Cost of Steam

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

Industrial Technologies Program

Boosting the productivity and competitiveness of U.S. industry through improvements in energy and environmental performance

A BestPractices SteamTechnical Brief

How To Calculate The True Cost of Steam

U.S. Department of Energy

Energy Efficiency and Renewable Energy


Bringing you a prosperous future where energy is clean, abundant, reliable, and affordable

How To Calculate The True Cost of Steam

How To Calculate The True Cost of Steam


Knowing the correct cost of steam is important for many reasons, and all of them have to do with improving the companys bottom line, including: To properly evaluate the economics of proposed process efficiency or capacity-improvement projects; if the calculated cost is not accurate, many good energy projects may be missed or rejected, and bad projects may be approved for implementation To serve as a basis for optimizing the steam generation system, and minimize costs To ensure more effective negotiations with the utility or third party Independent Power Producers To properly evaluate proposed cogeneration projects. Steam is used for a variety of applications in commerce and industry: Process heating Vacuum jets Shaft work for mechanical drives Power generation Space heating. In industrial manufacturing facilities, process heating accounts for an average of more than 60% of thermal energy use, predominantly in the form of steam. Process heating also accounts for a significant portion of controllable operating costs. It is one of the few areas of opportunity where management can reduce operating costs and improve profits.

The True Cost of Steam


To determine the true cost of steam, we need to know more details about the steam in question. Are we discussing steam at the point of use? Steam at the point of generation? From which boiler? At what header pressure or at what quality? Average costs or marginal costs? If average costs, do they include both fixed and variable costs, or only the latter? Furthermore, we must distinguish between the cost of generation and the cost of consumption. If the plant has only one steam generator (boiler), uses a single fuel, and has a single steam pressure level, it is relatively easy to assign a cost to the steam. However, in most cases, there are multiple steam sources and multiple fuels. There are also multiple steam pressure levels with multiple paths by which the steam pressure is reduced; for example, steam pressure can be reduced via pressure-reducing valves (PRVs) or turbines. Determining the true cost of steam then becomes far more complex. Several approaches have been tried, including the second law or exergy analysis method, the Nelson method, and the simulation modeling method. Of these, computerized simulation models are the most convenient, powerful, and reliable. In most companies, the reported cost of steam is the average cost of generation at a particular production rate. The total operating costsfuel, power, water, chemical additives, labor, maintenance, depreciation, interest, and administrative overheadsare divided by the total amount of steam produced. This may be a convenient corporate financial benchmark, but is not particularly useful for managing the steam system to minimize costs. For that, we need a better method for steam cost accounting.

How To Calculate The Tr ue Cost of Steam

One of the problems is that the cost of steam depends on the generation rate, especially in complex multi-boiler multi-fuel plants that also have steam turbines. To most people, this is not intuitively obvious. In this BestPractices Steam Technical Brief, we will show how to calculate the steam cost at different process operating rates, and demonstrate through an illustrative example that the only way to do this accurately is through steam-system modeling. Consider the simplified system shown in Figure 1, taken from an actual plant. Exhaust to Atmosphere Flue Gas Combustion Air Fuel Input Blowdown Steam BFW Sludge to Disposal Main Steam Header Vent C Vent B BPST Flash Drum Deaerator Vent A Bypass BFW Makeup BD to Sewer
BPST = Backpressure Steam Turbine BFW = Boiler Feedwater BD = Blowdown

Steam for Sootblowing Boiler

Alkali Scrubber

kW

Process

Condensate Tank

Figure 1. Typical Schematic Flowsheet for a Simple Steam System


In the following equations, the operating cost of the boiler is CO per hour and the process requires S pounds/hour (lb/h) of steam. To deliver this much steam, it is necessary to actually generate (1+X)S lb/h of steam, where X is a factor typically ranging from 5 to 20%. So we already have two distinct equations to determine the cost of steam: (a) generating cost CG, $/lb = CO/(1+X)S (b) consumption cost CG, $/lb = CO/S Which cost equation should we use? We use the first equation when we are interested in making the generation system more efficient. We use the second one when we are interested in determining the true cost of process operation and when we are evaluating energy conservation projects.

