Precast Concrete Frames Guide

Download as pdf or txt
Download as pdf or txt
You are on page 1of 58

Overview

Precast Concrete

Frames Guide
September 2003

Irish Precast Concrete Association Cumann Concrit Ramhtheilgthe na hireann

Concrete Built is Better Built

Contents
Foreword
3 4 4 6 6 7 7 7 8 9 9 9 10 11 12 13 14 16 16 17 18 18 18 19 19 19 19 20 20 21 21 22 22 23 24 24 25 25 26 26 26 27 28 28 29 29 29 30 30 31 32 32 1

Overview

1.1 Introduction 1.2 Benefits of Precast Structures 1.3 Health &Safety 1.4 Quality &Accuracy 1.5 Speed of Construction & Buildability 1.6 Choosing a Construction Method - Comparative Costs 1.7 Sustainability 1.8 Thermal Capacity 2.1 Forms of Contract - Selecting a Contractual Route 2.2 Traditional Approach to Procurement 2.3 Nominated Sub-contract - Early nomination 2.4 Precast Contruction Cycle 2.5 Design Statement

Procurement of a Precast Concrete Frame

Precast Construction Methods

3.1 Design Parameters - Maximising Cost Benefit 3.2 Single Storey - Industrial Frames 3.3 Multi-Storey - Column &Beam 3.4 Cross Wall Construction 3.5 Precast Car Park Frame & Deck 3.6 Mixed Construction

Designing for Structural Stability

4.1 Design Approach 4.2 Designing for Horizontal Loads 4.3 Structural Integrity - Design for Accidental Loading 4.3.1 Progressive Collapse & Stability Ties 4.4 Joints & Connections 4.5 Column to Foundation Fixing Detail 4.5.1 Projecting Starter-Bars 4.5.2 In Situ Pocket Foundation 4.5.3 Bolted or Baseplate Connections 5.1 Columns 5.2 Beams 5.3 Beam Column Connections 5.4 Precast Floors 5.4.1 Selecting a Precast Floor System 5.4.2 Hollowcore Floor 5.4.3 SolidWideslab Floors 5.4.4 Double-Tee FloorSlabs 5.5 Precast Floors with Composite Toppings 5.6 Checking Calculations 5.7 Precast Stairs 5.8 Precast Balconies 5.9 Architectural Cladding Panels 5.10 Architectural Wall Panels - Rain Screens 5.11 Architectural Composite Panels 6.1 Development of Component Drawings 6.2 Production Scheduling 6.3 Materials 6.4 Moulds 6.5 Production Techniques 6.6 Curing 6.7 Quality 6.8 Handling &Storage

Precast Elements

Production

Site Erection

Contents
33 33 33 33 34 35 36 37 37 38 39 39 40 40 41 41 42 42 43 43 44 44 45 45 46 46 47 47 48 48 49 49 50 50 51 51 52

7.1 MethodStatement 7.2 Columns 7.3 Beams 7.4 Construction Speed 7.5 Access &Cranage

Appendix - Structural Details Column to Beam Connections


DETAIL 1: High Parapet Concealed Gutter Detail DETAIL 2: Eaves Gutter Detail DETAIL 3: Valley Gutter Detail DETAIL 4: Detail at Splayed Corbel DETAIL 5: Steel Billet Detail DETAIL 6: Square Corbel Detail DETAIL 7: Non-Continuous Column and Spine Beam Connection DETAIL 8: Continuous Column and Spine Beam Connection DETAIL 9: Typical Side Bearing Detail: Rectangular Edge Beam DETAIL 10: Typical 5 Storey+ End Bearing Detail: Rectangular Edge Beam

Floor to Beam Connections - Hollowcore Floor

DETAIL 11: Typical End Bearing Detail: Rectangular Edge Beam DETAIL 12: Typical Side Bearing Detail: L-Shaped Beam DETAIL 13: Typical End Bearing Detail: L-Shaped Beam DETAIL 14: Typical 5 Storey+ End Bearing Detail: L-Shaped Beam DETAIL 15: Typical End Bearing Detail: Inverted T-Shaped Spine Beam DETAIL 16: Typical 5 Storey+ End Bearing Detail: Inverted T-Shaped Spine Beam DETAIL 17: Typical End Bearing Detail: Inverted T-Shaped Spine Beam DETAIL 18: Typical Side & End Bearing Detail: Rectangular Edge Beam

Floor to Beam Connections - Wideslab Floor

Floor to Wall Connections - Hollowcore Floor

DETAIL 19: Typical End Bearing Detail: External Wall DETAIL 20: Typical 5 Storey+ End Bearing Detail: External Wall DETAIL 21: Typical Side Bearing Detail: External Wall DETAIL 22: Typical 5 Storey+ Side Bearing Detail: External Wall DETAIL 23: Typical End Bearing Detail: Internal Wall DETAIL 24: Typical 5 Storey+ End Bearing Detail: Internal Wall DETAIL 25: Typical Side Bearing Detail: External Wall DETAIL 26: Typical 5 Storey+ Side Bearing Detail: External Wall DETAIL 27: Typical End Bearing Detail: External Wall DETAIL 28: Typical 5 Storey+ End Bearing Detail: External Wall DETAIL 29: Typical End Bearing Detail: Internal Wall DETAIL 30: Typical 5 Storey+ End Bearing Detail: Internal Wall

Floor to Wall Connections - Wideslab Floor

Members List

Note

The IPCA and its members who produced this guide have endeavoured to ensure the accuracy of its contents. However, the guidance and recommendations given should always be reviewed by those using the guide in the light of the facts of their particular case and specialist advice obtained as necessary. No liability for negligence or otherwise in relation to this guide and its contents is accepted by the members of the IPCA, or its servants or agents. Produced by Brian Murch
Dip Arch. Tech

and Caroline Quinn

BBS, MA(Hon), Dip MP, MSc.

Irish Precast Concrete Association Unit 8, Newlands Business Park, Clondalkin, Dublin 22. Tel: +353 1 464 0082 Fax: +353 1 464 0087 email: [email protected] Web: www.irishconcrete.ie

Foreword
This publication is an introduction to precast concrete frames, their components, design and the principal considerations relative to their use and specification. Produced by the Irish Precast Concrete Association, it is the first Frames Guide of its kind which deals specifically with the range of products available on the Irish market. One of the key objectives of the publication is to improve the understanding of precast as a construction method. There has been a significant shift in recent years towards prefabricated methods of construction. This shift is changing construction practice and is encouraging construction professionals to take a fresh look at the benefits of precast. It is envisaged that the new Precast Frames Guide will provide a source of reference for Irish professionals and educators who are involved in this process. Educating the current and next generation of young professionals in the correct use and appreciation of precast construction is one of the primary objectives of the IPCA Precast Frames Guide. Concrete has considerable advantages as a construction material, including inherent fireproofing, sound and durability characteristics. The full potential of concrete is realised by precast which delivers high quality product produced in a controlled, safe environment free from weather restrictions. Irish precast companies employ a staff of highly trained engineers who are experts in precast techniques. When introduced to the design process at an early stage, these specialists can often make significant cost savings by proposing a range of efficiencies, particularly in the standardisation of construction components and in the efficient scheduling of the construction programme. The value of this expert resource has yet to be fully realised and it is hoped that this guide will promote greater liaison between the precaster and the design team.

Safecast

IPCA members are Safecast producers. Member companies work to high standards in relation to Health & Safety, Planning and Environment and Archaeological guidelines which are subject to ongoing assessment by the Irish Concrete Federation. Raw materials are sourced from quarries which have the relevant planning requirements and are used in accordance with best practice and in an environmentally conscious manner.

Offices - Curved Precast Cladding Panels


3

Overview
1.1 Introduction
Precast concrete framed construction is well established as one of the principal construction methods in Europe. In Ireland, the precast industry has built a close working relationship with developers, offering practical advice and a range of technical services at design and construction stages. Precast manufacturers have a critical role to play in the proper planning and execution of precast buildings. Involving the precaster at the early design stage is the best way to achieve the most economical building solution. Early involvement also allows the manufacturer to schedule production so as to maximise cost savings brought about by the use of standardised components and early completion. Precast concrete buildings previously had an identifiable appearance. However, with advances in technology and technique, precast buildings are now indistinguishable from those constructed using non-precast methods. Designers no longer work within tight constraints. Increasingly, the situation is that precasters are able to accommodate greater variety and complexity, effectively designing their elements to meet design requirements. Continuous investment and innovations have transformed the precast industry so that complex plan layouts and external treatments can now be accommodated. Organic designs can be achieved using standardised precast components. The use of standardised components does not imply a modular appearance. Nowadays, precast elements, including floors, stairs and wall panels combine seamlessly with non-precast elements to produce free-flowing spaces. Curved precast panels with a variety of highly attractive and durable finishes can be manufactured to meet the most challenging design requirements. Precast concrete can now be incorporated in every building type. Whether the building has a regular or an irregular shape, the entire structure or elements of that structure, such as frame, floors, walls, stairs or balconies, can all be precast. Precast construction is virtually unlimited in its application and is suitable for single and multi-storey construction. Offices and hotels are commonly constructed in precast, as are hospitals, schools, industrial units and multi-storey car parks, apartments and housing. In fact, precast building elements should be considered as an option on every construction project. The most common error is to take an all precast or no precast approach to design. In fact, a key issue for designers is to identify which construction method, or mix of construction methods and materials is most appropriate for the specific requirements of the building. The most economical solution might well consist of a mix of cast in situ and factory assembled units. Preliminary structural investigation may identify solutions such as beams and floor slabs fabricated off site being erected on cast in situ columns. These structural elements are then integrated as a composite structure when the floor screed is poured. The proper investigation of construction options at the early design stage is critical to optimising structural performance and delivering the most economical building package.

