Cementing 1
Cementing 1
Cementing 1
2
), where D is in mm (2a)
or
I = u.Su67 (
o
2
-
2
), where D is in inches (2b)
FIGURE 29: Well OW-910 anchor casing
Bett 122 Report 10
Capacities are as follows:
Casing capacity (13"): 80.64 l/m;
Casing displacement (13"): 90.65 l/m;
(Note: that the steel volume is equal to the difference in the numbers above)
Capacity of open-hole (17"): 155.18 l/m;
Annulus capacity - open hole and casing: 64.53 l/m.
I
shoctuck
= 80.64 l/m (294.7 m 284.1 m) 1 m
3
/ 1000 l = 0.9 m
3
I
uthoIc
= 155.18 l/m (296.3 m 294.7 m) 1 m
3
/ 1000 l = 0.2 m
3
I
opcnhoIc
= 64.53 l/m (294.7 m - 51.2 m) 1 m
3
/ 1000 l = 15.7 m
3
Capacity of previous casing (20") : 185.32 l/m
Casing displacement (13"): 90.65 l/m
Capacity of casing annulus: 94.7 l/m
I
csg
= 94.67 l/m 51.2 m 1 m
3
/ 1000 l = 4.9 m
3
Safety excess factor of 50% on an open hole is used (a rule of thumb where no caliper measurements
are available), hence:
Calculated volume:
Shoe track, I
shoctuck
: 0.9 m
3
Rat hole, I
uthoIc
: 0.2m
3
Open-hole annulus, I
opcnhoIc
: 15.7 m
3
Casing annulus, I
csg
: 4.9 m
3
Calculated volume: 21.7 m
3
I
cxccss
= 16.8 m
3
50% = 8.4 m
3
50% safety margin in open hole 8.4 m
3
Total slurry volume, I
s
: 30.1 m
3
B. Displacement volume
This is the internal volume of casing between the cement head and the float collar (shown in blue in
Figure 29):
Therefore displacement vol. = 80.64 l/m (284.1 m + 11.9 m) 1 m
3
/ 1000 l = 23.9 m
3
C. Placement duration, T
p
Slurry pump rate used = 900 l/min
Displacement rate = 900 l/min
I
p
=
:ol. o slurry
pump rotc
+
Jispl. :ol.
Jispl. rotc
+ plugs Jrop timc + contingcncy timc (3)
Duration (min):
Slurry mixing and pumping: 33
Displacement time: 27
Plugs dropping time: 15
Contingency time: 60
Total placement duration: 135 min
Report 10 123 Bett
D. Pump pressure to land the plug, P
p
P
p
= byJrostotic prcssurc outsiJc cosing -byJrostotic prcssurc insiJc cosing (4)
Density of cement slurry: 1.7 kg/l
Density of fluid inside the casing: 1.0 kg/l
Collapse pressure limit for casing: 7.8 MPa (78 bars)
Hydrostatic pressure (Pa):
P
h
= pgE (5)
Hydrostatic pressure outside the casing: 49.7 bars
Hydrostatic pressure inside the casing: 30.8 bars
Pressure to land plug (excluding friction pressure): 18.9 bars
E. Amount of cement blend and mix-water
Amount o ccmcnt blcnJ =
Slurry :olumc
Slurry yiclJ
(6)
Therefore, the amount of cement blend = 33,074 kg
Hix wotcr = wotcr rcquircmcnt pcr ton o blcnJ omount o ccmcnt blcnJ (7)
Therefore, mix-water required = 18.2 m
3
8.1.2 Well HE-53 in Hverahlid field, Iceland Inner string cementing
Well HE-53 anchor casing, 13" was cemented in place with an inner-string cementing operation.
