Tata Steel 2
Tata Steel 2
Tata Steel 2
Submitted by:
CERTIFICATE
Ref:- G-BF/
Date:-
ACKNOWLEDGEMENTS
I would like to take this opportunity to express my sincere gratitude towards my
mentor and guide Mr. Debashis Chakraborty whose tireless efforts and help
culminated to make my project work fruitful. It also has been a great experience to
learn from the other members of G Blast Furnace. I would like to especially thank
Mr. A.K. Pathak (Foreman) and would always be indebted towards him. It would not
have been without his peerless efforts and guidance that I have been able to
complete my project work successfully. It has been due to him and my guides
motivation that kept me going through the project work.
I also would like to thank Mr. Awatar Singh (Asst.Foreman), Mr. Raghav Kumar
(Sr.Tech.) Mr.Abid Ali (Tech.) for their guidance in my field work. Finally, I would
like to extend my thanks towards TATA Steel for providing me with this invaluable
learning opportunity.
INTRODUCTION
TO
TATA STEEL
FOUNDER: JAMSHETJI NUSSERWANGJI TATA
(1893-1904)
death.
CHAIRMAN:RATAN N TATA
BRIEF INTO
G BLAST FURNACE
G blast furnace is one of the major producers of pig iron in TATA STEEL. It
fulfills the needs of its two customers:
LD#1 (Temporary customer)
LD#2 (Permanent customer)
PIG IRON is taken to LD#2 & LD#1and after purification it goes to Slab
Caster by track mounted Torpedo Ladles of 200 tones capacity. This Pig Iron is
the primary input for steel making at LD#2 & LD#1.
Two by-products which are generated in the process of producing hot metal are
BF Gas & Slag.
The slag is granulated at G Blast Furnace and sent to slag granulation &
drying plant by belt conveyer. The dried granulated slag serves as input for
cement making at Lafarge India Ltd.
The BF gas generated is cleaned and sent to gas ring main to be used as fuel in
the works division. Thus, this process not only helps in maintaining the
environment but also results in cost saving to the company.
FIG. shows G BF
OVERVIEW
FURANCE
OF
BLAST
bustle pipe, tuyeres and the equipment for casting the liquid iron and slag. Once
a "taphole" is drilled through the refractory clay plug, liquid iron and slag flow
down a trough through a "skimmer" opening, separating the iron and slag.
Modern, larger blast furnaces may have as many as four tapholes and two
casthouses. Once the pig iron and slag has been tapped, the taphole is again
plugged with refractory clay.
Design production
1.8 MTPA
Design productivity
Hearth diameter
11.05 meters.
Working volume
2308 M3
Inner Volume
2648 M3
Iron notches
Trough
Tuyere
Charging system
1.50 bar
Coal injection
Cooling system
Cu and CI Staves
Hearth Refractory
Special Probes
Hot Stoves
Gas Cleaning Plant
FURNACE PARAMETERS
Rated daily hot metal production: 5200 t
Max. Wind can be blown 250Km3 per hour with 6% Oxygen enrichment
Hot blast temperature 1175 deg C
Max blast pressure 3.5 bars
High top pressure 1.5 bars
REFRACTORIES USED
Furnace has no refractory above the tuyere up to throat.
HEARTH
Super micro pore carbon bricks are used for longer campaign life.
One layer of high conductivity carbon block above graphite for the hearth pad
to maximize the cooling.
Two rows of cooling water pipes has been provided for the under hearth
cooling. Supermicropore carbon and one layer of mullite (High alumina) blocks
have been installed which have an optimum resistance to hot metal penetration.
Large no. of thermocouples has been provided at all levels in the hearth area for
monitoring hearth temperature.
BUSTLE PIPE AND TUYERE STOCK
High alumina refractory bricks, arch type
High alumina precast special bricks
Mortar for high alumina bricks
With this lining, the expected temp on external shell will be 85 deg with
following conditions;
HBT 1250 deg
Wind flow rate 250Knm3/hr.
HOT BLAST MAIN and MIXING CHAMBER
High alumina ref bricks, mortar & cartable.
CI STAVES ZONE
Ramming mix between cast iron staves
Ramming around copper staves
Silicon carbide bricks (Bosh)
Mortar for silicon carbide.
CAST HOUSE:
# CASTING
Casting is the process of tapping out liquid metal & slag from blast furnace and
separating them out. Casting is done in cast house. With two tap holes, casting
can be done either from single tap hole or both the tap holes. Normally casting
duration is 2-3 hrs/cast.
