Constructing The Building 2
Constructing The Building 2
Constructing The Building 2
Introduction .............................................................................. 13-1 Foundation Construction ........................................................... 13-2 13.2.1 Layout .......................................................................... 13-2 13.2.2 Soils ............................................................................. 13-6 13.2.3 Pile Foundation ............................................................ 13-9 13.2.4 Masonry Foundation Construction .............................. 13-15 13.2.5 Concrete Foundation Construction .............................. 13-17 13.2.6 Wood Foundation Construction................................... 13-19 13.2.7 Foundation Material Durability ................................... 13-20 13.2.8 Field Preservative Treatment ....................................... 13-25 13.2.9 Substitutions ............................................................... 13-26 13.2.10 The Top Foundation Issues for Builders ...................... 13-26 13.2.11 Inspection Points ........................................................ 13-27
13.3
Structural Frame ..................................................................... 13-27 13.3.1 Floor Framing ............................................................ 13-31 13.3.2 Wall Framing ............................................................. 13-34 13.3.3 Roof Framing ............................................................. 13-38 13.3.4 The Top Structural Frame Issues for Builders .............. 13-40
13.4
Building Envelope .................................................................. 13-41 13.4.1 Substitution of Building Envelope Materials ............... 13-42 13.4.2 Building Envelope Inspection Points ........................... 13-42 13.4.3 The Top Building Envelope Issues for Builders ........... 13-43
13.5
COASTAL CONSTRUCTION MANUAL
TABLE OF CONTENTS
13.5.1 Decks ......................................................................... 13-44 13.5.2 Storage Buildings ....................................................... 13-46 13.5.3 Swimming Pools and Hot Tubs ................................... 13-46 13.5.4 Walkways and Sidewalks ............................................ 13-48 13.6 Utility/Mechanical Equipment ................................................ 13-49 13.6.1 Elevators .................................................................... 13-49 13.6.2 Heating, Ventilating, and Cooling (HVAC) Systems .... 13-50 13.6.3 Electrical Systems ...................................................... 13-53 13.6.4 Water and Wastewater Systems ................................... 13-53 13.6.5 Tanks.......................................................................... 13-54 13.7 References .............................................................................. 13-55
Figures
Figure 13-1 Figure 13-2 Figure 13-3 Figure 13-4 Figure 13-5 Figure 13-6 Figure 13-7 Figure 13-8 Figure 13-9 Figure 13-10 Figure 13-11 Figure 13-12 Figure 13-13 Figure 13-14 Site layout. ................................................................... 13-3 Typical pile notching process. ....................................... 13-4 Overnotched pile. ......................................................... 13-4 Properly notched pile. ................................................... 13-5 Plan view of foundation showing techniques for squaring a building. ................................................. 13-6 Damage caused by slope failure. ................................... 13-8 Typical wood-pile foundation........................................ 13-9 Diagonal wood bracing in a wood-pile foundation. ................................................................. 13-12 Knee bracing in a wood-pile foundation. ..................... 13-13 Open masonry foundation. .......................................... 13-16 Concrete foundation. .................................................. 13-17 Concrete house. .......................................................... 13-18 Wood decay at the base of a post supported by concrete. ................................................................ 13-21 Minimizing the least dimension of wood contact surfaces. ......................................................... 13-22
13-ii
TABLE OF CONTENTS
Figure 13-15 Figure 13-16 Figure 13-17 Figure 13-18 Figure 13-19 Figure 13-20 Figure 13-21 Figure 13-22 Figure 13-23 Figure 13-24
Drip cut minimizes horizontal water movement along the bottom surface of a wood member. ............... 13-24 Exposure of end grain in stair stringer cuts. ................. 13-24 Deterioration in a notched stair stringer. ...................... 13-24 Alternative method of installing stair treads. ................ 13-25 Hurricane Iniki (1992), Hawaii. Connector failure caused by insufficient nailing.......................... 13-28 Reinforcement of overnotched piles. ......................... 13-29 Beam support at misaligned piles. ............................. 13-30 Proper pile notching for two-member and four-member beams. ................................................... 13-30 Metal twist strap ties (circled). .................................... 13-31 Plywood web I-beams used as floor joists with metal brace used to keep the bottoms of the joists from twisting. .......................................... 13-32 Acceptable locations for splices in multiplemember girders. .......................................................... 13-33 Using full-height sheathing improves transfer of shear. ...................................................................... 13-35 Hurricane Andrew (1992), Florida. Roof sheathing found in debris. ........................................... 13-39 Sheathing nails (circled) missed roof rafter in new construction. .................................................... 13-39 Building damage from Hurricane Opal at Pensacola Beach, Florida. ........................................... 13-45 Stair elevation system. ................................................ 13-46 Recommendations for orientation of in-ground pools. ......................................................................... 13-48 Cantilever floor framing for air-conditioning/ heat pump compressor platformplan view................ 13-51 Cantilever floor framing for air-conditioning/ heat pump compressor platform elevation view......... 13-51 Wood-brace-supported air-conditioning/heat pump compressor platform plan view. ...................... 13-52
Figure 13-25 Figure 13-26 Figure 13-27 Figure 13-28 Figure 13-29 Figure 13-30 Figure 13-31 Figure 13-32 Figure 13-33 Figure 13-34
13-iii
TABLE OF CONTENTS
Wood-brace-supported air-conditioning/heat pump compressor platform elevation view. ............... 13-52 Anchoring techniques for aboveground tanks. ............. 13-55
Tables
Table 13.1 Table 13.2 Table 13.3 Table 13.4 Table 13.5 Table 13.6 Table 13.7 Soil Type Definitions Based on USDA Unified Soil Classification System ................................ 13-7 Engineering Properties of Soil Types Classified by USDA ..................................................... 13-7 Foundation Inspection Points ...................................... 13-27 Floor Framing Inspection Points ................................. 13-34 Wall Inspection Points ................................................ 13-37 Roof Frame Inspection Points ..................................... 13-40 Building Envelope Inspection Points ........................... 13-43
Formulas
Formula 13.1 Pile Driving Resistance for Drop Hammer Pile Drivers .................................................. 13-10
13-iv
C H A P T E R 13
NOTE
The National Flood Insurance Program (NFIP) regulations state that for buildings in V zones, a registered professional engineer or architect shall develop or review the structural design, specifications and plans for the construction, and shall certify that the design and methods of construction to be used are in accordance with accepted standards of practice for meeting the provisions of the NFIP regulations regarding buildings in V zones (see Chapter 6 of this manual).
NOTE
Sections of this chapter refer to specific requirements of the 2000 International Building Code (referred to as the IBC 2000), prepared by the International Code Council (ICC 2000a). The ICC also prepared the 2000 International Residential Code for One- and Two-Family Dwellings (ICC 2000b), referred to as the IRC 2000. Designers should refer to pertinent sections of the IRC 2000, in addition to those of the IBC 2000 cited here.
13-1
C H A P T E R 13
weaken the building significantly so that it is hazardous to occupy under any conditions and more likely to fail in a severe natural hazard event. Builders may find that the permitting and inspection procedures in coastal areas are more involved than those in inland areas. Not only must all Federal, state, and local Coastal Zone Management and other regulatory requirements be met, the design plans and specifications may need to be sealed by a design professional. Building permit submittals often must include detailed drawings and information for all the elements of the wind-resisting load path, including sheathing material, sheathing nailing, strap and tiedown descriptions, bolted connections, and pile description and placement. The placement of utilities above the DFE, breakaway walls, and flood equalization openings must be clearly shown. Site inspections will likely focus on the approved plans, and building officials may be less tolerant of deviations from these approved construction documents. Several sections of this chapter identify points for possible inspections.
NOTE
If there is a conflict between design drawings and standard code practice, the most conservative should apply.
NOTE
Foundation design is discussed in detail in Section 12.4.3, in Chapter 12 of this manual.
Figure 13-2 shows the typical process of pile-notching. The use of a chain saw for this process can lead to inaccuracies at this early stage of construction. Figure 13-3 shows a wood pile that is overnotched; Figure 13-4 shows a pile properly notched to support the floor girder, and cut so that there is plenty of wood remaining at the top of the pile.
