EIA Practice in India and Its Evaluation
EIA Practice in India and Its Evaluation
EIA Practice in India and Its Evaluation
SWOT analysis
Ritu Paliwal ⁎
Centre for Regulatory and Policy Research, TERI School of Advanced Studies, Habitat Centre,
Lodhi Road, Delhi-110003, India
Received 1 July 2005; received in revised form 1 December 2005; accepted 1 January 2006
Available online 6 March 2006
Abstract
In India Environmental Impact Assessment (EIA) has been formally introduced in 1994. It relied on the
institutional framework that has a strong supporting legislative, administrative and procedural set-up. Both
central and state authorities together are sharing the responsibility of its development and management. A
Strength, Weakness, Opportunity and Threat (SWOT) analysis taken up in this article has suggested that
there are several issues that need to be readdressed. It highlights several constraints, ranging from improper
screening and scoping guidelines to ineffective monitoring and post project evaluation. The opportunities
are realised as increasing public awareness, initiatives of environmental groups and business community
and forward thinking to integrate environmental consideration into plans and policies. Poor governance,
rapid economic reforms, and favours to small-scale units are some of the foreseen threats to the system.
This article concludes with some suggestions to improve EIA process in India.
© 2006 Elsevier Inc. All rights reserved.
1. Introduction
The concept of environmental protection and resource management has traditionally been
given due emphasis and woven in all facets of life in India. These age-old practices teach people
to live in perfect harmony with nature. Nevertheless, changing life styles, increasing pace of
urbanization, industrialization and infrastructure development have caused environmental
pollution and degradation (Chopra et al., 1993). The losses manifest as pollution in air, water
and land leading to biodiversity losses and potential health hazards.
Consequently, rules, laws and policies on environmental protection were introduced. One such
effort, i.e., the Environmental Impact Assessment (EIA), particularly aims to optimise a trade-off
between developmental activities and socio-ecological losses. It is a management tool to be linked
closely to the project life cycle to ensure that appropriate environmental information is provided at
the correct time (Wood, 1995). The overall objective of the EIA is to design developmental
projects and activities taking into consideration the environmental perspective.
In India, the first EIA was ordered, during early 1980s, on the Silent river valley hydroelectric
project, which was a controversial project (Valappil et al., 1994; MoEF, 2003a). This project, proposed
by the Kerala State Electricity Board (KSEB) to build a 130 m high dam across the Kuntipuzha river
and a reservoir,1 was considered a big threat to the biodiversity and forest ecosystem of the Silent
valley. Later in 1985, the project was abandoned and Silent Valley was declared as a national park. This
case marked a new beginning in India and since then, EIAwas extended to other activities. Projects like
mining, industries, hydroelectric plants, thermal power plants, atomic power plants, ports and harbours,
rail, roads, highways, bridges, airports and communication project, required EIA if:
However, EIA was introduced in 1994, when MoEF passed an EIA notification under Envi-
ronmental Protection Act (EPA), 1986, which made EIA mandatory for 29 highly polluting
activities and later on three more activities were added to this list (Appendix A) (MoEF, 1994;
MoEF, 2004). Over the years, the system has undergone several amendments to improve the
environmental clearance (EC) process and to make it an integral component of decision-making.
This paper will add knowledge about the EIA process in India. It describes the current
statutory, administrative and procedural arrangements for EIA in India. To highlight the systems
constraints, future potentials and challenges a SWOT (strength, weakness, opportunity and threat)
analysis has been taken up in this work. The SWOT is based on authors' own experiences during
field visits, professional's views (i.e., government officials, consultants and managers) revealed
during informal talks, and semi structured interviews and available literature on the subject. The
SWOT suggests that there is a huge possibility to improve the system but the strong legal
framework is a positive and supportive feature. Opportunities and threats discussed are relevant in
the present context and should be given due consideration while thinking on making EIA more
accessible. At present there are many efforts going to improve the environmental appraisal
process and compliance by MoEF. This paper concludes with some contemplation on the
potential steps considered necessary to improve the effectiveness of the EIA process. These
suggestions are not only felt significant for Indian system but may also prove helpful for other
developing countries those are undergoing similar developments.
2. Institutional arrangements
The EIA process is now well established and EC is provided to over 1500 development
projects (Table 1). It rests on three pillars of statutory, administrative and procedural frameworks.
1
http://envfor.nic.in/divisions/ic/wssd/doc3/chapter18/css/Chapter18.htm.
