Integrating Earned Value Management With CC Execution
Integrating Earned Value Management With CC Execution
Over the past decade, many business and government organizations have benefitted by executing projects using Critical Chain (CC). For example, Realizations customers have reported gains of at least $3.5B by doing projects 20-50% faster. In parallel, Earned Value Management (EVM) metrics have also become popular. The US government requires that all large projects measure and report status using EVM. Most people believe that CC and EVM are in conflict and cannot be implemented together. This white paper will debunk this assumption. In fact, it proposes neither CC nor EVM is a complete solution, and they must be integrated to assure projects are on time, on budget and deliver the full scope. It also provides practical instructions for integrating EVM and CC.
In addition, these metrics can be broken down by different departments, scope items, etc. to create variance reports that are then used as performance measurements. (Instead of using effort, Earned Value (EV) is sometimes calculated using the budgeted dollars.)
Critical Chain
The value of Critical Chain lies in solving root causes of schedule and cost overruns in projects. Significant time and capacity are lost in projects because the required inputs, resources, decisions etc. do not come together at the right time; there is confusion about priorities; and there are bottlenecks and resource conflicts in execution. All these things happen because traditional project schedules become obsolete soon after planning is done. Lacking schedules that can be followed in the execution, people resort to localized ad hoc priorities. These localized priorities lead to lack of synchronization, priority conflicts and bottlenecks. Critical Chain enables Real-Time Synchronization of tasks and resources as ground conditions change in execution. Critical Chain recognizes that fixed schedules dont work and instead, plans are created with explicit time buffers and flexible task scheduling. In execution, duration updates are gathered and relative priorities are determined by the buffer index (BI) of each task. This way, instead of following a fixed schedule, resources are now synchronized to the same set of real-time priorities. CC plans have shortened tasks with explicit buffers. The time saved by using CC is reflected by an overall shorter project.
Buffer Index computes priorities based on the chain remaining and buffer remaining.
In execution, consider a scenario where the project buffer is in control but consumes considerably more resources than planned. This situation may arise if the project team has the flexibility to increase resources. The additional resources may be necessary because of an increase in scope or the original estimations were inadequate. It may also be a consequence of poor execution or inadequately trained resources. Whatever the reason may be, it is important that the project manager recognizes the increase in resources. They may be able to reduce resources where they are no longer required or make other budget trade-offs. If nothing else can be done to bring the budget under control, the project manager will have to reset expectations about the project budget. CPI can provide an early warning signal for overruns by capturing the scope accomplished against the budget spent. What about SPI? Lets consider another example.
Assume each task in the project takes 10 days and there is only one resource available for each of the resource types (R1, R2, R3, R5, R7, R8). Also, assume that the network accurately captures task dependencies, i.e. task T2 can only be started after task T1 is done. The Critical Path (T1 T2 T3 T8) is highlighted in red. What is not captured in this plan is that T1, T4, T6 all require the same resource (R1). Due to resource dependencies, there is a need to measure both Critical Path completion as well as total of the feeding paths. Insufficient progress on Critical Path or insufficient progress on feeding paths may delay the project. SPI in this case will highlight the problem of insufficient feeding path progress.
Lets make a Critical Chain plan for the above network. The network will become aggressive with shorter time. The tasks will be aggressive. Both task and resource dependencies will be captured in the Critical Chain. Buffers will be added at the end and at integration points.
The longest chain (known as Critical Chain) of this project has shifted (T1 T4 T6 T7 T8). The Critical Chain is now highlighted in red. Any delays on R1s tasks will immediately impact the overall project buffer. If the project buffer is in control, then SPI performance should also be good. In fact, the project buffer should highlight a possible SPI problem sooner because it is based on the worse chain (original Critical Chain or the Feeding Chains). If the project buffer is under control and SPI is not good then resource dependencies are missing and should be captured in the plan. Summary of Integration needs:
Tasks are higher level, making it difficult to estimate earned value. Not all work, level of effort (LOE), or resources are captured in CC plan. Having buffers in CC plan makes it difficult to: Define baseline for EVM Define accountability for buffers
In order to integrate EVM and CC, we need to resolve these contradictions. Therefore, the questions are: Planning What is the trade-off between cost and schedule in a project? How should buffers in CC plans be accounted into the EVM baseline? CC requires higher level of tasks for better prioritization however EV needs more details to estimate EV. How to define tasks? Is there a change on how LOE tasks are baselined or progressed? Execution How will progress updates happen for CC and EVM? EV may encourage wrong priorities. How can we counter these behaviors in execution? Who has accountability of buffers? How do we make decisions based on CPI, SPI and Buffer Index?
Planning: There is no need to make a trade-off between schedule and cost. In fact, both cost and schedule are important for a project. Generally, it is true that faster execution will cost less. However, in order to ensure planned scope is accomplished against planned budget, one must monitor and control cost. Below are the steps for planning: Step 1: Create a Critical Chain buffered plan with the right level of task detail. One-third of the project schedule will be buffer and two-third task times. (By definition, if a plan is feasible with the amount of uncertainty in the execution, there is buffer in the plan. This step makes buffers explicit.)
Step 2: Fix start dates of chains based on an offset for integration point. The offset is required to ensure that feeding chain start is not too early for EVM baseline calculation or too late to make project buffer red. The offset for a feeding chain is equal to (feeding chain length/CC chain length)* project buffer size. Step 3: Expand the task durations by the buffer settings (same timeline, no buffers). Step 4: Baseline the expanded plan for EVM. Step 5: Capture the scope associated with each task in a checklist and estimate the earned value for each item. The sum of the earned value for each item is the total earned value for the task. Do not use the resource load from the CC plan as some resources may not be captured at the task level. Step 6: CC plan should maintain consistency with EVM. When new scope is added in a CC plan, then it needs to be reflected in EVM baseline as well. If tasks are split in CC plan (to better model execution) without change of scope or effort, then it is also recommended to update the EVM baseline for consistency.
Note: Cost accounts should be defined at CC plan tasks or a higher level of the Work Break down Structure (WBS). LOE tasks for support and management resources should be maintained outside of CC plans. LOE can be tied to milestones or deliverables in the CC plan and earned on completion. It is not recommended to give automatic credit based on elapsed time. Execution: EV for CC tasks is reported based on the checklist completions. CC requires remaining duration updates. Remaining duration cannot be derived from % complete. It is possible for the last 20% of effort to take 80% of the duration. As a result when working with CC and EVM, EV and remaining duration updates must be made independently. Continue to maintain actual cost of work performed (ACWP) as done today. An adjustment may be required for charge codes based on cost accounts. Picture below depicts execution integration: Update Reporting Effort Tracking
Project Metrics In order to prevent working on wrong priorities, BI priorities must be followed in the execution. When the tasks are not completed or more tasks are opened, BI will immediately flag the issue. The accountability of buffers is jointly shared by project manager, resources manager and portfolio manager. The reasons for buffer consumption will make it obvious if the responsibility of actions/decisions lies with the project manager, the resource manager, or the portfolio manager.
CPI GOOD
Buffer recovery is required. Check if adding resources will help.
SPI GOOD
This will happen when the longest chain is behind schedule and feeding chains are executing well. Plan buffer recovery. Resources are wasted. Make resource concentration effective for project by: Cutting resources Cutting the time lines X
CPI POOR
Resources are wasted. Make resource concentration effective for project by: Cutting resources Cutting the time lines This can only happen if resource dependencies are missing in CC plan as discussed in the beginning. Fix the CC plan.
SPI POOR
In this case BI will be bad too. So, buffer recovery is required. Check if adding resources will help.
Conclusions
A good integration of CC and EVM without conflicts is possible and will make a complete solution for the project management. Use CC to manage timelines and EVM to manage cost for the given scope. The guidelines are: Use CC plan tasks or higher level in WBS as cost accounts Expand the CC plan tasks to get the EVM baseline. Effort is modeled as checklist in CC tasks EV is reported by checklist and task completion on CC tasks LOE is reported based on milestone or deliverable completions Follow BI priorities in execution React to the BI, CPI and SPI metrics as discussed
AFTER
54 projects completed in 2008. On-time delivery improved to 83%. 32% reduction in CH-47 turnaround time. 52% reduction in UH-60 turnaround time. 8 aircraft returned to customer ($90M in cost avoidance). 18,000 sq ft of hangar space freed up ($2M in cost savings). 586 engines produced per year (23% increase). 30% reduction in engine turnaround time. 15 days piece-part cycle time (70% reduction). 25% increase in throughput. 30 days landing gear turnaround time (50% reduction). $60M monetized in assets from reduced turnaround time. Ongoing improvement: 10 days piece-part turnaround time (30% further reduction). On-time delivery increased to 83%. 3 aircraft on station, 2 aircraft returned to Air Force, a replacement value of 300 M. 15% cycle time reduction, 15% increase in output with 13% fewer resources; 22% reduction in support shops cycle time. 44 aircraft throughput in FY10 (33% increase). 24 aircraft on station, 12 aircraft returned to Air Force. Engine piece-part repair: 42 days backshop cycle time (69% reduction). 434 parts/month throughput (67% increase). Engines and Modules: 50 modules/month throughput (10% increase). 8 days cycle time (55% reduction). Turnaround time reduced to 115 days. 4 aircraft in repair cycle (3 returned to customer). Production output increased from 185 hours/day to 273. 1 dock spaces freed up (additional revenue potential $35M). Produced 17 aircraft a year. Cycle time of 195 days. 2.6 aircraft on base on average. Cycle time of 155 days. 11% capacity released for additional workload. Average turnaround time reduced to 146 days. 44% increase in throughput from Q4 2008 to Q4 2009. 25% increase in throughput. Turnaround time reduced to 37-121 days. Mechanic output increased to 4.75 hours per day. 40% reduction in overtime. Turnaround time 160 days. 7 aircraft in repair cycle. 75% fewer defects. Throughput increased to 6.3 aircraft per month. Black Hawk throughput increased by 40% in just 6 months. 50% reduction in Apache turnaround time. 15% reduction in CH47 turnaround time. 15% reduction in Pave Hawk turnaround time despite increased scope. Repair cycle time for MK48 reduced to 82 days. Repair cycle time for LAV25 reduced to 124 days. Repair cycle time for MK14 reduced to 59 days. Repair cycle time for LAVAT reduced to 122 days.
476 engines produced per year. 4-8 weeks piece-part cycle time. 60 days landing gear turnaround time.
Erickson Air-Crane
Only 33% projects completed on time. 5 aircraft on station. Cycle time of 165 days.
US Air Force, Ogden Air Logistics Center 572nd AMXG, C130 Production Line
Aircraft Maintenance, Repair and Overhaul
33 aircraft throughput in FY09. 36 aircraft on station. Engine piece-part repair: 137 days backshop cycle time. 260 parts/month backshop throughput. Engines and Modules: 45 modules/month throughput. 18 days cycle time. Turnaround time 162 days. 7 aircraft in repair cycle.
US Air Force, Oklahoma City Air Logistics Center B-1 Production Line
Aircraft Repair and Overhaul
US Air Force, Oklahoma City Air Logistics Center B52 Production Line
Aircraft Upgrade and Repair
Produced 11 aircraft a year. Cycle time of 225 days. 4 aircraft on base. Cycle time of 183 days. Average turnaround time was 327 days.
US Air Force, Oklahoma City Air Logistics Center KC135 Production Line
Aircraft Maintenance, Repair and Overhaul
US Air Force, Warner Robins Air Logistics Center C17 Production Line
Aircraft Upgrade and Repair
Throughput of 178 hours per aircraft per day. Turnaround time 46-180 days. Mechanic output was 3.6 hours per day. Turnaround time 240 days. 13 aircraft in repair cycle. Throughput of 5.4 aircraft per month. Throughput for Black Hawk was much lower than required. Turnaround times were unacceptable. Work scope per aircraft was increasing.
Repair cycle time for MK48 was 168 days. Repair cycle time for LAV25 was 180 days. Repair cycle time for MK14 was 152 days. Repair cycle time for LAVAT was 182 days.
AFTER
Reduced H-46 turnaround time to 167 days, while work scope was increasing. Reduced H-53 turnaround time to 180 days. Delivered 23 aircraft in the first 6 months. Throughput increased to 46 aircraft per year. Job completion rate increased to 98%. Increased on-time delivery to 95+%. Reduced cost per job to $3,355, a 33% reduction. Overtime dropped by 49%, a $9M saving in the first year. Produced 9 aircraft in the first 9 months of 2009. Project 1 delivered on time. Project 2 delivered 1 day earlier (with 10% extra scope). Actual cost was 96% of planned budget.
Job completion rate was 94%. On-time delivery was less than 60%. Cost per job was $5,043. Produced 6 aircraft in 2008. Projects were late and over budget.
Votorantim
Process Plant Turnaround (Nickel Smelting)
AFTER
Cycle time for prototype builds reduced to 8 weeks. 87% projects on time. 15% immediate increase in throughput. 11 projects completed (83% increase). 80% projects on time (60% increase). 110 filings in 2010 (30% increase). 149 launches in 2010 (75% increase). 563 days cycle time for development in 2010 (40% faster). Actual cycle time reduced to 23 months; almost all projects are within the committed cycle time of 24 months. Increased throughput to 52 new products in the 1st year, and to 70+ in the 2nd year, with no increase in head count. 88% projects on time. 20% faster time-to-market. 98% on-time delivery. 10% of projects finished ahead of schedule. 15 cameras launched in 2005. 7 cameras launched in spring window. All 15 cameras launched on time. 85% of small projects on time. Major tools released on time for three years in a row. Completed 7 projects in the first 8 months of 2007. 1 software release every 2 months. Schedule slips on device programs cut by 50%. Development cycle time reduced to 9 months. On-time delivery increased to 90%. In 2008, completed 12 projects/quarter. 90% on time, with same number of resources. 100% due-date performance. 30% reduction in lead times and sampling costs.
e2v Semiconductors
Semiconductor Design and Manufacturing
Heineken, Spain
CPG New Product Development
LSI Logic
ASIC Design Technology Development
Marketing Architects
Advertising Product Development
Medtronic
High Tech Medical Product Development
Medtronic, Europe
High Tech Medical Product Development
Skye Group
Garment Design
ENGINEEr-To-orDEr RESULTS
BEFORE
ABB AG, Power Technologies Division
Electrical Power Transmission, Engineer-to-Order Throughput was 300 bays per year. Engineering cycle time was 8 months. On-time delivery was 85%. Completed an average of 6.9 projects per year. Reflectors were the constraint in Antenna and Satellite delivery.
AFTER
Throughput increased to 430 bays per year. Engineering cycle time reduced to 3 months. On-time delivery improved to 95%. 16% increase in manufacturing throughput (revenues). Completed 10 projects in first 8 months of 2009. 31% increase in throughput-dollars. Doubled Reflectors throughput and reduced cycle time by 28%, alleviating delivery constraint. Increased productivity in Antenna Assembly and Test by 64% and subsequently another 26%. Reduced cycle time for Electronic units, allowing subsystems to finish 30% faster. Stabilized schedule and returned money to Government 4 quarters in a row. Operation turned profitable. 64 days overall cycle time (25% reduction). 10 days production cycle time (60% reduction). 22 machines in 5 months (47% higher throughput). 22% improvement in EBIT. Design Engineering takes 9 months. Production Engineering takes 5 months. Fabrication and Assembly takes 5 months with 22% improvement in labor productivity. 27 casings per year (30% increase). 90% on-time delivery. 20-30% faster cycle time. Project cycle times reduced by 20%. Lateness reduced by 50%. 63% gains in productivity. 15% more projects completed. Completed 334 projects in the first 9 months. Revenues increased by 88% and profits by 300%. Revenues of 170 M. Profits of 22 M. Cycle time reduced to 14 weeks. On-time delivery improved to 90%.
ABB Crdoba
Power Transformers, Engineer-to-Order
Electronic units were late, delaying Satellite subsystems. Classified Government program was behind schedule and losing money. Operation was losing $200M a quarter.
Ismeca Semiconductor
Engineer-to-Order
84 days overall cycle time. 24 days production cycle time. 15 machines in 8 months was highest throughput ever. Design Engineering took 15 months. Production Engineering took 9 months. Fabrication and Assembly took 8 months. 20 casings per year. 60% on-time delivery. Long project cycle times with frequent delays. Difficult to synchronize Design and Manufacturing. 70% of projects were late. High overtime and outsourcing. Struggled to complete 200 projects per year. Revenues were flat, business was just breaking even. Revenues of 130 M. Profits of 13 M. Cycle time was 17 weeks. On-time delivery was 80%.
koda Power
Engineered-to-Order Steam Generators
TECNOBIT
Defense Products Design and Manufacturing
Von Ardenne
Equipment for Manufacturing Solar Panels, Engineer-to-Order
AFTER
Throughput increased by 45% per person. Lead times shortened by 10-25%. On-time delivery improved to 90+%. Throughput increased by 14% in the first 6 months. Cycle time reduced by 25% and project completions increased 17% with over 90% on-time delivery. Cycle time from first silicon to production for 2nd generation was 8 months.
Alna Software
Customized Software Development
AFTER
14% increase in revenue/man-month. 20% reduction in cycle time. 0 projects in crisis in 2008. Due-date performance increased to 95%. Throughput increased by 30%. SAP functionality project completions increased by 30% to 20 projects a month. Throughput increased by 25% to 24-30 projects per month. 171 sales projects completed per year. 52% increase in throughput-dollars. 2.5 months cycle time (58% faster). 60 projects/year throughput (33% increase). 100% on-time delivery on all orders. 3 orders executed in the same timeframe. 128 projects completed in 11 months. 30% increase in overall throughput. 44% increase in non-project throughput. On track to finish pylon project in 7 months.
Celsa Group
IT Projects
Railcare Wolverton, UK
Spirit Aerosystems
Aircraft Engineering
AFTER
142 projects completed in 2005. 153 projects completed in 2006. Project finished 3 weeks early. Productivity increased by 25% with only 19,500 manhours needed. Increased on-time delivery to 98+%. Average cycle time dropped to 30 days. 7 months to project completion. (55% additional revenue 4 months earlier). Completed 11 months of work in 6 months. Project on time (5 M penalty avoided). On-time delivery improved by 30%. Lead times reduced by 25%. 120-160 days completion time (68% faster). 10-33% reduction in 2007 cycle time. 5-33% additional reduction in 2008 cycle time. 8.8 days shutdown achieved. $4M revenue gained. Set net operating hours industry record (6690 hours per year). Delays reduced by 40%. 76% reduction in cycle time. 29% increase in throughput. 30% reduction in cycle time measured over 900 projects. 30% improvement in resource utilization. 88% on-time delivery performance.
eircom
emcocables Emesa
Long delays in processing requests. Long cycle times. Long cycle times. Low utilization of resources. Poor visibility of project slips.