The details of the operation, as shown in Figure 30, are as follows:
13" 68.0 lb/ft casing set at: 302.5 m
17" hole depth: 304.5 m
18" 87.5 lb/ft previous casing shoe depth: 69.0 m
Cement. string (drill pipe) nominal size: 5", 19.5 lb/ft
The casing was cemented with class A cement with the following specifications and additives:
Slurry density: 1.67 kg/l
Silica (Sibron M-300): 40% BWOC
Lightweight agent, perlite: 2% BWOC
Bentonite (Wyoming): 2% BWOC
Retarder: 0.5% BWOC
A. Slurry volume calculation
Capacities are as follows:
Casing capacity: 78.1 l/m
Capacity of open hole: 155.2 l/m
Annulus capacity open-hole and casing: 64.5 l/m
Capacity of casing/casing annulus: 69.1 l/m
Capacity of the drill pipe: 9.1 l/m
The volume of the hole was measured using a caliper log as shown in Figure 31. The volume obtained
with the caliper log was 26.1 m
3
. To get the open-hole volume, the volume between the casing string
is subtracted from the caliper log volume.
Bett 124 Report 10
A 20% safety excess factor is used in the open hole section with a caliper log measurement (a rule of
thumb where a caliper measurement is available).
Caliper vol. (m
3
) Calculated vol. (m
3
)
Shoe track: 1.6 1.6
Rat hole & casing/open hole: 21.3 15.4
Casing/casing annulus: 4.9 4.9
Total volume: 27.8 21.9
20% and 50% excess respectively: 4.3 7.7
Total slurry volume: 32.1 m
3
29.6 m
3
In this case, the rule of thumb method works well comparing with and without a caliper log. Caliper
logs should be used because the hole washout and caving can sometimes be excessive and thus an
excess factor based on local and previous wells should be used if available.
B. Displacement volume
This is the internal volume of a drill pipe between the rig floor and the stab-in collar.
Therefore displacement vol. = 2.64 m
3
C. Placement duration, T
p
Slurry pump rate used = 1000 l/min
Displacement rate = 1000 l/min
Ip =
:ol. o slurry
pump rotc
+
Jisploccmcnt :ol.
Jisploccmcnt rotc
+contingcncy timc (8)
FIGURE 31: Well HE-53 caliper log FIGURE 30: Well HE-53 anchor casing
Report 10 125 Bett
Duration (min)
Slurry mixing and pumping: 32
Displacement time: 3
Contingency time: 60
Total placement duration: 95 min
Note: The displacement time is much shorter in inner string cementing compared to single stage
cementing which in turn leads to reduced placement duration.
D. Maximum pump pressure at surface, P
a
P
u
= cosing collopsc prcssurc limit - Jicrcntiol byJrostotic prcssurc ot collor ]oint (9)
Density of cement slurry: 1.67 kg/l
Density of fluid inside the casing: 1.0 kg/l
Collapse pressure limit for casing: 13.4 MPa (134 bars)
It is necessary to have the casing full of water/mud at all times during a cementing operation to
minimise chances of collapsing the casing. The weakest point in the casing and the most susceptible
to collapse is the stab-in collar joint. Using Equation 5:
Pressure (bars)
Pressure from cement slurry at the collar joint: 46.3
Pressure from fluid inside casing at collar joint: 28.5
Differential pressure at collar joint: 17.8
Collapse strength of casing: 134.0
Maximum pump pressure at surface: 116 bars
Note: Due to the friction in the drill pipe string, the downhole pressure will be lower.
8.2 Cement slurry design
Cement slurry is to be prepared using Class A cement and fresh water using the following dry-mixed
additives BWOC: 40% silica flour, 2% bentonite, 2% perlite and 0.5% HR-12 retarder. The cement
slurry density, water volume and slurry yield is calculated for 100 kg of cement.