Hot metal is poured into torpedo ladles with the help of tilting runner. The
torpedo ladle of 300 t capacities is placed below the cast house floor on railway
tracks and are filled alternately using tilting runner.
Slag after passing through runners, goes for granulation, which is a process of
breaking slag in to small particles by spraying high pressure water on hot
stream of slag. Granulated slag is used for making cement.
# MUD GUN
One is in each cast house to stop the tap hole after casting is over. The mud gun
can be operated from the control desk situated in each cast house. Operation is
characterized by three movements.
1) Slewing forward: This order is given by a lever on the control desk.
2)Ramming: Once the required mass has been injected, the machine remains in
ramming position depending on the quality of the mass used or from the
taphole opening technique selected (normal drill or soaking bar).
3) Slewing backward: The machine reaches its rest position and can be cleaned
and refilled for the next operation.
It has piston ramming pressure 200 bar.
Maximum swiveling angle : 109 deg
Plugging gun angle
: 10 deg,
Nozzle inner dia
: 200 mm.
Clay injection rate
: 3-4 liters/second
Slewing time
: 15-20 seconds*adjustable
Clay barrel diameter
: 480 mm
Height of the gun
: 1500 mm approx
# TAP HOLE OPENER:
One tap hole opener in each cast house to open the tap hole. To have the
possibility of opening the hole with rotation only and to safe guard the tap hole
mushroom it is equipped with modern hydraulic technique, such as
Drill diameter
: 38-70mm
Drill speed
: 0.1 - 0.15 m/Sec
Drill angle
: 8 - 12 deg- Normal 10 deg
Driving mode
Flushing air pressure
Flushing air flow
Water flushing pressure
: Full hydraulic
: 6 to 10 bars
: 2700 liter/minute at minimum pressure
: 2 to 5 bars
# INSTRUMANTATION:
Rotation position transmitter mounted on the hydraulic feed motor for drill
depth measurements and Automation (automatic switch on and off of hammer)
of drilling after the tap hole drill has reached its exact working position.
Normal drilling with forward hammering.
# IRON RUNNER & TILTING RUNNER
Cast able covered iron runner, which takes hot metal to tilting runner in each
cast house, which are also made of cast able. With this tilting runner, two
torpedoes placed on railway tracks beneath the cast house, are filled up
alternately. Tilting runner in both the cast houses is pneumatically driven.
# SLAG RUNNERS:
Slag runners in both the cast houses are also made of castable and completely
covered. Through these slag runners, slag goes to granulation cold runners,
which are three in numbers.
# CAST HOUSE CRANE:
One over head crane in each cast house of Capacity 35T/5T.Where all
movements are initiated by a portable control unit hanging from the crane and
operator can also operate it, sitting in a cabin provided in the crane. One Jib
crane has been provided to transfer loads from cast house A to Cast house B.
# SLAG GRANULATION PLANT:
There are three no of cold runners. Slag coming from any cast house, can be
diverted to any three cold runners. However #1 is normally used for tap hole A
and #3 for tap hole B whereas #2 for any of the above tap holes.
Cold runner #1 & 2 are connected to granulation pit #1 where as cold runner #
3 is connected to granulation pit # 2.These two granulation pits are inter
connected also.
As soon as hot liquid slag enters into any cold runner, it comes in contact with
high pressure water jet and slag gets granulated. The granulated slag with water
Each granulation pit is equipped with individual over head crane to transfer
granulated slag from pit to series of belt conveyors. This granulated slag goes
to slag drying plant where from it is finally sent to cement making plant.
There is separate water pump house equipped with three big (Q-1275m) and
two small water circulating pumps to feed water to cold runners.
STOCK HOUSE
It handles the raw materials. After collecting all the raw materials in their
respective bin it is now screened via weigh feeder and weighed in weigh
hopper to its full capacity or as per the requirement. From
weigh hopper through discharge feeder it is fed on to MB#1 conveyor. From
MB#1 conveyor material is fed on to MB#2 conveyor and it is collected in
the P/W hoper through Tilting Rocker.
Process description:
1. From storage bins raw materials are being fed on to screener via weigh feeder.
2. Weigh feeder feed rate is V/F control, so its feed rate can be adjusted to our
requirement for efficient screening. No screener is provided for (below bin1 to 6)
fluxes/additives.
3. The screened material is collected in weigh hopper to its full capacity or as per the
burden table requirement.
