Chapter 7 Executive Summaryy
Chapter 7 Executive Summaryy
EXECUTIVE SUMMARY
Parameter
Guideword
Possible Causes 1. Material fouling in the pipe or mixer. Pipe leakage. Pump failure. Final element (valve) malfunction.
Possible Consequences 1. Different reaction will occur; the single raw material will undergo undesired reaction at such pressure and temperature. The product of the undesired reaction will contaminate the production line and impose problems such as corrosion to other subsystems. Loss of profit.
Action Required 1. 2. 3. 4. Pipe cleaning (pigging). Pipe leak testing and maintenance. Pump maintenance. Valve testing and maintenance.
Safeguard 1. Install auxiliary system for pump and final element in the flow control system. Install alarm system for no flow detection.
NO FLOW
2. 3. 4.
2.
2.
3.
OVERFLOW
1. 2. 3.
Faulty control system. Unresponsive pump. Final element (control valve) malfunction.
1. 2. 3.
Unbalanced reaction in the reactor. Excessive raw material contaminates the product. Pipe rupture or overfilled reactor.
1.
2.
1.
2.
Install auxiliary system for pump and final element in the flow control system. Install level control system in the reactor.
Reaction Temperature
HIGH
1. 2. 3. 4.
Uncontrolled heating. Unresponsive heating system. Unresponsive cooling system. Scaling of carbonates on the reactor wall surface.
1. 2. 3.
Undesired reactions producing unwanted products. Product contamination and quality deterioration. Rupture of reactor due to overpressure.
1. 2. 3.
Reduce heating of the reactor. Increase rate of cooling of reactor. Reduce reactor pressure by opening the pressure relief valve.
1. 2. 3.
Install cooling system. Install pressure control system. Install pressure relief valve.
1. 2.
1.
2.
1. 2.
Set inlet control valve to fail open. Set outlet control valve to fail close.
1. 2. 3.
Reactor cools, reactant concentration builds. Amount of unreacted material increases. Loss of production time.
1.
1.
Install auxiliary system for final element in the flow control system.
1. 2. LOW
1. 2. 3.
In the event of overheating, cooling is insufficient. Overheating of reactor causes overpressure. Overpressure can cause reactor rupture.
1.
1.
Guideword NO FLOW
Possible Causes
Possible Consequences 1. 2. 3. No heat transfer activities occurs Desired temperature is not achieved Process line will be interrupted especially reaction section.
Action Required
Safeguard
1. 2. 3. 4.
Material fouling in the pipe or mixer. Pipe leakage. Pump failure. Final element (valve) malfunction
1. 2.
3. 4.
Pipe cleaning (pigging). Pipe leak testing and maintenance. Pump maintenance. Valve testing and maintenance.
1.
Install auxiliary system for final element in the flow control system.
Feed Flow
HIGH FLOW
1.
1.
1.
1. 2.
Install auxiliary system for final element in the flow control system.
Install check valve or butterfly valve to achieve directional flow.
Feed Flow
REVERSE FLOW
1. 2.
1. 2.
Difficult to control the temperature flowing out Cooling is not effective for next equipment.
1.
1.
Feed Flow
LOW FLOW
1. 2. 3. 4.
Material fouling in the pipe or mixer. Pipe leakage. Unresponsive pump. Final element (valve) malfunction
1. 2.
Desired temperature is not achieved Process line will be interrupted especially reaction section.
1. 2.
3. 4.
Pipe cleaning (pigging). Pipe leak testing and maintenance. Pump maintenance. Valve testing and maintenance.
1.
Install auxiliary system for final element in the flow control system.
Pressure
HIGH PRESSURE
1. 2.
1. 2.
1. 2.
3.
Pressure
LOW PRESSURE
1. 2.
1. 2. 3.
1.
2.
Deviation MORE
Possible Causes 1. 2. 3. Excessive heat from hot stream. Increased flow rate of hot stream. Reduced flow rate of cold stream.
Possible Consequences 1. 2. 3. Pressure will increase Explosion will occur Failure of other equipment
Action Require 1. 2. 3. Increase cold stream flow rate. Reduce hot stream flow rate. Check for obstruction/leaking at cold stream pipeline. 1. Install temperature/flow control system.
Temperature
LESS
1. 2. 3.
Excessive heat sink from cold stream. No/low flow of hot stream. High flow rate of cold stream.
1. 2.
1. 2.