Apartments Curved Precast Cladding Panels

1.2 Benefits of Precast Structures

The considerable advantages of precast construction are combined with the inherent benefits of concrete to provide a superior construction product. These include:
Inherent

Fire Properties - Concrete has its own inbuilt fire resistance which is present during all construction phases. Fire resistance is typically achieved without the application of additional sprays or linings. This is an important inherent advantage over steel and timber solutions. Precast frames are generally 4

Overview
designed for one hour inbuilt fire rating. This either totally eliminates or greatly reduces the need for additional fire protection and the associated costs.
Economies

are generated through reduced requirements for formwork, access scaffolding and less reliance on wet trades. Reduced on-site supervision by the main contractor is also a saving. Compared to cast in situ concrete, the following savings can be expected: Formwork 75% less Scaffolding 75% to 90% less Wet Concrete 90% less
Health

& Safety - Once precast floor slabs are installed, they provide a safe working platform for site operatives. Simultaneously installing precast stairs offers safe and easy access between floors.
Reduced

Construction Programme, due to speed of construction, gives earlier return on investment, freeing up the project critical path and allowing earlier completion. It is estimated that a precast structure takes up to 20% less time to construct than a similar cast in situ structure.
Greater

Project Control from a completion/project management perspective and from a costing perspective.
Factory

Production ensures increased accuracy and quality of finish and decreases weather dependency. Compared with cast in situ structures, site labour is reduced by between 50% and 80% using precast. Work for following trades is reduced by between 30% and 50% depending on finishes.
Buildability

- Precast frames can greatly improve buildability because sensitive parts of the operation can be moved from the site to the factory.
Larger

Clear Spans - Reducing the number of columns is critically important in developments such as sports stadia and car parks. Longer spans and shallower construction depths can be obtained by using prestressed concrete beams and floors.
Proven Designs and Methodologies - Precast frame design incorporates proven

designs and methodologies which have been developed over many years.
Sound

Resistance - Precast structures meet the highest standards for resistance to sound transmission. Test figures show the airborne sound insulation of a 150mm concrete floor is 50 db.
Composite

Action - Prestressed precast elements act compositely with an in situ structural screed (topping), combining the benefits of precast and in situ construction.
Less

Wastage - Precast systems significantly reduce the amount of waste materials produced on site.
Loose

Reinforcement - The amount of loose reinforcement on site is reduced by between 80% and 90%.
Airtightness

- Air infiltration in precast buildings is minimal because of the relatively small number of joints in the construction. This factor combined with the thermal mass of concrete gives excellent thermal performance.
A

Complete Service from design to manufacture to installation is available.

Overview
1.3 Health & Safety
IPCA members have developed a standard approach to facilitate the implementation of the highest Health & Safety standards. Member companies are now in a position to supply customers with standard procedures, outlining systems of work and the responsibilities of each party. Safe and successful precast installation requires teamwork. This means close co-operation and co-ordination of all participants, including the client, architect, engineer, precaster and the contractor. To achieve the desired schedule and results, the basic working relationship between these parties must be established at an early stage. To achieve this end, the Irish Precast Concrete Association has published a Precast Model Risk Assessment manual as part of the Irish Concrete Federations Health & Safety Manual. The manual identifies potential risks and suitable controls during the manufacture, transport and erection of precast products. The Responsibilities Check List identifies the Health & Safety requirements in relation to the precast concrete elements. A typical Responsibilities Check List sets out suggested responsibility for managing each item either to the Contractor (the purchaser of the precast concrete product) or the Precaster (the supplier and erector of the precast components). The Precast Model Risk Assessment is intended for use to assist all those involved in the manufacture, design, specification, use and erection of precast floors. The IPCA is currently working with the Health &Safety Authority to produce a code of practice for the installation of load-bearing structures. The installation of precast units should only be undertaken by specialists who are trained, competent, and experienced in this work. IPCA members provide Health & Safety training to all personnel in the safe erection of precast units and associated areas such as Safe Pass, Working at Heights, Slinger/Banksman, Mobile Elevated Platforms, Hoist, Crane, Power Tool, Manual Handling, Forklift, Abrasive Wheels, Role of the Supervisor, etc.

1.4 Quality & Accuracy

Precast concrete units are manufactured in factory conditions where strict manufacturing controls apply. This ensures that reinforcement bars are accurately located and that clients receive high quality products manufactured to controlled dimensional tolerances. Precast delivers a high performance product with a quality appearance.

Precast Housing - Cross Walls, Floors and Cladding Panels

Overview
1.5 Speed of Construction & Buildability
Speed of construction and tight construction programmes are primary considerations in most building projects and this is where precast concrete excels. To maximise the advantage of precast, two critical factors should be taken into consideration:
Design the building layout to maximise repetition of precast units Design construction details to maximise the number of

standardised

components The importance of these two factors cannot be over emphasised. Adherence to good design practice will speed up the manufacturing process and make construction faster. Maximum efficiency can be achieved by rationalising designs in consultation with precast concrete frame manufacturers.

1.6 Choosing a Construction Method Comparative Costs


Sports Stadium Precast Raker Beams

In making cost comparisons between alternative systems, it is imperative that total like for like costs are considered. There are substantial savings to be made using precast construction which are not evident when a direct elemental cost comparison is made with alternative construction methods. To get an accurate like for like cost, whole building costs must be estimated. To accurately assess whole building cost, each of the advantages of precast as listed in section 1.2 (pages 4 & 5) must be accurately costed. Savings through factors such as earlier completion dates, inbuilt fireproofing, reduced formwork, scaffolding, reduced wet trades and increased budget control can be significant. Also, fast-track procurement and construction may minimise capital costs by reducing financing costs and securing earlier rental income. The precast frame package typically includes columns, beams, floors, wall panels, stairs, landings, balconies etc., all of which have an inbuilt minimum one-hour fire protection. Specialist precast frame producers will assist design teams in evaluating the scope for standardised precast components for a particular project. Budget costings and erection programmes can be prepared by the precaster on receipt of outline drawings and a list of performance criteria.

1.7 Sustainability

Most of the sustainable developments throughout Europe use concrete as the primary construction material. Concrete is long lasting and requires virtually no maintenance or replacement and does not require the application of toxic paints or preservatives. Even highly exposed precast concrete units (such as box culverts) are virtually maintenance free and have a design life of 120 years.

Precast Apartments - Cross Wall Construction

Overview
Precast maximises the sustainable potential of concrete by reducing the amount of construction waste on site to almost zero. IPCA manufacturing plants are monitored on an ongoing basis by a qualified Planning and Environmental Engineer to ensure that each IPCA member implements an ongoing environmental programme. Because of its inherent fire and soundproofing properties, concrete (and particularly precast) lends itself to multi-storey, high density developments which greatly contribute to a sustainable use of land and justifies investment in quality public transport. These types of precast concrete developments offer a sustainable and viable alternative to urban sprawl type housing. Concrete is 100% recyclable and is generally supplied (in Ireland) within a 30 mile radius, with the resultant savings in transport costs and fossil fuels.

1.8 Thermal Capacity

The thermal capacity, particularly of exposed concrete, offers considerable energy savings. Modern buildings have a tendency to overheat throughout the year. Ventilation and air conditioning equipment is sometimes used as an expensive high energy solution to this problem. Using the inherent thermal capacity of concrete, particularly in combination with other passive systems, can either reduce or eliminate the capital and running cost of air conditioning. Exposed concrete acts like a storage heater in absorbing heat. Daytime temperatures are reduced by 3C to 4C and peaks in temperature are delayed by up to six hours. The exposed soffits of floor slabs and other Offices - Exposed Precast Concrete Ceiling/Floor Soffit concrete elements including beams and columns act as a passive system providing an effective cooling capacity of up to 25W/m2 of surface area, which is more than adequate for the average commercial building. This principle is utilised by architects and engineers to bring about considerable energy savings. Concrete has excellent sustainability credentials allowing for a reduction in the use of fossil fuels and greenhouse gases. By using concrete as a passive moderator, there are enormous potential savings as 90% of the energy consumed in the life cycle of the building is attributable to heating and cooling.