4. The under size of screener in case of ore and sinter is fed onto FC#2 conveyor.
5. From FC#2 conveyor it is fed onto FC#4 conveyor and it finally discharges it on
to the ground.
6. The undersize of coke screener is taken in FC#1conveyor and recirculated via N/C
circuit to generate coke for bin #9&10 and N/C for bin #6.
7. In case of problem in N/C circuit it can be diverted to conveyor FC#3 through
FC#1 and it discharges the fine coke onto the ground.
8. From weigh hopper materials are fed on to MB#1 conveyor via discharge feeder
as per burden table requirement. It is also V/F control and its feeding on MB#1 can
be controlled.
9. There is a hanging magnet above MB#1 to capture any iron bearing materials that
comes along with the raw material.
11. From MB#1 material is fed on to MB#2 conveyor and through Tilting Rocker it
is taken in P/W hopper.
12. Coke and metallic (ore +sinter+fluxes/additives) are fed separately on to the
MB#1 conveyor.
13. The sequence is Line1-coke, Line2-Metallic, Line3- coke, Line4- Metallic and
the sequence is repeated from line1 to 4.This is called as four charging sequence.
14. The burden table has the flexibility of 12 lines. Line #13 is used for charging
extra coke.The raw material system comprises of different circuits:
SINTER CIRCUIT
2. Process Description: There are four sources from where sinter can received
in G blast furnace.
Source#1: SP#2
Sinter from SP#2 is fed on conveyor no. #553.
From conveyor #553 sinter is fed on SC#1 conveyor.
From conveyor SC#1 sinter is fed on SC#2 conveyor.
From conveyor SC#2 sinter is fed on SC#3 conveyor.
From conveyor SC#3 via tripper trolley sinter is taken in their respective bins.
Source#2: SP#3
Sinter from SP#3 is fed on SSC#10 conveyor.
From SSC#10 conveyor sinter is fed on SC#3 conveyor.
From conveyor SC#3 via tripper trolley sinter is taken in their respective bins.
Source#3: SP#4
Sinter can also be received from SP#4 via SP#3 through the same route.
Source#4: SP#1
In extreme emergency sinter can also be received from SP#1 via track hopper
through ore circuit.
In extreme emergency sinter can also be received from SP#1 via R.M.H yard
through ore circuit.
In extreme emergency sinter can also be received from SP#1 via R.M.B.B tippler
through ore circuit
COKE CIRCUIT
Purpose: Coke is one of the most important raw materials used in the blast
furnace.
Function of coke:
It supplies heat for the melting of iron ore/sinter and slag.
It acts as a reductant for the reduction of iron ore/sinter.
2. Process Description:
Coke from coke plant is taken in KC#1 conveyor via an inclined chute at the tail
end of KC#1.
KC#1 is driven by a 3ph/50hz/414v induction motor and a gear box arrangement.
At the discharge end of KC#1 there is a hanging electromagnet to capture any iron
bearing material that comes along with the coke.
From KC#1 coke is taken into KC#2 conveyor driven by a 3ph/50hz/415v
induction motor and a gear box arrangement.
From KC#2 conveyor coke is taken into KC#3 conveyor which is also driven by a
3ph/50hz/415v electric motor and a set of gear box arrangement.
From KC#3 conveyor via tripper trolley coke is taken into respective coke bins.
ORE CIRCUIT
1. Purpose:
Ore is one of the iron bearing material used in blast furnace to produce molten iron.
Fluxes are used in blast furnace to remove the gang material from the blast furnace
Ore/fluxes from track hopper is fed on OC#1 conveyor via apron feeder. From OC#1
conveyor through a set of conveyor ore/fluxes is received on OC#5 conveyor.
From OC#5 conveyor via ore tripper trolley ore/fluxes is taken in their respective
bins.
Source#2:- From R.M.H Yard
Ore/fluxes from R.M.H yard is fed on mobile hopper by a pay loader .From mobile
hopper through a set of conveyor ore/additives is fed on OC#5 conveyor.
From OC#5 conveyor via ore tripper trolley ore/additives is taken in their respective
bins.
Source#3:- From R.M.B.B Tippler
1. Purpose: Coke/Nut coke is one of the most important raw material used in the
blast furnace.
Function of coke:
It supplies heat for the melting of iron ore/sinter and slag.
It acts as a reductant for the reduction of iron ore/sinter.
Its being porous provides permeability to the burden.
It gives mechanical support to the burden.
2. Process Description:
The under size from coke screener KS#1,KS#2,KS#3&KS#4 is fed on FC#1
conveyor.
