Chevron Bangladesh Drilling Morning Report: Date: 10/27/2013

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5
At a glance
Powered by AI
The document discusses the daily drilling report and safety procedures for Bibiyana-18 well. It provides details on drilling operations, personnel, equipment, and mud properties.

Many safety procedures and inspections are listed on page 1, including pre-job meetings, safety checks, and permit to work processes. Radar stats and incident reviews are also mentioned.

Page 2 describes the drilling operations from the previous day, which included running and setting a tie back packer and liner, and tripping out of hole with running tools.

Chevron Bangladesh Drilling Morning Report

Date: 10/27/2013

Well Name: Bibiyana-18 Slot: 8 Rig: WDI 801 End Date:

Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :
TVD End (mOTH):
Water Depth (m) Target Depth (MD) (mOTH)

Rpt No: 36 Hours: 24.00 1,083 / 127

SBU Drilling Well Category : Drlg Well Category 1


Depth End (MD) (mOTH):
Field Name Original Spud Date Actual End Date Country

Original KB to Mud Line (m) Target Depth (TVD) (mOTH)

Bibiyana
Actual Start Date

Bangladesh 7/16/2013 18:00 4,080


Total AFE Amount (Cost)

3,721.52 24,305,837

AFE/WBS Number

100632 Safety/Inspections
Date Safety Check Tour Des

10/27/2013 00:00 10/27/2013 00:00 10/27/2013 00:00 10/27/2013 00:00 10/27/2013 02:30 10/27/2013 06:00 10/27/2013 06:00 10/27/2013 06:00 10/27/2013 06:00 10/27/2013 06:30 10/27/2013 06:30 10/27/2013 06:30 10/27/2013 06:30 10/27/2013 07:00 10/27/2013 08:30 10/27/2013 11:00 10/27/2013 11:30 10/27/2013 12:00 10/27/2013 12:15 10/27/2013 12:15 10/27/2013 14:00 10/27/2013 14:30 10/27/2013 17:00 10/27/2013 18:00 10/27/2013 18:30

Pre-Job Meeting Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting PTW Audit Safety Procedures Safety Procedures Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting PTW Audit PTW Audit Safety Meeting Pre-Job Meeting Pre-Job Meeting

Night Night Night Night Night Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Night Night Night Night Night Night Night Night Night Night Night

Cleaning mud tank @BYWP (PTW) RADAR, Ops, Tnt#07 & GEMS#08 @BYWP Gen. Crane Lifting @BYWP Gen. Forklift Ops @BYWP Replace lamp at mud tank @BYWP (PTW) General Hotwork at workshop @BYWP(PTW) Diesel Transfer @BYWP(PTW) MPI job by Smith @BYWP(PTW) Gen. Crane Lifting @BYWP w/Kamal Ent., RADAR Cards, Tnt#07 @BYWP Gen. Housekeeping (K/E) @BYWP Gen. Forklift Ops @BYWP Use of camera @BYWP (PTW) Service of centrifuge at NOV @BYWP (PTW) Cleaning mud tank@BYWP T-Card Audit Radar stat, incident review @BYWP RADAR, Ops, Tnt#07 & GEMS#08 @BYWP Gen. Forklift Ops @BYWP Gen. Crane Lifting @BYWP Centrifuge servicing at NOV @BYWP General Hotwork at workshop @BYWP Ops. Review, Tnt#07 @BYWP General hotwork at Workshop @BYWP (PTW) Replace mechanical seal of water pump @BYWP (PTW) Gen. Crane Lifting @BYWP w/Kamal Ent., RADAR Cards, Tnt#07 @BYWP Gen. Housekeeping (K/E) @BYWP T-Card Audit General hotwork at Workshop @BYWP Cutting inside generator room @ BYWP (PTW) Run RTTS in the well @ BYWP (PTW) RADAR, Ops, Tnt#07 & GEMS#08 @BYWP Radar stat, incident review @BYWP
Incident Desc

10/27/2013 18:30 Pre-Job Meeting 10/27/2013 18:30 Pre-Tour Safety Meeting 10/27/2013 18:30 Pre-Job Meeting 10/27/2013 19:30 Safety Procedures 10/27/2013 20:30 PTW Audit 10/27/2013 22:00 Pre-Job Meeting 10/27/2013 22:30 Pre-Job Meeting 10/27/2013 23:30 Pre-Tour Safety Meeting 10/27/2013 23:30 Safety Procedures Safety / Environmental Incidents
Incident Cat.