Library Building - Exposed Concrete Columns & Ceiling/Floor Soffit

Procurement of a Precast Concrete Frame


2.1 Forms of Contract Selecting a Contractual Route
There are a number of alternative contractual arrangements such as: a) Direct contract (with client) b) Domestic sub-contract c) Nominated sub-contract d) Management contract The client needs to assess the options, understand the advantages and disadvantages of the different forms of contract and select the best option relative to the specific project requirements. It is important to appreciate that the form of contract selected often determines the level of responsibility and input requirements from the different parties. The relative responsibilities and level of input can vary significantly, depending on the contractual route chosen. A clear understanding of how responsibilities are apportioned and where shared responsibilities exist is key to ensuring the smooth progress of the project.

2.2 Traditional Approach to Procurement

The traditional procurement route involves the issuing of a bill of quantities by the quantity surveyor. This is frequently done on a selective tendering basis, following an evaluation of precast concrete producers. The tender package prepared by the clients design team should comprise the following: Site Location Map Architects general arrangement drawings Preliminary structural layout plans including dimensions Notional beam and column positions and structural zones Limitations on beam and column sizes Locations of stairs and lifts Services constraints Major voids in floor slabs General and specific loading Foundation, roof and cladding principles Preliminary Health & Safety issues relevant to the site The drawings should be accompanied by a performance specification which defines design and performance criteria for the frame.

2.3 Nominated Sub-contract Early Nomination

Increasingly, the precast concrete manufacturer is nominated in advance of the main contract being awarded. This fast-track approach ensures that the benefits of precast construction are optimised. Once nominated, the precast company can complete the detailed design of the frame and produce workshop drawings. Early nomination benefits the client in the following ways: By maximising the number of standardised components Ensuring the timely production of components Speeding up the construction process Reducing cost It is important that good communications between the precast factory and the site are established from the outset. Their demands on each other and on the design team must be outlined in advance and closely monitored throughout the project.

2.4 Precast Construction Cycle

Procurement of a Precast Concrete Frame

The precast construction cycle typically includes the following stages: Design Team Set-up Roles and responsibilities to be clarified between the Client, Architect, Consulting Engineer and Precaster. Preliminary Health & Safety Statement Copies of the Preliminary Health & Safety Statement must be made available to the project team by the Project Supervisor at the design stage, as it may impact on the design of the structure. Precast Health & Safety Statement The Precaster will produce a site specific Health & Safety Statement for the project. Design Risk Assessment A Design Risk Assessment will be produced by the Precaster. Access and Cranage Access and cranage requirements must be agreed for the duration of the project. Design Statement A design statement will be issued by the Precaster for review by the Consulting Engineer. This document will include stability calculations, loadings, codes and regulations. Preliminary Drawings It is important to agree gridlines and layouts as early as possible to allow the precast design team to progress. Document Control A document control procedure must be agreed, as documents will require amendments and revisions during the early stages. Approval Procedure An agreed approval procedure must be outlined at an early stage to avoid potential delays. Drawing Sign-Off Procedure The production process will commence when drawings and component details are approved. Late instructions/revisions should be minimised as they may cause delays which can impact on costs. Programme A project programme will be produced by the Precaster. Method Statement The Precaster will produce a Method Statement providing a project specific safe system of work. Site Preparation by the main contractor To avoid delays on-site, the main contractor must ensure that starter-bars and profiles are set-up accurately in readiness for the precast contractor. Delivery and Acceptance A procedure must be agreed for the delivery and acceptance of materials on site. Installation The Precasters specialist teams will install the components in accordance with the project programme. 10 Approval and Sign-off The Resident Engineer must review and sign-off the precast areas on completion.

Procurement of a Precast Concrete Frame


2.5 Design Statement
When outlining the design of the project, the precast manufacturer typically provides the following for approval by the Consulting Engineer:
Design calculations and analysis Proposed load paths - Structural idealisation Temporary stability - Permanent stability Bracing and connection details Fire resistance Interaction with non-precast elements Codes of practice or relevant test data Special requirements

11

Precast Construction Methods


3.1 Design Parameters Maximising Cost Benefit
Designers can maximise the economic benefit of precast construction by using consistent structural grids, uniform loading and regular storey heights. The structural grids may have offsets which form curved or other irregular shapes, without compromising the general uniformity of the structural grid. This technique is used to good effect in many buildings where a curve is required in one section of the building or in some of the elevations. Variations in storey height are also relatively easy to accommodate. Component Standardisation Well designed frame elements in standard sizes facilitate economic construction. The dimensions of beam and column sections should be standardised wherever possible, allowing the precast designer to fully utilise available moulds. Always approach the precast supplier at the earliest possible stage to ensure that elements/section sizes are standardised where possible to suit the suppliers system. Standard Mould Sizes Moulds are often manufactured to set widths with the capability to vary the section depth. Commonly used section dimensions are:
Floor

slabs - 1.2m width for hollowcore slabs - 2.4m widths for wideslab and double-tees. - 300mm minimum width and thereafter in increments of 50mm.

Columns Beams

- 300mm minimum width and thereafter in increments of 50mm.

Note To ensure a modular interface between columns and beams, the upstands on spine beams and edge beams should be equal to the width of the largest column.
Walls

are typically produced in 150mm or 200mm section sizes.


Party

Walls - 150mm thick precast concrete party walls are sufficient to meet sound insulation requirements under the current building regulations. Higher requirements can easily be accommodated by increasing the wall thickness.

Other items to be considered include: Maximum Clear Span Maximising the clear span capabilities of precast units minimises the number of columns required. Service Requirements Specify service requirements at an early stage to allow the precast designers to provide service ducts in precast units where appropriate. Planning Precast installation should be planned to avoid stop-start installation. A plan which allows the precaster to install in an alternative location while the main contractor screeds an area of floor, for example, will maximise efficiency and avoid unnecessary delays. The return to site of installation crews and the removal and re-installation of costly equipment such as cranes are inefficiencies which can be planned out at the design stage.

12

Precast Construction Methods


There are three main forms of precast frame construction: 1) Portal Frames 2) Column and Beam (single storey and multi-storey) 3) Cross Wall Construction

3.2 Single Storey Industrial Frames

Portal Frames A Portal Frame is a frame consisting of precast columns connected at the top by a pitched or sloping horizontal beam. The low pitched roof typically has a 4 slope. Portal Frames are economical to produce and are often associated with industrial or warehouse buildings where a clear span of up to 35m or more is required. It is straightforward to design, provided the flexural rotations at the end of the main portal are achieved. Generally a neoprene pad (or other durable pad) is inserted at the bearing to facilitate this flexibility and to avoid potential damage to the bearing ledge.

Industrial - Portal Frame

Additional Floors In the case of Portal Frames, first floors or mezzanines can be easily constructed by creating a corbel in the column element to facilitate the installation of a secondary post and beam. Dowel bar or pinned connections are generally applied between the column and rafter sections. The horizontal load acting on the gable walls is distributed to the outer columns by single bay (sometimes multi-bay) roof bracing and gable bracing at each end of the building. The diaphragm action of the roof also contributes to the stability of the building.

13

Precast Construction Methods


3.3 Multi-Storey Column & Beam
Much of precast construction is Column & Beam. Todays Column & Beam frames are considerably more advanced than earlier structures. In particular, jointing techniques and composite action between columns, floors and beams have been developed. These have contributed greatly to increases in span capability, material efficiency and reduced costs. Multi-storey buildings can have different column configurations. The most common Multi-Storey Precast Frame type of structure is composed of a combination of continuous (multi-storey) columns at the perimeter and floor to floor (single storey) columns on the inner structure. Other options are to use either single storey or multi-storey columns throughout the structure. Continuous columns (bypassing each floor) have a corbel at each floor level to support the surrounding beams. Spandrel beams are typically positioned between the continuous columns on each elevation. Columns can be manufactured in lengths of up to 24m. However, the most economic length in terms of cost and handling is 15m. The key advantage of continuous columns is speed of installation. Single storey columns which are jointed at each floor level are more often located inside the perimeter of the building*. Spine beams are typically erected over single Storey Columns these columns and are connected using high strength dowel bars in grouted dowel tubes, cast into the beams and columns. Continuous spine beams, resting on and connected to several columns are commonly used. These often cantilever over the end of the last column to facilitate a drop-in beam. See Detail, page 15. With this method of precast construction, buildings are erected one floor at a time with beams placed at the head of columns at one level before the upper level columns are erected and connected through the beams to the columns below. *Note Structures using single storey columns at the perimeter are not uncommon. These structures have continuous edge beams which are jointed to the columns using high tension steel dowels grouted into dowel tubes cast into both columns and beams.