Calculating the Cost of Steam Generation


The first step, which has several components, is to calculate the cost of generating steam from the boiler(s): 1. Fuel (CF) 2. Raw water supply (CW)

How To Calculate The True Cost of Steam

3. Boiler feed water treatmentincluding clarification, softening, demineralization (CBFW) 4. Feedwater pumping power (CP) 5. Combustion air fan (FD or ID) power (CA) 6. Sewer charges for boiler blowdown (CB) 7. Ash disposal (CD) 8. Environmental emissions control (CE) 9. Maintenance materials and labor (CM) Calculating the cost of generating steam is relatively easy. The total variable cost of raising steam, CG, is the sum of all these individual contributions, expressed as dollars per thousand pounds ($/Klb) of steam generated: CG = CF + CW + CBFW + CP + CA + CB + CD + CE + CM Fuel cost is usually the dominant component, accounting for as much as 90% of the total. It is given by: CF = aF x (HS hW)/1000/B where aF = fuel cost, ($/MMBtu) HS = enthalpy of steam, Btu/lb hW= enthalpy of boiler feedwater, Btu/lb B = overall boiler efficiency, fractional. Overall boiler efficiency is based on combustion air supply at ambient temperature, and boiler feedwater makeup temperature to the deaerator. It is assumed that boiler feedwater preheat from ambient to condensate temperature (usually about 200F) will be done by heat exchange against a process stream, outside the boiler island battery limits, with only some top-up heat recovery against hot boiler blowdown. The use of steam to preheat boiler feedwater was common when energy was cheap, but using surplus process heat instead (from below the process pinch temperature) represents a significant opportunity for improved cycle efficiency. Overall boiler efficiency becomes primarily a function of the final flue gas temperature, and will typically be in the range of 80 to 85% when the excess air ratios are near optimal. In principle, one should calculate the individual cost components rigorously for the site-specific conditions. In practice, it is usually sufficient to use an approximation: CG = CF (1 + 0.30) The number 0.30 represents a typical value for the sum of cost components 2 through 9 above (in oil- and gas-fired facilities). However, it could be more in smaller facilities, or in those that use coal and biomass. Normally, maintenance costs could be considered fixed, rather than variable. If the plant has multiple boilers, however, and there is an option to shut down one or more of them as the steam production rate is reduced, then maintenance costs should more properly be considered to be variable. The second step is to calculate the cost of steam at lower pressure levels. This is not easy, as the cost depends upon the path that the steam follows from the point of generation to the point of use. Low-pressure steam that is produced through a pressure letdown station, usually a pressure-reducing valve (PRV), has substantially the same enthalpy as the higher-pressure steam from which it was made. Therefore, it will be superheated, and the normal practice is to desuperheat it using condensate. The low-pressure steam cost is then calculated from the high-pressure steam cost as: CL = CH x (HSL hW)/(HSH hW) where HSL = enthalpy of low-pressure steam, Btu/lb HSH = enthalpy of high-pressure steam, Btu/lb.

How To Calculate The True Cost of Steam

Making low-pressure steam through a PRV is inefficient. For steam flows over 50,000 lb/h, it is usually far more cost effective to extract by-product power by passing the steam through a backpressure steam turbine. When the low-pressure steam is produced through a turbine, its cost is calculated as: CL = CH 1000 x aE x (HSH H*SL)/3413/T/G where aE = electrical power cost, $/kWh H*SL= enthalpy of low-pressure steam from isentropic expansion of high-pressure steam, Btu/lb T = isentropic efficiency of steam turbine, fractional G = generator efficiency, fractional. The difficulty is to assign the correct cost to the increase or decrease in low-pressure steam consumption, which depends on the path followed by steam from the point of generation to the point of use (for example, PRV or turbine). The only way to determine the correct value is to develop a heat and material balance simulation model of the system.

