PWD Bill Format
PWD Bill Format
( Reference to P.Account Code ChapterX.para 288 & para 544 and 548 of P.W.D Manual) (For contractors and suppliers this form provides only for payments for work or supplies actually measured) 1. The full name of work as given in the estimate should be entered against the line "name of work"except in the case of bills or Stock" materials 2. The purpose of supply applicable to the case should be filled in and the rest scored out. 3. If the out lay in work is recorded by sub heads,the total for each sub head should be shown in column 5 and against this total there should be an entry in column 6 also,in no other case should any entries be made in column 6.
ADP NO /S.R NO
Memorandum Of Payments
4. The figure against(k) should be tested to see that if agrees with the total of item 4 and 5. 5. If the net amount tobe paid is less than Rs.10 and it can not be included in a cheque,the payment should be made in case ,the pay order being altered suitable and the alteration attested by dated initials. 6. The payee's acknowledgement should be for the gross amount paid as per item (i.e ,a+b+c) 7. Payment should be attested by some known person when the payee's acknowledgement is given by a mark seal or thumb impression. 8. The column "Figures for Works Abstract" is not required in the case of the bill suppliers.
RECOVERY
Reference to agreement of Work Order issued by Executive Engineer Provincial Highway Division Mirpurkhas Vide No TC/G-55/ Dated / /2011
STIP: DATE OF START: ACT: DATE OF START: STIP: DATE OF COMPL: ACT: DATE OF COMPL:
Work in Progress
1. Certified that work has been done as per P.W.D (Highways sspecifications) 2. Certified that compaction tests have been carried out at site & results achieved found satifactory as per modified AASHO specification
D 420 Ac)
SION
VISION
198
contractor)
er issued by Division
ay
/ /2011
ogress
P.W.D
n carried ory as
Unit
Items of works or supplies grouped under Sub Heads or Sub Works of Estimates.
Remarks
2 3 4 5 6 1. CUT IN SAND DUNES. Earth work excavation in ashes, sand, soft soil or silt clearance including all lifts and leads. 665.50 Rs. /= Rs. P%0 Cft 2. FILLING SOFT SAND.
Earth work excavation in ashes, sand, soft soil or silt clearance including all lifts and leads, including dressing in leveling of earth work to design section etc. complete.(ashes, sand, silt or soft soil), including earth work compaction by sheep foot roller, moisture content upto 85% density modified AASHO.
665.50
Rs.
/=
Rs.
Preparing base course including supplying and spreading stone metal of approved quality properly graded to maximum size of 1 1/2" in required thickness to proper camber and grade including supplying and spreading 15 cft. Screening and non plastic quarry fines, filling depressions with stone metal after initial rolling including watering and compacting the same so as to achieve 100% density as per modified AASHO specifications.(Rate includes providing and using templates, camber plates, screens, forms etc. as directed). Rate includes all cost of materials, T&P, labours and carriage upto site of work.
Rs.
/=
Rs.
Providing surface dressing Ist coat on new or existing surface with 30 Ibs Bitumen of 80/100 penetration and 4.0 cft of crush bajri of required size of 3/4"-3/8", including cleaning the road surface, rolling after each etc. complete. Rate includes all cost of materials, labours, T&P, and carriage upto site of work.
Rs.
/=
Rs.
Providing surface dressing 2 coat on new or existing surface with 39 Ibs Bitumen of 80/100 penetration and 4.25 cft of crush bajri of required size of 3/4"-3/8", including cleaning the road surface, rolling after each etc. complete. Rate includes all cost of materials, labours, T&P, and carriage upto site of work.
Rs.
/=
Rs.
Earth work for embankment from borrow pits including laying in 6" layers, clod breaking, ramming, dressing complete, lead upto 100 ft., lift upto 5 ft. ( In ordinary soil )
P% 0Cft Total Add/Deduct ( - ) Total Add Diff: cost of bitumen @ Rs. P/Ton Grand Total Say Total
/= /= /= /= /= /= /=
Remarks
7 /=
/=
mum size of 1 1/2" in quarry fines, filling 00% density as per . as directed). Rate
/=
/=
/=
/= /= /= /= /= /= /=