Continuous Spine Beams

14

Precast Construction Methods


Typically, multi-storey precast buildings consist of a combination of Column & Beam and Cross Wall construction where the benefits of each are used to optimise structural and cost efficiencies. Lift shafts and gable walls are common cross wall elements used in conjunction with Column & Beam structures, adding significantly to the structural stability of the building. COLUMN TO BEAM CONNECTIONS
COLUMN TO BEAMBeam CONNECTIONS Precast Concrete
designed for partial continuity over internal support
See Detail Below 35mm Outer Skin 80mm Insulation 35mm Liner Sheet 175mm Purlin

Precast Concrete Beam simply supported on single storey Precast Concrete Columns
Apex Depth 1385

6m Eaves Height

400x400 Precast Column

Continuous Precast Concrete Parapet Columns with Precast Height 1885mm to the Beams connected face of the Columns

Top of Foundation 650mm

DETAIL A: Steel Billet Detail:

Typical Multi-Storey Frame

Column

h Minimising Beam Depth Reducing the depth of the beam effectively reduces Column the depth of the services Precast void (i.e. the space Grouted into soffit). Pocket This between the false ceiling and the floor with High Strength in turn reduces the height of the building which Concrete supplied results in cost savings. Minimising beam depth on-site by Main Grout Tubes is particularly important where a computer floor Contractor or other raised floor is required, increasing the Reinforcing Bars overall floor height.
Beam Cantilever Drop-in Beam

Continuous Spine Beam

Column

single storey Column

Composite beams are frequently used to minimise the beam depth. However, with a composite beam the final loading capacity will not be achieved until the screed is applied. Therefore, in the temporary condition, temporary propping may be required to avoid over-stressing or excessive deflection of the 1.5h min. beam.

Composite Beams 100mm

DETAIL A: Square Corbel Detail:

Engineering Brick

300mm min.

15

Precast Construction Methods


3.4 Cross Wall Construction Housing, Apartments, Student Accommodation, Hotels

Cross wall construction, using precast floors and load bearing walls, is normally associated with multi-storey buildings. This type of construction is ideal for buildings of a cellular structure, for example hotels, offices, student accommodation, housing and apartment developments.

Apartments - Cross Wall Construction

Cross wall multi-storey structures consist of precast floors and load bearing walls, where the walls are designed as the means of primary support. Longitudinal stability is achieved by external wall panels and/or diaphragm action involving the floors and roof, which are connected back to lift cores or staircases, which are also formed by precast wall panels. The system provides a structurally efficient building with main division walls offering a high degree of sound insulation between adjacent dwellings, offices, etc. One of the advantages of cross wall construction is that an early dry box working construction is created, allowing subsequent trades access to achieve a fast build programme using the minimum of wet trades. These walling systems can produce buildings in excess of 20 storeys. However, in the Irish context, structures greater than 10 storeys are rarely required, primarily due to planning restrictions.

3.5 Precast Car Park Frame & Deck

Precast frames are commonly used for basement or roof top car parks, whether independent, free standing or forming part of a mixed development. The majority of car parks in Ireland are concrete column and deck structures. These are specialist structures, but their layout is ideally suited to a precast solution. A typical layout allows a standard bay size in the region of 15.6m x 7.2m which is generally the optimal solution. The 7.2m distance relates to the beam or spandrel span and the 15.6m dimension will suit 400mm thick hollowcore floor units. The use of deep hollowcore units generally negates the need for inboard columns which inhibit vehicle manoeuvrability and obstruct the opening of vehicle doors. Spandrel panels are combined beam and wall panel units. Spandrel panels also act as internal vehicle barriers or as external vehicle barriers when used at the perimeter of the structure. 16

Car Park

Precast Construction Methods


3.6 Mixed Construction
Precast concrete is particularly suited to mixed construction because it readily combines with virtually all other commonly used construction materials. Tried and tested standard details for the interfacing of concrete and other construction materials are well established. Combining precast concrete with steel, cast in situ concrete, masonry and glass maximises the benefits of each material. The most economical result can sometimes be achieved by mixed construction methods. In some projects, the designers requirements can only be met by using mixed construction. Mixed construction requires a considered approach. Nowadays there is increased emphasis Industrial on fire resistance, acoustics, low maintenance Precast Wall Panels and aesthetics. These properties are substantially inherent in concrete, but are not necessarily inherent in substitute materials. Steel, for example, needs substantial fire protection. The substitution of precast elements with steel must be carefully appraised. A good example of mixed construction is steel frame and precast concrete wall panels and floors. Using precast as the dominant form of construction in mixed construction reduces construction time, shuttering and wet trades. The number of reinforcing bars is greatly reduced and site safety is greatly improved by the installation of precast floors which act as safe working platforms. Since most of the construction is carried out in the factory, there is less down-time and noise disturbance. The number of operatives on site is also greatly reduced.

Industrial - Precast Floors

17

Designing for Structural Stability


4.1 Design Approach
When designing multi-storey precast concrete structures, the frame should be considered as an entity and not as a collection of individual components. Consideration of the interaction and relationship between the frame, floors and cladding is critical to the overall building design and particularly to achieving a buildable, cost effective structure. When general requirements including the architectural design have been decided, the structural design can proceed in stages. The following aspects must be considered: Precast Concrete Components Joints Stability Structural Integrity Multi-storey frames are generally analysed in the assumption that they are pin-jointed, braced structures. Stability is provided by concrete or masonry shear walls around staircases and/or lift shafts. Other methods of achieving stability are sometimes employed. In frames up to three storeys high, it may be possible to consider the frame unbraced and to rely for stability on cantilever action in the columns and moment fixity at the foundations.

4.2 Designing for Horizontal Loads

Horizontal loads (predominantly wind loads), are usually transmitted to moment resisting frames or to shear walls by the roof and floors acting as horizontal diaphragms. Diaphragm action can be described as the action of the floor/roof, acting as a deep beam, transmitting applied horizontal forces to the foundations. A diaphragm floor/roof must be capable of sustaining shear forces and bending moments. The precast concrete floor is analysed by considering the slab to be a deep horizontal beam. The floor units must be tied and grouted together at the joints to ensure full plate action of the floor.

4.3 Structural Integrity Design for Accidental Loading

Office Blocks Precast Cladding Panels

The designer must ensure that the building is capable of sustaining local damage without catastrophic failure or progressive collapse. Structural integrity in the context of avoiding progressive collapse is normally obtained by using the fully tied solution incorporating full horizontal and vertical ties. The function of a tie system is to enable the structure to bridge over a section failure and limit the extent of the damage to a localised area. Test information on the performance of precast structures can be obtained from the BRE (UK).

18

Designing for Structural Stability


4.3.1 Progressive Collapse & Stability Ties
Progressive collapse occurs when the collapse of a structural element gives rise to a chain reaction type failure of adjacent structural elements. Such a progressive collapse occurred to the steel truss supported flooring units in New Yorks Twin Towers on September 11th 2001. In relation to the robustness of structures B.S. 8110 Part 1, clause 2.2.2.2. states: Structures should be planned and designed so that they are not unreasonably susceptible to the effects of accidents. In particular, situations should be avoided where damage to small areas of a structure or failure of a single element may lead to collapse of major parts of a structure. To prevent progressive collapse of a precast structure, steel ties anchor the elements to the structural frame. These ties must withstand accidental loads such as fire, explosion or subsidence or the collapse of an adjacent component.

35mm Outer Skin 80mm Insulation 35mm Liner Sheet 175mm Purlin

4.4 Joints & Connections

400x400 Precast Column

The design and construction of joints is the most important aspect of precast construction. Joints provide strength/robustness and transmit forces between the structural components. There are a number of different methods for connecting Parapet units including tie-bars, steel billets or plates, in conjunction with the use of high Height strength grouts. The joint must also be capable of withstanding abnormal loads 1885mm caused by fire, impact, explosion or subsidence. The failure of a single joint should never lead to structural instability.

Top of Foundation 650mm

4.5 Column to Foundation Fixing Detail

A number of factors determine which type of column to foundation fixing detail should be used. These factors include: Design requirements, i.e. fixed or pinned base. Ground conditions. Presence of services around the column base, e.g. drainage, DETAIL A:mains, Steel Billet gas etc. There are three main methods of fixing precast columns to the in situ foundation : 1. Projecting Starter-Bars. 2. Bolt or Baseplate Connections. 3. In situ Pocket Foundation.

Detail:

4.5.1 Projecting Starter-Bars

The number and size of projecting starter-bars is determined by the project engineer to suit design requirements. The starter-bars are cast into the in situ base by the main contractor at locations specified on the drawings. The precast columns can then be erected on the base, with the starter-bars projecting into dowel tubes provided in the precast columns. This method of fixing a precast column to an in situ base is extensively used in medium to high rise buildings where the complete structure is designed as a braced frame and thus a pinned connection is required at the base.

