The following information relates to a production period: Product Volume Material Direct Machine Labour Cost Cost Per unit labour time Per unit (Rs.) Per unit Per unit A 500 5 1 /2 hour 1 /4 hour 3 B 5,000 5 1 /2 hour 1 / 4 hour 3 C 600 16 2 hours 1 hour 12 D 7,000 17 11/2 1- 1 / 2 hours 9 hours Total production overhead recovered by the cost accounting system is analyzed under the following headings: Factory overhead applicable to machine- oriented activity Set-up costs are Cost of ordering materials Handling materials 37,424 4,355 1,920 7,580 8,600
Administration for spare parts These overhead costs are absorbed by products on a machine hour rate of Rs. 4.80 pe hour giving an overhead cost per product of: A = Rs. 1.20 B = Rs. 1.20 C = Rs. 4.80 D = Rs. 7.20
However, investigation into the production overhead activities for the period reveals the following totals: Product Number of Number of Number of Number of set-ups material times material spare parts Orders was handled A 1 1 2 2 B 6 4 10 5 C 2 1 3 1 D 8 4 12 4 You are required: a) To compute an overhead cost per product using Activity Based Costing, tracing overheads to production units to means of cost drivers. b) To comment briefly on the differences disclosed between overheads traced by the present system and those traced by Activity Based Costing. Q2)Having attended a CIMA course on Activity Based Costing (ABC) you decide to experiment by applying the principles of ABC to the four products currently made and sold be your company. Details of the four products and relevant information are given below for one period: Product A B C D Output in units 120 100 80 120 Cost per unit Rs. Rs. Rs. Rs.
Direct material 40 50 30 60 Direct labour 28 21 14 21 Machine hours (per unit) 4 3 2 3 The four products are similar and are usually produced in production runs of 20 units and sold in batches of 10 units. The production overhead is currently absorbed by using a machine hour rate, and the total of the production overhead for the period has been analyzed as follows: Machine departments costs (rent, business, rates, depreciation and supervision) Set up costs Stores receiving Inspection / Quality control Materials handling and despatch 10,430 5,250 3,600 2,100 4,620
You have ascertained that the cost drivers to be used are as listed below for the overhead costs shown: Cost Cost Driver Set up costs Number of production runs Stores receiving Requisitions raised Inspection / Quality control Number of production runs Materials handling and dispatch Orders executed The number of requisitions raised on the stores was 20 for each product and the number of orders executed was 42, each order being for a batch of 10 of a product. You are required: a) To calculate the total costs for each product if all overhead costs are absorbed on a machine hour basis; b) To calculate the total costs for each product, using activity based costing; c) To calculate and list the unit product costs from your figures in (a) and (b) above, to show the differences and to comment briefly on any conclusions which may be drawn which could have pricing and profit implications.