Table 1
Status of EIAs cleared in different sectors since 1994
River valley projects Industrial projects Thermal power projects Mining projects a Other sectors b Total
1994 8 20 15 13 + 24 24 104
1995 13 55 13 19 + 51 29 180
1996 6 54 26 39 + 15 30 170
1997 4 98 39 7 + 17 21 186
1998 9 34 17 9 11 80
1999 5 45 17 25 12 104
2000 5 52 15 17 36 125
2001 12 63 14 9 23 121
2002 12 83 7 31 25 158
2003 16 220 5 19 55 315
Total 1543
Source: MoEF, Annual reports (1994–2004).
a
Environmental clearance + site clearance.
b
Include transport, ports, harbours, airports, highways and communication projects.
2
The NCEPC were to deal with complex environmental degradation issues and review of environmental implications
of developmental activities was a part of its responsibilities (Valappil et al., 1994).
2.2. Administrative framework
The existing EC process is a two-tier system involving both central and state authorities (Fig. 1).
At central level, Impact Assessment division (IA) under MoEF, regional offices of MoEF and
Central Pollution Control Board (CPCB) are three important institutions, whereas SPCBs and state
Departments of Environment (DoE) are working at the province level.
2.2.1. Role of IA
IA, in consent with relevant state and central authorities, is responsible for setting guidelines
for the preparation of the EIA reports, questionnaires and checklists for major sectors (MoEF,
2003b). It prepares and issues various notifications and amendments pertaining environmental
laws. IA has constituted six multi-disciplinary expert committees known as Environmental
Appraisal Committee (EAC), as specified in the EIA Notification (Appendix B), to carryout
review for the mining, industries, thermal power plant, river valley and hydro-electricity project,
nuclear power plant, infrastructure and miscellaneous activities.
The appraisal process of EC, involving review of the EIA report and various documents
submitted by the project proponent, is the leading responsibility of IA. IA may also seek
clarification from the proponent and conduct site visits if it feels necessary during the review
procedure. Based on the documents submitted and clarification presented IA either grants or
rejects the environment clearance of the developmental project. This division also carries out
follow-ups of the litigation in the various courts regarding EC decisions, notifications and
amendments issued.
State Government
3
Regional offices and area of work: Banglore—Karnataka, Andhra Pradesh and Goa; Bhopal—Madhya Pradesh,
Chattisgarh, Maharashtra, Gujarat, Dadar and Nager Haveli, Daman and Diu; Bubaneshwar—Orrisa, Andaman and
Nicobar Islands, Bihar, Jharkhand and West Bengal; Lucknow—Uttar Pradesh, Uttaranchal and Rajasthan; Shilong—
Arunachal Pradesh, Assam, Manipur, Meghalaya, Tripura, Nagaland, Mizoram and Sikkim. (Regional Office (Upper East
or Eastern Plateau) Yet to be made functional at Ranchi).
2.3. Procedural framework
The whole process of environmental clearance involves many ministries and departments
(Fig. 2). The process starts when project proponent applies for NOC to respective SPCBs or other
local authorities (i.e., Delhi Pollution Control Committee in Delhi). Site clearance is required for
some of the activities i.e., mining, prospecting and exploration of major minerals, pithead thermal
power plants, multipurpose river valley projects and major ports and harbours. Consents from
airport authority and state forest departments are also considered necessary if any airport is
nearby and project involving any forestland respectively. Once the project proponent receives all
the approvals, he submits an application to MoEF for environmental clearance.
Application to SPCB for NOC Site clearance from NOC from State Forest Department /
(under Air and Water Act) MoEF (if required) Airport Authority (if required)
No No No
Yes Yes
Yes
No Is project
accepted?
Yes
2.3.1.1. Screening. Screening determines whether EIA is required or not. In India, 32 activities
listed in schedule I (Appendix A), any project in ecologically fragile areas4 and any project falling
under coastal zone regulation, requires an EIA (MoEF, 1989a,b, 1991a,b, 1992, 2001a, 2004).
The investment clause has also been formulated to streamline screening process. It specifies that
new projects with investment more than 100 crores and modernisation projects involving
investment more than 50 crores require EIA. This clause is not applicable to industries involving
hazardous chemical processes (see Appendix A).
2.3.1.2. Scoping. Scoping identifies the concerns and issues to be addressed for a particular project.
MoEF has set guidelines and review checklists for relevant issues for different project types (MoEF,
2001b) and provides general questionnaires for all the sectors. Study of alternatives and public
hearings are undertaken at this stage only. Alternate scenario must account for no project condition
along with project scenario employing best-suited technology or processes (MoEF, 2001b).
