This document outlines requirements for a contractor's establishment on a construction site and general obligations. It discusses:
1) The contractor must establish camps, offices, workshops and testing facilities on site in approved locations, and provide accommodation and facilities for staff. All temporary structures must be removed on completion.
2) During construction, the contractor's camps and staff quarters must be maintained in a neat and tidy condition.
3) The contractor must comply with all legal and contractual requirements, and be responsible to the public and employer.
Payment for the contractor's general obligations is broken into fixed, value-related, and time-related portions. The contractor will be paid in installments based on milestones and work completed
This document outlines requirements for a contractor's establishment on a construction site and general obligations. It discusses:
1) The contractor must establish camps, offices, workshops and testing facilities on site in approved locations, and provide accommodation and facilities for staff. All temporary structures must be removed on completion.
2) During construction, the contractor's camps and staff quarters must be maintained in a neat and tidy condition.
3) The contractor must comply with all legal and contractual requirements, and be responsible to the public and employer.
Payment for the contractor's general obligations is broken into fixed, value-related, and time-related portions. The contractor will be paid in installments based on milestones and work completed
This document outlines requirements for a contractor's establishment on a construction site and general obligations. It discusses:
1) The contractor must establish camps, offices, workshops and testing facilities on site in approved locations, and provide accommodation and facilities for staff. All temporary structures must be removed on completion.
2) During construction, the contractor's camps and staff quarters must be maintained in a neat and tidy condition.
3) The contractor must comply with all legal and contractual requirements, and be responsible to the public and employer.
Payment for the contractor's general obligations is broken into fixed, value-related, and time-related portions. The contractor will be paid in installments based on milestones and work completed
This document outlines requirements for a contractor's establishment on a construction site and general obligations. It discusses:
1) The contractor must establish camps, offices, workshops and testing facilities on site in approved locations, and provide accommodation and facilities for staff. All temporary structures must be removed on completion.
2) During construction, the contractor's camps and staff quarters must be maintained in a neat and tidy condition.
3) The contractor must comply with all legal and contractual requirements, and be responsible to the public and employer.
Payment for the contractor's general obligations is broken into fixed, value-related, and time-related portions. The contractor will be paid in installments based on milestones and work completed
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online from Scribd
Download as pdf or txt
You are on page 1of 2
1300-1
SERIES 1000 : GENERAL
SECTION 1300 : CONTRACTOR' S ESTABLISH- MENT ON SITE AND GENERAL OBLIGATIONS CONTENTS 1301 SCOPE 1302 GENERAL REQUREMENTS 1303 PAYMENT 1301 SCOPE This Section covers the establishment of the Contractor's organisation, camp and constructional plant on the site and their removal on completion of the contract. t also covers payment for certain general obligations, risks and liabilities and general items of cost not covered elsewhere. 1302 GENERAL REQUIREMENTS (a) Camps, constructional plant and testing facilities The Contractor shall establish his construction camps, offices, stores, workshops and testing facilities on the site. The exact location of these facilities shall be approved beforehand by the Engineer. Accommodation, ablution and other facilities for site staff shall also be provided as required and the standard of accommodation and the location of all facilities shall comply with the requirements of the authorities concerned and those of the Engineer. Prior to starting with construction, the Contractor shall also move all constructional plant and personnel to the site. On completion of the work and after receiving approval in writing from the Engineer, all constructional plant, buildings, fencing and other temporary structures shall be removed and the camp site shall be restored to its original condition and left neat and tidy. (b) Maintenance during construction During construction the Contractor's camps, staff living quarters and other facilities shall be maintained in a neat and tidy condition. (c) Legal and contractual requirements and responsibility to the public The Contractor shall take all the necessary steps to comply with the General Conditions of Contract, particularly in respect of the insurances and sureties required and his general obligations to the public and the Employer. He shall comply with all the regulations of statutory bodies. 