From FC#1 conveyor through flap gate KFFG1 coke is taken on vibro feeder
KFF1.
From KFF1 coke is fed on NC#1 conveyor.
From NC#1 coke is fed on vibro feeder KFF2.
From KFF2 coke is taken on NC#2 conveyor.
From NC#2 coke is fed on double deck screen KFS1.
Over size of upper deck screen KFS1 (+34 mm) is fed on NC#3 conveyor.
From NC#3 conveyor coke is taken in bin #9 or #10 through flap gate
KFFG2.
Over size of lower deck screen (+8 to 34 mm) is fed on NC#4 conveyor.
The under size of double deck screen is taken in hopper KFB1.
From KFB1 coke fines is periodically discharged through vibro feeder
KFF3/ KFF4.
From KFF3/KFF4 coke fines is fed on NC#5 conveyor.
From NC#5 conveyor coke fines is fed on FC#3.
Finally FC#3 discharges it on to the ground.
REGULATORY ENVIRONMENT
G Blast Furnace is governed by the central and state pollution control board
requirement and the department proactively fulfills all the regulatory
requirements. The department is accredited with ISO 14001 certification for
sound environmental management system. Under this department all the legal/
statutory requirements related to pollution control, waste disposal and safety
are met.
The department has a dedicated team to monitor and improve safety, health and
environmental processes with the support of central team. A safety, health and
environmental committee have been constituted at the department level, which
ensures implementation of all statutory and non statutory needs. G Blast
Furnace adheres to all the financial disciplines and prescribed under various
acts, such as income tax, sales tax etc. All employees have voluntarily signed
the Tata code of conduct, emphasizing corporate ethical behavior. Apart from
this, the department also has an annual safety plan and environment plan which
forms the part of this AOP document to address issues involving safety and
occupational health needs.
SOURCES OF DUST
BINS/BUNKERS/SILOS
BELT CONVEYORS
VIBRO-SCREENS
VIBRO FEEDERS
BUCKET ELEVATORS
TRANSFER POINTS
BLAST FURNACE
ELECTROSTATIC PRECIPITATORS
In all industries the burnt gases are passing through an Equipment called
Electrostatic Precipitator to eliminate the dust particles.
In the simplest terms, a Precipitator is a large box. The dust-laden gases are
drawn into one side of the box. Inside, high voltage electrodes impart a
negative charge to the particles entrained in the gas. These negatively charged
particles are then attracted to a grounded collecting surface, which is positively
charged.
The gas then leaves the box up to 99.9% cleaner than when it entered.
Electrostatic Precipitator removes dust particles from the exhaust gas stream of
a process industry. Often, the process involves combustion, but it can be any
industrial process that would otherwise emit dust particles to the atmosphere.
There are six activities that take place:
Ionization Charging of particles
Migration - Transporting the charged particles to the collecting surfaces
Collection - Precipitation of the charged particles onto the collecting surfaces
Chargedissipation - Neutralizing the charged particles on the collecting
surfaces
Particle dislodging - Removing the particles from the collecting surface to the
hopper
Particle removal - Conveying the particles from the hopper to a disposal point
STEEL INDUSTRY
Dust emission problems in the sintering plant of the Steel Factory mainly arise
from the exhaust gases from the combustion zones and from the ventilation air
out of crushers, sieves, coolers, and loading stations. The average dust emission
level is about 1520 kg/tonne of sinter which is returned to the process when
collected. Blast furnaces may have outputs upto 20003000 tonnes/24 hr. Waste
gas is produced at a rate of approximately 4000 m3 at STP per tonne of pig iron
with a dust content after coarse separation of approximately 10 gm/m3. The
dust contained in the exhaust gas extracted from the top of the blast furnace
mainly consists of iron oxide, silica, and lime. The draft required to suck the
flue gases and fumes out of the stock house and cast house is generated with
the help of an ID Fan. The Stock house ID Fan at the G blast furnace has a
capacity of 400000 cubic meters/ hr with rated power of 696 BKW while the
one at cast house has a capacity of 650000 cubic meters/hr with rated power of
1002 KW.
EMISSION & DISCHARGE LEVELS FROM G BLAST FURNACES.
SPM
SO2
NOx
Norms
150
57.9-78.7 0.2
0.2-0.3
0.1
10
0.79-2.2
1.54-3.10
COMPONENTS OF ESP
The devices used for gas solid separation, Electrostatic Precipitators has the
widest of application in view of its various advantages. It can handle Large
volume of gases from which solid particles are removed. The critical
components of Electrostatic Precipitator are indicated below.