Setting Up the Model


A simulation model is the mathematical representation of a physical process defined in terms of equations, constraints, and assumptions. The model must tie together the mass and energy interactions between the major subsystemsfuel system, boilers, steam turbines, gas turbines, deaerators, flash drums, desuperheaters, economizers, heat exchangers, and process steam users/sources. The model accounts for the significant flows into and out of each subsystem, as well as for the boiler system as a whole. For the system shown in Figure 1, the inputs and outputs across the boilerhouse boundaries are: Inputs = Condensate return from process + boiler feedwater makeup Outputs = Steam to process + blowdown from flash drum + vents to atmosphere (A, B, and C) For material balance, neglecting losses, we set inputs = outputs (however, for many systems, losses can be significant and need to be tracked). There are several internal subsystem balances that have to be satisfied as well. For the boiler itself: Steam generation + boiler blowdown (before flash) = boiler feedwater For the steam header: Steam generation = steam to process + steam to PRV + steam to turbogenerator + steam for soot blowing For the condensate tank: Deaerator feed = boiler feedwater makeup + combined process condensates vent A Boiler blowdown will be at the boiler temperature, and will flash when the boiler feedwater is let down to atmospheric condition. This flash vapor can be recovered for use in the deaerator. Normally, the blowdown is let down to the deaerator (DA) pressure, and the vent flow labeled C in Figure 1 is zero. Thus, for the blowdown flash drum, the balance is: Blowdown from boiler = blowdown from drum + flash vapor to deaerator For the deaerator, Boiler feedwater = deaerator feed + steam to the deaerator from the PRV + steam to the deaerator from the turbine + blowdown flash vapor vent B

How To Calculate The True Cost of Steam

In addition to the material balances, we must also develop the heat (enthalpy) balance equations for each subsystem. The combined set of equations is solved algebraically. Examination of the overall balance shows that there is one more unknown variable than there are equations, so it is necessary to solve the problem iteratively. This is not a problem, and the calculations tend to converge fairly rapidly in a unique solution. The recommended computational strategy is to assume a trial value of steam generation rate, and proceed to solve the equations for boiler feedwater makeup, condensate return, blowdown, and boiler feedwater. The individual subsystem balances are then solved in a top-down sequence: steam header, blowdown flash drum, condensate tank and deaerator. The new calculated steam rate is then compared with the assumed trial rate, and this is repeated until the two values converge to within an acceptable difference. The net cost of operating the system is equal to the cost of steam generation less the credit for power generation in the turbine. For simple systems with steady steam demand, the calculation only needs to be done once, and then adjusted periodically when external circumstances or assumptions change. A computer-based model may not even be necessary. Most large industrial steam systems are typically much more complex: with multiple boilers, multiple fuels, multiple pressure levels, and alternative connection paths (for example, PRVs and turbines) between the different steam headers, as in Figure 2. For them, it is particularly important that an accurate computer-based model is developed, and that the model is run frequently, perhaps as often as three times per day.

Methodology for Marginal Steam Pricing


Models can be configured to varying levels of detail. A model that is too simple may lack the discrimination to detect important effects. A model that is too detailed may be needlessly complicated and expensive to develop, without offering compensating value in terms of being a better decisionmaking tool. The sugar refinery example of Figure 2, which has seven boilers, four pressure levels, and three turbogenerators, represents the optimum level of detail for most industrial facilities, and provides acceptable results with only one iterative calculation loop. The average steam generation cost can be calculated quite easily, but how can the consumption cost be calculated? Before going further, we need to understand the distinction between average costs and marginal, or incremental, costs. The essential definitions are: Average Cost = and Marginal Cost = Incremental Operating Cost Co = Incremental Steam Consumption S Total Operating Cost Total Steam = Co S

For evaluating energy conservation and/or efficiency improvement projects, it is the marginal cost that should be determined. The first step is to decide on basic operating parameters for the combined heat and power system, including condensate return rate, boiler blowdown, deaerator pressure, fuel mix, condensate temperature, boiler feedwater makeup supply temp, the process steam demand profile, PRV, and steam turbine flows. The model is then used to calculate the total operating cost for this base case scenario, as in Table 1. How does the total operating cost change if the consumption of low-pressure steam, at 12 pounds per square inch gauge (psig), in the process either increases or decreases by some amount, Y lb/h? To determine this, we manually change the input value of the low-pressure process steam consumption by the appropriate amount, and make a note of the new operating cost calculated by the model. However, the model should accurately incorporate the plant operating policy for fluctuations in the