FEDERAL EMERGENCY MANAGEMENT AGENCY
13-2
C H A P T E R 13
A rule of thumb regarding notching is to notch no more than 50 percent of the pile cross-sectional area. Notching more than this area will require reinforcing the pile with a steel plate (or material of similar strength). Section 13.3 presents additional information concerning the reinforcement of overnotched and misaligned piles. The primary floor girders spanning between pile or foundation supports should preferably be oriented parallel to the primary flow of potential flood water and wave action. This orientation (normally at right angles to the shoreline) allows the lowest horizontal structural member perpendicular to flow to be the floor joists. Thus, in an extreme flood, the girders would not likely be subjected to the full force of the storm water and debris along their more exposed surfaces.
13-3
C H A P T E R 13
13-4
C H A P T E R 13
Figure 13-4 Properly notched pile. Note that the outer member of this three-member beam is supported by the through-bolt rather than the beam seat.
One of the most important layout steps is to square the first-floor framing. The entire structure is built upon the first floor; therefore, it is imperative that the first floor be level and square. The squaring process normally involves taking diagonal measurements across the outer corners and shifting either or both sides until the diagonal measurements are the same, at which point the house is square. An alternative is to take the measurements of a 3-4-5 triangle and shift the floor framing until the 3-4-5 triangular measurement is achieved. See Figure 13-5 for an illustration of these squaring methods.
13-5
C H A P T E R 13
Figure 13-5 Plan view of foundation showing techniques for squaring a building.
60 ft
60 ft
66'
28 ft
-2
1 /2"
28 ft
Piles
66'
Piles
15 ft
38 ft 10 ft
38 ft
- 21 /2 "
9 ft
10 ft
Porch
60 ft
18 '-1 0 7/
12 ft
" 7 /16
16 "
Porch
60 ft
20
ft
0 '-1 18 16 ft
12 ft
16 ft
Diagonal Method
13.2.2 Soils
The soils on any site can vary between solid rock to loose sand. The foundation design will be based on soil assumptions derived from sources that include the following: soil borings a review of borings from nearby sites a test pit dug at or near one of the pilings or foundation corners information from the local office of the Natural Resource Conservation Service (formerly Soil Conservation Service) and Soil Surveys published for each county test piles Designs are frequently prepared in which the bearing capacity of the soil is assumed and it is the builders responsibility to verify that design assumption. In pile-supported structures, where the building support relies upon friction between the pile and soil, two important soil parameters must be known or determined: for cohesionless soils, the angle of internal friction for cohesive soils, the cohesion value in lb/ft2 The United States Department of Agriculture (USDA) has developed the Unified Soil Classification system, which categorizes and describes soil types (see Table 13.1). General engineering guidelines about the properties of these soil types are listed in Table 13.2.
13-6 FEDERAL EMERGENCY MANAGEMENT AGENCY
WARNING
The amount of long-term and storm-induced erosion expected to occur at the site (see Section 7.5, in Chapter 7 of this manual) must be determined before any assumptions about, or analyses of, the soils are made. Only those soils that will remain after erosion can be relied on to support the foundation members.
C H A P T E R 13
Table 13.1
Symbol
GW GP GM GC SW
Description
Well-graded gravels and gravel mixtures Poorly graded gravel-sand-silt mixtures Silty gravels, gravel-sand-silt mixtures Clayey gravels, gravel-sand-clay mixtures Well-graded sands and gravelly sands Poorly graded sands and gravelly sands Silty sands, poorly graded sand-silt mixtures Clayey sands, poorly graded sand-clay mixtures Inorganic silts and clayey silts Inorganic clays of low to medium plasticity Organic silts and organic silty clays of low plasticity Inorganic silts, micaceous or fine sands or silts, elastic silts Inorganic clays of high plasticity, fine clays Organic clays of medium to high plasticity
Sands
SP SM SC ML
CL OL MH CH OH
Cohesion (lb/ft2)
Gravels
GP GM GC SW loose
Sands
0 - 250 250 - 500 500 - 1000 500 - 1000 1000 2000 2000 - 4000 13-7
C H A P T E R 13
NOTE
Permafrost conditions (e.g., as in coastal areas of Alaska) are not addressed in this manual. Permafrost refers to subsoil that remains permanently frozen.
The soil bearing capacities listed in Table 13.2 are intended to provide a suggested range of values that can be used when other data are not available. However, soils can vary significantly in bearing capacity from one site to the next. This manual recommends that a geotechnical engineer be consulted when any unusual or unknown soil condition is encountered. Slope stability is often difficult to predict unless there is a history of slope failures at or near the site, or unless soil borings taken at the site indicate that failures are possible. An experienced geotechnical engineer can predict from the steepness of the slope, the drainage of the site above the slope, the soil type, and the angle of internal friction of the soil whether slope failure is likely at a particular site. The International Building Code 2000, hereafter referred to as the IBC 2000 (ICC 2000a), provides some guidance on the placement of footings near slopes. Figure 13-6 shows what can happen to buildings placed near the location of a slope failure.
13-8
C H A P T E R 13
NOTE
See Chapter 12 for a discussion of pile capacities compared to the installation method.
Precautions must be taken in the handling and storage of pressure-preservativetreated round or square wood piles. They should not be dragged along the ground or dropped. They should be stored well-supported on skids so that there is air space beneath the piles and they are not in standing water. Additional direction and precautions for pile handling, storage, and construction are found in Section 13.2.6 of this manual and in Section M4-91 of the American WoodPreservers Association (AWPA) Standards (AWPA 1994). A major consideration in the effectiveness of pile foundations is the method for inserting the piles into the ground, which can determine the pile load capacity. The best method is to use a pile driver, which uses leads to hold the pile in position while a single- or double-acting diesel- or air-powered hammer drives the pile into the ground. The pile driver method, while cost-effective for a development with a number of houses being constructed at one time, can be expensive for a single building. The drop hammer method is a lower-cost alternative to the pile driver. A drop hammer consists of a heavy weight that is raised by a cable attached to a power-driven winch and then dropped onto the end of the pile.
COASTAL CONSTRUCTION MANUAL 13-9
C H A P T E R 13
It is common practice to estimate the ultimate capacity of a single pile on the basis of the driving resistance. Several formulas are available for making such estimates. However, the results are not always reliable and may over-predict or under-predict the capacity, so the formulas should be used with caution. One method for testing the recommended capacity developed from a formula is to load test at least one pile at each location of known soil variation. One formula for determining pile capacity is shown as Formula 13.1, which is for drop hammer pile drivers. Formulas for other pile driver configurations are provided in Foundation and Earth Structures Design, U.S. Department of the Navy Manual 7.2 (USDN 1982).
Qall = 2WH/ (S + 1)
where:
Qall = allowable pile capacity in lb W = weight of the striking parts of the hammer in lb
H = effective height of the fall in ft S = average net penetration, given as in per blow for the last 6 in of driving
The advantage of driving piles, compared to using the other methods discussed below, is that the driving operation forces the soil outward around the pile, densifying the soil and causing increased friction along the sides of the pile, which provides greater pile load resistance. A disadvantage of pile driving, particularly with light equipment, is that it allows the piles to wander away from their intended locations. The resulting variation in the final locations of the pile tops can complicate subsequent construction of floor beams and bracing. The problem is worsened by piles with considerable warp, nonuniform soil conditions, and material buried below the surface of the ground such as logs, gravel bars, and abandoned foundations. It is prudent to inquire about subsurface conditions at the site of a proposed structure before committing to the type of pile or the installation method. A thorough investigation of site conditions can help prevent costly installation errors.