Control cold and hot stream flow. Check for obstruction/leaking at hot stream pipeline.
1.
Possible Consequences 1. 2. 3. Excess flow to T-101: off specification products. Weeping, dumping and flooding could occur. Inefficient distillation process.
Feed Flow
LOW FLOW
1.
1. 2. 3.
1. 2.
1.
Feed Flow
NO FLOW
1. 2.
Unresponsive/failed control valve. Leaking in feed pipeline. Overflow or flooding in the column.
1. 2. 3. 1. 2.
Drop in liquid level in T-100. Temperature rise in T-100. Loss of production. Reduced efficiency of distillation process. Product contamination.
1. 2.
1. 2.
Install low flow/level alarm. Install Pressure relief valve Add check valve/butterfly valve for one directional flow.
Feed Flow
REVERSE FLOW
1.
1. 2.
1.
Temperature
HIGH
1. 2.
1. 2.
1. 2.
1.
Temperature
LOW
1. 2.
1.
1.
1.
Pressure
HIGH
1. 2. 3.
Loss of overhead condenser. Excessive heat input from reboiler. Reboiler tube leak or
1. 2. 3. 4.
Over pressuring of column. Change of temperature profile. Product quality and controllability are disturbed. Redundancy in control loop and
1. 2. 3.
1. 2.
Add high pressure alarm. Add additional independent high pressure indication and alarm to reflux drum.
4.
5.
3.
Pressure
LOW
1. 2. 3.
4.
Loss of heating medium. Low temperature feed. Overheads pressure controller fails control valve open. Excess overheads cooling.
1. 2. 3. 4. 5. 6.
Inefficient distillation. Deviation of temperature profile. Deviation in product specification. Contamination of product. Vacuuming inside column. Rupture of column.
1. 2. 3. 4.
Increase refluxed flow to column. Increase feed flow rate. Increase reboiler duty. Reduce condenser duty.
1. 2.
Install low pressure alarm. Install safety valve to stabilize pressure inside column.
HIGH
1. 2. 3.
Bottom outlet pump fails. Excess feed to column. Overheads on total reflux.
1. 2.
1.
2.
Check for pump malfunction, address the problem. Reduce feed and reflux flow rate.
3.
Sources 1) Flood
Response Plan Evacuate area with vehicles and move to higher altitude place.
Immediate action
Immediate action
Within a minute
1. Set off emergency siren/alarm to notify all personnel in plant vicinity. 2. Contact local fire and police department. 3. Control access to affected area. 4. Mitigate fire spread by engaging fireproof doors and firewall. 5. Smoke and toxic gases release from fire - notify personnel to put on oxygen masks. 1. Contain and collect liquid spill in a sump. 2. For vapor chemical release, sprinkler system is used to deactivate the vapor chemical by either using neutralization chemical or dissolution with water. 3. Remove contaminated clothing. 4. Skin contact need to be rinsed with water for 15 minutes. 5. If the situation is life threatening, announce for immediate evacuation of the area. 6. Emergency shutdown for all process equipment in the plant. 7. Announce to residents surrounding the plant area to stay indoors and ensure enclosed homes. 8. For denser than atmosphere vapor chemical release, move personnel to higher grounds. 9. For lighter than atmosphere vapor chemical release, move personnel to assembly point at lower grounds. 1. Announce for immediate evacuation.
Equipment 1) rupture/leak Facility failure 1) roof collapse 2) structure cracking 3) air pressure system Utility failure 1) gas 2) electricity 3) cooling water Product contamination 1) raw material 2) container 3) process equipment
Immediate action
1. Provide bleed line/ process bypass for the affected equipment. 2. If not available, shutdown all equipment in the same process line. 1. For roof collapse, ensure helmet is worn and evacuate the affected facility. If not possible, take cover under rigid materials such as desks for immediate cover, and then continue for evacuation. 2. For structure cracking, immediately evacuate the building. If not possible, take cover under rigid materials. 3. For air pressure system failure, set immediate evacuation alarm/siren. Disengage air pressure system from power source. 1. Immediate shutdown of all equipment under the affected utility. 2. Set evacuation alarm/siren. 3. Return for normal operation if the failure is resolved.
Immediate action
Immediate action
Immediate action
1. Stop raw material flow to container. 2. Stop material flow from container to process. 3. Cease/pause the production process at affected process equipment. 4. Resolve contamination problem.
Plant Layout:
Emergency Exit
Main Entrance