No safety or environmental incident

Page 1/5

Report Printed : 10/28/2013

Chevron Bangladesh Drilling Morning Report

Date: 10/27/2013

Well Name: Bibiyana-18 Slot: 8 Rig: WDI 801 End Date:

Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :

Rpt No: 36 Hours: 24.00 1,083 / 127

SBU Drilling Well Category : Drlg Well Category 1


Daily Operations
Report Start Date

Report End Date

10/27/2013 00:00
Daily Field Est Total (Cost) Cum Field Est To Date (Cost) Daily Mud Field Est (Cost) Cum Mud Cost to Date (Cost)

10/28/2013 00:00
Drilling Hours (hr) Cum Rotating Hrs on Casing

183,430
Operations Summary

12,595,851

900,253

Continue RIH tie back packer assembly w/5 dp F/993m T/2770m. Safety wash F/2770m T/2798.7m (tag), S/O 3m attempt to PT back side w/o success had communication. Cont to S/O to depth of 2807m (hanger/liner moving down hole). Sting in 3m w/ tie back liner, test annulus 1000 psi, good. Set tie back packer, ok. Test annulus 4k psi, ok. Circulate & TOH with tie back running tool, L/D running tool. P/U 27 jnts 5'' HWDP to 252.83m.
Comments

0:00 - 05:00 Ops: 00:00 - 05:00, P/U & M/U Halliburton RTTS packer, perform surface checks, ok. Cont to RIH Halliburton RTTS on 5'' DP F/252.83 m T/ 1560m.
Max Drill Gas Required Matls next day Avg Background Gas Head Count

148.0 Halliburton batch mixer in customs. CCTV: driller has camera for derrick,stabbing board, mud pump. STP recorder non-operational. Safety Observation Cards
Observation Typ # Rpts Com

CVX-5, WDI-25, Other-41

71 During pulling out,crew was pushing back the iron roughneck , the driller started lowering the drill pipe to floor which might cause getting caught in between.Stopped the driller immediately and crew moved away safely. Tenet #2. SUJON KAZI - Floorman
Contact

Daily Contacts Dewayne Cole Raymond Teale Kitichai Leekitchakorn Randy Roberts Palash Saha Miah Mohammed Fahad Time Log
Start Time End Time Phase Activity Dur (hr) Unsched Event? UE Time (hr) UE Ref No. Com

00:00

06:00

PRODTBG, TBG

TIH

6.00 Yes

6.00 13

Cont to TIH w/tie back liner packer on 5'' DP fr, 993m to 2770m.

Page 2/5

Report Printed : 10/28/2013

Chevron Bangladesh Drilling Morning Report

Date: 10/27/2013

Well Name: Bibiyana-18 Slot: 8 Rig: WDI 801 End Date:

Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :

Rpt No: 36 Hours: 24.00 1,083 / 127

SBU Drilling Well Category : Drlg Well Category 1


Time Log
Start Time End Time Phase Activity Dur (hr) Unsched Event?

UE Time (hr)

UE Ref No.

Com

06:00

11:30

PRODTBG, TBG

LNRTB

5.50 Yes

5.50 13

Safety wash to locate top of liner, wash f/ 2770m t/ 2798.7m tag top of line, observe pressure increase 200 psi. Stop mud pumps and open drill pipe to atmosphere, lower drill string and observe seal action as seals entered the liner top PBR, after 2.86m of seal assembly inside of PBR set 10k weight. Close annular and open drill pipe to atmosphere , increase pressure to perform test of seal assembly/ PBR connection and when pressure was to 300 psi a sudden release of pressure through drill pipe indicated connection was lost. Open BOP, pick up on drill pipe and start pumps, lower drill string and discovered that liner hanger/liner moved down hole. Wash and lower drill string to locate new liner top depth. At 2807m observe pressure increase stop mud pumps, with drill pipe open to atmosphere lower drill pipe and observe seal action as seal packs (4) entered PBR of liner hanger. After all 4 seal packs inside PBR went to slack off weight and discovered that liner hanger/ liner were moving downward, continue working weight as movement progressed with 10/12k WOB and movement stopped when liner top was at 2813.46m shoe was at TD of the 8-1/2" hole section. Close annular and pressure test to 1,000psi on annulus and drill pipe open to atmosphere (good test) bleed off pressure and attempt to establish circulation since movement in liner occurred, maximum pressure applied 1,400 psi. Pressure held, no circulation. Bleed off pressure.