13-10
C H A P T E R 13
The soils investigation should include determinations of the following: the type of foundations that have been installed in the area in the past the type of soil that might be expected, from past soil borings and soil surveys whether the proposed site has been used for any other purpose, which would indicate whether there are any buried materials on the site how the site may have been used in the past, from a search of land records for past ownership A less desirable but frequently used method of inserting piles into sandy soil is jetting. Jetting involves forcing a high-pressure stream of water through a pipe advanced along the side of the pile. The water blows a hole in the sand into which the pile is continuously pushed or dropped until the required depth is reached. Unfortunately, jetting loosens the soil around the pile and the soil below the tip, resulting in a lower load capacity. Holes for piles may be excavated by an auger if the soil is sufficiently clayey or silty. In addition, some sands may contain enough clay or silt to permit augering. This method can be used by itself or in conjunction with pile driving. If the hole is full-sized, the pile is dropped in and the void backfilled. Alternatively, an undersized hole can be excavated and a pile driven into it. When the soil conditions are appropriate, the hole will stay open long enough to drop or drive in a pile. In general, piles dropped or driven into augered holes may not have as much capacity as those driven without augering. If precast concrete piles or steel piles are used, only a regular pile driver with leads and a single- or double-acting hammer should be used. For any pile driving, the building jurisdiction or the engineer-of-record will probably require that a driving log be kept for each pile. The log will show the number of inches per blow as the driving progressesa factor used in determining the pile capacity, as shown in Formula 13.1. As noted in Section 12.4.3, the two primary determinants of pile capacity are the depth of embedment in the soil and the soil properties. 13.2.3.1 Diagonal Bracing of Piles The building design may include diagonal bracing of the piles in one or both plan directions. Figure 13-8 illustrates diagonal wood bracing. Diagonal bracing strengthens and stiffens the pile foundation at the cost of greater exposure to wave and debris impact. For most pile spacings and heights, diagonal bracing is designed as a tension-only brace. This means that the brace is too slender to be stable in resisting a compressive force. In a tensiononly bolted brace connection, there must be an end distance of 7 bolt
COASTAL CONSTRUCTION MANUAL 13-11
C H A P T E R 13
diameters in the brace (as illustrated in Figure 12-69, in Chapter 12) and a side distance of 4 bolt diameters in the pile. These clearances may be difficult to achieve if two adjacent braces end on the same side of a pile.
With tension-only braces, the design intent can be met only when all of the following conditions are met: The horizontal floor beams or girders just above the diagonals must serve as stiff, strong, and stable compression struts that span between the pile tops. These members allow forces to the piles that are not diagonally braced in the direction of the force to be transmitted to a pile that is braced in that direction. Solid connections, usually achieved with bolts, must be provided that transmit forces from the brace to the pile or floor system Bracing members must have sufficient strength to resist failure in tension throughout their life. This life will be shortened if the connections or the bracing members corrode, split, twist, bend, or otherwise change in such a way that their structural integrity is compromised. The placement of the lower bolted connection of the diagonal to the pile requires some judgment. If the connection is placed too high above grade, the pile length below the connection is unbraced and the overall bracing is less strong and stiff. If the connection is placed too close to grade, the bolt hole is more likely to be flooded or infested with termites. Because the bolt hole passes through the untreated part of the pile, flooding and subsequent decay or termite infestation will weaken the pile at a vulnerable location. The bolt hole should be treated with preservative as discussed in Section 13.2.8 of this manual and in Section M4-91 of the AWPA Standards (AWPA 1994).
13-12 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
13.2.3.2 Knee Bracing of Piles Knee braces can be effective in supporting the pile against the lateral forces of wind and water. Figure 13-9 illustrates knee bracing. Knee bracing increases the strength and stiffness of an elevated pile foundation by restraining rotation at the top of the pile and reducing the pile bending length. Knee bracing is not as stiff or as strong as diagonal bracing. Knee braces have an advantage over diagonal braces in that they present less obstruction to waves and debris. Knee braces are shorter than diagonal braces and are usually designed for both tension and compression loads.
Figure 13-9 Knee bracing in a wood-pile foundation.
The entire load path into and through the knee brace must be designed with sufficient capacity. The girder or beam to which the knee brace is connected must have the bending strength to resist the axial force in the knee brace. The connections at each end of the knee brace must have sufficient capacity in both tension and compression.
13-13
C H A P T E R 13
13.2.3.3 Grade Beams in Pile Foundations The pile foundation design may or may not include grade beams. When used, grade beams tie the piles together, usually in both horizontal directions. Grade beams are usually made of wood or reinforced concrete. Their exposure to ground contact and possible wave forces requires highly durable construction. Wood grade beams must be of treated wood and be field treated where cuts and bores are made. For concrete grade beams, the concrete mix design, cover thickness, and curing must optimize durability. In addition, in areas subject to erosion or scour, grade beams must be designed to be self-supporting. Durability of concrete and wood construction is discussed in Section 13.2.7. In V zones, grade beams must be used only for lateral support of the piles. If a floor is poured so that it is attached to or is monolithic with the grade beams, the bottom of the grade beam becomes the bottom of lowest horizontal structural member, which, as noted in Chapter 6, Section 6.4.3.3, must be at or above the Base Flood Elevation in order for the structure to be in compliance with the NFIP regulations. If grade beams are used with wood piles, it is important that the connection of the grade beam to the pile does not encourage water retention. The maximum bending moment in the piles occurs at the grade beams. Decay caused by water retention at that critical point in the piles would likely induce failure under high-wind or wave forces. 13.2.3.4 Wood-Pile-to-Wood-Girder Connections Piles are often notched to provide a bearing surface for a girder. The notching should not remove more than 50 percent of the pile cross section. Section 12.5.9 describes the load calculation that must be performed at this connection to resist failure in shear. The designer can state just how much bearing is needed for sufficient bearing strength and acceptable eccentricity. The girder must be truly bearing on the surface to be effective. If the bolts are not placed low in the girder, it can shrink away from the bearing and the load will be carried in the bolts. Where the side and bottom of a girder are in contact with a notched pile, the wood of the pile at the notch is mostly untreated because the pressure preservative does not fully penetrate the wood. The surfaces of the pile exposed by notching should be treated with a field preservative. The pile-to-girder connection may be subjected to large uplift forces in strong winds. The bolted connection must withstand these forces. The bottom bolt must be at least 4 bolt diameters from the bottom of the girder. The top bolt must be at least 7 bolt diameters from the top of the pile. The bolts should not be too widely spaced vertically across a sawn wood deep girder, as shrinkage will cause the girder to split between the bolts. A glue-laminated or parallel strand girder will be drier at installation and much less susceptible to this
13-14 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
problem. Bolted connections should always be installed with washers on both the head and threaded ends of the bolt. Vertical lag bolt, spike, or nail connections into the top of a wood pile should be avoided. Such connections have no building-code-allowed capacity in withdrawal and a reduced capacity in shear. In addition, the penetration invites water intrusion and subsequent decay that would further weaken the connection. For connections made with spikes driven into the side grain of a member, the spikes should be driven into drilled guide holes so that the wood will not be split. Exposed wood should be assumed to have a moisture content greater than 19 percent in coastal areas. There is evidence that fasteners embedded in treated wood or naturally durable wood with a moisture content of more than 19 percent are prone to corrosion, because of the treatment chemicals and the natural wood extractive. The IBC 2000 (ICC 2000a) requires that fasteners for pressure-preservative-treated wood be of hot-dipped galvanized steel, stainless steel, silicon bronze, or copper. The California Redwood Association recommends the use of hot-dip galvanized nails in redwood.
NOTE
For more information about protecting metal connectors from corrosion, refer to FEMA NFIP Technical Bulletin 8, Corrosion Protection for Metal Connectors in Coastal Areas, in Appendix H.
WARNING
Open masonry foundations In earthquake hazard areas require special reinforcement detailing and pier proportions to meet the requirement for increased ductility.
C H A P T E R 13
and for differential movement between the materials. Expansion and contraction joints must be placed so that the materials can easily move against each other.
WARNING
Figure 13-10 shows an open masonry foundation with only two rows of piers. It is unlikely that this foundation system could resist overturning caused by the forces described in Chapter 11.
Masonry is used for piers, columns, and foundation walls. As explained in Chapter 6, the NFIP regulations require open foundations (e.g., piles, piers, posts, and columns) for buildings constructed in V zones. Buildings in A zones may be constructed on any foundation system. However, because of the history of observed damage in coastal A zones, and the magnitude of the flood and wind forces that can occur in these areas, this manual recommends that only open foundation systems be constructed in coastal A zones. Figure 13-10 shows an open masonry foundation.