COLLECTING ELECTRODE
PLAIN BEARING
SUPPORT INSULATOR
SHAFT INSULATOR
EMITTING ELECTRODE
SHOCK BAR
RAPPING HAMMERS
GAS SCREEN SHEET
COLLECTING ELECTRODE
Collecting plates are designed to receive and retain the precipitated particles
and then removed into the hopper. In addition, the collecting plates are part of
the electrical power circuit of the precipitator. Baffle plates
shield the
precipitated particles from the gas flow. And smooth surfaces provide for high
operating voltages. Collecting plates are suspended from the precipitator casing
and form the gas passages of the precipitator.
Collecting plates are connected at or near the center by rapper beams, which
then serve as impact points for the rapping system. Top, center, or bottom
spacer bars may be used to keep the collecting plates aligned. This maintains
electrical clearances to the discharge system. ESP Collecting Electrodes are
manufactured from steel strip which is cold roll formed to the desired profiles.
DISCHARGE/EMITTING ELECTRODE
Discharge electrodes emit charging current and provide voltage. This generates
an electrical field between the discharge electrodes and the collecting plates.
The electrical field forces dust particles in the gas stream to migrate towards
the collecting plates. Finally the particles precipitate onto the plates. Common
types of discharge electrodes include
straight round wires
twisted pairs of wires
barbed discharge wires
rigid masts
rigid frames
rigid spiked pipes
spiral wires
Discharge electrodes are typically supported from the upper discharge frame
and are held in alignment between the upper and lower discharge frames. The
upper discharge frame is in turn supported from the roof of the precipitator
casing. High-voltage insulators are incorporated into the support system. In
weighted wire systems, the discharge electrodes are held taut by weights at the
lower end of the wires.
These Screens are of modular design manufactured out of Steel sheets and hang
within a frame work in the ESP inlet casing to maintain uniform distribution
pattern of gas flow throughout the cross section of ESP
The whole emitting frame system is suspended from the roof through
Supporting Insulator to avoid any short circuiting.
The Rapping Mechanism Shaft for electrodes is connected to the driving
mechanism through Shaft Insulator
RAPPING MECHANISM
The collecting electrodes are fixed loosely to suspension beams on pins. They
are joined together in the bottom rapping beam. Both, the firm bottom and the
top loose attachment provide a perfect transfer of energy from the rapping
hammers to the entire row of collecting electrodes. The rapping is carried out in
regular, programmed intervals and guarantees removal of deposited dust from
the electrodes to the hoppers.
Tumbling Hammers Strike the collecting plates and rigid electrodes directly, so
that all areas receive proper rapping acceleration and no energy is lost to
support structure.
HOPPERS
The G Blast furnace has in total 3 ESPs, one at the stock house and two at the
cast house (one being in standby). Also there are total 8 dust extraction
systems. The stock house ESP sucks only the dust generated at the site while
the one at cast house has to handle both dust and fumes.
FEATURES OF ESP
Generally ESP
- can collect dust in both wet and dry conditions;
- can collect all sizes of particles, from microns
to coarsers;
- probably the most versatile collecting equipment;
- offers the highest efficiency, can be designed
in principle for any
- efficiency without excessive pressure drop;
- operates with low operation cost (though initial cost is more);
- can operate over a wide range of inlet conditions, i.e., temperature,
pressure, dust burden, humidity, etc.;
- offers negligible pressure drop (rarely crosses 1015 mm); can be built in
multiple units, for almost any gas volume;
- has a long life, comparatively free from abrasioneffect due to low operating
velocity
CORONA POWER
Precipitator corona power is the useful electrical power applied to the flue gas
stream to precipitate particles. Either precipitator collecting efficiency or outlet
residual can be expressed as a function of corona power in Watts/1000 acfm of
flue gas, or in Watts/1000 ft of collection area.
The separation of particles from the gas flow in an electrostatic precipitator
depends on the applied corona power. Corona power is the product of corona
current and voltage. Current is needed to charge the particles. Voltage is needed
to support an electrical field, which in turn transports the particles to the
collecting plates.
In the lower range of collecting efficiencies, relatively small increases in
corona power result in substantial increases in collecting efficiency. On the
other hand, in the upper ranges, even large increases in corona power will result
in only small efficiency increases. Equally, in the lower range of the corona
power levels, a small increase in the corona power results in a substantial
reduction in the gas stream particle content. In the upper range of the corona
power level, a large increase is required to reduce the particle content .
