GCP Received From Blast Furnace Section

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4



   !"$#&%'!( )+*-, .0/ 1 234265798;:=< > ?4@


4.5 4.5.1 BLAST FURNACE GAS CLEANING SYSTEM Scope of work The scope of work of the Bidder under this specification covers, but not limited to, the following : i) Design engineering, manufacture, assembly, inspection, testing, shop painting and erection, testing & commissioning of complete BF Gas Cleaning plant as per technical specification and relevant Chapter of GTS. Demonstration of performance guarantee. Supply of commissioning spares (list to be furnished by the Bidder and to be approved by the Purchaser/Consultant). Supply of spares for 2 years normal operation of the plant. A list of such spares shall be furnished by the Bidder alongwith quantity & itemised price. The list shall be approved by the Purchaser / Consultant. All the matching flanges / utility connections shall be included. Supply of all consumables, initial fill of oils, lubrication and other consumables.

$% &% #%       %   $% ! %  $! 

ii) iii) iv)

v) vi) 4.5.2

Data / Drawings to be Furnished Alongwith Tender i) ii) Overall layout drawing of complete Gas Cleaning Plants showing major dimensions & clearances General arrangement and cross-sectional drawings of GCP indicating the location various systems, equipments, auxiliaries, piping, etc. GA drawings of major equipments. List of pumps, drives alongwith specification and Kw rating. Data sheets / catalogues for various equipment, valves and bought out items. Process flow sheets and schematic diagrams of various utilities indicating flow rates, pressures, temperatures, consumptions, etc. Schematic diagrams for hydraulic /pneumatic / lubrication systems
Chapter 4.5 Page 1 of 4

iii) iv) v) vi) vii)

Copyright 2007. MECON Limited. All Rights Reserved

ABCDE E F DGBHICFEDJBKC L M"LG$N&O'IMP Q O-R S0T U VW4V6XY9G;I=T U W4Z


viii) ix) 4.5.3 Equipment schedule indicating quantity, estimated weights and source of supply (Indigenous / Imported) Detailed write-up on features provided for process & safety interlocks including functional diagrams

$% &% #%       %   $% ! %  $! 

The data/ drawings to be furnished by successful Bidder for Purchaser/ Consultants approval i) ii) iii) iv) Write-up on Control philosophy for smooth operation of gas cleaning plant. GA & Cross Sections drgs of GCP with binding dimensions. Equipment GA drawings showing details and Sections alongwith technical data sheet, bill of material. Structural drawing showing platforms with approach ladders at various levels of GCP tower for maintenance of different equipment. Utility / services requirement and terminal point where such utilities / services are required.

v) 4.5.4 4.5.4.1

Technical Specification Description of the unit The dust laden gas from dust catcher enters the gas cleaning plant based on the principle of two stage wet gas cleaning housed in a single tower and designed for the following parameters. i) ii) iii) Medium to be handled C.V. of gas Expected analysis of B.F. Gas (by volume) : : : Blast furnace gas 875 kcal/ Nm CO2 CO H2 N2 24.3 % 26.1 % 3.1 % 46.5 %

iv) v) vi)

Type No. of units Volume of BF gas

: : :

Two stage system with Annular gap scrubber One 5,40,000 Nm /hr (Normal) 5,90,000 Nm /hr (Max)
Chapter 4.5 Page 2 of 4

Copyright 2007. MECON Limited. All Rights Reserved

[\]^_ _ ` ^a\bc]`_^d\e] f g"fa$h&i'cgj k i-l m0n o pq4p6rs9a;c=n o q4t


vii) viii) ix) x) xi) Temp. of the gas Pressure of the gas at inlet Dust content of the inlet gas to GCP Moisture content of inlet Gas of GCP Outlet pressure of the gas : : : : 150 200C 600C (Peak Temp. for 30 min.) 2.3 2.5 kg/cm (g) 17 .0 gms/ Nm (max) 8.0 gms/ Nm (normal) 70 gm/ Nm. : 2.0 2.3 kg/cm (g) (when TRT is in operation) 1000 mmWC (when TRT is not in operation) 5 mg/Nm (max) 40 deg.C