2.3.1.4. Impact prediction. Once collecting the relevant environmental information, con-
sequences of the project are outlined. The prediction analysis should forecast the nature and
significance of the expected impacts, or explain why no significant impacts are anticipated. Several
mathematical models are listed in the manual of MoEF for environmental and socio-ecological
impacts predictions. Suggestions have also been made on the kind of conditions where they could
be used. Socio-economic and ecological impacts are essential to be covered in this analysis.
2.3.1.5. Impact mitigation measures. In an EIA, mitigation measures are proposed to avoid
or reduce environmental and social impacts. Environmental Management Plan (EMP), risk
assessment report and disaster management plan (if hazardous substances are involved in the
project), rehabilitation plan (if displacement of people is anticipated) are prepared to suggest
remedial measures. EMP in particular should entail following aspects (MoEF, 2001b).
• Pollution prevention
• Waste minimization
4
Doon Valley (Uttar Pradesh); Murud Janjira, Dahanu Taluka and Mahabaleshwar Panchgani (Maharastra); Aravalli
ranges in Gurgaon (Haryana) and Alwar (Rajasthan).
• End-of-pipe treatment
• Mitigation measures
• Protection of the sensitive receptors
In addition to this EMP must be supplied with the work plan, time schedule, place and cost of
implementing the mentioned measures.
2.3.1.6. Documentation. At the end of all the above-mentioned steps, a concise but
comprehensive report is prepared. It summarises the description of the project, regional settings,
baseline conditions, impact prediction and important findings of the study. Project proponents hire
consultants to carry out the EIA and preparation of report for them.
2.3.1.7. Public hearing. The Indian system provides an opportunity to involve affected people
and vulnerable groups to develop terms of references for EIA thus incorporating their concerns
into decision-making process. The SPCB is required to publish notices for public hearing in two
local newspapers and one of which should be in vernacular language of the concerned locality
(MoEF, 1994). The date, time and place of the hearing should be mentioned in the notice. EIA
notification also makes provision for access to the executive summary of the project at the offices
of district collector, district industry centre, commissioner of the municipal corporation/local
body, SPCB and state DoE (MoEF, 1994). The composition of the public hearing panel has also
been specified by the law, which may consist of members of local authorities and representatives
of the public nominated by the district collector.
2.3.1.8. Review and decision-making. The review and decision-making starts as the proponent
files an application accompanied by the documents i.e., EIA and EMP report, NOC, risk
assessment and emergency preparedness plan, rehabilitation plan, details of public hearing,
clearance from airport authority and state forest departments, etc., to IA. The IA reviews the report
with reference to the guidelines provided by MoEF in its manual (MoEF, 2001b). The IA is free to
conduct site visits if considers necessary. Based on the EIA review and other information, the IA
either grants or rejects the environment clearance to the project. The assessment has to be
completed within a period of 90 days from the receipt of the requisite documents from the project
authorities and completion of public hearing. The decision has to be conveyed to the proponent
within 30 days thereafter.
2.3.1.9. Post Project Monitoring (PPM). The PPM aims to ensure that an action had been
implemented in accordance with the measures specified while providing the EC. Thus, it performs
a dual task of identifying the actual environmental impacts of the project and checks if the EMP is
having the desired mitigation measures. Post-implementation monitoring is the responsibility of
MoEF's six regional offices and SPCBs.
3.1. Strengths
Strength identifies resources and capabilities of the EIA system, which may aid to develop
the system further. It shows that there are huge possibilities to improve the system but strong
legal framework is a positive and supportive feature. The strength of Indian system also lies in
existence of regulatory authorities to execute the law all over the country.
3.2. Weaknesses
Present EIA practice in India is restricted to project level, which also has several weaknesses. It
is perceived merely as a bureaucratic requirement limited to selection of project or pollution
control technology (Lohani et al., 1997; Rao, 1997).
3.2.1. Screening and scoping processes are not well defined
The screening process is based on list of 32 projects listed in schedule-I of EIA notification,
amount of investment and sensitive zones, as discussed in Section 2.3, not on level of impact,
types and complexities of pollutants, size of project or raw material and technology used, etc., as
considered in China (Chen et al., 1999; Wang et al., 2003). Screening guidelines in India do not
specify if rapid EIA could be conducted (TERI, 2002). Scoping on the other hand is left on project
proponents who most of the time are not interested in considering diverse impacts. For instance,
in industrial estate of Haldia, most of the industrial projects never tried to estimate the impacts of
their effluents on the ground water and nearby flowing river streams. All of them got rid of it by
saying that impact of their loadings would be negligible when compared with the quantum of flow
in the river Hoogly. Analysis of alternatives is also a weak link in EIA. Most of the time it is
restricted to ‘with project’ and ‘without project’ scenarios (World Bank, 1999). Site clearance
happens much before environmental clearance process because of which comparative assessment
of sites is also not given due consideration.
