining IATF Recognition 4th Edition were
released on October 1, 2013 and requires full implementation
by April 1, 2014. This article highlights some of the most
significant changes that affect registrants within the scheme.
NSF-ISR does wish to qualify that this summary is being provided
to assist organizations with understanding some of the changes,
but organizations should obtain the official document from the
Automotive Industry Action Group (AIAG) and fully read it to
understand the entire impact.
At the time of release, the IATF also published Certification Body Communiqu
#2013-006 (available from the IATF website) which describes the removal of
manufacturing site extensions from the ISO/TS 16949 certification scheme.
Existing site extensions will need to transition into single certified sites between
April 1, 2014 and April 1, 2015 according to the process described in the memo.

In summary, it appears the changes to the Rules align with the IATF strategy
of raising the bar as coverage and detail of audits appear to have increased
from a requirement perspective and the consequences for not performing
to expectation have been made more severe. The interpretation of these
requirements is subject to change as future meetings are planned with IATF
members to better understand intent and application. The remainder of this
article discusses selected clauses and changes to the requirements and scheme.

Clause 1.0 Eligibility Change Summary
Fabless sites are not eligible for TS certification. Fabless is defined as an
organization which outsources all fabrication activity. Sites manufacturing only
aftermarket parts are not eligible for TS certification.
2.9 Appeals and complaints Change Summary
The appeals process shall not impact timings related to nonconformity
management (NC) or the certificate decertification process.
3.1 Certification agreement with client Change Summary
The certification body (CB) shall have a legally enforceable agreement with the
client which includes that consultants to the client cannot be physically present
at the clients site during audits or participate in audits in any way. The audit
team shall be knowledgeable in the legally enforceable agreement with the
client.
3.2 Notice of changes by a client Change Summary
Client failure to inform the CB of changes is considered a breach of the legally
enforceable agreement and may result in certificate withdrawal.
NSF-ISR
1-888-NSF-9000 (USA)
[email protected]
www.nsf-isr.org
International
Strategic
Registrations
Registered to
ISO/TS 16949
NSF-ISR
1-888-NSF-9000 (USA)
[email protected]
www.nsf-isr.org
International
Strategic
Registrations
5.2 Audit day determination Change Summary
Longer days (over eight hours) are now allowable when covering a third shift.
Time shall be spent on that shift and shall not exceed a total of four hours (0.5
days). Multiple shift patterns are to be audited at each shift. Minimum audit
time in manufacturing sites is to be a third of the total audit days. On-site
verification of past corrective action reports (CARs) is required and that
effort is in addition to the specified man days and is not entered into the IATF
database. Ring-fencing- allowable criteria are now defined and IAOB approval
is required prior to implementation. Justifications for additional timing due to
scope expansion shall be maintained in audit planning documents. Regarding
headcount changes, if the minimum number of days increases or decreases, the
change shall be applied to the current audit. Records shall be maintained.
5.6 Establishing the audit team Change Summary
For the initial certification audit, the CB shall appoint an audit team that has not
previously audited the client in the past three years for TS. The CB may appoint
one auditor from a previous cycle to participate in the recertification audit, but
this auditor is not allowed for subsequent surveillances.
5.7 Audit planning Change Summary
5.7.1 Client info for audit planning CB shall require the client to provide pre-
planning information as an input for developing an audit plan. The list of
information to provide has been slightly revised.
5.7.2 Audit plan The summary of analysis of pre-planning information is to
be maintained as part of the audit record (see Annex 3 of the Rules). When
complete information is not received prior to plan issuance, the audit plan
shall include additional time to collect and review information on-site prior to
the opening meeting. The audit plan shall include a minimum of one hour on
site, prior to the opening meeting, for verification of changes, performance
and scorecard reviews. The plan can be adjusted as needed and the extra hour
is in addition to the specified days (the extra hour is not entered in the IATF
database). The audit plan shall identify when interactions with remote support
functions will be audited. It also needs to identify when on-site reviews of
corrective actions from previous audits are verified. Further, the audit plan shall
contain record of the total number of hours audited per day and the total days
per team member.
5.8 Conducting on-site audit activities Change Summary
Each audit shall include implementation of requirements for new customers
since the last audit. The on-site audit shall cover manufacturing on all shifts
where it occurs, including sample of shift changeover. During stage 2,
recertification and transfer audits, all manufacturing processes shall be audited
on each shift. The surveillance cycle shall include auditing of all manufacturing
processes during each shift.