19

oundation 650mm

Designing for Structural Stability


4.5.2 In situ Pocket Foundation
h Precast Column Grouted into Pocket with High Strength Concrete supplied on-site by Main Contractor

The in situ Pocket Foundation will provide a fixed base connection to the precast column, which is particularly useful in low rise precast industrial units where the cantilever action of the column provides the lateral stability for the building, thus reducing the amount of horizontal and vertical bracing required.
100mm

The column is embedded into the pocket pad foundation by a distance of at least 1.5 times the maximum column foot dimension. When structural requirements determine that the column must have a large foot dimension, the in situ pocket foundation can become uneconomical and other foundation solutions should be employed. The main contractor is responsible for the preparation of column foundations. This work must be carried out to a high degree of accuracy to avoid delays in the installation of columns.

1.5h min.

Engineering Brick

300mm min.

4.5.3 Bolted or Baseplate Connections

DETAIL A: Typical Dimensions of Internal Beams

Steel baseplates are attached to the precast concrete column during manufacture by casting-in grade 8.8 threaded bars and bolting the baseplate to the column. Alternatively, mild steel bars can be welded to the baseplate and cast onto the foot of the column during the curing process. The column is then fixed to the in situ foundation using cast-in holding down bolts to form a pinned base connection. Alternatively, the precast column can be fixed onto an existing base using holding down bolts which are drilled into place and fixed using a chemical anchor resin.
h

COLUMN TO BEAM CONNECTIONS

Baseplate equal in size, or less than column size Precast Column Levelling Shim

Four corner pockets with anchor bars welded to baseplate Alternative Baseplate Detail h

40mm min.

Baseplate

Nut & Washer In situ concrete or mortar Tapered Sleeve

1.5h min.

Holding-Down Bolt Holding-Down Plate

200mm min.

In Situ Concrete Foundation

20

Precast Elements
5.1 Columns
The following is relevant to column design: a) Columns are designed for combined axial compression and bending. b) Column bending moments at beam level are determined from the eccentric loading at the connection. c) In the case of slender unbraced columns, the additional moments due to Floor slenderness effects are added to the total design moment at each floor level.
Apex Depth 1385

5.2 Beams

Reinforced or prestressed concrete beams in a precast concrete frame are designed for the specified loadings and support conditions. The beam may be composite or non-composite. Composite beams act with the floor, column and screed to form a monolithic structure.

Flo a) Inverted Tee-Beam

Precast Column - Installation

Beams are typically designed as simply supported with a characteristic concrete strength of between 40N/mm2 and 50N/mm2. Beams generally span from column to column. Alternatively, the beam can cantilever over the end of the column to facilitate a drop-in beam. See diagram page 15.
Floor Floor

Precast beam profiles are generally inverted T-Beams or l-Beams designed to facilitate the support of the precast concrete floor units.

Floor a) Inverted Tee-Beam Floor Floor Floor Floor Floor

Floor

Floor

Floor

Floor

c) Changes in Floor Level

Floor a) Inverted Tee-Beam a) Inverted Tee-Beam Floor

b) Rectangular Beam b) Rectangular Beam Floor

Floor

d) Changes in Floor Level Floor Floor in Floor Level c) Changes Floor Floor

or Floor Floor Floor Floor

Floor

Floor Floor Floor

b) Rectangular Beam d) Changes in Floor Level d) Changes in Floor Level e) Changes in Floore) Level 21 Changes in Floor Level

oorc) Level Changes in Floor Level

Precast Elements
Internal Beams to Column Head Edge Beam to Column Head

Split Level Beams to Column Face

Mid-Height Column Splice Half Joint to Column Arm

Floor Level Column Splice

Beam to Deep Column Corbel

Beam Half Joint

Continuous Beam to Column Head

Beam to Column Face

Beam to Shallow Column Corbel

Beam to Column Haunch

Beam to Column Splice

Continuous Beam to Column Splice Column Baseplate on Retaining Wall

Column in Grouted Pocket

Column on Bolted Shoe or Brackets

Column in Grouted Sleeve

Column on Bolted Baseplate on Pad Footing

5.3 Beam Column Connections

The Steel Billet is a common method of connecting precast beams to precast columns. The billet is cast into the body of the column and projects from the column face to form a seating for the floor beam. Another common method of column to beam connection is the formation of a concrete corbel in the column.

5.4 Precast Floors

DETAIL A: Steel Billet Detail: Safety, quality, and the transfer of the installation process to the manufacturer are factors driving the growing market share for precast floors. Precast concrete units have significant time-saving advantages over propped formwork flooring methods. Reducing the construction programme and presenting the building ahead of schedule for rental are important cost-saving factors.
Units are manufactured to exact standards in factory conditions and installed by Health & Safety trained operatives. In addition, openings can be left for services such as cabling and service hangers and fixings installed as part of the precast sub-contract package. Precast floor units are typically supported by concrete or steel beams or on solid block walls. Precast concrete floors are particularly valued for their excellent sound insulation and fireproofing qualities.

22

Precast Elements
In situ Topping

5.4.1 Selecting a Precast Floor System

There are three main precast floor unit types. The specific structural characteristics of each type must be taken into account in assessing the most suitable option for a particular application. In some applications the structural capabilities such as In situ Infill Hollowcore Slab spanning ability will determine the choice. In short-span buildings, structural and material efficiency or proximity to site might be the determining factor. The most suitable choice is relative to the specific project requirements and conditions.
In situ Topping In situ Topping

Double-Tee Slab Hollowcore Slab

In situ Infill

In situ Topping In situ Topping In situ Topping

Hollowcore Slab Wideslab Double-Tee Slab

In situ Infill Steel Lattice Reinforcing

In situ Topping In situ Topping

Double-Tee Slab Wideslab

Steel Lattice Reinforcing

Precast floor systems have a number of advantages: In situ Topping a) Reduction in Frame Size Precast floors can be designed to act compositely with the structure of the building to reduce frame sizes: e.g. main support beams supporting solid slab and screed can be designed as T-beams.
Wideslab Steel Lattice Reinforcing

b) Progressive Collapse Prestressed composite floors can be tied-in to the main structure and are therefore particularly suited to buildings where progressive collapse is a consideration. c) Diaphragm Action Precast floor slabs together with the structural screed provide a structural deck with full diaphragm action where required in multi-storey buildings.

23

Precast Elements
5.4.2 Hollowcore Floor

Hollowcore slabs derive their name from the circular voids or cores which run from end to end of the slab. The cores can function as cable/services ducts and significantly reduce the self-weight of the slabs, maximising structural efficiency. Units are available in standard 1200mm widths and in depths of 150mm to 500mm. Hollowcore slabs have excellent long-span capabilities, achieving a maximum capacity of 2.3 KN/sq.m over a 16 metre span. The long-span capability is ideal for office, retail or car park developments. Units are installed with or without a structural screed, depending on requirements. Slabs arrive on site with a smooth pre-finished soffit. In car parks and other open structures, pre-finished soffits offer a maintenance free solution.

Hollowcore Floor Units

5.4.3 Solid Wideslab Floors

Solid Wideslab is sometimes referred to as plate flooring which is generally used in residential developments. Wideslab flooring contains an internal mesh/strand which facilitates notching and the forming of opes.

Apartments - Wideslab Floors

There are two distinct types of wideslab: a) In situ screeded slabs 2400mm wide and in depths of 65mm to 200mm deep with spans of up to 7.5m. These slabs are generally for upper floors and have smooth self-finishing soffits. Some manufacturers can apply a specialist painted finish to the soffit as part of the contract. Generally a 75mm structural screed is required. A triangular steel lattice girder reinforcement which projects into the screed can be used to increase the spanning capabilities of the wideslab unit and the overall robustness of the floor. The pre-camber of prestressed units should be discussed with the technical department of the selected precast company. 24

Precast Elements
b) Pre-screeded slabs 150mm to 200mm deep are delivered self-finished for ground floor applications. These slabs are particularly suited to poor ground conditions or where cut and fill is required. Maximum spans of 7.5m can be achieved.

5.4.4 Double-Tee Floor Slabs

Double-Tee floor units are produced in standard widths of 2400mm and in depths of between 250mm and 1000mm. The system offers greater structural capacity at longer spans than hollowcore or wideslabs, but often requires a deeper floor zone. The Double-Tee system is the only system which offers a solution for spans over 16m. Note: For design advice, span/load details and material specifications, please contact the Technical Service Department of the relevant precast company.

Double-Tee Floor Units

5.5 Precast Floors with Composite Toppings

Structural toppings can be combined with precast units to produce Precast Composite Floors. The advantage of Precast Composite Floors is the increased bending and flexural stiffness. Structural toppings can also be specified to improve acoustic performance and reduce vibration. In situ toppings will also improve thermal performance. Structural toppings are generally 75mm to 100mm thick and it is recommended that their thickness should not be less than 50mm. Provided there is sufficient anchorage/bonding with the precast unit, the topping and unit can be considered as a monolithic.

