Project Monitoring and Control
Project Monitoring and Control
Project Monitoring and Control Why do we monitor? What do we monitor? When to we monitor? How do we monitor?
Why do we monitor?
Simply because we know that things dont always go according to plan (no matter how much we prepare) To detect and react appropriately to deviations and changes to plans
What do we monitor?
What do we monitor?
Inputs Time Money Resources Material Usage Tasks Quality/Technical Performance Outputs Progress Costs Job starts Job completion Engineering / Design changes Variation order (VO)
When do we monitor?
End of the project Continuously Regularly Logically While there is still time to react As soon as possible At task completion At pre-planned decision points (milestones)
7
Where do we monitor?
At head office? At the site office? On the spot? Depends on situation and the whats
How do we monitor
Through meetings with clients, parties involved in project (Contractor, supplier,etc.) For schedule Update CPA, PERT Charts, Update Gantt Charts Using Earned Value Analysis Calculate Critical Ratios Milestones Reports Tests and inspections Delivery or staggered delivery PMIS (Project Management Info Sys) Updating
9
10
Project Control
Control process and activities needed to correct deviations from plan Control the triple constraints
time (schedule) cost (budget, expenses, etc) performance (specifications, testing results, etc.)
12
13
14
16
17
Earned Value Chart basis for evaluating cost & performance to date
18
19
20
EXAMPLE
Assume that operations on a Work Package cost RM 1,500 to complete. They were originally scheduled to finish today. At this point, we actually spent RM1,350. And we estimate that we have completed two thirds (2/3) of the work. What are the cost and schedule variances? CV = BCWP ACWP = 1500 (2/3) 1350 = - 350 SV = BCWP BCWS = 1500 (2/3) 1500 = - 500 CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74 SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67 Spending higher than budget, and given what we have spent, we are not as far along as we should be (have not completed as much work as we should have)
21
Possible to have one of indicators to be favorable while the other unfavorable Might be ahead of schedule and behind costs Six possibilities (see figure next slide)
22
23
Time t
Month 17
24
Solution
BCWS = 475,000 BCWP = 300,000 ACWP = 350,000 CV = BCWP ACWP SV = BCWP BCWS
CV = 300,000 350,000 = -50,000 (negative value - cost overrun) SV = 300,000 475,000 = -175,000 (negative value - behind schedule) Cost Performance Index (CPI) = BCWP/ACWP = 300/350 = 0.86 Schedule Performance Index (SPI) = BCWP/BCWS = 300/475 = 0.63 Time Performance Index (TPI) = STWP/ATWP Scheduled Time Work Performed (STWP) can be estimated Time t = Schedule Variance/Slope of Planned costs = -175,000/ (475,000/17) = - 6.26 months Time Difference= 17- 6.26 = 10.74 TV = 10.74/17 = 0.63
25
Critical ratio
Sometimes, especially large projects, it may be worthwhile calculating a set of critical ratios for all project activities The critical ratio is actual progress x budgeted cost
scheduled progress actual cost
If ratio is 1 everything is probably on target The further away form 1 the ratio is, the more we may need to investigate
26
A B C D E
60 50 30 20 25
40 50 20 30 25
27
Summary
Need proper project monitoring and control mechanisms Tools available to help in monitoring and controlling activities There are human control and management aspects not covered here
29