Precast Concrete Frames Guide
Precast Concrete Frames Guide
Precast Concrete Frames Guide
Precast Concrete
Frames Guide
September 2003
Contents
Foreword
3 4 4 6 6 7 7 7 8 9 9 9 10 11 12 13 14 16 16 17 18 18 18 19 19 19 19 20 20 21 21 22 22 23 24 24 25 25 26 26 26 27 28 28 29 29 29 30 30 31 32 32 1
Overview
1.1 Introduction 1.2 Benefits of Precast Structures 1.3 Health &Safety 1.4 Quality &Accuracy 1.5 Speed of Construction & Buildability 1.6 Choosing a Construction Method - Comparative Costs 1.7 Sustainability 1.8 Thermal Capacity 2.1 Forms of Contract - Selecting a Contractual Route 2.2 Traditional Approach to Procurement 2.3 Nominated Sub-contract - Early nomination 2.4 Precast Contruction Cycle 2.5 Design Statement
3.1 Design Parameters - Maximising Cost Benefit 3.2 Single Storey - Industrial Frames 3.3 Multi-Storey - Column &Beam 3.4 Cross Wall Construction 3.5 Precast Car Park Frame & Deck 3.6 Mixed Construction
4.1 Design Approach 4.2 Designing for Horizontal Loads 4.3 Structural Integrity - Design for Accidental Loading 4.3.1 Progressive Collapse & Stability Ties 4.4 Joints & Connections 4.5 Column to Foundation Fixing Detail 4.5.1 Projecting Starter-Bars 4.5.2 In Situ Pocket Foundation 4.5.3 Bolted or Baseplate Connections 5.1 Columns 5.2 Beams 5.3 Beam Column Connections 5.4 Precast Floors 5.4.1 Selecting a Precast Floor System 5.4.2 Hollowcore Floor 5.4.3 SolidWideslab Floors 5.4.4 Double-Tee FloorSlabs 5.5 Precast Floors with Composite Toppings 5.6 Checking Calculations 5.7 Precast Stairs 5.8 Precast Balconies 5.9 Architectural Cladding Panels 5.10 Architectural Wall Panels - Rain Screens 5.11 Architectural Composite Panels 6.1 Development of Component Drawings 6.2 Production Scheduling 6.3 Materials 6.4 Moulds 6.5 Production Techniques 6.6 Curing 6.7 Quality 6.8 Handling &Storage
Precast Elements
Production
Site Erection
Contents
33 33 33 33 34 35 36 37 37 38 39 39 40 40 41 41 42 42 43 43 44 44 45 45 46 46 47 47 48 48 49 49 50 50 51 51 52
7.1 MethodStatement 7.2 Columns 7.3 Beams 7.4 Construction Speed 7.5 Access &Cranage
DETAIL 11: Typical End Bearing Detail: Rectangular Edge Beam DETAIL 12: Typical Side Bearing Detail: L-Shaped Beam DETAIL 13: Typical End Bearing Detail: L-Shaped Beam DETAIL 14: Typical 5 Storey+ End Bearing Detail: L-Shaped Beam DETAIL 15: Typical End Bearing Detail: Inverted T-Shaped Spine Beam DETAIL 16: Typical 5 Storey+ End Bearing Detail: Inverted T-Shaped Spine Beam DETAIL 17: Typical End Bearing Detail: Inverted T-Shaped Spine Beam DETAIL 18: Typical Side & End Bearing Detail: Rectangular Edge Beam
DETAIL 19: Typical End Bearing Detail: External Wall DETAIL 20: Typical 5 Storey+ End Bearing Detail: External Wall DETAIL 21: Typical Side Bearing Detail: External Wall DETAIL 22: Typical 5 Storey+ Side Bearing Detail: External Wall DETAIL 23: Typical End Bearing Detail: Internal Wall DETAIL 24: Typical 5 Storey+ End Bearing Detail: Internal Wall DETAIL 25: Typical Side Bearing Detail: External Wall DETAIL 26: Typical 5 Storey+ Side Bearing Detail: External Wall DETAIL 27: Typical End Bearing Detail: External Wall DETAIL 28: Typical 5 Storey+ End Bearing Detail: External Wall DETAIL 29: Typical End Bearing Detail: Internal Wall DETAIL 30: Typical 5 Storey+ End Bearing Detail: Internal Wall
Members List
Note
The IPCA and its members who produced this guide have endeavoured to ensure the accuracy of its contents. However, the guidance and recommendations given should always be reviewed by those using the guide in the light of the facts of their particular case and specialist advice obtained as necessary. No liability for negligence or otherwise in relation to this guide and its contents is accepted by the members of the IPCA, or its servants or agents. Produced by Brian Murch
Dip Arch. Tech
Irish Precast Concrete Association Unit 8, Newlands Business Park, Clondalkin, Dublin 22. Tel: +353 1 464 0082 Fax: +353 1 464 0087 email: [email protected] Web: www.irishconcrete.ie
Foreword
This publication is an introduction to precast concrete frames, their components, design and the principal considerations relative to their use and specification. Produced by the Irish Precast Concrete Association, it is the first Frames Guide of its kind which deals specifically with the range of products available on the Irish market. One of the key objectives of the publication is to improve the understanding of precast as a construction method. There has been a significant shift in recent years towards prefabricated methods of construction. This shift is changing construction practice and is encouraging construction professionals to take a fresh look at the benefits of precast. It is envisaged that the new Precast Frames Guide will provide a source of reference for Irish professionals and educators who are involved in this process. Educating the current and next generation of young professionals in the correct use and appreciation of precast construction is one of the primary objectives of the IPCA Precast Frames Guide. Concrete has considerable advantages as a construction material, including inherent fireproofing, sound and durability characteristics. The full potential of concrete is realised by precast which delivers high quality product produced in a controlled, safe environment free from weather restrictions. Irish precast companies employ a staff of highly trained engineers who are experts in precast techniques. When introduced to the design process at an early stage, these specialists can often make significant cost savings by proposing a range of efficiencies, particularly in the standardisation of construction components and in the efficient scheduling of the construction programme. The value of this expert resource has yet to be fully realised and it is hoped that this guide will promote greater liaison between the precaster and the design team.