Reinforced masonry has much more strength and ductility for resisting large wind, water, and earthquake forces than does unreinforced masonry. This manual also recommends that permanent masonry construction in and near coastal flood hazard areas (both A zones and V zones) be fully or partially reinforced and grouted solid regardless of the purpose of the construction and the design loads. Grout should be in conformance with
13-16 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
the requirements of the IBC 2000 (ICC 2000a). Knockouts should be placed at the bottom of fully grouted cells to ensure that the grout completely fills the cells from top to bottom. For concrete masonry units, choosing Type I moisture controlled units and keeping them dry in transit and on the job will minimize shrinkage cracking. Usually, for optimum crack control, Type S mortar should be used for belowgrade applications and Type N mortar used for above-grade applications. The IBC 2000 specifies grout proportions by volume for masonry construction.
NOTE
In areas not subject to earthquake hazards, breakaway walls below elevated buildings may be of unreinforced, ungrouted masonry construction.
NOTE
Section 7.7 of the ACI Building Code RequirementsforStructuralConcrete, ACI318-95(ACI1995),specifiesminimum amounts of concrete cover for various construction applications.
13-17
C H A P T E R 13
During placement, concrete will normally require vibration to eliminate air pockets and voids in the finished surface. The vibration must be sufficient to eliminate the air, but not separate the concrete or water from the mix. To ensure durability and long life, it is especially important in coastal, saltwater-affected locations that concrete construction be carried out carefully in a fashion that promotes durability. Appendix J, in Volume III of this manual, describes the IBC 2000 requirements for more durable concrete mixes with lower water-cement ratios and higher compressive strengths (5,000 psi) to be used in a salt water environment. The IBC 2000 also requires that additional cover thickness be provided. Proper placement, consolidation, and curing is also essential for durable concrete. The concrete mix water-cement ratio required by the IBC 2000 or by the design should not be exceeded by the addition of water at the site. It is likely that concrete will have to be pumped at many sites because of access limitations or elevation differences between the top of the forms and the concrete mix truck chute. Pumping concrete will require some minor changes in the mix so that the concrete will flow smoothly through the pump and hoses. Plasticizers should be used to make the mix pumpable; do not use water to improve the flow of the mix. Concrete suitable for pumping generally must have a slump of at least 2 inches and a maximum aggregate size of 33-40 percent of the pump pipeline diameter. Pumping will also increase the temperature of the concrete, thus changing the curing time and characteristics of the concrete (depending on the outdoor temperature). Freeze protection may be needed, particularly for columns and slabs, if pouring is done in cold temperatures. Concrete placed in cold weather takes longer to cure, and the uncured concrete may freeze, which will adversely
13-18 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
affect its final strength. Methods of preventing concrete from freezing during curing include the following: heating adjacent soil before pouring on-grade concrete warming the mix ingredients before batching warming the concrete with heaters after pouring (avoid overheating) placing insulating blankets over and around the forms after pouring selecting a cement mix that will shorten curing time (e.g., hi-early) Like masonry, concrete is used for piers, columns, and walls. However, the recommendation made in Section 13.2.4 of this manual regarding open foundations in coastal A zones applies to concrete foundations as well. In addition, because the environmental impact of salt-laden air and moisture make the damage potential significant for concrete, this manual recommends that all concrete construction in and near coastal flood hazard areas (both V zones and A zones) be constructed with the more durable 5,000-psi minimum compressive strength concrete regardless of the purpose of the construction and the design loads.
C H A P T E R 13
Avoid frequent or prolonged skin contact with pentachlorophenol or creosotetreated wood; when handling it, wear long-sleeved shirts and long pants and use gloves impervious to the chemicals (e.g., vinyl-coated gloves). Pentachlorophenol-pressure-treated wood should not be used in residential interiors except for laminated beams or for building components that are in ground contact and are subject to decay or insect infestation and where two coats of an appropriate sealer are applied. Sealers may be applied at the installation site. Urethane, shellac, latex epoxy enamel, and varnish are acceptable sealers. Creosote-treated wood should not be used in residential interiors. Coal tar pitch and coal tar pitch emulsion are effective sealers for outdoor creosotetreated wood-block flooring. Urethane, epoxy, and shellac are acceptable sealers for all creosote-treated wood. Wood foundations are being constructed in some parts of the country as part of a basement or crawlspace. These foundation elements have walls constructed with pressure-preservative-treated plywood and footings constructed with wide pressure- preservative-treated wood boards such as 2x10s or 2x12s. Because the NFIP regulations allow continuous foundation walls (with the required openings) in coastal A zones, continuous wood foundations might seem to be acceptable in these areas. However, because of the potential forces from waves less than 3 feet high (as discussed in Chapters 11 and 12), a wood foundation supported on a wood footing is not recommended in coastal A zones.
C H A P T E R 13
when it arrives at the job site can be as high as 19 percent, but this moisture content is quickly reduced as the wood dries in the finished building. (The moisture content of the large members (i.e., greater than 3x) will be much more than 19 percent when they arrive at the job site, and it will take months to drop below 19 percent.) The potential for deterioration is greatest at end grain surfaces. Water is most easily absorbed along the grain, allowing it to penetrate deep into the member where it does not readily dry. Figure 13-13 illustrates deterioration in the end of a post installed on a concrete base. This is a typical place for wood deterioration to occur. Even when the end grain is more exposed to drying, the absorptive nature of the end grain creates an exaggerated shrink/swell cycling, resulting in checks and splits, which in turn allow increased water penetration.
Figure 13-13 Wood decay at the base of a post supported by concrete.
Exposed pile tops present the vulnerable horizontal end grain cut to the weather. Cutting the exposed top of a pile at a slant will not prevent decay, and may even channel water into checks. Water will enter checks and splits in the top and side surfaces of beams and girders. It can then penetrate into the untreated core and cause decay. These checks and splits occur naturally in large sawn timbers as the wood dries and shrinks over time. They are less common in glue-laminated timbers and built-up sections. It is generally, but not universally, agreed that caulking the checks and splits is unwise because caulking is likely to promote water retention more than keep water out. The best deterrent is to try to keep the water from reaching the checks and splits. Framing construction that readily collects and retains moisture, such as pile tops, pile-beam connections, and horizontal girder and beam top surfaces, can be covered with flashing or plywood. However, there should always be an air gap between the protected wood and the flashing so that water vapor passing
COASTAL CONSTRUCTION MANUAL 13-21
C H A P T E R 13
out of the wood is not condensed at the wood surface. For example, a closefitting cap of sheet metal on a pile top can cause water vapor coming out of the pile top to condense and cause decay. The cap can also funnel water into the end grain penetrations of the vertical fasteners. When two flat wood surfaces are in contact in a connection, the contact surface will tend to retain any water directed to it. The wider the connections least dimension, the longer the water will be retained, and the higher the likelihood of decay. Treated wood in this contact surface will be more resistant to decay, but only at an uncut surface. Make the least dimension of the contact surface as small as possible. When the contact surfaces are for structural bearing, provide only as much bearing surface as needed, considering both perpendicular-to-grain and parallel-to-grain bearing design stresses. For example, deck boards on 2x joists have a smaller contact surface least dimension than deck boards on 4x joists. A beam bolted alongside an unnotched round wood pile has a small least dimension of the contact surface. Figure 13-14 illustrates this least dimension concept.
Figure 13-14 Minimizing the least dimension of wood contact surfaces.
Contact Surfaces
Contact Surfaces
Connectors
Connectors
Poor durability performance has been observed in exposed sistered members. Where sistered members must be used in exposed conditions, they should be of ground-contact-rated treated wood and the top surface should be covered with a self-adhering modified bitumen (peel and stick) flashing membrane. This material is available in rolls as narrow as 3 inches wide. These membranes seal around nail penetrations to keep water out. In contrast, sheet-metal flashings over sistered members, when penetrated by nails, can channel water into the space between the members.