25

Precast Elements
5.6 Checking Calculations
The following items should be checked when designing precast floors: Applied Loading Assumed Loading Distribution Design Assumptions (structural screed, temporary propping, etc.) Section Size Strand Pattern - Number and Location of Prestressing Strands Fire Rating Cover Service Stresses - Allowable vs Actual Ultimate Bending Moments - Allowable vs Actual Ultimate Shear - Allowable vs Actual Deflection Workshop Drawings It is important that design assumptions made about the slab are reflected in the production drawings used to manufacture the slabs. For example, the drawings should confirm the designed reinforcement strand pattern, whether open cores are required for forming stability tie details and if temporary propping is required while pouring the structural screed. Slab Widths All three flooring systems can be produced in narrower widths than the standard widths indicated. However, sq.m prices for off-standard widths are higher than for standard widths. Consequently, buildings designed on grids which are a multiple of 1200mm will maximise the cost benefit of precast floors.

5.7 Precast Stairs

Precast stairs do not require the propping and fixing which is necessary for cast in situ stairs. Stair units are connected to floors and landings using steel angle joints. Other connections such as continuous halving joints and intermittent halving joints are sometimes used. Combined stairs and landing units are also available. Once installed, precast stairs allow immediate, safe access to upper floors for following trades. Precast stairs are particularly cost effective when duplicated. The greater the number of identical units required, the lower the cost.

5.8 Precast Balconies

Precast balconies are manufactured mainly for use in apartment complexes. Units have steel bars projecting from the back which tie-in with the steel mesh in the structural screed of the precast floor units. Balcony units are temporarily supported while the structural floor screed is being poured. When the screed has set, the supports are removed leaving the balcony unit cantilevered from the floor edge. Precast balcony units typically have integral drainage slots to receive drainage outlets and an upstand to facilitate proper weatherproofing details at door threshholds.

Student Accommodation Precast Stairs

Apartments Precast Balconies

26

Precast Elements
5.9 Architectural Cladding Panels
Factory produced concrete cladding offers virtually unlimited scope for architectural expression. There is a wide range of high durability, low maintenance surfaces, including both integral and applied finishes. Both highly polished and textured finishes are achievable. Brick, tile, marble and granite are typical finishes, but virtually any decorative stone can be applied. The most cost effective wall panels comprise of reconstituted stone, i.e. naturally coloured, designed and finished to look like natural stone. Panels are typically 150mm thick and may be up to 9m in length and 3.8m high. Panel sizes are generally only limited by transport and cranage constraints. When installed, cladding panels may be either stacked off the ground, one above the other, thus transferring all vertical loads directly to the ground, or alternatively they may be independently supported at each floor level by means of localised concrete corbels. Lateral fixings are secured to either beams or columns. The main advantages of precast cladding are: Tight quality control measures are in place both pre and post casting. Installation is swift and panels are typically sized so that they can span grid to grid and floor to floor, allowing a large area of the building to be weathered in the shortest time possible. No scaffolding is required as all fixings are accessed from the rear of the panels. In most cases, glazing units and insulation may be fitted to the precast units in the factory, speeding up the work of following trades. To make precast units more cost effective, it is important that panel sizes are maximised and a degree of repetition exists. This approach ensures that a number of panels may be cast from a single mould.

Offices - Precast Architectural Cladding Panels - Polished

27

Precast Elements
5.10 Architectural Wall Panels Rain Screens

Office - Precast Cladding Panels - Curved

Precast wall panels are high strength units which can be quickly installed with little or no site preparation. Natural stone blend, reconstituted stone and terracotta -faced panels are available. Panels arrive on site complete with fixing brackets. The wall is lifted into position and attached to the column which can be either concrete or steel. Connections between floors, beams, columns and wall panels are designed to ensure that all loads, both lateral and vertical, are transferred along the dedicated load path to the appropriate foundation/ restraint. Because the loads acting on the panel are transferred into the column, no strip foundation is required. Precast walls can function simply as security walls or may act as a bearing for precast floor units.

5.11 Architectural Composite Panels

Precast wall panels have been used as rain screens in Ireland for many years. However, Composite Panels are now being manufactured which comprise of an outer leaf of finished concrete (or terracotta tile), a layer of insulation and a backing leaf of plain grey concrete, cast as a single unit. The insulation is installed under controlled factory conditions and is protected from the elements by the concrete outer leaf. To fully optimise the system, the inner leaf of the sandwich panel can be used as a load-bearing element to support floor units, thus offering further economies in the building and minimising the need for co-ordination of different trades. Wall panels can eliminate the following on-site activities: Foundation laying Block laying Plastering

Office - Precast Brick-Faced Panel

Precast Composite Panel

28

Production
6.1 Development of Component Drawings
On confirmation of the clients order, the scope of the work is first analysed by the production team. When technical and production issues have been resolved, production is then scheduled. As the project progresses, correspondence is referenced and stored. Working drawings are then produced by the manufacturers office in consultation with the clients consultants. All relevant information, such as the position of fixings, penetrations, cast-in items, openings, lifting anchors, etc., is clearly noted on the drawings. The production details are then forwarded to the consultants for approval. Production can take place when formal approval has been received from the project principals.

6.2 Production Scheduling


Apartments - Precast Cladding Panels

The production of precast components is scheduled to meet the production programme. Machine changes and mould alterations are kept to a minimum to achieve the most efficient batch production. This can only be achieved with the co-operation of the entire project team.

6.3 Materials

Most precast companies have computer controlled batching and mixing plants. Complex mixes for a variety of different concrete products are stored in the batching plant systems. This is an important facility since accurate sand/cement/ gravel/water mix is critical to the integrity and durability of precast components. Precast components are reinforced by inserting steel bars or cages into the mould. Steel is generally cut and bent into the required shape. This can be done manually or by automated means. An alternative to steel cages or strands is the use of fibre reinforcement. The fibres used can be produced from steel, glass or synthetic materials such as polypropylene. Certification of all materials is available from the precaster on request.

Battery Moulds - Precast Wall Panels

29

Production
6.4 Moulds
Adjustable

The main mould types include: long-line mould systems can be used to cast a variety of beam and column sections. The flexibility to pour sections, in a range of sizes, from one mould, ensures optimum productivity and facilitates the quick turnaround of precast components required on fast-track construction programmes.
Battery moulds consist of a series of steel faced sections with variable perimetral

formers positioned to form the required dimensions. These sections open apart to allow preparatory work and are then mechanically closed and clamped together to form a multi-cast mould. Typical applications would include retainer wall panels and other panel sections complete with door and window openings, suitable for apartment or housing developments.
Specialised

or bespoke moulds are manufactured to produce a specific oneoff range of products. Moulds can be manufactured from different materials such as plywood, steel or fibreglass and may be lined with a range of purpose-made patterned liners to imitate natural finishes. The choice of mould material is usually determined by the number of casts required and the complexity of the shape and size of the finished product. Specialised moulds can be adjusted and may be used for similar projects in the future.

6.5 Production Techniques


Floors Hollowcore and Wideslab units are manufactured on long-line steel casting beds, using automated casting techniques. The mix design and volumes of concrete required are programmed into the system. The steel beds are thoroughly cleaned prior to use and a release agent is applied to produce a quality surface finish. Reinforcing strands are placed on the bed and hydraulically tensioned. The concrete is then placed onto the bed and compacted mechanically by extrusion or slipform machines. All necessary slots and opes are electronically marked and cut. Wall Panels Panels can be produced in flat beds, vertical battery moulds, horizontal tilting tables or carousel systems. Most panels require steel or other reinforcement. The reinforcing steel is placed in the mould and the concrete mix is then poured. Wall panels produced in vertical battery moulds have a smooth surface on both sides. Panels produced on tilting moulds have one side mechanically finished and one side with a trowelled finish. A trowelled finish is used where walls have further finishes applied or where the face of the panel is concealed inside a cavity wall. Lifting handles are cast-in which are used in the de-moulding process and when erecting the finished units on site.

Hollowcore Floor Manufacture

30

Precast Panel Polishing

Production

Wall Panels - Flat Bed Production


Columns & Beams Columns & Beams are cast in horizontal moulds or in long-line moulds. Precasters typically have a range of standard moulds which cater for the most commonly specified column and beam sizes. However, specials can be manufactured to specified dimensions by making simple adjustments to the mould. Circular columns can also be produced in vertical cast arrangement to comply with architectural and structural requirements. Stairs A number of systems are available for casting stairs. Stairs can be produced in bespoke moulds or in variable moulds. Units can be cast in the upright position or in the inverted position. Alternatively, units can be vertically cast on their edge giving a mould finish to the top and back of the stairs and leaving one side to be hand finished. Straight stair units, or a combined stairs and landing unit can be produced in a variety of finishes.