11:30

13:00

PRODTBG, TBG

LNRTB

1.50 Yes

1.50 13

Slack off 10K Ibs and rotate string 12 turns to the right. Release torque and P/U 2m to engage setting dogs, slack off and set packer wit 42K down weight, continue until 70K weight down, Set the tie back packer and pressure test annulus against packer with mud at 4000 psi. pressure hold(good test). Bleed off pressure. Apply 500 psi down the drill string as picking up on drill pipe to disengage the PBR pack off after observing a pressure release , start mud pumps and at 2 bpm to clear the running tool from liner hanger. Note: New TOL at 2,808m, (top of PBR for Tie back packer)

13:00 13:30

13:30 20:30

PRODTBG, TBG PRODTBG, TBG

CC TOH

0.50 Yes 7.00 Yes

0.50 13 7.00 13

Circulate bottoms up. No gas % on bottom/up. Flow check (static). TOH with drill pipe and tie back running tools to surface. Soft breaks to running tools and L/D the same. Rig Service PJSM for RIH RTTS Packer. P/U 27 jnts 5" HWDP & RIH T/ 252.83 m.
SSE

20:30 21:00 21:30

21:00 21:30 00:00

PRODTBG, TBG PRODTBG, TBG PRODTBG, TBG


Company

UNITMAIN HESMTG TIH

0.50 Yes 0.50 Yes 2.50 Yes


Total Headcount

0.50 13 0.50 13 2.50 13

Personnel Chevron Weatherford Weatherford 16 17 Rig Expat 45 Rig National Page 3/5 Report Printed : 10/28/2013

Chevron Bangladesh Drilling Morning Report

Date: 10/27/2013

Well Name: Bibiyana-18 Slot: 8 Rig: WDI 801 End Date:

Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :

Rpt No: 36 Hours: 24.00 1,083 / 127

SBU Drilling Well Category : Drlg Well Category 1


Personnel
Company Total Headcount

SSE

Weatherford Aker-Kvaerner Weatherford Halliburton Weatherford MI Swaco Weatherford Weatherford Brandt - NOV HAL - Wireline Weatherford Weatherford Chevron Smith International Schlumberger Weatherford Weatherford Chevron Weatherford Weatherford Chevron Weatherford Weatherford Chevron Weatherford Weatherford Weatherford Mud Checks
Date Depth (MD) (mOTH) Depth (TVD) (mOTH)

22 1 3 6 2 2 0 6 0 8

Shamolima Catering Wellhead Eng LWD/MWD Cementing DD Mud Engineers Gyrodata TRS Solids Control Wireline

5 SLS 0 Ayun ent 1 PetroBangla 3 Inspection Slickline 0 Completion/Liner hands 0 Shafiq Brothers 0 0 0 0 11 WWT BanglaCat Bangla Industrial Hunting Casing NOV Tech

0 Cenelec 0 HES 0 SPM 0 MD Totco Tech 0 LAMPRELL


Mud/Brine Type Sample Source Checked By YP Calc (lbf/100ft)

10/27/2013 22:00
Flow Line Temperature (C) Vis 3rpm Fluid Density (lb/gal)

4,031.0
Gel 10 sec (lbf/100ft)

3,670.26 NAF
Gel 10 min (lbf/100ft)

Active Pit
Gel 30 min (lbf/100ft)

13.30
Vis 6rpm Vis 300rpm

22.0
Vis 600rpm

30.0
Funnel Viscosity (s/qt)

33.0
PV Calc (Pas)

17 0
ROC (Wet) (% by wt) (lb/lb) Retort NAF by Volume (%)