Slurry density d is given by:
J =
moss o (ccmcnt + wotcr + bcntonitc + silico + pcrlitc + rctorJcr)
:olumc o (ccmcnt + wotcr + bcntonitc + silico + pcrlitc + rctorJcr)
(10)
The specific gravities of cement, bentonite, silica flour, perlite and HR-12 retarder are 3.14, 2.65, 2.63,
2.2 and 1.22, respectively (Bourgoyne Jr. et al., 1991). Using the materials specific gravities in
Equation 10, slurry density, d, is then given by:
J =
1uu + c +(Z + 1)b + ( +1)s + (X + 1)p + r
1uu
S.14
+
c
1
+ [Z +
1
2.6S
b + [ +
1
2.6S
s [X +
1
2.2
p +
r
1.22
(11)
Water volume, E is given by:
E = c + Zb + s + Xp (12)
Note: There is no water requirement for HR-12 retarder (Bourgoyne Jr. et al., 1991).
Bett 126 Report 10
Slurry yield v is given by:
: =
1uu
S.14
+
b
2.6S
+
s
2.6S
+
p
2.2
+
r
1.22
+ c +Zb +s + Xp
(13)
Data values are as follows:
e = 46 l for class A cement
Z = 5.3 l per kg of bentonite when dry mixed (Gabolde and Nguyen, 2006)
Y = 0.4 l per kg of silica
X = 7.8 l per kg of perlite (Bourgoyne Jr. et al., 1991).
Equations 11, 12 and 13 give the following solutions for 100 kg of cement:
Slurry density, d = 1.69 kg/l; Water volume, E = 88.2 l; Slurry yield, v = 137.3 l.
8.3 Pressure to lift the casing
There may be danger of the casing being pumped out of the well, especially surface and intermediate
(anchor) casing. Conditions which favour such an occurrence include: lightweight casing, short
casing string length, large-diameter casing, high-density slurry, low-density displacement fluid and
high annular friction pressures. The forces acting on the casing while cementing are as shown in
Figure 32. Under static conditions, differential pressure F is given by:
F = (P
h
A) - (w
c
+ w
d
) (14)
When pumping, the pressure acting on the cross-sectional area internal diameter (ID) must be added to
Equation 14 as shown below:
F = |(P
h
A) + (P
p
o)] - (w
c
+w
d
) (15)
If F is positive, the casing may come out of the well. The value of P
p
giving a F value of zero is the
critical pump pressure above which the casing may be pumped from the well. The cementing service
FIGURE 33: Balanced plug
FIGURE 32: Forces acting on casing
while cementing (Nelson, 1990)
Report 10 127 Bett
crew should ensure that the pump pressure during cement placement does not exceed this value unless
the casing is restrained (Nelson, 1990).
The case study in Section 8.1.1 for well OW-910 is used to check if there is danger of floating the
casing out of the well: 13", 54.50 lb/ft (79.5 daN/m) anchor casing which was set at 294.7 m depth
with 1.7 kg/l cement slurry and 1 kg/l water for displacement, the float was set at 284.1 m. Casing
external diameter (D
o
) is 339.7 mm and internal diameter (D
i
) is 320.4 mm. Under static conditions:
F = [1.72 10
3
9.81 294.68 /4 (339.7/1000)
2
] - [((294.68 + 11.9) 79.5) +
(1.0 10
3
9.81 (284.12 + 11.9) /4 (320.4/1000)
2
) + (1.72 10
3
9.81
(294.68 284.12) /4 (320.4/1000)
2
)]
= 178 kN
From the above calculations, it can be seen that the casing will come out of the well even in static
conditions.
The pump pressure, P
p
, to pump the plug as calculated in sub-section D of section 8.1.1 is 18.9 bars.
Apart from the positive upward-acting differential force, with the pump pressure acting on the inside
of the casing, the additional force due to pump pressure F
p
is:
F
p
= 152 kN
Therefore, the total force, F
T
, acting on the casing is:
F
T
= 330 kN
In this case, the total force acting on the casing while cementing is acting upwards and unless the
casing is restrained, it could be lifted out of the well. The rheology of the slurry also creates friction to
prevent the casing from moving up.