$% &% #%       %   $% ! %  $! 

xii) xiii)

Dust content of the gas at the outlet Outlet temp.of the gas

: :

The hot dust laden gas from the dust catcher enters the 1st stage of the GCP tower from the top located above the annular gap cone scrubber, and cooled to saturation temperature by direct contact with water in a hollow scrubber where the gas stream enters the spraying zone of the scrubber and passes through the water curtain emitted by the injecting nozzles (BISCHOFF TYPE TOWER) arranged to give an upward and downward sprays into the downward flowing gas. Pumped water from the cone base and returned clarified water will be used for spraying. There shall be provision of emergency water supply to the upper stage of the scrubber in case of power failure. In the 1st stage, besides saturation, coarse dust particles are also entrapped into the water droplets. The slurry water from the 1st stage will be directed to the existing over ground launder for discharging into the existing effluent treatment plant. The greater part of the free water in the gas will be separated into the tower sump as the gas leaves the 1st stage of the tower. Part of the pre-cleaned gas coming out after the 1st stage cleaning can be used for pressure equalizing of the BF top equipment. The saturated, cooled pre-cleaned gas from the 1st stage now enters the 2nd stage cleaning equipment housed in the same tower (along with 1st stage equipment). The 2nd stage gas cleaning equipment comprises of annular gap scrubber (BISCHOFF TYPE), where the gas flows through the annular gap passage. Radial and tangential sprays will supply the clarified water necessary for the removal of dust particles. Normally 3 nos. of single annular gap elements are provided. Each of the three elements
Copyright 2007. MECON Limited. All Rights Reserved Chapter 4.5 Page 3 of 4

uvwxy y z x{v|}wzyx~vw "{$&'} - 0 469{;}= 4


will comprise a fixed cone within which a hydraulically operated inner cone operates. The differential pressure necessary for gas cleaning and top pressure will be regulated by raising or lowering the movable cones to vary the annular gaps. Sufficient power shall be provided to move to the cone 100% in either diversiform in emergency. 1st stage as well as 2nd stage of GCP tower shall be provided with sump water level control system to maintain BF operation as will prevent gas escape. GCP shall be suitable for Blast furnace operation with coal injection and hence appropriate corrosion protection necessary will be applied to meet the acidic re-circulating water found with the use of coal injection. The clean gas, coming out of the 2nd stage scrubber, passes through water droplet separator (demister), wherein water droplets get separated out from the gas stream. The gas entering the demister, passes through fixed directional vanes inducing a spinning action in the gas stream. Free moisture is collected as a result of the centrifugal forces produced by the spinning action. Slurry water is collected at the bottom of the 2nd stage scrubber and also at the bottom of the droplet separator. The slurry water is then directed to over ground launder for discharging into the effluent treatment plant. Clarified water from the effluent treatment plant will be pumped back to GCP 1st stage and 2nd stage scrubber. The clean gas with dust content of 5 mg/ Nm from the moisture separator will be used to meet the fuel requirements of various consumers of the steel plant. The clean gas line will also be provided with suitable facilities for connection to TRT for power generation. When TRT is in operation the pressure drop across the scrubber will only be that necessary to achieve the required gas cleanliness. The remaining pressure reductions to a pressure suitable for distribution within the works shall be performed by .the TRT. The scrubber and TRT shall be interlocked to insure accurate control of the furnace top. In case TRT is out of operation the scrubber will reduce the outlet gas pressure to the pressure in the clean gas system. The GCP will be complete with all the necessary instrumentation and controls, electrics, service platforms and supporting structures, stairs / ladders for easy approach to various instruments / valves / equipment, handling facilities as required, etc. for easy operation and maintenance.

$% &% #%       %   $% ! %  $! 

Copyright 2007. MECON Limited. All Rights Reserved

Chapter 4.5

Page 4 of 4

You might also like