Safecast
IPCA members are Safecast producers. Member companies work to high standards in relation to Health & Safety, Planning and Environment and Archaeological guidelines which are subject to ongoing assessment by the Irish Concrete Federation. Raw materials are sourced from quarries which have the relevant planning requirements and are used in accordance with best practice and in an environmentally conscious manner.
Overview
1.1 Introduction
Precast concrete framed construction is well established as one of the principal construction methods in Europe. In Ireland, the precast industry has built a close working relationship with developers, offering practical advice and a range of technical services at design and construction stages. Precast manufacturers have a critical role to play in the proper planning and execution of precast buildings. Involving the precaster at the early design stage is the best way to achieve the most economical building solution. Early involvement also allows the manufacturer to schedule production so as to maximise cost savings brought about by the use of standardised components and early completion. Precast concrete buildings previously had an identifiable appearance. However, with advances in technology and technique, precast buildings are now indistinguishable from those constructed using non-precast methods. Designers no longer work within tight constraints. Increasingly, the situation is that precasters are able to accommodate greater variety and complexity, effectively designing their elements to meet design requirements. Continuous investment and innovations have transformed the precast industry so that complex plan layouts and external treatments can now be accommodated. Organic designs can be achieved using standardised precast components. The use of standardised components does not imply a modular appearance. Nowadays, precast elements, including floors, stairs and wall panels combine seamlessly with non-precast elements to produce free-flowing spaces. Curved precast panels with a variety of highly attractive and durable finishes can be manufactured to meet the most challenging design requirements. Precast concrete can now be incorporated in every building type. Whether the building has a regular or an irregular shape, the entire structure or elements of that structure, such as frame, floors, walls, stairs or balconies, can all be precast. Precast construction is virtually unlimited in its application and is suitable for single and multi-storey construction. Offices and hotels are commonly constructed in precast, as are hospitals, schools, industrial units and multi-storey car parks, apartments and housing. In fact, precast building elements should be considered as an option on every construction project. The most common error is to take an all precast or no precast approach to design. In fact, a key issue for designers is to identify which construction method, or mix of construction methods and materials is most appropriate for the specific requirements of the building. The most economical solution might well consist of a mix of cast in situ and factory assembled units. Preliminary structural investigation may identify solutions such as beams and floor slabs fabricated off site being erected on cast in situ columns. These structural elements are then integrated as a composite structure when the floor screed is poured. The proper investigation of construction options at the early design stage is critical to optimising structural performance and delivering the most economical building package.
The considerable advantages of precast construction are combined with the inherent benefits of concrete to provide a superior construction product. These include:
Inherent
Fire Properties - Concrete has its own inbuilt fire resistance which is present during all construction phases. Fire resistance is typically achieved without the application of additional sprays or linings. This is an important inherent advantage over steel and timber solutions. Precast frames are generally 4
Overview
designed for one hour inbuilt fire rating. This either totally eliminates or greatly reduces the need for additional fire protection and the associated costs.
Economies
are generated through reduced requirements for formwork, access scaffolding and less reliance on wet trades. Reduced on-site supervision by the main contractor is also a saving. Compared to cast in situ concrete, the following savings can be expected: Formwork 75% less Scaffolding 75% to 90% less Wet Concrete 90% less
Health
& Safety - Once precast floor slabs are installed, they provide a safe working platform for site operatives. Simultaneously installing precast stairs offers safe and easy access between floors.
Reduced
Construction Programme, due to speed of construction, gives earlier return on investment, freeing up the project critical path and allowing earlier completion. It is estimated that a precast structure takes up to 20% less time to construct than a similar cast in situ structure.
Greater
Project Control from a completion/project management perspective and from a costing perspective.
Factory
Production ensures increased accuracy and quality of finish and decreases weather dependency. Compared with cast in situ structures, site labour is reduced by between 50% and 80% using precast. Work for following trades is reduced by between 30% and 50% depending on finishes.
Buildability
- Precast frames can greatly improve buildability because sensitive parts of the operation can be moved from the site to the factory.
Larger
Clear Spans - Reducing the number of columns is critically important in developments such as sports stadia and car parks. Longer spans and shallower construction depths can be obtained by using prestressed concrete beams and floors.
Proven Designs and Methodologies - Precast frame design incorporates proven
designs and methodologies which have been developed over many years.
Sound
Resistance - Precast structures meet the highest standards for resistance to sound transmission. Test figures show the airborne sound insulation of a 150mm concrete floor is 50 db.
Composite
Action - Prestressed precast elements act compositely with an in situ structural screed (topping), combining the benefits of precast and in situ construction.
Less
Wastage - Precast systems significantly reduce the amount of waste materials produced on site.
Loose
Reinforcement - The amount of loose reinforcement on site is reduced by between 80% and 90%.
Airtightness
- Air infiltration in precast buildings is minimal because of the relatively small number of joints in the construction. This factor combined with the thermal mass of concrete gives excellent thermal performance.
A
Overview
1.3 Health & Safety
IPCA members have developed a standard approach to facilitate the implementation of the highest Health & Safety standards. Member companies are now in a position to supply customers with standard procedures, outlining systems of work and the responsibilities of each party. Safe and successful precast installation requires teamwork. This means close co-operation and co-ordination of all participants, including the client, architect, engineer, precaster and the contractor. To achieve the desired schedule and results, the basic working relationship between these parties must be established at an early stage. To achieve this end, the Irish Precast Concrete Association has published a Precast Model Risk Assessment manual as part of the Irish Concrete Federations Health & Safety Manual. The manual identifies potential risks and suitable controls during the manufacture, transport and erection of precast products. The Responsibilities Check List identifies the Health & Safety requirements in relation to the precast concrete elements. A typical Responsibilities Check List sets out suggested responsibility for managing each item either to the Contractor (the purchaser of the precast concrete product) or the Precaster (the supplier and erector of the precast components). The Precast Model Risk Assessment is intended for use to assist all those involved in the manufacture, design, specification, use and erection of precast floors. The IPCA is currently working with the Health &Safety Authority to produce a code of practice for the installation of load-bearing structures. The installation of precast units should only be undertaken by specialists who are trained, competent, and experienced in this work. IPCA members provide Health & Safety training to all personnel in the safe erection of precast units and associated areas such as Safe Pass, Working at Heights, Slinger/Banksman, Mobile Elevated Platforms, Hoist, Crane, Power Tool, Manual Handling, Forklift, Abrasive Wheels, Role of the Supervisor, etc.