0.0 Klb/h Note: Boiler #7 pressure can


be set to either 300 or 400 psig

0.0 Klb/h Boiler #3


Max. Cap. (Klb/h) 37 Boiler Eff. (%) 82 % of Capacity 85 Max. Cap. (Klb/h) 37 Boiler Eff. (%) 83 % of Capacity 85 Max. Cap. (Klb/h) 37 Boiler Eff. (%) 81 % of Capacity 82 Max. Cap. (Klb/h) 37 Boiler Eff. (%) 73 % of Capacity 50 Max. Cap. (Klb/h)110 Boiler Eff. (%) 83 % of Capacity 88

0.0 Klb/h Boiler #4 Boiler #5 Boiler #6 Boiler #7

0.0 Klb/h

0.0 Klb/h

0.0 Klb/h

Swing Boiler
Max. Cap. (Klb/h) 32 Boiler Eff. (%) 83 % of Capacity 85

Boiler #1

Boiler #2

Max. Cap. (Klb/h) 50 Boiler Eff. (%) 84 % of Capacity 0

300 psig Users 0.8 Klb/h TG #2,3 TG #1

300 psig 550F 421.8 F (saturated) 1284 Btu/lb

200 psig Users 15.6 Klb/h

200 psig 387.9F (saturated) 1204 Btu/lb 80 psig Users 13.3 Klb/h Blow Off 12 psig Users 250.5 Klb/h

80 psig 324.1F (saturated) 1189 Btu/lb

12 psig 244F (saturated) 12 psig

Vent

Deaerator Tmin = 10 Soft Water Makeup

Condensate from LP DA 0.0 Klb/h

LPDA = Low-Pressure Deaerator TG = Turbogenerator

New Preheat Train Blowdown to Sewer

How To Calculate The True Cost of Steam

Figure 2. Simplified Schematic Flowsheet of Combined Heat and Power System for a Sugar Refinery

How To Calculate The True Cost of Steam

Table 1: Base-Case Steam Generation Costs from Model


Assumptions/Basis:
Required Power Generated Power Full Rate Operation Total Boiler Duty Gas Heating Value 8.32 MW 7.80 MW (includes direct mechanical drives) 7680 h/yr 370.8 MMBtu/h 1020 Btu/cubic foot Psig 200 80 12 300 12 12 300 Klb/h 15.6 13.3 250.5 1.7 21.3 -5.4 297 BD = Blowdown ST = Steam Turbine

Comments

Process Steam Demand

Parasitic Steam Demand

Sootblowing and losses Deaerator BD flash vapor recovery

Total Steam Generation Required:

Operating Costs:
Quantity 363.6 KCF/h 0.52 MW 246.4 gpm 47.4 gpm Unit Cost, $ @ Unit 2.40 KCF 61.0 MWH 1.00 Kgal 0.25 Kgal Total MM$/yr 6.70 0.24 0.11 0.01 7.06

Gas (fuel) Purchased Power Softened Water Wastewater

Operating Policy and Constraints


1. Boilers #1 through 6, capacity limits: Minimum = 30% of design Preferred Rate = 85% of design Maximum safe = 95% of design 2. Boiler #7 is operated independently of others; direct coupled to Steam Turbine #1 (steam demand for ST#1 depends on compressor load) 3. Steam flow capacity constraints on turbogenerators ST #2 and #3: Min Max ST#2 20 60 Klb/h ST#3 40 120

process-steam demand. For example, important information includes whether the reduction in steam input to the low-pressure header is through a PRV or through a steam turbine, whether the required degree of superheat is being maintained, whether the correct boiler and fuel are being scaled back, whether the equipment capacity constraints are being observed, and whether the correct boiler and turbine efficiencies are being used at the new flow conditions. This procedure is repeated for several additional perturbations, and the results are tabulated and illustrated in Table 2 and Figure 3. Table 2 shows that the marginal cost of low-pressure steam varies significantly with operating rate, because the low-pressure steam follows different paths through the combined heat and power system. At the low end, when the process steam demand is 152.8 Klb/h, the gas boiler (#1) is being operated at its minimum rate (30% of capacity). Under these conditions, gas is the more expensive fuel, and the coal boilers (#2 through 6) are operated to provide the balance of steam demand. Turbogenerators #2 and #3 are at their minimum operating rates, 20 and 40 Klb/h respectively. As the process steam requirement increases the load on the coal boilers increases, as well as the amount of steam passed through turbogenerator #3 up to its maximum capacity of 110 Klb/h. As the steam demand increases, further, the flow through turbogenerator #2 starts to increase. At some point the preferred operating rate of 85% for the coal boilers is reached. Further increases in steam demand must now be supplied from the gas boiler. Once the flow through turbogenerator #2 reaches its maximum capacity of 60 Klb/h, further demand for lowpressure steam can now only be provided by passing high-pressure steam through a PRV. The marginal cost of low-pressure steam therefore takes a dramatic rise. As low-pressure steam demand continues