8
pH Filtration Sz (m) NAF/Water Ratio Chlorides (mg/L)

9
CaCl2 (mg/L)

55
Electric Stability (V)

93
Water Phase Salinity (mg/L)

70 348,900
Retort Water by Volume (%)

49,500
High Gravity Solids (lb/bbl) Corrected Solids (%)

294,674.00 24.87
API Filtrate (cc/30min) API Filter Cake (1/32")

720.0
Retort Solids (% by Volume) (%)

301.15
NaCl (mg/L)

27.00
HTHP Filtrate (cc/30min)

14.50
HTHP Filter Cake (1/32")

58.50 1
Visibility (km)

80.1/19.9 Weather Conditions


Wave Ht (m) Swell Ht (m) Wave Dir () Wind Spd (knots) Wind Dir P Bar (mmHg) T High (C)

2.4
T Low (C)

Support Vessels
Vessel Name Vessel Type Arrival Date Depart Date Note

Unscheduled Events
Referen ce No. Start Date End Date Event Type Unsch Maj Cat Unsch Detail Description Accountable Party Contractor

13

10/25/2013

NPT

EQP

CSG LN

Trouble with liner hanger set. Problem with establish the circulation, restricted on flow path.

Rig Contractor Weatherford Casing & Tubing Running, Liner Hngrs/Whipst ocks

Page 4/5

Report Printed : 10/28/2013

Chevron Bangladesh Drilling Morning Report

Date: 10/27/2013

Well Name: Bibiyana-18 Slot: 8 Rig: WDI 801 End Date:

Total Time: 34.60 Time from Spud: 34.60 Days Since Last DAFW / RI Case :

Rpt No: 36 Hours: 24.00 1,083 / 127

SBU Drilling Well Category : Drlg Well Category 1


Mud Additive Amounts
Des Date

Rec

Consumed

On Loc

Base Oil Df1 Job Supply Amounts


Supply Item Des

10/27/2013
Date Received

12.0
Consumed Cum On Loc

234.0

Diesel Drill String/BHA BHA #<stringno>, <des>


Bit Run Nozzles (1/32") String Components Comment Drill Bit Length (m) String Length (m)

10/27/2013

7,582.0

136,583.0

IADC Bit Dull

Bit Total Fluid Area (nozzles) (in) Max Nominal OD (in)

BHA ROP (m/hr)

String/BHA Components
Item Des Len (m) Mass/Len (lb/ft)

Drilling Parameters
Wellbore Cum Depth Drilled (mOTH) Pick-Up String Weight (1000lbf) Depth Start (MD) (mOTH) TVD Start (mOTH) Cum Drilling Time (hr) Flow Rate (gpm) Drilling Torque Depth End (MD) (mOTH) TVD End (mOTH) RPM (rpm) Drill Time (hr) On Bottom Drill Time (hr) Stand Pipe Pressure (psi) Interval ROP (m/hr)

Weight on Bit (1000lbf)

Drill Str Wt (1000lbf)

Weight of String in Air (1000lbf)

Slack-Off String Weight (1000lbf)

Casing Strings
Casing Description Comment Set Depth (MD) (mOTH) Set Depth (TVD) (mOTH) Run Date

Casing Components
Top Depth (MD) (mOTH) Btm Depth (MD) (mOTH) Len (m) Jts Item Des OD (in) ID (in)

Tubing Strings
Tubing Description Comment Set Depth (MD) (mOTH) Run Date

Tubing Components
Item Des Jts Len (m) OD (in) ID (in) Top (mOTH) Btm (mOTH)

BOP Test
Date Com

10/22/2013 Wellbores
Wellbore Name

Perform full BOP test. Annular 250/3500 psi other test 250/5000 psi
Parent Wellbore

Original Hole Directional Surveys


Description

Original Hole
Date

Actual Survey Survey Data


Date MD (mOTH) Incl () Azm () TVD (mOTH) VS (m) NS (m)

7/18/2013
EW (m) DLS (/30m)

Page 5/5

Report Printed : 10/28/2013