Force Majeure
Force Majeure
Force Majeure
Editors Note:The devastating 2005 hurricane season wreaked unthinkable havoc on the Gulf Coast region of the country.While the rebuilding process continues, contractors should consider including force majeure clauses in future contracts to protect their businesses from possible catastrophesboth man-made and acts of God.The following three articles contain detailed information on force majeure. Contractors, of course, should seek advice of legal counsel in all contract negotiations.
C
What qualifies as a force majeure event?
42
Basics
BY DENISE L. NESTEL
perform. In rare occasions, a contract simply defines force majeure loosely to include anything beyond the parties control.
onstruction contracts uniformly stipulate that contractors must diligently pursue work until completion, or face damages and possible termination. The one-two punch of Katrina and Rita sparked a renewed interest in force majeure clauses, particularly the protection available when work cannot be pursued because of events beyond control.
events that make performance impossible are contractual force majeure events. If a contract limits force majeure events to acts of God, then the event must be exclusively nonhuman and without human intervention. This is not the case in most construction contracts. In construction contracts, a force majeure event often includes acts of God and forces of nature, but also man-made events such as strikes, civil unrest, terrorism, inability to obtain resources, actions of governing authorities, enactment of governmental regulations, etc. The common denominator is that these events are beyond the control of the party seeking excuse from its failure to
Do all contracts have force majeure clauses, and, if so, where are they located?
Not all contracts contain force majeure clauses. Even if protection from force majeure events exists, the clause may not be captioned force majeure or include this term. Instead, the risk of impossibility due to uncontrolled events is often addressed in delay or changes clauses.
In conversation, force majeure is often used synonymously with acts of God or forces of nature. However, on a construction project, a force majeure event is, quite simply, whatever the contract says that it is. Not all uncontrollable conditions or
majeure event must be not only beyond control of the party seeking protection, but also be unforeseeable. Foreseeability is determined at the time of entering the contract, not at the time the event occurs.
project. A hurricane, for example, requires demobilization of the project. But, as some contracts recognize, a force majeure may stop just part of the work and provide an excuse for only the affected part. For example, the contract may provide that only those acts subject to the force majeure are excused, but construction may continue in other areas, or that other types of work, such as purchasing of materials, must continue. A force majeure clause provides an excuse only so long as the impact of the force majeure prevents performance. Occasionally, a force majeure clause allows the affected party to terminate the contract if the force majeure is of a specified duration.
premium demanded by transporters still operating in the affected areas. However, the contractor should review the changes or claims clause to see if it may still be able to recoup costs.
| 43