How To Calculate The Tr ue Cost of Steam

Table 2: Results of Perturbation Analysis for Marginal Cost of Low-Pressure Steam


Steam, Klb/h Low-pressure to process Total 152.8 152.9 219.2 219.3 226.9 227.0 257.0 257.1 266.8 266.9 280.0 194 264 272 304 314 328 Op Rate, % of cap Steam Flow, Klb/h Coal Boiler TurboTurboBoilers #1 generator #2 generator #3 43 80 85 85 85 93 30 30 30 83 100 100 20 20 28 60 60 60 40 110 110 110 110 110 PRV Flow Klb/h 2.6 2.6 2.6 2.6 12.9 26.8 Cost MM$/yr 6.3 6.9 7.0 7.5 7.8 8.1 (Cost) MM$/yr 0.60 0.06 0.51 0.29 0.30 (Low-pressure Steam steam) Cost Klb/h $/Klb 66.4 7.7 30.1 9.8 13.2 1.18 1.18 1.18 1.01 1.01 2.21 2.21 3.85 3.85 2.96 2.96

to increase, the maximum capacity of the gas-fired boiler is reached, and the coal-fired boilers need to be used, pushing them to their maximum safe operating limit of approximately 95%. Notice that the marginal fuel starts out as coal, then switches to gas, and then switches back to coal. The marginal low-pressure steam cost depends not only on the marginal fuel; it also depends on the path that the incremental steam flow follows between the point of generation and the point of use. The results of Table 2 are plotted graphically in Figure 3, and show that the net steam cost is not constant. In fact, the net steam cost varies significantly with consumption rate, depending on the path being followed. The operating policy, as described above, is implicit in these curves. The same approach can be taken to determine the marginal cost curves for medium- and high-pressure steam. 4.5 4 3.5 3 Normal Operating Point

Cost, $/Klb

2.5 2 1.5 1 0.5 0 120

140

160

180

200

220

240

260

280

300

Low-Pressure Steam to Process, Klb/h

Figure 3. Variation of Net Low-Pressure Steam Cost (Marginal) with Consumption Rate Illustrative Example for Evaluating a Proposed Energy Conservation Project
This example is for a proposed project to use the exhaust vapors from an evaporator as the heat source for the reboiler of a distillation column, as illustrated in Figure 4. Anticipated savings will be in 15-psig steam to the reboiler and cooling water load on the evaporator condenser, but the steam supply to the evaporator chest will have to be upgraded from 15 psig to 50 psig. The existing steam balance is shown in Figure 5. The plant operates 8,000 hours per year. The combined heat and power system balance was calculated using a simulation model, which

How To Calculate The True Cost of Steam

Existing Process:
210 F Cooling Water 10 MMBtu/h Column

Evaporator 11 MMBtu/h 15 psig steam

10300 lb/h 10 MMBtu/h 15 psig steam Product 200 F

Feed 212 F

Proposed Retrofit:
250 F

Evaporator 11 MMBtu/h 50 psig steam

Column

Feed Product 200 F 212 F 10580 lb/h

Figure 4. Flowsheet Schematic of Proposed Retrofit


also accounted for two significant operating constraints: a maximum turbine capacity is 50 Klb/h, and a minimum PRV flow rate is 5 Klb/h. The process conditions, steam flow rates, and power generation in the steam turbine before and after project implementation are summarized in Table 3. The results from using the conventional approach to pricing steam are illustrated in Table 4. The marginal cost of 200 psig saturated steam is taken to be its fuel value, calculated as: 1000 (HS hW) aF /B = $3.00/Klb. No value is assigned to condensate. Full credit for low-pressure steam is taken for cogenerated power. In the base case, total steam use = 21 MMBtu/h at 15 psig = 22.2 Klb/h. In the proposed case, total steam use = 11 MMBtu/h at 50 psig = 12.1 Klb/h. The net project savings would then be computed to be: Savings = (22.2 x 1.00 12.1 x 2.75) x 8000 = $88,600 per year The project loses money because the loss of power credit exceeds the fuel savings. From this calculation, the project would clearly not appear to be beneficial.