1303 PAYMENT Item Unit 13.01 The Contractor's general obligations: (a) Fixed obligations . . . . . . . . . . . . . . . . . lump sum (b) Value-related obligations . . . . . . . . . . . lump sum (c) Time-related obligations . . . . . . . . . . . . . . month Payment of the lump sums tendered under Subitems (a), (b) and the rate per month for Subitem (c) shall, for the three subitems together, include full compensation for all the Contractor's charges in respect of the following items, collectively termed the "Contractor's General Obligations". (i) Setting up and maintaining his organisation, camps, accommodation and constructional plant on the site and their removal on completion of the contract. (ii) Complying with the requirements of the General Conditions of Contract and Section 1200, including the effecting of insurances and providing the sureties required. (iii) All general site and office overheads, profit, financing costs, risks, legal and contractual responsibilities and other costs and obligations of a preliminary or general nature which are not specifically measured for payment under any other items of payment. The lump sum tendered under Subitem 13.01(a) above shall represent full compensation for the fixed part of the Contractor's general obligations (ie that part which is substantially fixed and is not a function of the time required for the completion of the Contract or of the value of the work). Should the final value of the work (excluding any payments in terms of the General Conditions of Contract) increase or decrease by 20% or less in relation to the tendered amount (less any allowances, if any, in the tender for price adjustments in terms of the General Conditions of Contract), the lump sum tendered for Subitem 13.01(a) shall not be subject to any variation whatsoever. However, should the said increase or decrease of the final value of the work exceed 20% of the tendered amount, the provisions of the General Conditions of Contract shall apply to that portion of the said increase or decrease which is in excess of 20% of the tendered amount. Payment of the lump sum tendered under Subitem 13.01(a) will be made in three instalments, as follows: (1) The first instalment, 50% of the lump sum, will be paid in the first payment certificate after the Contractor has met all his obligations under this Section and has made a substantial start with construction in accordance with the approved programme. (2) The second instalment, 35% of the lump sum, will be paid when the value of the work done reaches one half of the tendered amount, excluding contingencies and price adjustments in terms of the General Conditions of Contract. (3) The third and final instalment, 15% of the lump sum, will be paid when the Works have been completed and the Contractor has fulfilled all the requirements of this Section. Before any payment is made under this subitem, the Contractor shall satisfy the Engineer that he has provided camps and constructional plant of good quality on the site, the value of which exceeds that of the first instalment. The Contractor may also be required to furnish documentary proof that he owns the camps and constructional plant on the site, the value of which shall exceed that of the first instalment. 1300-2 n the event of the Contractor not being able to satisfy the Engineer as to the ownership of the camps and constructional plant, the Engineer shall have the right to withhold parts of any payments to be made under this subitem, until the Works have been completed. The lump sum tendered under Subitem 13.01(b) shall represent full compensation for that part of the Contractor's general obligations, which are a function of only the value of the work, but not of the period of completion. Should the final value of the work (excluding any payments in terms of the General Conditions of Contract) increase or decrease by 20% or less in relation to the tendered amount (less any allowances, if any, in the tender for price adjustments in terms of the General Conditions of Contract), the lump sum tendered for Subitem 13.01(b) will be increased or decreased pro rata in full settlement of any difference in value-related general obligations resulting from an increased or decreased value of the work. However, should the said increase or decrease in the final value of the work exceed 20% of the tendered amount, the above-mentioned pro rata increase or decrease in the lump sum tendered under Subitem 13.01(b) shall apply up to the limit of 20%, and the provisions of the General Conditions of Contract shall apply to that portion of the said increase or decrease which is in excess of the said limit of 20% of the tendered amount. The lump sum tendered in Subitem 13.01(b) will be payable monthly in instalments in relation to the value of work done (excluding the value of any price adjustments in terms of the General Conditions of Contract). The tendered rate per month for Subitem 13.01(c) represents full compensation for that part of the Contractor's general obligations which are mainly a function of construction time. The tendered sum will be paid monthly, pro rata for parts of a month, from the date on which the Contractor has received a written instruction, in terms of the General Conditions of Contract, to start the work until the end of the period for completion of the Works, plus any extension thereof as provided for in the General Conditions of Contract, provided that: (a) should the Works be certified as having been completed before the contractual date for completion of the Works, the Contractor will then be entitled to payments in regard to the unexpired period for completion; (b) should the progress of the Contractor in terms of the value of work done be in arrears in regard to his approved original programme, payments in respect of this item may be limited to payments for that period, which, in his original programme (after suitable adjustments in respect of the extension of time granted) agrees with the actual value of work done. Any payment made under tem 13.01 will not be taken into account when determining whether the value of a certificate complies with the "minimum amount of interim certificate", as laid down in the appendix to tender. The adjustments specified in Subitems (a), (b) and (c) will be made only if the value of the work or the period for completion were to change and it is agreed that such adjustments will be in full settlement of the changed compensation for amended general obligations.