CHAPTER 1: Operations As A Competitive Weapon: Key Equations
CHAPTER 1: Operations As A Competitive Weapon: Key Equations
Productivity =
Output Input
F pc
Q=
Fm Fb cb c m
ES = max (EF times of all activities immediately preceding activity) EF = ES + t LS = LF t LF = min (LS times of all activities immediately following activity)
2. Activity slack:
S = LS ES or S = LF EF
3. Project costs:
te =
2 =
5. z-transformation formula:
(Variance)
z= where
T TE
T = due date for the project TE = (expected activity times on the critical path) = mean of normal distribution
1.
Mean: x =
x
i =1
2.
=
3.
(x
x)
n 1
or
( x )2 n i
n 1
b.
x =
4.
p =
b.
p (1 p ) n
5.
6.
Utilization, expressed as a percent: Utilization = Average output rate 100% Maximum capacity
2.
b.
{ [ Dp + ( D Q)s]
M=
product 1
+ [ Dp + D Q) s ]product 2
( T ) n T e n!
2.
SINGLE-SERVER MODEL
MULTIPLE-SERVER MODEL
FINITE-SOURCE MODEL
s
0<n<s ns
= 1 P0
Pn = (1 ) n
( ) n P0 n! Pn = n ( ) P 0 s! s n s
P0 = 1
s 1 ( ) n ( ) s + P0 = s! n = 0 n!
1 1
n N N! P0 = n = 0 ( N n )!
L=
L = W
L=N
(1 P0 )
L q = L
P0 ( ) s Lq = s!(1 ) 2
Lq = N
+ (1 P0 )
W=
W = Wq +
W = L[( N L ) ]
Wq = W
Wq =
Lq
Wq = Lq [( N L) ]
3.
4.
Theoretical minimum number of workstations: TM = Idle time (in seconds): nc t Efficiency (%):
t (100) nc
5.
6.
7.
Number of containers:
Average demand during lead time + Safety stock Number of units per container d ( + )(1 + ) = c
Weeks of supply =
Average aggregate inventory value Weekly sales (at cost) Annual sales (at cost) Average aggregate inventory value
2.
Inventory turnover =
Loaddistance score: ld = li d i
i
2.
Center of gravity: x
l x = l
i i i i
and
l y = l
i i i i
Cycle inventory =
Q 2
2.
Pipeline inventory = dL
Total annual cost = Annual holding cost + Annual ordering or setup cost
3.
C=
Q D ( H ) + (S ) 2 Q
4.
2 DS H
5.
6.
7.
Reorder point(R) = Average demand during the protection interval + Safety stock = dL + zL Protection interval = Lead time (L)
8.
2DS H
p pd
Total annual cost = Annual holding costs + Annual ordering or setup cost
C=
Q pd D ( H ) + (S ) 2 p Q
ELS D
Quantity discounts: Total annual cost = Annual holding cost + Annual setup cost + Annual cost of material
C= Q D ( H ) + ( S ) + PD 2 Q
3.
Ft +1 =
4.
Dt + Dt 1 + Dt 2 + " + Dt n +1 n
5.
Exponential smoothing:
Ft +1 = Dt + (1 ) Ft
6.
At = Dt + (1 )( At 1 + Tt 1 ) Tt = ( At At 1 ) + (1 )Tt 1 Ft +1 = At + Tt
7.
Forecast error:
=
MAD = MAPE =
8.
( E t E ) 2 n 1 Et n ( E t / Dt )(100%) n
9.
Projected on - hand On - hand MPS quantity Projected inventory at the end = inventory at the + due at the start requirements end of last week of this week this week of this week
2. Available to promise a. week 1
Available - to - On - hand Orders booked up MPS quantity promise in = quantity in + in week 1 to week S when the next MPS arrives week 1 week 1
b. week t
Available - to - Orders booked up MPS quantity promise in = in week t to week S when the next MPS arrives week t
Performance measures:
Job flow time = time of completion Time job was available for first processing operation Makespan = Time of completion of last job Starting time of first job Average WIP inventory = Sum of flow times Makespan Sum of time in system Average inventory = Makespan Total inventory = Scheduled receipts for all items + On-hand inventories of all items Productive work time Utilization = Total work time available
2.
Critical ratio:
CR =
3.
Slack per remaining operations: (Due date Today' s date) Total time remaining S RO = Number of operations remaining
10
CD-ROM SUPPLEMENTS
SUPPLEMENT G: Learning Curve Analysis
z 1. Required sample size in a time study: n = p t 2. Normal time for a work element: NT = t ( F )( RF ) 3. Normal time for the cycle: NTC = NT 4. Standard time: ST = NTC(1 + A)
AOQ =
p ( Pa )( N - n) N
F = P ( l + r )n
2. Present value of a future amount
P=
F (1+ r )n
P=
4. Straight-line depreciation
D= I S n
12