3.3. Opportunities
With more education and awareness, people are becoming environment conscious. Change in
income levels, demand for personal comfort and socially responsible behaviour of industrial units
would open up opportunities to improve the implementation of laws and policies.
3.4. Threats
Several advantages and opportunities have been realized in EIA system, yet certain threats exist,
which are mentioned below.
For the purposeful implementation of EIA regulation, the ministry is rethinking on its
commitment by updating policy guidelines, simplifying the procedural aspects and placing
measures to strengthen the role of regulatory agencies. This effort also requires better monitoring
support and availability of environmental expertise. On understanding the weaknesses and
challenges in the Indian system, there are certain suggestions for improvements in the Indian EIA
practice to facilitate greater rigour in analysis, appraisal, monitoring and enforcement to achieve
broader objective of protecting the environment.5
One of uncertainties in the EIA prediction is due to lack of reliable and accurate data.
Therefore, it is suggested to organize a common database exclusively where all relevant agencies
may pool in the data and this data could be made available to the project proponents on request.
This data may be charged and money collected from this source may be utilized in upgrading the
data bank.
The EMPs should clearly suggest mitigation, monitoring and institutional measures to
eliminate, compensate, or reduce impacts to acceptable levels during construction as well as
operation phase of an activity. Implementation of EMP must ensure effectiveness of mitigation
measures and also detect the need for any corrective action. Continuous monitoring and
assessment of the system, public participation and simplified administrative procedures are
obligatory to facilitate the adequate implementation. Good environmental monitoring practices
not only establish a baseline data of the region but also increase understanding of cause–effect
relationship between an activity and environmental changes and checks accuracy of an EIA
prediction, thereby increasing knowledge base for better EIA of the future projects.
Concept of industrial estate should be promoted for SSIs. Grouping of these units in an
industrial estate should be done considering regional aspects such as carrying capacity, optimal
utilization of natural resources, utilization of waste from one unit as resource to another and
establishment of common waste treatment plants (Singhal and Kapoor, 2002).
5
Policymaker may look at the problem differently, considering “improvement” in terms of enhancements in realization
of multiple objectives, e.g., reducing adverse environmental impacts, reducing costs of implementation of mitigation
measures, reduction in transactions costs (and time), promoting economic and social development; while adhering to
various constraints, including administrative capacities, availability of necessary disciplinary expertise, legal limits on
time allowed, etc., as suggested by one of the reviewers.
4.5. Integrate environmental concerns into plans and policies
There is a need to improve the role of local planning agencies in the EIA process. To
incorporate environmental concerns into plans and policies, Mc Donald and Brown (1995)
have illustrated certain ways: (i) Local strategic plans—determining the form of future
developments that can take place in an area taking cumulative impacts and carrying capacity
in account; (ii) Zoning schemes—addressing specific landuse patterns, permitted and
prohibited in the area, as set out in local plan; (iii) Sub-divisional plans—setting layouts of
future settlement pattern while conserving natural areas such as watercourse, riparian habitats,
agricultural land, etc.
It is very essential to spot major stakeholders involved in EIA system. While preparing the
technical and procedural guidance material needs of all the stakeholders should be considered to
indicate the roles and duties of each of them. Effective public involvement in the process brings
forth wide range of social, cultural and emotional concerns, to establish terms of reference of
scoping, which may be deemed out side the scope of EIA. It would make decision socially
acceptable. In addition, it is necessary to sensitise, inform and train stakes to make them
understand the significance of EIA process. Capacity building of regulatory agencies in terms of
staff, technical expertise and monitoring facilities is also recommended. Making inter
organization coordination more smooth would facilitate information sharing process. It is also
required to develop disciplinary expertise to mainstream the cumulative impact assessment and
SEA at plan and policy levels.
5. Conclusion
It has been recognised that India is well verse with apt legal provisions, which are very
essential for further strengthening of the EIA process. Moreover, EIA process possesses a basic
structure, including screening, scoping, comprehensive study, progress report, review, public
participation, decision and follow-up measures.
To address the critical issues political commitment and public participation is indispensable.