13-22 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
Other methods of improving exposed structural frame durability include the following: Use drip cuts to avoid horizontal water movement along the bottom surface of a member. Figure 13-15 shows this type of cut. Avoid assemblies that form buckets and retain water adjacent to wood. Avoid designs that result in ledges below a vertical or sloped surface. Ledges collect water quite readily, and the resulting ponding due to rain or condensation alternating with solar radiation will cause shrink-swell cycling, resulting in checks, which allow increased water penetration. To the extent possible, minimize the number of vertical holes in exposed horizontal surfaces from nails, lags, and bolts. Where possible, avoid the use of stair stringers that are notched for each stair. Notching exposes the end grain, which is then covered by the stair. As a result the stair will tend to retain moisture at the notch, right where the bending stress is greatest at the minimum depth section. Figure 13-16 illustrates this stair stringer exposure. Figure 1317 shows the type of deterioration that can result. An alternative stair stringer installation is shown in Figure 13-18 where the stair treads are either nailed onto a cleat, or the stringer is routed out so the tread fits into the routed-out area. Even these alternatives allow water retention at end grain surfaces; therefore these surfaces should be field-treated with wood preservative. Caulk joints at wood connections to keep water out. Caulk only the top joints in the connection. Recaulk after the wood has shrunk (which can take up to a year for larger members). When structurally possible, consider using spacers or shims to separate contact surfaces. A space of about 1/16 inch will discourage water retention by capillary action, but can easily fill with dirt and debris. A 1/4-inch1/2-inch space is sufficient to allow water and debris to clear from the interface. This spacing has structural limitations; a bolted connection with an unsupported shim will have much less shear capacity than an unspaced connection, because of increased bolt bending and unfavorable bearing stress distribution in the wood.
13-23
C H A P T E R 13
Figure 13-15 Drip cut minimizes horizontal water movement along the bottom surface of a wood member.
Drip Cut
13-24
C H A P T E R 13
Stair Tread
Stair Stringer
Stair Stringer
2x Cleat
C H A P T E R 13
Tributyltin oxide (TBTO) is available, but should not be used in or near marine environments, because the leachates are toxic to aquatic organisms. Sodium borate is also available, but it does not readily penetrate dry wood, and it rapidly leaches out of wood when water is present; therefore, it is not recommended.
13.2.9 Substitutions
NOTE
When substitutions are proposed, the designers approval should be obtained before the substitution is made. The ramifications of the change must be evaluated, including the effects on the building components, constructability, and long-term durability. Code and regulatory ramifications must also be considered.
During construction, a contractor may find that materials called for in the construction plans or specifications are not available or that the delivery time for those materials will be too long and will delay the completion of the building. These conflicts will require that decisions be made about substituting one type of construction material for another. Because of the high natural hazard forces imposed on a building near the coast, and the effects of the severe year-round environment in coastal areas, some substitutions must be made only after approval by a design professional and, if necessary, the local building official.
13-26
C H A P T E R 13
Reason
Ensure that pile is not overnotched, that it is field-treated, and that bolts are properly installed with washers and proper end and edge distance Verify presence of positive connection with properly nailed, corrosion-resistant connector Ensure that the bottom of the joist is prevented from bending/buckling Sheathing must act as shear diaphragm Ensure that the wood does not absorb too much moisture prior to installation exposure promotes checks and splits in wood, warp and separation in plywood Install new floors level and eliminate need to repair large splits in new material
2. Joist-to-girder connection 3. Joist blocking 4. Sheathing nailing number, spacing, depth 5. Material storage protection from elements prior to installation 6. Joist and beam material excessive crown or lateral warping, large splits
WARNING
It is important to note that the connections described in this manual are designed to hold the building together in a design event. Builders who have not experienced such an event may underestimate the importance of installing connectors according to manufacturers recommendations. It is extremely important that connectors be installed properly.
13-27
C H A P T E R 13
The nails required for the connection hardware may not be regularly found on the job site. Full-diameter 8d to 20d short nails are commonly specified for specific hurricane/seismic connection hardware. To develop their full strength, these connections require that all of the holes in the hardware be nailed with the proper nails. In the aftermath of recent hurricanes, failed connector straps and other hardware were often found to have been attached with too few nails, nails of insufficient diameter, or the wrong type of nail. Figure 13-19 shows a connector that failed because of insufficient nailing.
Figure 13-19 Hurricane Iniki (1992), Hawaii. Connector failure caused by insufficient nailing.
WARNING
Proper nail selection and installation are critical. Contractors should not substitute different nails or nailing patterns without approval from the designer.
NOTE
Additional information about pneumatic nail guns can be obtained from the International Staple, Nail and Tool Association, 512 West Burlington Ave., Suite 203, LaGrange, IL 60525-2245. A report prepared by National Evaluation Service, Inc., titled Power-Driven Staples and Nails for Use in All Types of Building Construction (NES 1997), presents information about the performance of pneumatic nail guns and includes prescriptive nailing schedules.
13-28
As mentioned previously, connection hardware must be corrosionresistant. If galvanized connectors are used, additional care must be taken during nailing. When a hammer strikes the connector and the nail during installation, some of the galvanizing protection is knocked off. One way to avoid this problem is to use corrosion-resistant connectors that do not depend on a galvanized coating, such as stainless steel or wood (see Section 12.6.6, in Chapter 12 of this manual). Stainless steel nails should only be used with stainless steel connectors. An alternative to hand-nailing is to use one of the pneumatic hammers now available that shoot nails into connector holes. All connections between members in a wood-frame building are made with nails, bolts, screws, or a similar fastener. Each of these fasteners is installed by hand. The predominant method of installing nails is by pneumatic nail gun. Many nail guns use nails commonly referred to as sinkers. Sinkers are slightly smaller in diameter and thus have lower withdrawal and shear capacities than those of the same size common nail. Nail penetration is governed by air pressure for pneumatic nailers, and this is an important quality control issue for builders. Many prescriptive codes have nailing schedules for various building elements such as shearwalls and diaphragms.
FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
Toenailing should not be used to make a structural connection. Toenailing reduces the withdrawal capacity of the nails and frequently splits the wood, reducing the capacity even further. Pile alignment and notching are critical not only to successful floor construction, but also to the structural adequacy during a natural hazard event. Construction problems related to these issues are also inevitable, so solutions to pile misalignment and overnotching must be developed. Figure 13-20 illustrates a method of reinforcing an overnotched pile, including one that is placed on a corner. The most appropriate solution to pile misalignment is to re-drive a pile in the correct location. An alternative is illustrated in Figure 1321, which shows a method of supporting a beam at a pile that has been driven outside the layout of the pile foundation. Figure 13-22 illustrates proper pile notching for both two-member and four-member beams.
Figure 13-20 Reinforcement of overnotched piles.
Beam
1/4"
x 6" Wide Galvanized Steel Plate or 1/4" x 3" x 3" Angle Support
Equal Distance
Pile
Pile Beam
Bolts
Pile Bolts
In-Line Pile
Corner Pile
13-29
C H A P T E R 13
A
d Twice Horizontal Depth (d) of Support Angle
Support Angle
Section A-A
Figure 13-22 Proper pile notching for twomember and four-member beams.
Beam
Beam
Bolts
Bolts
Pile Pile
Two-Member Beam
13-30
C H A P T E R 13
After the square foundation has been built, the primary layout concerns regarding how the building will perform under loads are confined to other building elements being properly located so that load transfer paths are complete.
NOTE
See FEMA NFIP Technical Bulletin 8, Corrosion Protection for Metal Connectors in Coastal Areas, in Appendix H.
13-31
C H A P T E R 13
Floor framing materials other than 2x sawn lumber are becoming popular in many parts of the country. These materials include wood floor trusses and wood I-beams. Depending on the shape of the joist and the manufacturer, the proper installation of these materials may require some additional steps. For instance, some wood I-beams require solid blocking at the end of the joist where it is supported so that the plywood web does not crush. Figure 13-24 illustrates the use of plywood web I-beams as joists. As shown in the figure, the bottom flanges of the joists are braced with a small metal strip that helps keep the flange from twisting. Solid wood blocking is a corrosion-resistant alternative to the metal braces.
Figure 13-24 Plywood web I-beams used as floor joists with metal brace used to keep the bottoms of the joists from twisting. Also note gluelaminated beam.
Floor surfaces in high-wind, flood, or seismic hazard areas are required to act as a diaphragm, as discussed in Chapter 12. For the builder, this means that the floor joists and sheathing are an important structural component. Therefore, the following installation features may require added attention: Joints in the sheathing should fully bear on top of a joist, not a scabbed-on board used as floor support. Nailing must be done in accordance with a shear diaphragm plan. Construction adhesive is important for preventing squeaky floors, but the adhesive must not be relied upon for shear resistance in the floor. Joints in the sheathing across the joists must be fully blocked with a fulljoist-height block. (Horizontal floor diaphragms with lower shear capacities can be unblocked if tongue-and-groove sheathing is used.)
