SERC Solar PV System Field-Inspection Checklist

PROJECT INFORMATION
Property Address Brief System Description Number of Modules and Array STC DC Wattage Array Orientation Array Tilt Inverter capacity (W or kW) Estimated System Annual kWhac Production Yes No N/A Inspection Checklist Prior to the Field Inspection Utility has given permission to interconnect the PV system System installed by a qualified installer City inspection(s) have been passed: Permit #______________ Date____________ As-built electrical drawings received Final electrical design has professional engineer's stamp PV system plans and drawings received (showing array layout, balance-of-system (BOS) locations, components, disconnects, wiring, and conduit specifications) Roof has 10 or more years useful life remaining (if roof-mounted). *Please note, SERC funds may be used to address the impacted roof area directly under the array, but not to replace an entire roof. PV module specifications Inverter specifications Combiner-box specifications Solar resource is documented from location where array shading will be most significant Total Solar Resource Fraction (TSRF) is 75% or greater at all points on the collector(s) Note

Yes

No

N/A

Field Inspection - PV Modules and Array PV modules are physically installed per plans (number and layout) Array is optimized for performance without sacrificing aesthetics Trees and plants will not grow tall enough to shade array Array installation is neat and permanent Roof penetrations are secure and weather tight PV module model number matches plans PV modules warranted (recommended 10 year 90%, 25 year 80% minimum) PV panels are new, UL listed and California Energy Commission (CEC) approved Array is spaced a minimum of 1.5 inches off the roof, or is properly flashed into the roof String fuses or circuit breakers are DC-rated and no larger than module fuse rating PV modules are in good condition (no broken glass or cells, no discoloration, frames not damaged) Module connectors tight and secure Module interconnection conductors sunlight resistant, wet rated, 75C or 90C rated Wire and conduit sizes installed per plans Wiring is installed with shortest distance from PV panels to inverter or where aesthetically suitable Wiring is neat and secure Wiring is not readily accessible Conductors are not in contact with roof surface Conduit supported properly Electrical boxes are accessible and suitable for environment No potential for wire damage (e.g., deburred metal and proper sheathing to protect wires) Confirm metallic PV module frame grounding uses a dedicated grounding conductor or the rack/module system is UL listed for grounding Proper grounding of all other metallic surfaces that might possibly become energized (conduit, combiner boxes, disconnect enclosures, etc.) Dissimilar metals are electrically isolated to avoid galvanic corrosion Aluminum is not placed in direct contact with concrete Protective fencing installed and will not shade array (if required)

Note

Yes

No

N/A

Yes

No

N/A

Field Inspection Inverter and Electrical Inverter is installed per work order Confirm inverter model number matches plans Inverter is warranted (recommended 10 years minimum) Inverter(s) is new and CEC approved Wire and conduit sizes installed per plans Installation is neat and permanent Inverter is easily accessible DC disconnect is DC-rated and permanently installed and readily accessible AC disconnect is permanently installed and accessible Penetrations to building shell are sealed and fire resistance maintained Sum of PV breaker and panel main breaker less than 120% of panel rating Utility power connected Internet connection operational (if applicable) Field Inspection - System Labeling All equipment and parts are labeled as required Label identifies PV power source attributes at DC disconnect Label identifies AC point of connection Outdoor labels designed to withstand the elements Emergency and maintenance contact information

Note

Note

Yes

No

N/A

Yes

No

N/A

System Documentation Customer Manual is provided and mounted in a preserved location near the unit controls. ___Operation and maintenance instructions, including homeowners responsibilities (if applicable) ___Electrical design showing modules and meters ___System & contractor warranty ___Manufacturers' warranties ___Permit(s) ___Parts and source list ___Emergency and maintenance contact information Owner Education ___Basic system operation ___Proper system disconnect sequence and safety procedures ___Reading meters and inverter display ___Required maintenance ___Emergency contact

Note

Note

Yes

No

N/A

Post Inspection - Performance Testing (performed by Installer or Independent Contractor) Note Performance tests performed by: Date and time: Solar irradiance level: Ambient temperature: Array temperature: Measure and record open-circuit voltage (Voc) and polarity of each string (verify all strings have the same number of modules) Measure and record short-circuit current (Isc) of each string Inverter startup sequence follow manufacturers instructions for initial startup Confirm inverter shuts down if AC utility is disconnected and does not restart for at least five minutes after utility is reconnected (requirement of UL 1741) Measure and record maximum power point current (Imp) for each string. (Current measurements for each string should be within a 0.1A range of each other, assuming consistent weather conditions, and all string having same tilt and azimuth angle. If a string is outside the range, check for shading or a ground fault.) Confirm inverters power reading using independent meters. (afterwards, inverter power readings may be used for subsequent reporting.) Confirm the system power output under actual conditions meets expected output. Actual performance should be within about 5% of expected STC power. This procedure includes system nameplate rating (kW), solar irradiance measurement (W/m2) and module cell temperature (C). Procedure is best conducted during consistent weather conditions, where no array shading is present, and solar irradiance is not less than 400 W/m2. Owner should check system AC power output monthly near solar noon on a clear day

References Field Inspection Guidelines for PV Systems. IREC V 1.1, June 2010. Brooks Engineering. irecusa.org/2010/07/irec-releases-2010-edition-ofits-field-inspection-guidelines-for-pv-systems/ Procuring Solar Energy: A Guide for Federal Facility Decision Makers. DOE EERE, September 2010. www1.eere.energy.gov/solar/pdfs/47854.pdf PV System Commissioning. Blake Gleason. SolarPro. October/November 2009. solarprofessional.com/files/sample/sp2_6_pg34_gleason.pdf Photovoltaic Power Systems and the 2005 National Electrical Code: Suggested Practices. John Wiles. SWTDI NMSU November 2008. www.nmsu.edu/~tdi/Photovoltaics/Codes-Stds/PVnecSugPract.html 2005/2008/2011 Photovoltaic Electrical Power Systems Inspector/Installer Checklist. John Wiles. SWTDI, NMSU. June 2011. http://www.nmsu.edu/~tdi/Photovoltaics/Codes-Stds/C-S-Resources.html?agree=agree National Electrical Code (Article 690 Solar PV Systems) . NFPA 70. www.nfpa.org/aboutthecodes/AboutTheCodes.asp?DocNum=70&cookie%5Ftest=1