Improved effectiveness will also depend on strength of government agency coordination,
integrated decision-making adequate training to various stakeholders and supporting infrastruc-
ture for purposeful monitoring and enforcement. It is required that EIA system be regularly
revisited for progressive refinement that should not only remove existing constraints but also take
care of future challenges.
It is further recommended that project level EIA needs immediate attention but efforts should
also be targeted to include environmental conservation concerns at policy and planning level.
Such initiatives would help in filling up the gaps in coordination between various government
authorities involved in planning and execution.
Acknowledgement
This research is part of an ongoing Ph.D. work at Centre for Regulatory & Policy Research,
TERI—School of Advanced Studies (TERI SAS), New Delhi and is supported by University
Grants Commission (UGC), India under Junior/Senior Research Fellowship Program. I would
like to thank Dr. Leena Srivastava, Supervisor and Dean, Centre for Regulatory and Policy
Research and Dr. Soan Ray, Co-supervisor and Lecturer, Department of Policy Research, TERI
SAS for their helpful comments and discussion during the preparation of this paper. I also
benefited from working on the project ‘Preparation of an AEQM (Area-wide Environmental
Quality Management) Plan for Haldia Planning Area’ and would like to thank Dr. T.S. Panwar,
Senior Fellow, Centre for Environmental Studies, Policy Analysis Division, The Energy and
Resources Institute (TERI), Delhi, for the opportunity. I also acknowledge the reviewers for their
valuable inputs.
1. Nuclear power and related projects such as heavy water plants, nuclear fuel complex, rare
earths.⁎
2. River valley projects including hydel power, major irrigation and their combination
including flood control (even if investment is less than 100 crores but command area is
more than 10,000 ha).⁎
3. Ports, harbours and airports (except minor ports and harbours).⁎
4. Petroleum refineries including crude and product pipelines.⁎
5. Chemical fertilizers (nitrogenous and phosphatic other than single super phosphate).⁎
6. Pesticides (technical) and intermediates.
7. Petrochemical complexes (both Olefinic and Aromatic) and petro-chemical intermediates
such as DMT, Caprolactam, LAB, etc., and production of basic plastics such as LLDPE,
HDPE, PP, PVC.
8. Bulk drugs and pharmaceuticals and intermediates.
9. Exploration for oil and gas and their production, transportation and storage.⁎
10. Synthetic rubber.⁎
11. Asbestos and asbestos products.
12. Hydrocyanic acid and its derivatives.
13. (a) Primary metallurgical industries (such as production of Iron and Steel, Aluminium,
Copper, Zinc, Lead and Ferro Alloys), (b) Electric arc furnaces (Mini steel plants).⁎
14. Chlor alkali industry.
15. Integrated paint complex including manufacture of resins and basic raw materials required
in the manufacture of paints.
16. Viscose staple fibre and filament yarn.⁎
17. Storage batteries integrated with manufacture of oxides of Lead and Lead Antimony alloys.⁎
18. All tourism projects between 200 m and 500 m of high water line and at locations with an
elevation of more than 1000 m with investment of more than Rs. 5 crores.
19. Thermal power plants.⁎
20. Mining projects (major minerals) with leases more than 5 ha.
21. Highway projects (except projects relating to improvement work including widening and
strengthening of roads with marginal land acquisition along the existing alignments
provided it does not pass through ecologically sensitive areas such as national parks,
sanctuaries, tiger reserves and reserve forests).⁎
22. Tarred roads in the Himalayas and or forest areas.
23. Distilleries.
24. Raw skins and hides
25. Pulp, paper and newsprint.⁎
26. Dyes and intermediates.
27. Cement.⁎
28. Foundries (individual).
29. Electroplating.
30. Meta amino phenol (added in 2000).
31. New townships, industrial townships, settlement colonies, commercial complexes, hotel
complexes, hospitals, office complexes for 1000 persons and above or discharging sewage
of 50,000 l/day and above or with an investment of Rs. 50 crores and above (added in
2004).
32. New industrial estates having an area of 50 ha and above and the industrial estates
irrespective of area if their pollution potential is high (added in 2004).
References
Author is a Ph.D. candidate at the Centre for Regulatory and Policy Research, TERI School of Advanced Studies, New
Delhi under the supervision of Dr. Leena Srivastava, Dean, Centre for Regulatory & Policy Research, TERI School of
Advanced Studies. Her area of research is ‘Adequacy of environmental impact assessment procedure in India and
challenges to effective implementation of environment management plan’. She had done her Masters in ‘Environment
Management’ from Guru Gobind Singh Indraprastha University, New Delhi.