13-32
C H A P T E R 13
13.3.1.1 Horizontal Beams and Girders As discussed in Appendix J, girders and beams can be solid sawn timbers, glue-laminated timbers (see Figure 13-24), or built-up sections. The girders span between the piles and support the beams and joists. The piles are usually notched to receive the girders. To meet the design intent, girders, beams, and joists must be square and level, girders must be secured to the piles, and beams and joists must be secured to the girders. The layout process involves careful surveying , notching, sawing, and boring. The bottom of the notch provides the bearing surface for downward vertical loads. The bolted connection between the girder and the vertical notch surface provides capacity for uplift loads and stability. Girder splices are made as required at these connections. Splices in multiple-member girders may be made away from the pile, but must be engineered so that the splices occur at points of zero bending moment. This concept is illustrated in Figure 13-25.
Figure 13-25 Acceptable locations for splices in multiple-member girders.
= girder
= support
= splice
13.3.1.2 Substitution of Floor Framing Materials The considerations discussed in Section 13.2.9 for substitution of foundation materials also apply to substitutions of floor framing materials. 13.3.1.3 Floor Framing Inspection Points As a guide for floor framing inspections, Table 13.4 suggests critical inspection points.
13-33
C H A P T E R 13
Inspection Point
1. Pile-to-girder connection
Reason
Ensure that pile is not overnotched, that it is field-treated, and that bolts are properly installed with washers and proper end and edge distance Verify presence of positive connection with properly nailed, corrosion-resistant connector Ensure that the bottom of the joist is prevented from bending/buckling Sheathing must act as shear diaphragm Ensure that the wood does not absorb too much moisture prior to installation exposure promotes checks and splits in wood, warp and separation in plywood Install new floors level and eliminate need to repair large splits in new material
2. Joist-to-girder connection 3. Joist blocking 4. Sheathing nailing number, spacing, depth 5. Material storage protection from elements prior to installation 6. Joist and beam material excessive crown or lateral warping, large splits
C H A P T E R 13
plates and sills must be in accordance with the design. Proper nailing and attachment of the framing material around openings is very important. Section 12.4.2 also highlights the difficulty of transferring large shear loads when there are large openings in the shearwall.
Figure 13-26 Using full-height sheathing improves transfer of shear.
13-35
C H A P T E R 13
It is very important that shearwall sheathing (e.g., plywood, OSB) with an exterior exposure be finished appropriately, with pigmented finishes such as paint (which last longer than unpigmented finishes) or semitransparent penetrating stains. It is also important that these finishes be properly maintained. Salt crystal buildup in surface checks in siding can cause damage to the siding. This damage is typically worse in siding that is sheltered from precipitation, because the salt crystals are made larger from salt spray but never washed off with fresh rainwater. To meet the design intent, walls: must be plumb and square to each other and to the floor, must be lined up over solid support such as a beam, floor joists, or a perimeter band joist, must not have any more openings than designated by the plans, must not have openings located in places other than designated on the plans, must consist of material expected to resist corrosion and deterioration, and must be properly attached to the floors above and below the wall, including holddown brackets required to transfer overturning forces. In addition, all portions of walls designed as shearwalls must be covered with sheathing nailed in accordance with either the plans or a specified prescriptive standard. 13.3.2.1 Interior Steel Frames In coastal buildings with large openings or cathedral ceilings, the design may include steel moment-resisting frames for wind and/or seismic lateral forces. These frames are necessary when even double-sheathed plywood walls have insufficient capacity. Figure 12-49, in Chapter 12, shows a steel moment frame installed in the wall of a coastal residential building. The fabrication of steel moment frames will usually be done by a steel specialty subcontractor, who will first prepare a set of shop drawings from the design drawings. The contractor and designer should both check the accuracy of the shop drawings. Most frames will have to be transported in sections and assembled on site with field bolting and/or welding. The building code or designer may require special inspection or shop certification for the shop and field frame welding. If the frame is not exposed, a finish of shop primer will be adequate. Exposed parts of the frame will require hot-dip galvanizing or some other finish suitable for exterior exposure.
13-36 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
Alignment of the frame in the building will be critical. It is also important that the connections that transfer forces to the frame be properly accomplished so that the frame can effectively brace the structure. These steel-to-wood connections are usually made with bolts, threaded rod welded to the steel for connecting to the wood, or with powder-actuated fasteners shot into the steel. The ability of these powder-actuated devices to transfer the shear and tension forces must be verified (and certified) by the supplier. 13.3.2.2 Substitution of Wall Framing Materials The considerations discussed in Section 13.2.9 for substitution of foundation materials also apply to substitutions of wall framing materials. 13.3.2.3 Wall Framing Inspection Points As a guide for wall framing inspections, Table 13.5 suggests critical inspection points.
Table 13.5 Wall Inspection Points
Inspection Point
1. Wall framing attachment to floors 2. Size and location of openings 3. Wall stud blocking 4. Sheathing nailing number, spacing, depth of nails 5. Material storage protection from elements prior to installation 6. Stud material excessive crown (crook) or lateral warping (bow) 7. Header support over openings
Reason
Ensure that nails used are of sufficient size, type, and number Critical to performance of shear wall Ensure that there is support for edges of sheathing material Sheathing must act as shear diaphragm
Ensure that the wood does not absorb too much moisture prior to installation (Exposure promotes checks and splits in wood, warp and separation in plywood.) Maintain plumb walls and eliminate eccentricities in vertical loading Ensure that vertical and lateral loads will be transferred along the continuous load path
13-37
C H A P T E R 13
IMPORTANT
The most common roof structure failure is the uplift failure of porch, eave, and gable end overhangs. The next most common is roof sheathing peeling away from the framing. The nailing of the sheathing at the leading edge of the roof, the gable edge, and the joints at the hip rafter or ridge are all very important, as is securing the roof framing to prevent uplift. This failure point is also the most likely place that progressive failure of the entire structure could begin.
Field investigations indicate failure of houses with wood-framed roofs occurs first at the roof, often at improper fastening between the roof sheathing and building frame. Figure 13-27 shows an example of what happened to plywood roof sheathing during Hurricane Andrew when fasteners had not been properly embedded into the top chord of the roof truss. This potential failure mode persists in new housing; Figure 13-28 shows nails that missed the roof rafters on a house being constructed in 1998.
13-38
C H A P T E R 13
Figure 13-27 Hurricane Andrew (1992), Florida. Roof sheathing found in debris. Staples were off-line and therefore not connected to top chord of supporting truss. Note light area on the underside of sheathing (highlighted) where top chord of truss was in contact with sheathing.
Figure 13-28 Sheathing nails (circled) missed roof rafter in new construction.
To meet the design intent, roofs must meet the following requirements: Roof trusses and rafters must be properly attached to the walls. Roof sheathing must be nailed according to either the construction plans or a specified prescriptive standard. Roofs must consist of materials expected to resist corrosion and deterioration, particularly the connectors.
COASTAL CONSTRUCTION MANUAL 13-39
C H A P T E R 13
13.3.3.1 Substitution of Roof Framing Materials The considerations discussed in Section 13.2.9 for substitution of foundation materials also apply to substitutions of roof framing materials. 13.3.3.2 Roof Frame Inspection Points As a guide for roof framing inspections, Table 13.6 suggests critical inspection points.
Table 13.6 Roof Frame Inspection Points
Inspection Point
1. Roof framing attachment to walls 2. Size and location of openings 3. "H" clips or roof frame blocking 4. Sheathing nailing number, spacing, depth of nails 5. Material storage protection from elements prior to installation 6. Rafter or ceiling joist material excessive crown or lateral warping 7. Gable-end bracing
Reason
Ensure that sufficient number, size, and type of nails is used in the proper connector Critical to performance of roof as a diaphragm Ensure that there is support for edges of the sheathing material Sheathing must act as shear diaphragm and resist uplift Ensure that the wood does not absorb too much moisture prior to installation (Exposure promotes checks and splits in wood, warp and separation in plywood.) Maintain level ceiling Ensure that bracing conforms to design requirements and specifications
WARNING
Do not substitute nails, fasteners, or connectors without approval of the designer.