NSF-ISR
1-888-NSF-9000 (USA)
[email protected]
www.nsf-isr.org
International
Strategic
Registrations
5.9 Audit findings Change Summary
If the surveillance audit is terminated, the certificate is suspended and a full
repeat audit shall occur within 90 days of the closing meeting date (CMD). If a
recertification audit is terminated, the audit shall be repeated. If the 90-day tim-
ing is exceeded, the client shall require stage 1 & 2 audits. If a transfer audit is
terminated, the client shall start over with stage 1 & 2.
5.10 Writing the audit report Change Summary
The final audit report shall be acknowledged by a client representative. The list
of required report contents has increased significantly. Added detail includes
items such as employment headcount specifics, customer specific requirements
(CSR) latest dates, scorecard summaries and actions, summary of manufacturing
process coverage, remote support location (RSL) specifics and coverage, sum-
mary of condition validation for ring fencing, etc. These changes shall require
additional off-site reporting time.
5.11 Nonconformity management Change Summary
5.11.1 The CB shall require client response to nonconformities within 60 days,
including evidence of correction; root cause methodology, analysis and results;
systemic corrective action; and verification of effectiveness.
5.11.2 If a nonconformance is not closed in 90 days, the audit result is deemed
failed and the IATF database is updated. This means that new clients are not
certified (and existing clients have their certificate immediately withdrawn) and
shall start over with stage 1 & 2. In exceptional cases where implementation of
corrective actions cannot be completed within 90 days from the end of the
audit, the CB shall consider the nonconformity open but 100% resolved if
the issue has been contained, an acceptable action plan with implementation
evidence has been submitted, an on-site follow-up visit prior to next audit has
been scheduled, and records for the justification of the situation are maintained
by the CB.
All nonconformances shall be reviewed at the subsequent visit. If not effectively
implemented, the CB shall issue a major nonconformance against the corrective
action process and reissue a major nonconformance against the repeat issue.
5.11.3 On-site verification Change Summary
Major nonconformances shall require an on-site verification within 90 days. If the
CB finds an accepted corrective action plan for a major nonconformance has
not been effectively implemented, the audit result is failed, the IATF database is
updated, and the client certificate is withdrawn. If the client does not effectively
implement a corrective action for a minor nonconformance, the auditor issues
a major nonconformance against the corrective action process and reissues a
major nonconformance against the repeat issue.
NSF-ISR
1-888-NSF-9000 (USA)
[email protected]
www.nsf-isr.org
International
Strategic
Registrations
6.0 Audits Change Summary
6.5.1 Stage 1 planning CB shall require the client to provide necessary
documentation for review, including a description of remote locations and the
support they provide or receive, etc.
6.8 Recertification audit activities Change Summary
For a major nonconformance, the client shall identify root cause and
implement the correction within 20 days.
7.1 Transfer audit Change Summary
A new CB shall not transfer a client in any IATF OEM special status condition
until after the current CB has conducted at least one on-site visit. The client
shall provide a new CB with audit reports from the prior three years including
evidence of corrective action report (CAR) closure for the site and any remote
support locations (RSLs). The new CB shall contact the IAOB regarding
transfer approval and verification of information.
8.3 Certificate suspension decision Change Summary
If the initiation of the decertification process is related to a major nonconfor-
mance or surveillance not conducted on time, the certificate shall be suspend-
ed. The CB shall request the client to provide a corrective action plan within a
maximum of 20 calendar days of the notice to suspend. When suspension is
related to surveillance audit timing missed, the CB shall reschedule and con-
duct a surveillance audit within 90 days of the suspension date.
8.4 Verification Change Summary
Major nonconformances require on-site verification and these visits are
considered special audits and shall be entered by the CB in the IATF
database. Where corrective actions are not effectively implemented, the audit
team shall recommend withdrawal of the certificate.
8.5 Reinstatement/withdrawal decision Change Summary
The CB can decide to reinstate or withdraw the certificate independent of the
clients customer special status condition. Records of the decision shall be
maintained by the CB. For recertification audits, the decertification process
shall be completed prior to the recertification decision.
Questions on this article may be directed to Jeff Greaves (NSF-ISR
Automotive Business Unit Manager) at [email protected] or
Tong Qiu (NSF-ISR Automotive Technical Manager) at [email protected].