Precast concrete units are manufactured in factory conditions where strict manufacturing controls apply. This ensures that reinforcement bars are accurately located and that clients receive high quality products manufactured to controlled dimensional tolerances. Precast delivers a high performance product with a quality appearance.
Overview
1.5 Speed of Construction & Buildability
Speed of construction and tight construction programmes are primary considerations in most building projects and this is where precast concrete excels. To maximise the advantage of precast, two critical factors should be taken into consideration:
Design the building layout to maximise repetition of precast units Design construction details to maximise the number of
standardised
components The importance of these two factors cannot be over emphasised. Adherence to good design practice will speed up the manufacturing process and make construction faster. Maximum efficiency can be achieved by rationalising designs in consultation with precast concrete frame manufacturers.
In making cost comparisons between alternative systems, it is imperative that total like for like costs are considered. There are substantial savings to be made using precast construction which are not evident when a direct elemental cost comparison is made with alternative construction methods. To get an accurate like for like cost, whole building costs must be estimated. To accurately assess whole building cost, each of the advantages of precast as listed in section 1.2 (pages 4 & 5) must be accurately costed. Savings through factors such as earlier completion dates, inbuilt fireproofing, reduced formwork, scaffolding, reduced wet trades and increased budget control can be significant. Also, fast-track procurement and construction may minimise capital costs by reducing financing costs and securing earlier rental income. The precast frame package typically includes columns, beams, floors, wall panels, stairs, landings, balconies etc., all of which have an inbuilt minimum one-hour fire protection. Specialist precast frame producers will assist design teams in evaluating the scope for standardised precast components for a particular project. Budget costings and erection programmes can be prepared by the precaster on receipt of outline drawings and a list of performance criteria.
1.7 Sustainability
Most of the sustainable developments throughout Europe use concrete as the primary construction material. Concrete is long lasting and requires virtually no maintenance or replacement and does not require the application of toxic paints or preservatives. Even highly exposed precast concrete units (such as box culverts) are virtually maintenance free and have a design life of 120 years.
Overview
Precast maximises the sustainable potential of concrete by reducing the amount of construction waste on site to almost zero. IPCA manufacturing plants are monitored on an ongoing basis by a qualified Planning and Environmental Engineer to ensure that each IPCA member implements an ongoing environmental programme. Because of its inherent fire and soundproofing properties, concrete (and particularly precast) lends itself to multi-storey, high density developments which greatly contribute to a sustainable use of land and justifies investment in quality public transport. These types of precast concrete developments offer a sustainable and viable alternative to urban sprawl type housing. Concrete is 100% recyclable and is generally supplied (in Ireland) within a 30 mile radius, with the resultant savings in transport costs and fossil fuels.
The thermal capacity, particularly of exposed concrete, offers considerable energy savings. Modern buildings have a tendency to overheat throughout the year. Ventilation and air conditioning equipment is sometimes used as an expensive high energy solution to this problem. Using the inherent thermal capacity of concrete, particularly in combination with other passive systems, can either reduce or eliminate the capital and running cost of air conditioning. Exposed concrete acts like a storage heater in absorbing heat. Daytime temperatures are reduced by 3C to 4C and peaks in temperature are delayed by up to six hours. The exposed soffits of floor slabs and other Offices - Exposed Precast Concrete Ceiling/Floor Soffit concrete elements including beams and columns act as a passive system providing an effective cooling capacity of up to 25W/m2 of surface area, which is more than adequate for the average commercial building. This principle is utilised by architects and engineers to bring about considerable energy savings. Concrete has excellent sustainability credentials allowing for a reduction in the use of fossil fuels and greenhouse gases. By using concrete as a passive moderator, there are enormous potential savings as 90% of the energy consumed in the life cycle of the building is attributable to heating and cooling.
The traditional procurement route involves the issuing of a bill of quantities by the quantity surveyor. This is frequently done on a selective tendering basis, following an evaluation of precast concrete producers. The tender package prepared by the clients design team should comprise the following: Site Location Map Architects general arrangement drawings Preliminary structural layout plans including dimensions Notional beam and column positions and structural zones Limitations on beam and column sizes Locations of stairs and lifts Services constraints Major voids in floor slabs General and specific loading Foundation, roof and cladding principles Preliminary Health & Safety issues relevant to the site The drawings should be accompanied by a performance specification which defines design and performance criteria for the frame.
Increasingly, the precast concrete manufacturer is nominated in advance of the main contract being awarded. This fast-track approach ensures that the benefits of precast construction are optimised. Once nominated, the precast company can complete the detailed design of the frame and produce workshop drawings. Early nomination benefits the client in the following ways: By maximising the number of standardised components Ensuring the timely production of components Speeding up the construction process Reducing cost It is important that good communications between the precast factory and the site are established from the outset. Their demands on each other and on the design team must be outlined in advance and closely monitored throughout the project.
The precast construction cycle typically includes the following stages: Design Team Set-up Roles and responsibilities to be clarified between the Client, Architect, Consulting Engineer and Precaster. Preliminary Health & Safety Statement Copies of the Preliminary Health & Safety Statement must be made available to the project team by the Project Supervisor at the design stage, as it may impact on the design of the structure. Precast Health & Safety Statement The Precaster will produce a site specific Health & Safety Statement for the project. Design Risk Assessment A Design Risk Assessment will be produced by the Precaster. Access and Cranage Access and cranage requirements must be agreed for the duration of the project. Design Statement A design statement will be issued by the Precaster for review by the Consulting Engineer. This document will include stability calculations, loadings, codes and regulations. Preliminary Drawings It is important to agree gridlines and layouts as early as possible to allow the precast design team to progress. Document Control A document control procedure must be agreed, as documents will require amendments and revisions during the early stages. Approval Procedure An agreed approval procedure must be outlined at an early stage to avoid potential delays. Drawing Sign-Off Procedure The production process will commence when drawings and component details are approved. Late instructions/revisions should be minimised as they may cause delays which can impact on costs. Programme A project programme will be produced by the Precaster. Method Statement The Precaster will produce a Method Statement providing a project specific safe system of work. Site Preparation by the main contractor To avoid delays on-site, the main contractor must ensure that starter-bars and profiles are set-up accurately in readiness for the precast contractor. Delivery and Acceptance A procedure must be agreed for the delivery and acceptance of materials on site. Installation The Precasters specialist teams will install the components in accordance with the project programme. 10 Approval and Sign-off The Resident Engineer must review and sign-off the precast areas on completion.