How To Calculate The Tr ue Cost of Steam

Boiler Feedwater Makeup Blowdown

Boiler

113 Klb/h 200 psig 390F (saturated) 43 50 psig 300F (saturated) 10 50 TG


DSH

200 psig Users 10.0 1000 kw 50 psig Users 10.0 23 10 Blow Off 0.4

15 psig 250F (saturated)


DSH

1 Vent 14 15 psig

15 psig Users 30.0 30

Deaerator

Condensate Header

Soft Water Makeup Blowdown to Sewer

TG = Turbogenerator DSH = Desuperheater

Figure 5. Combined Heat and Power System for Example Problem Table 3: Summary of Key Project Parameters (from model)
Existing
Evaporator Steam Pressure, psig Steam v, Btu/lb Steam Flow, klb/h Steam Pressure, psig Steam v, Btu/lb Steam Flow, klb/h Steam Generation in Boiler, klb/h Condensate Return to Boiler, klb/h Steam Flow thru 50/15 PRV, klb/h Steam Flow thru Turbine, klb/h Power Generated in Turbine, kW Cooling Tower Duty, MMBtu/h 15 945 11.64 15 945 10.58 113.00 60.00 18.00 50.00 2.00 Q

Proposed
50 910 12.09 15 945 0 102.00 49.90 5.00 40.00 1.60 Q-10

Difference

455

Reboiler

Combined Heat and Power System

-10.58 -11.00 -10.10 -13.00 -10.00 -0.40 -10

Now consider the results from the recommended simulation modeling approach, with the affected utilities priced consistently, as follows: Steam from boiler (at 200 psig) = $3.00 per Klb Condensate return to boiler = $0.30 per Klb Purchased electrical power = $0.05 per kWh Cooling tower duty = $0.50 per MMBtu The project economics are now calculated based on the material balance shown in Table 3: Net utility savings = boiler fuel savings reduced condensate credit reduced power generation credit + savings in cooling tower duty = (11 x 3.00 10.1 x 0.30 400 x 0.05 + 10 x 0.50) x 8000 = $120,000 per yr Estimated capital cost = $150,000 = 150/120 Simple payback = 1.25 years From this calculation, the project would clearly appear to be beneficial.

10

How To Calculate The True Cost of Steam

Table 4: Steam Valuation by Conventional Method


Steam Pressure, psig Superheat, F Total Enthalpy, Btu/lb Steam Latent Heat, Btu/lb Steam Desuperheater Water Added, lb/Klb Steam Lb Steam per Klb High-Pressure Steam Available Process Heat, Btu/Klb High-Pressure Steam Fuel Cost, $/Klb High-Pressure Steam Steam Cost, $/Klb Steam Power Credit, $/Klb Steam Net Steam Cost, $/Klb HP 200 150 1,288 838 0 1,000 926,000 3.00 3.00 0 3.00 MP 50 0 1,180 910 90 1,090 991,900 3.00 2.75 0 2.75 LP 15 0 1,164 945 0 1,000 945,000 3.00 3.00 2.00 1.00

Basis: Boiler produces 200 psig superheated steam Lower-pressure steam is desuperheated using 250 F Boiler Feedwater

Why do the two calculating methods give such different answers? The reason is that the simple method does not properly account for the different paths followed by steam, whereas the model method does. Thus, the model method is the recommended approach.