6.6 Curing

The curing process is an important part of component manufacture. Heating the concrete accelerates curing. Heat is applied in various ways such as steam or hot water running through a network of piping. Other methods include the use of hot air and the application of electrical current through reinforcing strands which act as heating elements. Covering the components with insulating sheets to retain heat and moisture helps the curing process.

31

Production
6.7 Quality
Considerable emphasis is placed on quality control at all stages in the production of precast concrete components. Many Irish precasters manufacture in accordance with ISO 9002 standards or with other internal quality systems. Key areas of quality control include: Test certificates for materials - cement/reinforcement/aggregates Aggregate testing Compressive strength testing Workability Mould standard and quality Preparation of reinforcement cages/strands Cast-in components and fittings Dimensional checks Assessment of early age strength for de-moulding/transfer strength, etc. Quality of finish

Storage Yard - Precast Cladding &Cross Walls - Apartments/Housing

6.8 Handling and Storage

When the units have reached the required strength, they are removed from the mould and labelled for later identification. They are then stacked on wooden battens or plastic pads.

32

Site Erection
7.1 Method Statement
The principles of site erection, the methods of making structural joints and the specification for materials are all in accordance with the requirements of BS 8110. At the commencement of each project a method statement confirming how the building will be manufactured, transported and installed should be prepared. The headings covered in this statement include: Safety (including the mandatory safety statement) Mould-work Materials Handling/Cranage and Transportation Site Installation (Procedure, Programme, Sequence) The design for temporary conditions during erection should take into account overall frame stability and the stresses in individual frame components and joints. Load paths through a partially completed structure may be different for those in a completed frame. An example is the temporary state when floor units have been placed on one side only of an internal beam. Here the connection should be checked for its resistance to torsion and if necessary, propped until the slabs on the other side of the beam are placed in position.

Precast Columns, Beams &Floors

7.2 Columns

Columns are typically erected in pockets onto pre-levelled plates giving a clearance of between 50mm to 75mm to the sides and bottom of the pocket. Temporary wedges are driven into the pockets and together with diagonal props are used to line and plumb the column. In situ concrete with an early strength of about 40 N/mm2 at three days is compacted into the pockets to ensure that a structural connection is made between the column and the foundation.

7.3 Beams

Beams are either grouted through sleeved connections between upper and lower columns or are supported on billet type corbels. Bolted cleat type connections or billets with a welded or bolted top fixing provide an immediate restraint to shear and torsional forces. Dowelled corbels and billets which depend on an in situ top fixing do not provide adequate restraint and temporary propping will be required to stabilise the beam. High strength grouts are used in all cases. Strengths of 30N/mm2 are required after eight hours.

7.4 Construction Speed

Installation times for precast units vary with each project, but the following rates of installation (based on one erection crew) are indicative.

Precast Cross Walls

single storey Columns Spine Beams or Edge Beams Wall Panels Floor Slabs Stairs and Landings

12 14 per day 12 15 per day 12 18 per day 350m2 per day 12 15 per day

33

Site Erection
7.5 Access and Cranage
Safe access to the site is a key consideration which must be agreed between the main contractor and the precaster prior to commencement on site. Suitable hard standing for cranage and articulated vehicles must also be provided. Ground floors or platforms used as storage spaces must be structurally stable and level. The position of the crane must be carefully planned to ensure that its capabilities are maximised and the installation period minimised. The following are some of the issues which should be taken into consideration before choosing a crane and finalising the construction sequence:
Public safety and on-site safety Access to public roads Component sizes and weights Maximum reach of the crane from

set-up position to final panel installation Any constraints such as overhead power lines Availability of secure standing areas for cranage

Telescopic Crane

34

Appendix
Appendix - Structural Details
Precast structural details deal with the connection of the precast concrete components to form a fully integrated structural frame. While some details are company specific or proprietary connection systems, generally all are based on tried and tested design assumptions and construction practices. For example, the steel insert or billet connection is a refinement of the traditional corbel support. Some of the proprietary bolted connections are modelled on connection systems used to connect structural steelwork elements. The following details are commonly used in connecting precast frame elements in Ireland. The details indicated are a guide only and are not related to a specific project. Project specific details should be produced by the design engineer taking all relevant factors into consideration.

Typical Precast Construction Components


4

6 12 14 13 8 7
1 Main Spandrel Beam 2 Hollowcore Unit 3 Internal Rectangular Beam 4 Gable Spandrel Beam 5 Gable Beam 6 Main Edge Beam 7 Landing Support Beam 8 Staircase and Landing 9 Ground Beam 10 Column 11 Wall 12 Double-Tee Unit 13 Internal Beam 14 Main Edge Spandrel Beam

11 10

35

COLUMN TO BEAM CONNECTIONS

COLUMN TO BEAM CONNECTIONS

Precast Column

Non-Shrink Grout

Precast Gutter Dowel Fixed to Roof Beam

Precast Prestressed Roof Beam

Bearing Pad Spiral Tube Cast into Precast Column Dowel Bar Grouted into Position using Non-Shrink Grout

36

DETAIL 1: High Parapet Concealed Gutter Detail

COLUMN TO BEAM CONNECTIONS

COLUMN TO BEAM CONNECTIONS

Non-Shrink Grout

Precast Gutter Dowel Fixed to Roof Beam

Precast Prestressed Roof Beam

Bearing Pad Spiral Tube Cast into Precast Column Dowel Bar Grouted into Position using Non-Shrink Grout

Precast Column

DETAIL 2: Eaves Gutter Detail

Non-Shrink Grout

Precast Gutter Dowel Fixed to Roof Beam

Precast Prestressed Roof Beam

Bearing Pad Spiral Tube Cast into Precast Column Dowel Bar Grouted into Position using Non-Shrink Grout

Precast Column

DETAIL 3: Valley Gutter Detail

37

COLUMN TO BEAM CONNECTIONS

COLUMN TO BEAM CONNECTIONS

Steel Tie-bar Slotted Through Precast Column Precast Column

Non-Shrink Grout

Position of Structural Precast Screed Flooring Unit

Precast Beam Non-Shrink Grout

Precast Beam Non-Shrink Grout

Dowel Bar Cast into Column Corbel

38

DETAIL 4: Detail at Splayed Corbel

COLUMN TO BEAM CONNECTIONS


Precast Column

COLUMN TO BEAM CONNECTIONS

Steel Tie-Bar Slotted Through Precast Column

Non-Shrink Position of Precast Flooring Unit Structural Screed Grout

Precast Beam Non-Shrink Grout Steel Billet

Precast Beam Non-Shrink Grout

Steel Dowel Welded To Steel Billet

DETAIL 5: Steel Billet Detail


Precast Column

Steel Tie-Bar Slotted Through Precast Column

Non-Shrink Position of Precast Flooring Unit Structural Screed Grout

Precast Beam Non-Shrink Grout

Precast Beam Non-Shrink Grout

Steel Dowel Cast into Column Corbel

DETAIL 6: Square Corbel Detail

39

COLUMN TO BEAM CONNECTIONS

COLUMN TO BEAM CONNECTIONS

Precast Column Grout Tubes Cast Into Spine Beam to Take Projecting Tie-bar Non-Shrink Grout

Position of Hollowcore Units

Grout Tubes Cast Into Precast Columns and Beams for Vertical Ties

DETAIL 7: Non-Continuous Column and Spine Beam Connection

Continuous Multi-storey Precast Column Dowel Tubes and Projecting Bars Non-Shrink Grout

Precast Beam

Precast Beam

Corbel

Precast Spine Beam

40

DETAIL 8: Continuous Column and Spine Beam Connection

FLOOR FLOOR TO TO BEAM BEAM CONNECTIONS CONNECTIONS - HOLLOWCORE HOLLOWCORE FLOOR FLOOR

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

Precast Precast Column Column Longitudinal Longitudinal Ties Ties Mesh Mesh Transverse Transverse Precast Precast Unit Unit and and Screed Screed

Peripheral Peripheral Tie Tie In In Situ Situ Concrete Concrete Infill Infill by Main by Main Contractor Contractor

35N 10 Concrete Grout Precast Precast Edge Edge Beam Beam (Reinforcement (Reinforcement not not indicated) indicated) Precast Precast Floor Floor Units Units Built-in Built-in (100mm (100mm End End Bearing) Bearing) Laid on 1:3 Mortar Bed by Main Contractor Laid on 1:3 Mortar Bed - by Main Contractor (Shear (Shear or or Friction Friction Wall Wall Ties) Ties)

DETAIL Side DETAIL 9: 11: Typical Typical EndBearing BearingDetail: Detail: Rectangular RectangularEdge EdgeBeam Beam

Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed

In Situ Concrete Infill by Main Contractor Peripheral Tie Filler by Builder

Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete

Precast Edge Beam (Reinforcement not indicated) Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 10: Typical 5 Storey+ End Bearing Detail: Rectangular Edge Beam

41

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

Precast Edge Beam (Reinforcement not indicated) Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR DETAIL 11: Typical End Bearing Detail: Rectangular Edge Beam