Uniformity
HALF YEARLY
Clean and lubricate access-door dog bolt and hinges.
Clean and lubricate interlock covers.
Clean and lubricate test connections.
Check exterior for visual signs of deterioration, and abnormal
vibration, noise, leaks
YEARLY
Conduct internal inspection
Clean top housing or insulator compartment and all electrical
insulation surfaces.
Check and correct defective alignment.
Examine and clean all contactors and inspect tightness of all
electrical connections.
Electrode breakage
Problem
Excessive
Gas
Volume
Rapping
Causes
The ESP is not designed properly
Hot excess air
Air Leakage
High Gas Temp.
Acceleration is not high enough
Electrode arrangement is not right
Failure of rapper motors
Gas
Distribution
Discharge
Electrode
Breakage
Discharge
Overflow in
Hoppers
Electrical
TROUBLESHOOTING
DUST ACCUMULATION
The most common cause of excessive dust accumulation on electrodes is a
failure of the rapper control system. Unless there is reason to suspect otherwise
(known high resistivity potential of the ash or other indications of hopper
plugging), this should be one of the first areas checked if power
input to the ESP decreases markedly. Checks of the control system will include:
i. Make sure that the power is on and that the fuse or circuit breaker has not
been opened.
ii. Check for proper operation of the switch and drive on rotary switches.
iii. Check manufacturer recommended procedures for testing rapper control
systems.
Rapper failure is also a potential cause of dust accumulation. The ESP's use
magnetic impulse/gravity impact type rappers.
A common cause of failure of this type of rapper is a short in the coil that
lifts the rapper. Methods for correcting this problem include:
i. Replace the defective rapper with a new one.
ii. Rebuild the defective rapper.
Corrective action for misalignment can only be done during a complete ESP
shutdown. Corrective actions include:
i) Plate straightening by: hydraulic press, localized heating with an
oxy/acetylene torch followed by water quench, remove the warped section of
a plate with a cutting torch and replace it. Major rebuilding will require
removal of the top of the ESP and replacement of entire plates.
ii) Wire correction: Bent wire frames or lower guide frames often cause the
wires to slacken and bow towards the plates. Distorted lower guide frames are
often difficult to straighten and may have to be replaced. If the distortion is not
too serious and only a few wires are slack, then they can be removed. The wires
can be tightened by crimping them in the direction of gas flow.
iii) General misalignment caused by a shift in guide frame components can
usually be corrected by realigning the frame.
Air Infiltration
Routine inspections of the ESP will reveal any locations of air infiltration into
the unit. Correction of this problem involves simple sealing of the leaking joint,
surface or door/hatch gasket.
SYSTEM DESCRIPTION
Below each of the two ESP Hopper outlets, a surge hopper with a level sensor,
a manual isolation gate and a model 3/8 vessel is mounted. When the
pneumatic conveying system is switched on (i.e. start command from ACC
PLC, level in the storage silo not high, sufficient pressure for conveying,
sufficient air pressure available for instrumentation, level in the surge hopper 1
or 2 has reached and the chain conveyer has switched on) only then all the 2
nos. inlet dome valve of the 3/8 vessel will open with fluidisation of surge
hoppers to allow fly ash to fill the respective 3/8 vessel below by gravity. All
the dome valves will then close with preset retentive timers and closing
confirmation is taken by the PLC with position limit switch for inflating the
dome valve seal. Seal pressure is confirmed through a pressure switch and only
thereafter compressed air from a dedicated air receiver is introduced into the
first 3/8 vessel(i.e. master vessel) and fly ash from the two 3/8 vessel is
conveyed in low velocity dense phase regime through a common 100 NB
conveying pipe into the storage silo.
Simultaneously two timers (on delay) are switched on for
minimum blow time and pipeline block time. Once the pipeline is fully flushed
with the minimum blow time, low air pressure signal is sensed through pressure
switch to cut off compressed air supply. After a time delay, seal is deflated and
after restart time of 5 or 10 secs the cycle is repeated.
Conveying air shall be cleaned and vented to the atmosphere
through the existing bag filter near the storage silo.
PROBLEM
CAUSE
REMEDY
No control signal to
solenoid
Solenoid fault
Wiring fault
No control signal to
solenoid
Solenoid fault
Wiring fault
Seal rupture
Blocked muffler on
quick exhaust of air
limit switch
Replace muffler
Pneumatic conveying
cycle not starting
Excessive loading of
material into pipeline.