11
slabs - 1.2m width for hollowcore slabs - 2.4m widths for wideslab and double-tees. - 300mm minimum width and thereafter in increments of 50mm.
Columns Beams
Note To ensure a modular interface between columns and beams, the upstands on spine beams and edge beams should be equal to the width of the largest column.
Walls
Party
Walls - 150mm thick precast concrete party walls are sufficient to meet sound insulation requirements under the current building regulations. Higher requirements can easily be accommodated by increasing the wall thickness.
Other items to be considered include: Maximum Clear Span Maximising the clear span capabilities of precast units minimises the number of columns required. Service Requirements Specify service requirements at an early stage to allow the precast designers to provide service ducts in precast units where appropriate. Planning Precast installation should be planned to avoid stop-start installation. A plan which allows the precaster to install in an alternative location while the main contractor screeds an area of floor, for example, will maximise efficiency and avoid unnecessary delays. The return to site of installation crews and the removal and re-installation of costly equipment such as cranes are inefficiencies which can be planned out at the design stage.
12
Portal Frames A Portal Frame is a frame consisting of precast columns connected at the top by a pitched or sloping horizontal beam. The low pitched roof typically has a 4 slope. Portal Frames are economical to produce and are often associated with industrial or warehouse buildings where a clear span of up to 35m or more is required. It is straightforward to design, provided the flexural rotations at the end of the main portal are achieved. Generally a neoprene pad (or other durable pad) is inserted at the bearing to facilitate this flexibility and to avoid potential damage to the bearing ledge.
Additional Floors In the case of Portal Frames, first floors or mezzanines can be easily constructed by creating a corbel in the column element to facilitate the installation of a secondary post and beam. Dowel bar or pinned connections are generally applied between the column and rafter sections. The horizontal load acting on the gable walls is distributed to the outer columns by single bay (sometimes multi-bay) roof bracing and gable bracing at each end of the building. The diaphragm action of the roof also contributes to the stability of the building.
13
14
Precast Concrete Beam simply supported on single storey Precast Concrete Columns
Apex Depth 1385
6m Eaves Height
Continuous Precast Concrete Parapet Columns with Precast Height 1885mm to the Beams connected face of the Columns
Column
h Minimising Beam Depth Reducing the depth of the beam effectively reduces Column the depth of the services Precast void (i.e. the space Grouted into soffit). Pocket This between the false ceiling and the floor with High Strength in turn reduces the height of the building which Concrete supplied results in cost savings. Minimising beam depth on-site by Main Grout Tubes is particularly important where a computer floor Contractor or other raised floor is required, increasing the Reinforcing Bars overall floor height.
Beam Cantilever Drop-in Beam
Column
Composite beams are frequently used to minimise the beam depth. However, with a composite beam the final loading capacity will not be achieved until the screed is applied. Therefore, in the temporary condition, temporary propping may be required to avoid over-stressing or excessive deflection of the 1.5h min. beam.
Engineering Brick
300mm min.
15
Cross wall construction, using precast floors and load bearing walls, is normally associated with multi-storey buildings. This type of construction is ideal for buildings of a cellular structure, for example hotels, offices, student accommodation, housing and apartment developments.
Cross wall multi-storey structures consist of precast floors and load bearing walls, where the walls are designed as the means of primary support. Longitudinal stability is achieved by external wall panels and/or diaphragm action involving the floors and roof, which are connected back to lift cores or staircases, which are also formed by precast wall panels. The system provides a structurally efficient building with main division walls offering a high degree of sound insulation between adjacent dwellings, offices, etc. One of the advantages of cross wall construction is that an early dry box working construction is created, allowing subsequent trades access to achieve a fast build programme using the minimum of wet trades. These walling systems can produce buildings in excess of 20 storeys. However, in the Irish context, structures greater than 10 storeys are rarely required, primarily due to planning restrictions.
Precast frames are commonly used for basement or roof top car parks, whether independent, free standing or forming part of a mixed development. The majority of car parks in Ireland are concrete column and deck structures. These are specialist structures, but their layout is ideally suited to a precast solution. A typical layout allows a standard bay size in the region of 15.6m x 7.2m which is generally the optimal solution. The 7.2m distance relates to the beam or spandrel span and the 15.6m dimension will suit 400mm thick hollowcore floor units. The use of deep hollowcore units generally negates the need for inboard columns which inhibit vehicle manoeuvrability and obstruct the opening of vehicle doors. Spandrel panels are combined beam and wall panel units. Spandrel panels also act as internal vehicle barriers or as external vehicle barriers when used at the perimeter of the structure. 16
Car Park
17
Horizontal loads (predominantly wind loads), are usually transmitted to moment resisting frames or to shear walls by the roof and floors acting as horizontal diaphragms. Diaphragm action can be described as the action of the floor/roof, acting as a deep beam, transmitting applied horizontal forces to the foundations. A diaphragm floor/roof must be capable of sustaining shear forces and bending moments. The precast concrete floor is analysed by considering the slab to be a deep horizontal beam. The floor units must be tied and grouted together at the joints to ensure full plate action of the floor.
The designer must ensure that the building is capable of sustaining local damage without catastrophic failure or progressive collapse. Structural integrity in the context of avoiding progressive collapse is normally obtained by using the fully tied solution incorporating full horizontal and vertical ties. The function of a tie system is to enable the structure to bridge over a section failure and limit the extent of the damage to a localised area. Test information on the performance of precast structures can be obtained from the BRE (UK).
18
35mm Outer Skin 80mm Insulation 35mm Liner Sheet 175mm Purlin
The design and construction of joints is the most important aspect of precast construction. Joints provide strength/robustness and transmit forces between the structural components. There are a number of different methods for connecting Parapet units including tie-bars, steel billets or plates, in conjunction with the use of high Height strength grouts. The joint must also be capable of withstanding abnormal loads 1885mm caused by fire, impact, explosion or subsidence. The failure of a single joint should never lead to structural instability.
A number of factors determine which type of column to foundation fixing detail should be used. These factors include: Design requirements, i.e. fixed or pinned base. Ground conditions. Presence of services around the column base, e.g. drainage, DETAIL A:mains, Steel Billet gas etc. There are three main methods of fixing precast columns to the in situ foundation : 1. Projecting Starter-Bars. 2. Bolt or Baseplate Connections. 3. In situ Pocket Foundation.
