Approval Procedures
Approval Procedures
Problem Statement
The Montgomery County Zoning Ordinance
can provide a more rational and streamlined
set of approval procedures for its various
development applications while remaining
comprehensive and transparent. A thorough
March 11, 2009
but systematic set of approval for a Project Plan, which was then applied to
procedures will ensure that the the optional method of development in the
following objectives are met: RMX, MXTC, TMX, and TOMX zones.
1. Citizens and developers are The advent of the floating zones, which
able to readily understand the require approval by the District Council, led
steps various development to the four types of rezoning plans we now
applications must take. have:
2. The rigor of the required
reviews and hearings is • Development Plan: R-4plex, R-MH,
balanced against the potential C-Inn, PD, MXPD, TS, PN, PRC,
local and regional impacts. PCC, TS-R, and TS-M zones.
3. Public noticing and the • Diagrammatic Plan: MXN zone.
ability to ensure transparency • Schematic Development Plan: OM,
are retained and enhanced. CT, C-3, RH, CP, HM, RS, LSC, I3,
4. Approval processes are tied and the RT zones.
to development type and
• Supplementary Plan: TS.
impact, not necessarily the
zone in which the
The “Combined Urban Renewal Project
development takes place.
Plan” is only used to expedite project review
5. Redundant processes and
and approval in urban renewal areas
hearings are reduced or
designated under Chapter 56.
eliminated.
6. Submittal requirements are
Most approvals are obtained through the
rational, consistent, and
preliminary and site plan review processes.
focused on providing the
The pre-preliminary plan is a plan seeking
information needed to make
advice (typically non-binding) from
the findings required for
Planning Department staff and/or the
approval.
Planning Board. Preliminary plans are
reviewed by the Planning Board when
Background properties subdivide or re-subdivide. Site
plans are detailed development plans
In 1928 there were basically two
approved by the Planning Board. Record
approval procedures: a certificate of
plats are legal documents that become part
occupancy and compliance was
of the County land records after subdivision
needed coincident with the
or re-subdivision.
application for a building permit and
that building permit required a plat to
Variances are heard by the Board of Appeals
be filed and kept with the office of
when an application cannot meet the
the Building Inspector. Things are a
standards of development for reasons of
little different now.
hardship or unusual circumstances.
For example, the creation of the
Special exceptions are approvals for
CBD zones led to the requirement
permitted uses that have restrictions beyond
the regular development standards is no consistent format to the sections within
typically due to concerns about these approvals and they are not grouped by
nuisances or adverse impacts. the agency with ultimate jurisdiction over
the approval. A better approach would be to
consolidate approval procedures into one
article and begin with a table that outlines
Rewrite Team Solution the processes, the review agencies, and their
After diagnosis of the existing roles:
approval procedures, a review of the
literature on development review,
and research into the review process
of several other jurisdictions, the
zoning rewrite team has come to
several conclusions: