Chevron Bangladesh Drilling Morning Report: Date: 10/27/2013
Chevron Bangladesh Drilling Morning Report: Date: 10/27/2013
Chevron Bangladesh Drilling Morning Report: Date: 10/27/2013
Date: 10/27/2013
Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :
TVD End (mOTH):
Water Depth (m) Target Depth (MD) (mOTH)
Bibiyana
Actual Start Date
3,721.52 24,305,837
AFE/WBS Number
100632 Safety/Inspections
Date Safety Check Tour Des
10/27/2013 00:00 10/27/2013 00:00 10/27/2013 00:00 10/27/2013 00:00 10/27/2013 02:30 10/27/2013 06:00 10/27/2013 06:00 10/27/2013 06:00 10/27/2013 06:00 10/27/2013 06:30 10/27/2013 06:30 10/27/2013 06:30 10/27/2013 06:30 10/27/2013 07:00 10/27/2013 08:30 10/27/2013 11:00 10/27/2013 11:30 10/27/2013 12:00 10/27/2013 12:15 10/27/2013 12:15 10/27/2013 14:00 10/27/2013 14:30 10/27/2013 17:00 10/27/2013 18:00 10/27/2013 18:30
Pre-Job Meeting Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting PTW Audit Safety Procedures Safety Procedures Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting PTW Audit PTW Audit Safety Meeting Pre-Job Meeting Pre-Job Meeting
Night Night Night Night Night Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Night Night Night Night Night Night Night Night Night Night Night
Cleaning mud tank @BYWP (PTW) RADAR, Ops, Tnt#07 & GEMS#08 @BYWP Gen. Crane Lifting @BYWP Gen. Forklift Ops @BYWP Replace lamp at mud tank @BYWP (PTW) General Hotwork at workshop @BYWP(PTW) Diesel Transfer @BYWP(PTW) MPI job by Smith @BYWP(PTW) Gen. Crane Lifting @BYWP w/Kamal Ent., RADAR Cards, Tnt#07 @BYWP Gen. Housekeeping (K/E) @BYWP Gen. Forklift Ops @BYWP Use of camera @BYWP (PTW) Service of centrifuge at NOV @BYWP (PTW) Cleaning mud tank@BYWP T-Card Audit Radar stat, incident review @BYWP RADAR, Ops, Tnt#07 & GEMS#08 @BYWP Gen. Forklift Ops @BYWP Gen. Crane Lifting @BYWP Centrifuge servicing at NOV @BYWP General Hotwork at workshop @BYWP Ops. Review, Tnt#07 @BYWP General hotwork at Workshop @BYWP (PTW) Replace mechanical seal of water pump @BYWP (PTW) Gen. Crane Lifting @BYWP w/Kamal Ent., RADAR Cards, Tnt#07 @BYWP Gen. Housekeeping (K/E) @BYWP T-Card Audit General hotwork at Workshop @BYWP Cutting inside generator room @ BYWP (PTW) Run RTTS in the well @ BYWP (PTW) RADAR, Ops, Tnt#07 & GEMS#08 @BYWP Radar stat, incident review @BYWP
Incident Desc
10/27/2013 18:30 Pre-Job Meeting 10/27/2013 18:30 Pre-Tour Safety Meeting 10/27/2013 18:30 Pre-Job Meeting 10/27/2013 19:30 Safety Procedures 10/27/2013 20:30 PTW Audit 10/27/2013 22:00 Pre-Job Meeting 10/27/2013 22:30 Pre-Job Meeting 10/27/2013 23:30 Pre-Tour Safety Meeting 10/27/2013 23:30 Safety Procedures Safety / Environmental Incidents
Incident Cat.
Page 1/5
Date: 10/27/2013
Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :
10/27/2013 00:00
Daily Field Est Total (Cost) Cum Field Est To Date (Cost) Daily Mud Field Est (Cost) Cum Mud Cost to Date (Cost)
10/28/2013 00:00
Drilling Hours (hr) Cum Rotating Hrs on Casing
183,430
Operations Summary
12,595,851
900,253
Continue RIH tie back packer assembly w/5 dp F/993m T/2770m. Safety wash F/2770m T/2798.7m (tag), S/O 3m attempt to PT back side w/o success had communication. Cont to S/O to depth of 2807m (hanger/liner moving down hole). Sting in 3m w/ tie back liner, test annulus 1000 psi, good. Set tie back packer, ok. Test annulus 4k psi, ok. Circulate & TOH with tie back running tool, L/D running tool. P/U 27 jnts 5'' HWDP to 252.83m.
Comments
0:00 - 05:00 Ops: 00:00 - 05:00, P/U & M/U Halliburton RTTS packer, perform surface checks, ok. Cont to RIH Halliburton RTTS on 5'' DP F/252.83 m T/ 1560m.
Max Drill Gas Required Matls next day Avg Background Gas Head Count
148.0 Halliburton batch mixer in customs. CCTV: driller has camera for derrick,stabbing board, mud pump. STP recorder non-operational. Safety Observation Cards
Observation Typ # Rpts Com
71 During pulling out,crew was pushing back the iron roughneck , the driller started lowering the drill pipe to floor which might cause getting caught in between.Stopped the driller immediately and crew moved away safely. Tenet #2. SUJON KAZI - Floorman
Contact
Daily Contacts Dewayne Cole Raymond Teale Kitichai Leekitchakorn Randy Roberts Palash Saha Miah Mohammed Fahad Time Log
Start Time End Time Phase Activity Dur (hr) Unsched Event? UE Time (hr) UE Ref No. Com
00:00
06:00
PRODTBG, TBG
TIH
6.00 Yes
6.00 13
Cont to TIH w/tie back liner packer on 5'' DP fr, 993m to 2770m.
Page 2/5
Date: 10/27/2013
Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :
UE Time (hr)
UE Ref No.
Com
06:00
11:30
PRODTBG, TBG
LNRTB
5.50 Yes
5.50 13
Safety wash to locate top of liner, wash f/ 2770m t/ 2798.7m tag top of line, observe pressure increase 200 psi. Stop mud pumps and open drill pipe to atmosphere, lower drill string and observe seal action as seals entered the liner top PBR, after 2.86m of seal assembly inside of PBR set 10k weight. Close annular and open drill pipe to atmosphere , increase pressure to perform test of seal assembly/ PBR connection and when pressure was to 300 psi a sudden release of pressure through drill pipe indicated connection was lost. Open BOP, pick up on drill pipe and start pumps, lower drill string and discovered that liner hanger/liner moved down hole. Wash and lower drill string to locate new liner top depth. At 2807m observe pressure increase stop mud pumps, with drill pipe open to atmosphere lower drill pipe and observe seal action as seal packs (4) entered PBR of liner hanger. After all 4 seal packs inside PBR went to slack off weight and discovered that liner hanger/ liner were moving downward, continue working weight as movement progressed with 10/12k WOB and movement stopped when liner top was at 2813.46m shoe was at TD of the 8-1/2" hole section. Close annular and pressure test to 1,000psi on annulus and drill pipe open to atmosphere (good test) bleed off pressure and attempt to establish circulation since movement in liner occurred, maximum pressure applied 1,400 psi. Pressure held, no circulation. Bleed off pressure.
11:30
13:00
PRODTBG, TBG
LNRTB
1.50 Yes
1.50 13
Slack off 10K Ibs and rotate string 12 turns to the right. Release torque and P/U 2m to engage setting dogs, slack off and set packer wit 42K down weight, continue until 70K weight down, Set the tie back packer and pressure test annulus against packer with mud at 4000 psi. pressure hold(good test). Bleed off pressure. Apply 500 psi down the drill string as picking up on drill pipe to disengage the PBR pack off after observing a pressure release , start mud pumps and at 2 bpm to clear the running tool from liner hanger. Note: New TOL at 2,808m, (top of PBR for Tie back packer)
13:00 13:30
13:30 20:30
CC TOH
0.50 13 7.00 13
Circulate bottoms up. No gas % on bottom/up. Flow check (static). TOH with drill pipe and tie back running tools to surface. Soft breaks to running tools and L/D the same. Rig Service PJSM for RIH RTTS Packer. P/U 27 jnts 5" HWDP & RIH T/ 252.83 m.
SSE
Personnel Chevron Weatherford Weatherford 16 17 Rig Expat 45 Rig National Page 3/5 Report Printed : 10/28/2013
Date: 10/27/2013
Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :
SSE
Weatherford Aker-Kvaerner Weatherford Halliburton Weatherford MI Swaco Weatherford Weatherford Brandt - NOV HAL - Wireline Weatherford Weatherford Chevron Smith International Schlumberger Weatherford Weatherford Chevron Weatherford Weatherford Chevron Weatherford Weatherford Chevron Weatherford Weatherford Weatherford Mud Checks
Date Depth (MD) (mOTH) Depth (TVD) (mOTH)
22 1 3 6 2 2 0 6 0 8
Shamolima Catering Wellhead Eng LWD/MWD Cementing DD Mud Engineers Gyrodata TRS Solids Control Wireline
5 SLS 0 Ayun ent 1 PetroBangla 3 Inspection Slickline 0 Completion/Liner hands 0 Shafiq Brothers 0 0 0 0 11 WWT BanglaCat Bangla Industrial Hunting Casing NOV Tech
10/27/2013 22:00
Flow Line Temperature (C) Vis 3rpm Fluid Density (lb/gal)
4,031.0
Gel 10 sec (lbf/100ft)
3,670.26 NAF
Gel 10 min (lbf/100ft)
Active Pit
Gel 30 min (lbf/100ft)
13.30
Vis 6rpm Vis 300rpm
22.0
Vis 600rpm
30.0
Funnel Viscosity (s/qt)
33.0
PV Calc (Pas)
17 0
ROC (Wet) (% by wt) (lb/lb) Retort NAF by Volume (%)
8
pH Filtration Sz (m) NAF/Water Ratio Chlorides (mg/L)
9
CaCl2 (mg/L)
55
Electric Stability (V)
93
Water Phase Salinity (mg/L)
70 348,900
Retort Water by Volume (%)
49,500
High Gravity Solids (lb/bbl) Corrected Solids (%)
294,674.00 24.87
API Filtrate (cc/30min) API Filter Cake (1/32")
720.0
Retort Solids (% by Volume) (%)
301.15
NaCl (mg/L)
27.00
HTHP Filtrate (cc/30min)
14.50
HTHP Filter Cake (1/32")
58.50 1
Visibility (km)
2.4
T Low (C)
Support Vessels
Vessel Name Vessel Type Arrival Date Depart Date Note
Unscheduled Events
Referen ce No. Start Date End Date Event Type Unsch Maj Cat Unsch Detail Description Accountable Party Contractor
13
10/25/2013
NPT
EQP
CSG LN
Trouble with liner hanger set. Problem with establish the circulation, restricted on flow path.
Rig Contractor Weatherford Casing & Tubing Running, Liner Hngrs/Whipst ocks
Page 4/5
Date: 10/27/2013
Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :
Rec
Consumed
On Loc
10/27/2013
Date Received
12.0
Consumed Cum On Loc
234.0
10/27/2013
7,582.0
136,583.0
String/BHA Components
Item Des Len (m) Mass/Len (lb/ft)
Drilling Parameters
Wellbore Cum Depth Drilled (mOTH) Pick-Up String Weight (1000lbf) Depth Start (MD) (mOTH) TVD Start (mOTH) Cum Drilling Time (hr) Flow Rate (gpm) Drilling Torque Depth End (MD) (mOTH) TVD End (mOTH) RPM (rpm) Drill Time (hr) On Bottom Drill Time (hr) Stand Pipe Pressure (psi) Interval ROP (m/hr)
Casing Strings
Casing Description Comment Set Depth (MD) (mOTH) Set Depth (TVD) (mOTH) Run Date
Casing Components
Top Depth (MD) (mOTH) Btm Depth (MD) (mOTH) Len (m) Jts Item Des OD (in) ID (in)
Tubing Strings
Tubing Description Comment Set Depth (MD) (mOTH) Run Date
Tubing Components
Item Des Jts Len (m) OD (in) ID (in) Top (mOTH) Btm (mOTH)
BOP Test
Date Com
10/22/2013 Wellbores
Wellbore Name
Perform full BOP test. Annular 250/3500 psi other test 250/5000 psi
Parent Wellbore
Original Hole
Date
7/18/2013
EW (m) DLS (/30m)
Page 5/5