Precast Column Precast Column Longitudinal Mesh Ties Transverse Longitudinal Mesh Ties Transverse Precast Unit and Screed Precast Unit and Screed

In Situ Concrete Infill by Main Contractor Peripheral Tie Filler by Builder Precast Edge Beam (Reinforcement not indicated) Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete 35N 10 Concrete Grout

Precast Edge Beam (Reinforcement not indicated) Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 12: Typical Side Bearing Detail: L-Shaped Beam


42

DETAIL 10: Typical 5 Storey+ End Bearing Detail: Rectangular Edge Beam

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed

Precast Edge Beam (Reinforcement not indicated)

Precast Floor Units Built-in (100mm End Bearing)

DETAIL 13: Typical End Bearing Detail: L-Shaped Beam

Precast Column Longitudinal Ties Mesh When Required Transverse Precast Unit and Screed

Filler by Builder Break Out Hollowcore Floor Unit Cores and Fill with Min. 35N 10 Concrete Precast Edge Beam (Reinforcement not indicated)

Precast Floor Units Built-in (100mm End Bearing)

DETAIL 14: Typical 5 Storey+ End Bearing Detail: L-Shaped Beam

43

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

Precast Column Mesh Transverse Projecting Bar from Spine Beam Precast Unit and Screed

Precast Floor Units (100mm End Bearing) Precast Spine Beam (Reinforcement not indicated)

DETAIL 15: Typical End Bearing Detail: Inverted T-Shaped Spine Beam

Precast Column Mesh Transverse Projecting Bar from Spine Beam Precast Unit and Screed

Filler by Builder Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete Precast Spine Beam (Reinforcement not indicated) Precast Floor Units (100mm End Bearing)

44

DETAIL 16: Typical 5 Storey+ End Bearing Detail: Inverted T-Shaped Spine Beam

FLOOR TO BEAM CONNECTIONS - HOLLOWCORE FLOOR

FLOOR TO BEAM CONNECTIONS - WIDESLAB FLOOR

Precast Column Mesh Transverse Projecting Bar From Spine Beam Precast Unit and Screed

Precast Floor Units (100mm End Bearing) Precast Spine Beam (Reinforcement not indicated)

FLOOR TO Detail: BEAM CONNECTIONS - HOLLOWCORE FLOOR DETAIL 17: Typical End Bearing Inverted T-Shaped Spine Beam

Precast Column Longitudinal Ties Mesh Transverse Precast Unit and Screed

In Situ Concrete Infill by Main Contractor

Precast Edge Beam (Reinforcement not indicated)

DETAIL 18: Typical Side & End Bearing Detail: Rectangular Edge Beam

45

FLOOR TO WALL CONNECTIONS - HOLLOWCORE FLOOR

FLOOR TO WALL CONNECTIONS - HOLLOWCORE FLOOR

External Wall

Internal Wall

Mesh Transverse Turned Down at Perimeter

Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 19: Typical End Bearing Detail: External Wall

External Wall

Internal Wall

Longitudinal Ties Mesh When Required Transverse

Precast Unit and Screed

In Situ Concrete Infill by Main Contractor

Filler by Builder

Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N. Concrete R.C. Band Beam (Peripheral Tie) R.C. Band Beam may not be required if shear/friction joint proves adequate

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

46

DETAIL 20: Typical 5 Storey+ End Bearing Detail: External Wall

FLOOR TO WALL CONNECTIONS - HOLLOWCORE FLOOR

External Wall

Internal Wall

Mesh Transverse Turned Down at Perimeter

Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

35N 10 Concrete Grout Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 21: Typical Side Bearing Detail: External Wall

External Wall

Internal Wall

Longitudinal Ties

Mesh Transverse

Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

35N 10 Concrete Grout R.C. Band Beam (Peripheral Tie) R.C. Band Beam may not be required if shear/friction joint proves adequate

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 22: Typical 5 Storey+ Side Bearing Detail: External Wall

47

FLOOR TO WALL CONNECTIONS - HOLLOWCORE FLOOR

FLOOR TO WALL CONNECTIONS - HOLLOWCORE FLOOR


Internal Wall

Precast Unit and Screed

Mesh Transverse

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 23: Typical End Bearing Detail: Internal Wall

Internal Wall

Precast Unit and Screed

Longitudinal Ties

Mesh Transverse

Filler by Builder

Break Out Hollowcore Floor Unit Cores and Fill with Min. 30N 10 Concrete

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

48

DETAIL 24: Typical 5 Storey+ End Bearing Detail: Internal Wall

FLOOR TO WALL CONNECTIONS - WIDESLAB FLOOR

External Wall

Internal Wall

Mesh Transverse Turned Down at Perimeter

Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

DETAIL 25: Typical Side Bearing Detail: External Wall

External Wall

Internal Wall

Longitudinal Ties

Mesh Transverse

Precast Unit and Screed

In Situ Concrete Infill by Main Contractor Peripheral Tie

R.C. Band Beam (Peripheral Tie)

R.C. Band Beam may not be required if shear/friction joint proves adequate

DETAIL 26: Typical 5 Storey+ Side Bearing Detail: External Wall

49

FLOOR TO WALL CONNECTIONS - WIDESLAB FLOOR

FLOOR TO WALL CONNECTIONS - WIDESLAB FLOOR

External Wall

Internal Wall

Mesh Transverse Turned Down at Perimeter

Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 27: Typical End Bearing Detail: External Wall

External Wall

Internal Wall

Longitudinal Ties

Mesh Transverse

Precast Unit and Screed

Peripheral Tie In Situ Concrete Infill by Main Contractor

R.C. Band Beam (Peripheral Tie)

R.C. Band Beam may not be required if shear/friction joint proves adequate

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

50

DETAIL 28: Typical 5 Storey+ End Bearing Detail: External Wall

FLOOR TO WALL CONNECTIONS - WIDESLAB FLOOR

When using Non-Structural Screeds Internal Wall to be Built Directly Off the Flooring Unit

Internal Wall

Precast Unit and Screed

Mesh Transverse

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 29: Typical End Bearing Detail: Internal Wall

When using Non-Structural Screeds Internal Wall to be Built Directly Off the Flooring Unit

Internal Wall

Precast Unit and Screed

Longitudinal Ties

Mesh Transverse

R.C. Band Beam R.C. Band Beam may not be required if shear/friction joint proves adequate

Precast Floor Units Built-in (100mm End Bearing) Laid on 1:3 Mortar Bed - by Main Contractor (Shear or Friction Wall Ties)

DETAIL 30: Typical 5 Storey+ End Bearing Detail: Internal Wall

51

Members
IRISH PRECAST CONCRETE ASSOCIATION
8 Newlands Business Park, Naas Road, Dublin 22. Tel: 01 4640082 Fax: 01 4640087 email: [email protected]

MEMBERS LIST

Banagher Concrete Ltd.

Queen Street, Banagher Estate, Co. Offaly. Tel: 0509 51417 Fax: 0509 51558 Email: [email protected] www.bancrete.com

Oran Precast Ltd.

Deerpark Industrial Estate, Oranmore, Co. Galway. Tel: 091 794537 Fax: 091 794586 Email: [email protected] www.oranprecast.ie

B.D. Flood Ltd.

Hilltown, Oldcastle, Co. Meath. Tel: 049 41477 Fax: 049 41311 Email: [email protected] www.floodflooring.com

OReilly Bros. Ltd.

Kingscourt, Co. Cavan. Tel: 042 67237 Fax: 042 67311 Email: [email protected] www.oreillyconcrete.com

Concast Precast Group


Hazelhatch, Newcastle, Co. Dublin. Tel: 01 628 8055 Fax: 01 627 2326 Email: [email protected] www.concast.ie

Quinn Group

Derrylin, Co. Fermanagh. Tel: 048 677 48866 Fax: 048 677 48800 Email: [email protected] www.quinn-group.com

Techrete Ireland Ltd.


Dublin Road, Howth, Co. Dublin. Tel: 01 839 0138 Fax: 01 839 0540 Email: [email protected] www.techrete.com

Ducon Concrete Ltd.

Ballymaquirke, Kanturk, Co. Cork. Tel: 029 56037 Fax: 029 56245 Email: [email protected] www.duconconcrete.com

Finlay Breton Concrete Pipes Ltd.


Tullvannon, Ballygawley, Co. Tyrone, BT70 2HW. Tel: 048 855 68441 Fax: 048 855 68447 Email: [email protected] www.finlaygroup.co.uk

52

Apartments &Offices - Brick-Faced Precast Panels

Notes

53

Notes

54

Irish Precast Concrete Association Cumann Concrit Ramhtheilgthe na hireann

Unit 8, Newlands Business Park, Naas Road, Clondalkin, Dublin 22, Ireland. Tel +353 1 464 0082 Fax +353 1 464 0087 Email [email protected] www.irishconcrete.ie

Concrete Built is Better Built


c

You might also like