Conclusion
Accurately determining steam costs is important for monitoring and managing energy use in a plant, for evaluating proposed design changes to the generation/distribution infrastructure and the process itself, and for continuing to identify competitive advantages through plant efficiency improvements. Steam costs are highly dependent on the path that steam follows in the generation and distribution system. Simulation models are simple, convenient, and reliable tools to follow these paths, calculate the correct costs, and to optimize the system. The method used for evaluating utility costs has a dramatic effect on project economics, and therefore the investment decision. Improper utility pricing can lead to bad decisions; good projects can be discarded, and bad projects can be implemented. Regrettably, this is relatively common. To avoid such mistakes, it is imperative that plant engineers and managers use appropriate methods for steam pricing, taking into account all the parameters that impact energy costsfuel, condensate, power generation, and cooling waterwhen evaluating proposed projects.

References and Additional Reading


1. ChemicaLogic, SteamTab software; www.chemicalogic.com. 2. D. Cooper, Do you value your steam correctly? Hydrocarbon Processing (July 1989). 3. Energy Information Agency, U.S. Department of Energy, Manufacturing Energy Consumption Survey: 1994, Report No. DOE/EIA-0512 (December 1994). 4. J. D. Kumana, Do Energy Saving Projects in Pulp/Paper Mills Really Pay? Paper presented at IPST Workshop, Atlanta, GA (March 1990). 5. J. D. Kumana, Use Spreadsheet-Based Combined Heat and Power Models to Identify and Evaluate Energy Cost-Reduction Opportunities in Industrial Plants, page 253, Procedures of 23rd Industrial Energy Technology Conference, Houston, TX (May 2001). 6. K. Nelson, A Practical Guide to Energy Accounting, Chemical Engineering (September 1994). 7. R. Smith, Chemical Process Design, Chapter 6, McGraw-Hill Inc., NY (1995).

11

A S TRONG E NERGY P ORTFOLIO

FOR A

S TRONG A MERICA

Energy efficiency and clean, renewable energy will mean a stronger economy, a cleaner environment, and greater energy independence for America. By investing in technology breakthroughs today, our nation can look forward to a more resilient economy and secure future. Far-reaching technology changes will be essential to Americas energy future. Working with a wide array of state, community, industry, and university partners, the U.S. Department of Energys Office of Energy Efficiency and Renewable Energy invests in a diverse portfolio of energy technologies that will: Conserve energy in the residential, commercial, industrial, government, and transportation sectors Increase and diversify energy supply, with a focus on renewable domestic sources Upgrade our national energy infrastructure Facilitate the emergence of hydrogen technologies as a vital new energy carrier.

A CKNOWLEDGEMENTS :
The Industrial Technologies Program would like to thank Kumana & Associates, for writing this BestPractices Steam Technical Brief, and the BestPractices Steam technical subcommittee for reviewing the publication.

The Opportunities
Biomass Program Using domestic, plant-derived resources to meet our fuel, power, and chemical needs Building Technologies Program Homes, schools, and businesses that use less energy, cost less to operate, and ultimately, generate as much power as they use Distributed Energy & Electric Reliability Program A more reliable energy infrastructure and reduced need for new power plants Federal Energy Management Program Leading by example, saving energy and taxpayer dollars in federal facilities FreedomCAR & Vehicle Technologies Program Less dependence on foreign oil, and eventual transition to an emisions-free, petroleum-free vehicle Geothermal Technologies Program Tapping the earths energy to meet our heat and power needs Hydrogen, Fuel Cells & Infrastructure Technologies Program Paving the way toward a hydrogen economy and net-zero carbon energy future Industrial Technologies Program Boosting the productivity and competitiveness of U.S. industry through improvements in energy and environmental performance Solar Energy Technology Program Utilizing the suns natural energy to generate electricity and provide water and space heating Weatherization & Intergovernmental Program Accelerating the use of todays best energy-efficient and renewable technologies in homes, communities, and businesses Wind & Hydropower Technologies Program Harnessing Americas abundant natural resources for clean power generation To learn more, visit www.eere.energy.gov

F OR A DDITIONAL I NFORMATION , P LEASE C ONTACT :


DOE Information Clearinghouse Phone: (800) 862-2086 Fax: (360) 586-8303 [email protected] Visit our home page at www.oit.doe.gov Please send any comments, questions, or suggestions to [email protected] Industrial Technologies Program Energy Efficiency and Renewable Energy U.S. Department of Energy Washington, DC 20585-0121

DOE/GO-102003-1736 September 2003

You might also like