Detail:
The number and size of projecting starter-bars is determined by the project engineer to suit design requirements. The starter-bars are cast into the in situ base by the main contractor at locations specified on the drawings. The precast columns can then be erected on the base, with the starter-bars projecting into dowel tubes provided in the precast columns. This method of fixing a precast column to an in situ base is extensively used in medium to high rise buildings where the complete structure is designed as a braced frame and thus a pinned connection is required at the base.
19
oundation 650mm
The in situ Pocket Foundation will provide a fixed base connection to the precast column, which is particularly useful in low rise precast industrial units where the cantilever action of the column provides the lateral stability for the building, thus reducing the amount of horizontal and vertical bracing required.
100mm
The column is embedded into the pocket pad foundation by a distance of at least 1.5 times the maximum column foot dimension. When structural requirements determine that the column must have a large foot dimension, the in situ pocket foundation can become uneconomical and other foundation solutions should be employed. The main contractor is responsible for the preparation of column foundations. This work must be carried out to a high degree of accuracy to avoid delays in the installation of columns.
1.5h min.
Engineering Brick
300mm min.
Steel baseplates are attached to the precast concrete column during manufacture by casting-in grade 8.8 threaded bars and bolting the baseplate to the column. Alternatively, mild steel bars can be welded to the baseplate and cast onto the foot of the column during the curing process. The column is then fixed to the in situ foundation using cast-in holding down bolts to form a pinned base connection. Alternatively, the precast column can be fixed onto an existing base using holding down bolts which are drilled into place and fixed using a chemical anchor resin.
h
Baseplate equal in size, or less than column size Precast Column Levelling Shim
Four corner pockets with anchor bars welded to baseplate Alternative Baseplate Detail h
40mm min.
Baseplate
1.5h min.
200mm min.
20
Precast Elements
5.1 Columns
The following is relevant to column design: a) Columns are designed for combined axial compression and bending. b) Column bending moments at beam level are determined from the eccentric loading at the connection. c) In the case of slender unbraced columns, the additional moments due to Floor slenderness effects are added to the total design moment at each floor level.
Apex Depth 1385
5.2 Beams
Reinforced or prestressed concrete beams in a precast concrete frame are designed for the specified loadings and support conditions. The beam may be composite or non-composite. Composite beams act with the floor, column and screed to form a monolithic structure.
Beams are typically designed as simply supported with a characteristic concrete strength of between 40N/mm2 and 50N/mm2. Beams generally span from column to column. Alternatively, the beam can cantilever over the end of the column to facilitate a drop-in beam. See diagram page 15.
Floor Floor
Precast beam profiles are generally inverted T-Beams or l-Beams designed to facilitate the support of the precast concrete floor units.
Floor
Floor
Floor
Floor
Floor
d) Changes in Floor Level Floor Floor in Floor Level c) Changes Floor Floor
Floor
b) Rectangular Beam d) Changes in Floor Level d) Changes in Floor Level e) Changes in Floore) Level 21 Changes in Floor Level
Precast Elements
Internal Beams to Column Head Edge Beam to Column Head
The Steel Billet is a common method of connecting precast beams to precast columns. The billet is cast into the body of the column and projects from the column face to form a seating for the floor beam. Another common method of column to beam connection is the formation of a concrete corbel in the column.
DETAIL A: Steel Billet Detail: Safety, quality, and the transfer of the installation process to the manufacturer are factors driving the growing market share for precast floors. Precast concrete units have significant time-saving advantages over propped formwork flooring methods. Reducing the construction programme and presenting the building ahead of schedule for rental are important cost-saving factors.
Units are manufactured to exact standards in factory conditions and installed by Health & Safety trained operatives. In addition, openings can be left for services such as cabling and service hangers and fixings installed as part of the precast sub-contract package. Precast floor units are typically supported by concrete or steel beams or on solid block walls. Precast concrete floors are particularly valued for their excellent sound insulation and fireproofing qualities.
22
Precast Elements
In situ Topping
There are three main precast floor unit types. The specific structural characteristics of each type must be taken into account in assessing the most suitable option for a particular application. In some applications the structural capabilities such as In situ Infill Hollowcore Slab spanning ability will determine the choice. In short-span buildings, structural and material efficiency or proximity to site might be the determining factor. The most suitable choice is relative to the specific project requirements and conditions.
In situ Topping In situ Topping
In situ Infill
Precast floor systems have a number of advantages: In situ Topping a) Reduction in Frame Size Precast floors can be designed to act compositely with the structure of the building to reduce frame sizes: e.g. main support beams supporting solid slab and screed can be designed as T-beams.
Wideslab Steel Lattice Reinforcing
b) Progressive Collapse Prestressed composite floors can be tied-in to the main structure and are therefore particularly suited to buildings where progressive collapse is a consideration. c) Diaphragm Action Precast floor slabs together with the structural screed provide a structural deck with full diaphragm action where required in multi-storey buildings.
23
Precast Elements
5.4.2 Hollowcore Floor
Hollowcore slabs derive their name from the circular voids or cores which run from end to end of the slab. The cores can function as cable/services ducts and significantly reduce the self-weight of the slabs, maximising structural efficiency. Units are available in standard 1200mm widths and in depths of 150mm to 500mm. Hollowcore slabs have excellent long-span capabilities, achieving a maximum capacity of 2.3 KN/sq.m over a 16 metre span. The long-span capability is ideal for office, retail or car park developments. Units are installed with or without a structural screed, depending on requirements. Slabs arrive on site with a smooth pre-finished soffit. In car parks and other open structures, pre-finished soffits offer a maintenance free solution.
Solid Wideslab is sometimes referred to as plate flooring which is generally used in residential developments. Wideslab flooring contains an internal mesh/strand which facilitates notching and the forming of opes.
There are two distinct types of wideslab: a) In situ screeded slabs 2400mm wide and in depths of 65mm to 200mm deep with spans of up to 7.5m. These slabs are generally for upper floors and have smooth self-finishing soffits. Some manufacturers can apply a specialist painted finish to the soffit as part of the contract. Generally a 75mm structural screed is required. A triangular steel lattice girder reinforcement which projects into the screed can be used to increase the spanning capabilities of the wideslab unit and the overall robustness of the floor. The pre-camber of prestressed units should be discussed with the technical department of the selected precast company. 24
Precast Elements
b) Pre-screeded slabs 150mm to 200mm deep are delivered self-finished for ground floor applications. These slabs are particularly suited to poor ground conditions or where cut and fill is required. Maximum spans of 7.5m can be achieved.
Double-Tee floor units are produced in standard widths of 2400mm and in depths of between 250mm and 1000mm. The system offers greater structural capacity at longer spans than hollowcore or wideslabs, but often requires a deeper floor zone. The Double-Tee system is the only system which offers a solution for spans over 16m. Note: For design advice, span/load details and material specifications, please contact the Technical Service Department of the relevant precast company.
Structural toppings can be combined with precast units to produce Precast Composite Floors. The advantage of Precast Composite Floors is the increased bending and flexural stiffness. Structural toppings can also be specified to improve acoustic performance and reduce vibration. In situ toppings will also improve thermal performance. Structural toppings are generally 75mm to 100mm thick and it is recommended that their thickness should not be less than 50mm. Provided there is sufficient anchorage/bonding with the precast unit, the topping and unit can be considered as a monolithic.
25
Precast Elements
5.6 Checking Calculations
The following items should be checked when designing precast floors: Applied Loading Assumed Loading Distribution Design Assumptions (structural screed, temporary propping, etc.) Section Size Strand Pattern - Number and Location of Prestressing Strands Fire Rating Cover Service Stresses - Allowable vs Actual Ultimate Bending Moments - Allowable vs Actual Ultimate Shear - Allowable vs Actual Deflection Workshop Drawings It is important that design assumptions made about the slab are reflected in the production drawings used to manufacture the slabs. For example, the drawings should confirm the designed reinforcement strand pattern, whether open cores are required for forming stability tie details and if temporary propping is required while pouring the structural screed. Slab Widths All three flooring systems can be produced in narrower widths than the standard widths indicated. However, sq.m prices for off-standard widths are higher than for standard widths. Consequently, buildings designed on grids which are a multiple of 1200mm will maximise the cost benefit of precast floors.
Precast stairs do not require the propping and fixing which is necessary for cast in situ stairs. Stair units are connected to floors and landings using steel angle joints. Other connections such as continuous halving joints and intermittent halving joints are sometimes used. Combined stairs and landing units are also available. Once installed, precast stairs allow immediate, safe access to upper floors for following trades. Precast stairs are particularly cost effective when duplicated. The greater the number of identical units required, the lower the cost.
Precast balconies are manufactured mainly for use in apartment complexes. Units have steel bars projecting from the back which tie-in with the steel mesh in the structural screed of the precast floor units. Balcony units are temporarily supported while the structural floor screed is being poured. When the screed has set, the supports are removed leaving the balcony unit cantilevered from the floor edge. Precast balcony units typically have integral drainage slots to receive drainage outlets and an upstand to facilitate proper weatherproofing details at door threshholds.
26
Precast Elements
5.9 Architectural Cladding Panels
Factory produced concrete cladding offers virtually unlimited scope for architectural expression. There is a wide range of high durability, low maintenance surfaces, including both integral and applied finishes. Both highly polished and textured finishes are achievable. Brick, tile, marble and granite are typical finishes, but virtually any decorative stone can be applied. The most cost effective wall panels comprise of reconstituted stone, i.e. naturally coloured, designed and finished to look like natural stone. Panels are typically 150mm thick and may be up to 9m in length and 3.8m high. Panel sizes are generally only limited by transport and cranage constraints. When installed, cladding panels may be either stacked off the ground, one above the other, thus transferring all vertical loads directly to the ground, or alternatively they may be independently supported at each floor level by means of localised concrete corbels. Lateral fixings are secured to either beams or columns. The main advantages of precast cladding are: Tight quality control measures are in place both pre and post casting. Installation is swift and panels are typically sized so that they can span grid to grid and floor to floor, allowing a large area of the building to be weathered in the shortest time possible. No scaffolding is required as all fixings are accessed from the rear of the panels. In most cases, glazing units and insulation may be fitted to the precast units in the factory, speeding up the work of following trades. To make precast units more cost effective, it is important that panel sizes are maximised and a degree of repetition exists. This approach ensures that a number of panels may be cast from a single mould.
27
Precast Elements
5.10 Architectural Wall Panels Rain Screens
Precast wall panels are high strength units which can be quickly installed with little or no site preparation. Natural stone blend, reconstituted stone and terracotta -faced panels are available. Panels arrive on site complete with fixing brackets. The wall is lifted into position and attached to the column which can be either concrete or steel. Connections between floors, beams, columns and wall panels are designed to ensure that all loads, both lateral and vertical, are transferred along the dedicated load path to the appropriate foundation/ restraint. Because the loads acting on the panel are transferred into the column, no strip foundation is required. Precast walls can function simply as security walls or may act as a bearing for precast floor units.
Precast wall panels have been used as rain screens in Ireland for many years. However, Composite Panels are now being manufactured which comprise of an outer leaf of finished concrete (or terracotta tile), a layer of insulation and a backing leaf of plain grey concrete, cast as a single unit. The insulation is installed under controlled factory conditions and is protected from the elements by the concrete outer leaf. To fully optimise the system, the inner leaf of the sandwich panel can be used as a load-bearing element to support floor units, thus offering further economies in the building and minimising the need for co-ordination of different trades. Wall panels can eliminate the following on-site activities: Foundation laying Block laying Plastering
28
Production
6.1 Development of Component Drawings
On confirmation of the clients order, the scope of the work is first analysed by the production team. When technical and production issues have been resolved, production is then scheduled. As the project progresses, correspondence is referenced and stored. Working drawings are then produced by the manufacturers office in consultation with the clients consultants. All relevant information, such as the position of fixings, penetrations, cast-in items, openings, lifting anchors, etc., is clearly noted on the drawings. The production details are then forwarded to the consultants for approval. Production can take place when formal approval has been received from the project principals.
The production of precast components is scheduled to meet the production programme. Machine changes and mould alterations are kept to a minimum to achieve the most efficient batch production. This can only be achieved with the co-operation of the entire project team.
6.3 Materials
Most precast companies have computer controlled batching and mixing plants. Complex mixes for a variety of different concrete products are stored in the batching plant systems. This is an important facility since accurate sand/cement/ gravel/water mix is critical to the integrity and durability of precast components. Precast components are reinforced by inserting steel bars or cages into the mould. Steel is generally cut and bent into the required shape. This can be done manually or by automated means. An alternative to steel cages or strands is the use of fibre reinforcement. The fibres used can be produced from steel, glass or synthetic materials such as polypropylene. Certification of all materials is available from the precaster on request.
29
Production
6.4 Moulds
Adjustable
The main mould types include: long-line mould systems can be used to cast a variety of beam and column sections. The flexibility to pour sections, in a range of sizes, from one mould, ensures optimum productivity and facilitates the quick turnaround of precast components required on fast-track construction programmes.
Battery moulds consist of a series of steel faced sections with variable perimetral
formers positioned to form the required dimensions. These sections open apart to allow preparatory work and are then mechanically closed and clamped together to form a multi-cast mould. Typical applications would include retainer wall panels and other panel sections complete with door and window openings, suitable for apartment or housing developments.
Specialised
or bespoke moulds are manufactured to produce a specific oneoff range of products. Moulds can be manufactured from different materials such as plywood, steel or fibreglass and may be lined with a range of purpose-made patterned liners to imitate natural finishes. The choice of mould material is usually determined by the number of casts required and the complexity of the shape and size of the finished product. Specialised moulds can be adjusted and may be used for similar projects in the future.
30
Production
6.6 Curing
The curing process is an important part of component manufacture. Heating the concrete accelerates curing. Heat is applied in various ways such as steam or hot water running through a network of piping. Other methods include the use of hot air and the application of electrical current through reinforcing strands which act as heating elements. Covering the components with insulating sheets to retain heat and moisture helps the curing process.
31
Production
6.7 Quality
Considerable emphasis is placed on quality control at all stages in the production of precast concrete components. Many Irish precasters manufacture in accordance with ISO 9002 standards or with other internal quality systems. Key areas of quality control include: Test certificates for materials - cement/reinforcement/aggregates Aggregate testing Compressive strength testing Workability Mould standard and quality Preparation of reinforcement cages/strands Cast-in components and fittings Dimensional checks Assessment of early age strength for de-moulding/transfer strength, etc. Quality of finish
When the units have reached the required strength, they are removed from the mould and labelled for later identification. They are then stacked on wooden battens or plastic pads.
32
Site Erection
7.1 Method Statement
The principles of site erection, the methods of making structural joints and the specification for materials are all in accordance with the requirements of BS 8110. At the commencement of each project a method statement confirming how the building will be manufactured, transported and installed should be prepared. The headings covered in this statement include: Safety (including the mandatory safety statement) Mould-work Materials Handling/Cranage and Transportation Site Installation (Procedure, Programme, Sequence) The design for temporary conditions during erection should take into account overall frame stability and the stresses in individual frame components and joints. Load paths through a partially completed structure may be different for those in a completed frame. An example is the temporary state when floor units have been placed on one side only of an internal beam. Here the connection should be checked for its resistance to torsion and if necessary, propped until the slabs on the other side of the beam are placed in position.
7.2 Columns
Columns are typically erected in pockets onto pre-levelled plates giving a clearance of between 50mm to 75mm to the sides and bottom of the pocket. Temporary wedges are driven into the pockets and together with diagonal props are used to line and plumb the column. In situ concrete with an early strength of about 40 N/mm2 at three days is compacted into the pockets to ensure that a structural connection is made between the column and the foundation.
7.3 Beams
Beams are either grouted through sleeved connections between upper and lower columns or are supported on billet type corbels. Bolted cleat type connections or billets with a welded or bolted top fixing provide an immediate restraint to shear and torsional forces. Dowelled corbels and billets which depend on an in situ top fixing do not provide adequate restraint and temporary propping will be required to stabilise the beam. High strength grouts are used in all cases. Strengths of 30N/mm2 are required after eight hours.
Installation times for precast units vary with each project, but the following rates of installation (based on one erection crew) are indicative.
single storey Columns Spine Beams or Edge Beams Wall Panels Floor Slabs Stairs and Landings
12 14 per day 12 15 per day 12 18 per day 350m2 per day 12 15 per day
33
Site Erection
7.5 Access and Cranage
Safe access to the site is a key consideration which must be agreed between the main contractor and the precaster prior to commencement on site. Suitable hard standing for cranage and articulated vehicles must also be provided. Ground floors or platforms used as storage spaces must be structurally stable and level. The position of the crane must be carefully planned to ensure that its capabilities are maximised and the installation period minimised. The following are some of the issues which should be taken into consideration before choosing a crane and finalising the construction sequence:
Public safety and on-site safety Access to public roads Component sizes and weights Maximum reach of the crane from
set-up position to final panel installation Any constraints such as overhead power lines Availability of secure standing areas for cranage
Telescopic Crane
34
Appendix
Appendix - Structural Details
Precast structural details deal with the connection of the precast concrete components to form a fully integrated structural frame. While some details are company specific or proprietary connection systems, generally all are based on tried and tested design assumptions and construction practices. For example, the steel insert or billet connection is a refinement of the traditional corbel support. Some of the proprietary bolted connections are modelled on connection systems used to connect structural steelwork elements. The following details are commonly used in connecting precast frame elements in Ireland. The details indicated are a guide only and are not related to a specific project. Project specific details should be produced by the design engineer taking all relevant factors into consideration.