4. Use only material rated and specified for the expected use and environmental conditions. 5. The weakest connections will fail first; the concept of continuous load path must be considered for every connection in the structure. It will be important to pay particular attention to these connections. 6. Exposed steel in the structural frame will corrode, even in places such as the attic space. Plan for it by installing hot-dipped galvanized or stainless steel hardware and nails. 7. Compliance with suggested nailing schedules for roof, wall, and floor sheathing is very important.
13-40
C H A P T E R 13
C H A P T E R 13
expansion sleeves or steel spikes intended for anchoring to concrete, which should provide a stronger and more reliable connection. Or, the use of plastic shims at metal doors may be appropriate to avoid termite attack. Proposed substitutions of materials must be thoroughly evaluated and must be approved by the designer (see Section 13.2.9). The building envelope must be installed in a manner that will not compromise the buildings structural integrity. For example, during construction, if a window larger than originally intended is to be installed because of delivery problems or other reasons, the contractor should obtain the designers approval prior to installation. The larger window may unacceptably reduce the shear capacity of the wall, or different header or framing connection details may be necessary. Likewise, if a door is to be located in a different position, the designer should evaluate the change to determine whether it adversely affects the structure. Adequate quality control (i.e., inspection by the contractors personnel) and adequate quality assurance (i.e., inspection by third parties such as the building official, the designer, or a test lab) must be provided. The amount of quality control/quality assurance will depend on the magnitude of the natural hazards being designed for, complexities of the building design, and the type of products/systems being used. For example, installation of windows that are very tall and wide and make up the majority of a wall deserves more inspection than isolated, relatively small windows. Inspection of roof coverings and windows is generally more critical than inspection of most wall coverings, because of the general susceptibility of roofing and glazing to wind and the resulting damage from water infiltration that commonly occurs when these elements fail.
13-42
C H A P T E R 13
Inspection Point
Reason
13-43
C H A P T E R 13
WARNING
Cantilever decks should not be placed over bulkheads or retaining walls where wave runup on the vertical structure could damage the deck.
C H A P T E R 13
for the primary building, because the failure modes are the same and the load mechanisms are the same. Indeed, sometimes the loads on appurtenant structures are even higher because of their exposure. In considering the potential loads on decks, the builder should keep in mind that many decks become screened-in porches with roofs and thus, in the event of high winds, experience even greater loads. Decks can be built to withstand severe events, as shown by Figure 13-29, a photograph of a deck that survived when the building did not.
Figure 13-29 Building damage from Hurricane Opal at Pensacola Beach, Florida. The deck, which was constructed to State of Florida Coastal Construction Control Line (CCCL) design requirements, survived; the building, which was not constructed to CCCL requirements, did not survive. See Appendix G for a discussion of the Florida CCCL.
Stairs leading from decks are frequently a source of storm-created debris. Stairs should have open risers and should be supported on posts or piles embedded below the expected depth of storm-induced scour if they are expected to survive a severe storm. Debris from stairs is minimized when the stairs are located on the landward side of the building rather than the seaward side. An alternative is to connect the stairs to the deck in such a way that the stairs can be removed or elevated above the expected flood depth. Frequently, such a design involves the use of winches and cables so that the stairs can be elevated by a person on the deck level. In order for the stair section to be lifted, the stair/deck connection must be hinged. Figure 13-30 illustrates this stair elevation technique. Note that this system cannot be used for stairs that provide the only means of egress and access for the building.
13-45
C H A P T E R 13
Figure 13-30 Stair elevation system. Note that this system cannot be used for stairs that provide the only means of egress and access for the building.
Deck
C H A P T E R 13
heater (if there is one), fuel supply, and other associated equipment must be found so that the following requirements are met: The equipment must be located in the proper place to supply the pool with water. The equipment must be elevated to or above the DFE so that the potential for flood damage is minimized. The equipment must be set so that wind, or seismic, and water forces (including inundation by salt water or sediment) will not displace or damage it. Unless specifically designed, most mechanical equipment is not intended to be inundated with salt water. Equipment installed in the corrosive coastal environment will normally require corrosion-resistant piping (usually PVC), stainless steel pump impellers, cast iron pump bodies, and totally enclosed electrical components. The design considerations for one-piece pools are covered in Section 12.9.4 in Chapter 12. The builder, however, must be able to execute the design intent, which includes the following: A one-piece pool must be able to resist flood forces with minimal damage, whether the pool is full or empty. This means that an inground pool must resist failure from buoyancy as well as wall fracture. The pool equipment must be easily returned to service after a severe event. A flexible connection between the pump and piping may help achieve this objective so the equipment can move under forces from the severe event. This coupling will also reduce stress on the pipe from vibration. Pool accessories (e.g., cleaning nets, lane dividers) can become airborne debris and should have a secure storage location. The design intent for concrete pools includes the following: Elevation of an in-ground pool should be such that scour will not permit the pool to fail from either normal internal loads of the filled pool or from exterior loads imposed by the flood forces. The pool should be located as far landward as possible and should be oriented in such a way that flood forces are minimized. This includes placing the pool with the narrowest dimension facing the direction of flow, orienting the pool so there is little to no angle of attack from flood water, and installing a pool with rounded instead of square corners. All of these design choices will reduce the amount of scour around the pool and thereby improve the chances the pool will survive the storm. These concepts are illustrated in Figure 13-31.
NOTE
Two articles concerning swimming pool design standards in V zones are included in Appendix L. The articlesScour Impact of Coastal Swimming Pools on Beach Systems and Conceptual Breakaway Swimming Pool Design for Coastal Areasreport the results of studies funded by FEMA.
CROSSREFERENCE
See Section 12.9.4, in Chapter 12, for design guidance and regulatory requirements regarding swimming pools.
13-47
C H A P T E R 13
Narrowest Dimension
Porch
0 Angle of Attack
Flood Flow
A concrete pool deck should be frangible, so that flood forces will create concrete fragments that will help reduce scour. The concrete deck should be installed with no reinforcing and should have contraction joints placed at 4-foot squares to encourage failure. See Figure 12-121, in Chapter 12, for details on constructing a frangible concrete pad. Pools should not be installed on fill in or near a V zone. Otherwise, a pool failure may result from scour of the fill material
C H A P T E R 13
the wood. Wood walkways at grade level should be anchored with posts buried several feet in the ground to prevent uplift from wind. During a severe flood event, scour may occur at the edges of the walkway and cause an uplift failure, so the posts should be buried a minimum of 8 feet below the expected level of scour (see Appendix I). There are several state-initiated guidance documents on walkway/walkover construction. Appendix I includes a construction guidance document from the State of Florida, Bureau of Beaches and Coastal Systems, Beach/Dune Walkover Guidelines (January 1998) and a document from Florida Sea Grant titled Beach Dune Walkover Structures (December 1983).
13.6.1 Elevators
Elevators are becoming commonplace in many coastal homes. Normally, these elevators have only a one- to four-person capacity, and they almost always require installation in an area that will at least be partially below the DFE. To minimize flood damage to the elevator and its parts, the builder should look for locations above the DFE to mount elevator equipment (e.g., electrical controls, hydraulic pumps). Normally, for fire safety reasons, elevators are equipped with a default device that sends the cab to the lowest floor when there is a power outage (which will always occur during a major storm). For the protection of the elevator equipment and the occupants, this manual recommends that a float switch be installed that activates when inundated by flood water and sends the elevator cab to a floor above the DFE. For additional information, see FEMA NFIP Technical Bulletin 4, Elevator Installation for Buildings Located in Special Flood Hazard Areas, in Appendix H.
NOTE
For additional information about the proper design and construction of utility system components for buildings in flood hazard areas, refer to Protecting Building Utilities From Flood Damage Principles and Practices for the Design and Construction of Flood Resistant Building Utility Systems, FEMA 348 (FEMA 1999).
