Project Monitoring Control
Project Monitoring Control
Frequency counts
Raw numbers
Subjective numeric ratings
Indicators
Verbal measures
Report Types
Routine
Exception
Special analysis
Report Types
Report Types
Meetings
Meetings
1. A negative is bad
2. The cost variances are calculated as the
earned value minus some other measure
underrun, the project manager must figure out what to do to get the
system back on target
Options may include borrowing resources, or holding a meeting of
project team members to suggest solutions, or notifying the client that
the project may be late or over budget
BCWP/BCWS
Milestone Reporting
Project Baseline
Baseline duration
Baseline Start
Baseline Finish
Baseline duration
Baseline Cost
Actuals
Actual duration
Actual Start
Actual Finish
Actual duration
Actual Cost
In-progress
Percent Completion
Weighted % completion
Remaining duration
Monitoring
Tracking Table
Entering Progress data
An Example
5 day job
Review after 3 days
40 % complete (remaining duration = ?)
Suppose remaining duration is 4 days
(duration value increases)
10
Variance Analysis
S-Curve
Milestones
Achieving milestones
Project successful completion
11
Project Control
Performance
Cost
Time
Controlling Performance
Controlling Cost
12
Controlling Time
Purposes of Control
13
14
Thank You
15