6 12 14 13 8 7
1 Main Spandrel Beam 2 Hollowcore Unit 3 Internal Rectangular Beam 4 Gable Spandrel Beam 5 Gable Beam 6 Main Edge Beam 7 Landing Support Beam 8 Staircase and Landing 9 Ground Beam 10 Column 11 Wall 12 Double-Tee Unit 13 Internal Beam 14 Main Edge Spandrel Beam
11 10
35
Precast Column
Non-Shrink Grout
Bearing Pad Spiral Tube Cast into Precast Column Dowel Bar Grouted into Position using Non-Shrink Grout
36
Non-Shrink Grout
Bearing Pad Spiral Tube Cast into Precast Column Dowel Bar Grouted into Position using Non-Shrink Grout
Precast Column
Non-Shrink Grout
Bearing Pad Spiral Tube Cast into Precast Column Dowel Bar Grouted into Position using Non-Shrink Grout
Precast Column
37
Non-Shrink Grout
38
39
Precast Column Grout Tubes Cast Into Spine Beam to Take Projecting Tie-bar Non-Shrink Grout
Grout Tubes Cast Into Precast Columns and Beams for Vertical Ties
Continuous Multi-storey Precast Column Dowel Tubes and Projecting Bars Non-Shrink Grout
Precast Beam
Precast Beam
Corbel
40
FLOOR FLOOR TO TO BEAM BEAM CONNECTIONS CONNECTIONS - HOLLOWCORE HOLLOWCORE FLOOR FLOOR
Precast Precast Column Column Longitudinal Longitudinal Ties Ties Mesh Mesh Transverse Transverse Precast Precast Unit Unit and and Screed Screed
Peripheral Peripheral Tie Tie In In Situ Situ Concrete Concrete Infill Infill by Main by Main Contractor Contractor
35N 10 Concrete Grout Precast Precast Edge Edge Beam Beam (Reinforcement (Reinforcement not not indicated) indicated) Precast Precast Floor Floor Units Units Built-in Built-in (100mm (100mm End End Bearing) Bearing) Laid on 1:3 Mortar Bed by Main Contractor Laid on 1:3 Mortar Bed - by Main Contractor (Shear (Shear or or Friction Friction Wall Wall Ties) Ties)
DETAIL Side DETAIL 9: 11: Typical Typical EndBearing BearingDetail: Detail: Rectangular RectangularEdge EdgeBeam Beam
Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed
Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete
Precast Edge Beam (Reinforcement not indicated) Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
DETAIL 10: Typical 5 Storey+ End Bearing Detail: Rectangular Edge Beam
41
Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed
Precast Edge Beam (Reinforcement not indicated) Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR DETAIL 11: Typical End Bearing Detail: Rectangular Edge Beam
Precast Column Precast Column Longitudinal Mesh Ties Transverse Longitudinal Mesh Ties Transverse Precast Unit and Screed Precast Unit and Screed
In Situ Concrete Infill by Main Contractor Peripheral Tie Filler by Builder Precast Edge Beam (Reinforcement not indicated) Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete 35N 10 Concrete Grout
Precast Edge Beam (Reinforcement not indicated) Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
DETAIL 10: Typical 5 Storey+ End Bearing Detail: Rectangular Edge Beam
Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed
Precast Column Longitudinal Ties Mesh When Required Transverse Precast Unit and Screed
Filler by Builder Break Out Hollowcore Floor Unit Cores and Fill with Min. 35N 10 Concrete Precast Edge Beam (Reinforcement not indicated)
43
Precast Column Mesh Transverse Projecting Bar from Spine Beam Precast Unit and Screed
Precast Floor Units (100mm End Bearing) Precast Spine Beam (Reinforcement not indicated)
DETAIL 15: Typical End Bearing Detail: Inverted T-Shaped Spine Beam
Precast Column Mesh Transverse Projecting Bar from Spine Beam Precast Unit and Screed
Filler by Builder Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete Precast Spine Beam (Reinforcement not indicated) Precast Floor Units (100mm End Bearing)
44
DETAIL 16: Typical 5 Storey+ End Bearing Detail: Inverted T-Shaped Spine Beam
Precast Column Mesh Transverse Projecting Bar From Spine Beam Precast Unit and Screed
Precast Floor Units (100mm End Bearing) Precast Spine Beam (Reinforcement not indicated)
FLOOR TO Detail: BEAM CONNECTIONS - HOLLOWCORE FLOOR DETAIL 17: Typical End Bearing Inverted T-Shaped Spine Beam
Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed
DETAIL 18: Typical Side & End Bearing Detail: Rectangular Edge Beam
45
External Wall
Internal Wall
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
External Wall
Internal Wall
Filler by Builder
Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N. Concrete R.C. Band Beam (Peripheral Tie) R.C. Band Beam may not be required if shear/friction joint proves adequate
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
46
External Wall
Internal Wall
35N 10 Concrete Grout Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
External Wall
Internal Wall
Longitudinal Ties
Mesh Transverse
35N 10 Concrete Grout R.C. Band Beam (Peripheral Tie) R.C. Band Beam may not be required if shear/friction joint proves adequate
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
47
Mesh Transverse
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
Internal Wall
Longitudinal Ties
Mesh Transverse
Filler by Builder
Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
48
External Wall
Internal Wall
External Wall
Internal Wall
Longitudinal Ties
Mesh Transverse
R.C. Band Beam may not be required if shear/friction joint proves adequate
49
External Wall
Internal Wall
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
External Wall
Internal Wall
Longitudinal Ties
Mesh Transverse
R.C. Band Beam may not be required if shear/friction joint proves adequate
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
50
When using Non-Structural Screeds Internal Wall to be Built Directly Off the Flooring Unit
Internal Wall
Mesh Transverse
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
When using Non-Structural Screeds Internal Wall to be Built Directly Off the Flooring Unit
Internal Wall
Longitudinal Ties
Mesh Transverse
R.C. Band Beam R.C. Band Beam may not be required if shear/friction joint proves adequate
Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)
51
Members
IRISH PRECAST CONCRETE ASSOCIATION
8 Newlands Business Park, Naas Road, Dublin 22. Tel: 01 4640082 Fax: 01 4640087 email: [email protected]
MEMBERS LIST
Queen Street, Banagher Estate, Co. Offaly. Tel: 0509 51417 Fax: 0509 51558 Email: [email protected] www.bancrete.com
Deerpark Industrial Estate, Oranmore, Co. Galway. Tel: 091 794537 Fax: 091 794586 Email: [email protected] www.oranprecast.ie
Hilltown, Oldcastle, Co. Meath. Tel: 049 41477 Fax: 049 41311 Email: [email protected] www.floodflooring.com
Kingscourt, Co. Cavan. Tel: 042 67237 Fax: 042 67311 Email: [email protected] www.oreillyconcrete.com
Quinn Group
Derrylin, Co. Fermanagh. Tel: 048 677 48866 Fax: 048 677 48800 Email: [email protected] www.quinn-group.com
Ballymaquirke, Kanturk, Co. Cork. Tel: 029 56037 Fax: 029 56245 Email: [email protected] www.duconconcrete.com
52
Notes
53
Notes
54
Unit 8, Newlands Business Park, Naas Road, Clondalkin, Dublin 22, Ireland. Tel +353 1 464 0082 Fax +353 1 464 0087 Email [email protected] www.irishconcrete.ie