13-49
C H A P T E R 13
COST CONSIDERATION
HVAC equipment that is not elevated above the DFE will probably need to be repaired or replaced after a flood.
cantilever floor framing (see Figures 13-32 and 13-33; this method requires careful detailing to prevent water penetration into the building floor and wall systems) pile-supported wood-brace-supported (see Figures 13-34 and 13-35) rooftop mount
13-50
C H A P T E R 13
Figure 13-32 Cantilever floor framing for air-conditioning/heat pump compressor platform plan view.
4'
Fig. 13-33
Band Joist
Exterior Siding
Corrosive-Resistant Flashing Solid 2x Blocking Treated 2x Joist Exterior Wall or Girder 8.67" Minimum Decking Material
Handrail Around Perimeter of Platform Rip Top of 2x at Slope to Provide Drainage (Field Treat With Preservative)
Figure 13-33 Cantilever floor framing for air-conditioning/heat pump compressor platform elevation view.
13-51
C H A P T E R 13
3'
Band Joist
4'
Floor Joists
Fig. 13-35
Solid Wood Block Between Diagonals Bolted to Interior Blocking 2x4 Wood Diagonal
3/8" Diameter Bolt Treated 2x Joist 3/4" Diameter Bolt Wit Washers at 2 ft on Center (Minimum of 3 Bolts)
Wood Spacer
13-52
C H A P T E R 13
CROSS-REFERENCE
Detailed information about the installation and protection of electrical system components is provided in Protecting Building Utilities From Flood Damage Principles and Practices for the Design and Construction of Flood Resistant Building Utility Systems, FEMA 348 (FEMA 1999).
WARNING
Utility system components must not be connected to breakaway walls under elevated buildings in coastal flood hazard areas. The resistance provided by electrical and plumbing lines and other utility system components can prevent the walls from breaking away as intended under flood forces.
13-53
C H A P T E R 13
13.6.5 Tanks
Small tanks used for fuel, such as propane tanks, should be elevated above the DFE; if a tank is detached from its location during a severe flood event, it can become a windborne or waterborne missile. In addition to being elevated, small tanks also need to be strapped or otherwise secured to the building so that they will not be detached by high winds or a seismic event. Any strapping used should be corrosion-resistant. This technique can be altered to accommodate an exterior location. Builders should keep in mind that the strapping must resist forces from all four plan directions. Larger tanks will normally be buried belowgrade or supported by and attached to a foundation. In a Special Flood Hazard Area, erosion and scour can expose the tank; the tank can fill with sediment/soil and salt water; or buoyancy forces on the tank can be sufficient to lift the tank out of the ground. Larger tanks may be used for septic tanks or for the storage of propane or fuel oil. This manual recommends the following for minimizing damage to belowgrade tanks: Orient the tank so that scour is minimized. Do this by orienting the tank with the narrowest dimension of the tank perpendicular to the flood flow, orienting the tank so there is no angle of attack of the flood water, and locating the tank so that flow diverted or channeled by nearby structures is not directed toward the tank. Secure the tank so that buoyancy forces will not lift the tank out of the ground. Do this by anchoring the tank to a concrete pad heavy enough to keep the tank in the ground. Aboveground tanks can be anchored in at least two ways (see Figure 13-36). In addition, the tank must be located such that scour does not undermine the slab foundation, and the openings of fill lines and overflows must be above the DFE so that flood water will not enter the tank.
WARNING
Do not anchor tanks to breakaway walls under elevated buildings.
13-54
C H A P T E R 13
Weld Bracing to Legs Concrete Slab Bracing Concrete Slab Weld Bracing to Legs CorrosionResistant Legs Legs of Tank Securely Anchored in Slab
13.7 References
American Concrete Institute. 1988. Cold Weather Concreting. ACI 306R13. Detroit, MI. American Concrete Institute. 1995. Building Code Requirements for Structural Concrete. ACI 318-95. Detroit, MI. American Concrete Institute. 1996. Placing Concrete by Pumping Methods. 304.2R Detroit, MI. American Institute of Timber Construction. 1984. Typical Construction Details. AITC 104-84. Englewood, CO. American Institute of Timber Construction. 1986. In-Service Inspection, Maintenance and Repair of Glued Laminated Timbers Subject to Decay Conditions. AITC Technical Note 13. American Society of Civil Engineers. 1982. Evaluation, Maintenance and Upgrading of Wood Structures: A Guide and Commentary. New York, NY. American Society of Civil Engineers. 1998. Minimum Design Loads for Buildings and Other Structures. ASCE Standard ASCE 7-98.
13-55
C H A P T E R 13
American Society for Testing and Materials. 1988. Standard Recommended Practices for Increasing Durability of Building Constructions Against Water-Induced Damage. Standard E 241-77. Philadelphia, PA. American Wood Preservers Association. 1991. Care of Pressure-Treated Wood Products. AWPA Standard M4-91. Woodstock, MD. American Wood Preservers Association. 1994. Standards. Woodstock, MD. Basham, K. 1995. Cold Weather Concreting. Journal of Light Construction. January. Bruce, Quarles, Shelly, et. al. 1997. Wood Performance in Service, Workshop Notes, Richmond, CA. California Redwood Association. Redwood File. Novato, CA. Chapdelaine, H. 1993. Building Porches That Last. Journal of Light Construction. June. Coastal Living Magazine. 1998. Good Decisions: Decked Out. January. Dost, W. 1986. Performance of Wood Construction Materials, Kapalua Bay Villas. WBRC report 35.04.20. Dost, W. A. 1990. Wood: Detailing for Performance. Mill Valley, CA: GRDA Publications. Federal Emergency Management Agency. 1999. Protecting Building Utilities From Flood Damage Principles and Practices for the Design and Construction of Flood Resistant Building Utility Systems. First Edition. FEMA 348. November. Forest Products Research Society. 1988. Wood Protection Techniques and the Use of Treated Wood in Construction. Madison, WI. Forest Products Society. 1996. Selection and Use of Preservative-Treated Wood. Madison, WI. Graham and Womack. 1972. Wood-Metal Corrosion, An Annotated Survey. Research Bulletin 21. Oregon State University College of Forestry, Forest Research Laboratory. Corvallis OR. Hamilton, P. 1994. On the Beach: Coastal Construction. Journal of Light Construction. April.
13-56 FEDERAL EMERGENCY MANAGEMENT AGENCY
C H A P T E R 13
Hamilton, P. 1997. Installing a Steel Moment Frame. Journal of Light Construction. March. Highley, S. Controlling Decay in Waterfront Structures. Forest Products Laboratory. 1989. International Code Council. 2000a. International Building Code. Final Draft. Birmingham, AL. July. International Code Council. 2000b. International Residential Code for Oneand Two-Family Dwellings. Birmingham, AL. McDonald, Falk, Williams and Winandy. 1996. Wood Decks, Materials, Construction and Finishing. Forest Products Society. Meyer, R. W.; Kellogg, R. M. 1982. Structural Use of Wood in Adverse Environments. New York: Van Nostrand Reinhold. Morrell, Helsing, Graham. Marine Wood Maintenance Manual. Research Bulletin 48. Oregon State University College of Forestry, Forest Research Laboratory. Corvallis, OR. National Evaluation Service, Inc. 1997. Power-Driven Staples and Nails for Use in All Types of Building Construction. National Evaluation Report NER272. Reissued September 1. Nnaji, Soronnadi, et al. 1996. Scour Impact of Coastal Swimming Pools on Beach Systems. Journal of Coastal Research. Winter. Ft. Lauderdale, FL. Schein, E. 1968. The Influence of Design on Exposed Wood in Buildings in the Puget Sound Area. USDA Pacific NW Forest and Range Experiment Station. Portland, OR. Simpson Strong-Tie Co., Inc. 1997. Simpson Wood Construction Connectors. State of Florida, Bureau of Beaches and Coastal Systems. 1998. Beach/Dune Walkover Guidelines. January. University of Florida Sea Grant Institute. 1983. Beach Dune Walkover Structures. December. U.S. Department of the Navy. 1982. Foundation and Earth Structures Design. Manual 7.2. Alexandria, VA. May. Yazdani, Nur, et al. 1997. Conceptual Breakaway Swimming Pool Design for Coastal Areas. Journal of Coastal Research. Winter. Ft. Lauderdale, FL.
COASTAL CONSTRUCTION MANUAL 13-57