8.4 Cement plug balancing
A cement plug is required in a 12" open hole, as shown in Figure 33, with a length L of 90 m by use
of a 5", 19.5 lb/ft drill pipe. The plug is to be set at 725 m depth as shown in Figure 33 and 1.5 m
3
of
polymer spacer V
sp1
(1.0 m
3
polymer and 0.5 m
3
water) is to be used as pre-flush ahead of the cement
slurry.
Open hole capacity C
h
: 76 l/m
Drill pipe capacity C
dp
: 9.1 l/m
Length of drill pipe being used D: 733 m
Annulus capacity between drill pipe and open hole C
an
: 63.4 l/m
The required volume of cement (V
cmt
) is given by:
I
cmt
= I C
h
(16)
Thus:
I
cmt
= 9u
76
1uuu
= 6.84 m
3
The length of the balanced plug Lp (with work string in place) is given by:
Ip =
I
cmt
C
un
+ C
dp
(17)
Thus:
I
p
=
6.84
[
6S.4
1uuu
+ [
9.1
1uuu
= 94.S m
Bett 128 Report 10
The displacement volume (V
d
) is given by:
I
d
= C
dp
( - I
p
) (18)
Thus:
V
d
= 5.7 m
3
The following should be noted when placing a cement plug:
1. In practice, the cement is frequently slightly under-displaced from the balance point to allow
cement slurry to fall while the pipe is being pulled, filling the space that was occupied by the
drill pipe.
2. High density spacer (polymer) is pumped ahead of slurry and water spacer is used for
displacement.
3. It is good to rotate the drill string while setting the plug to monitor that it is free.
4. There is a risk of cementing tubing getting stuck, especially when the duration of placement is
longer. The use of drill pipe wholly as a cementing tubing is not recommended. In Iceland,
3" fibreglass cementing pipes are being used at the lower portion of the cementing string
which can be drilled out.
9. CONCLUSIONS
The main conclusions of this work can be summarized as follows:
A good and sound cement sheath is achieved when the wellbore is well conditioned before
running the casing. It must be ensured that drilling mud cake is removed as much as possible as
this ensures proper bonding between the casing and formation.
The casing string should be well centralized in the wellbore to attain a good cement sheath all
around the casing. This will be achieved by ensuring the minimum stand-off of 70% in critical
sections of the well.
Bottom hole circulation temperature is very critical in the design of cement slurry and accurate
prediction is necessary as it affects the slurry thickening time and rheology.
The inclusion of silica flour in the design of cement slurry for geothermal wells ensures
longevity of the well since it helps prevent strength retrogression which occurs when cement
sheath is exposed to elevated temperatures of more than 120C.
The conditions encountered in the wellbore vary from one well to another and therefore pilot
tests of cement slurry should be conducted for each cement operation.
Cementing calculations have to be done cautiously, taking into consideration the experience of
the field being drilled, to ensure that correct volumes are pumped to avoid cases of wet shoe that
come as a result of over-displacement of cement. This also ensures that pressure limits are not
exceeded resulting in burst casings or fractured formations.
ACKNOWLEDGEMENTS
I would like to sincerely thank the UNU Geothermal Training Programme Director, Dr. Ingvar B.
Fridleifsson and Deputy Director, Mr. Ldvk S. Georgsson for offering me the opportunity to take
part in the programme. I would also like to extend my gratitude to the other UNU-GTP staff: Ms.
Thrhildur sberg, Mr. Ingimar G. Haraldsson, Ms. Dorthe H. Holme and Mr. Marks A.G. Wilde, for
their assistance and support during my stay in Iceland. Many thanks go to Mr. Sverrir Thrhallsson of
SOR for good guidance and sharing of valuable knowledge and experience throughout my training. I
would like to sincerely thank my supervisors from Mannvit Engineering, Hannes Sverrisson and
Hinrik A. Basson for their good guidance and technical support during my project report writing. My
Report 10 129 Bett
sincere thanks also go to Arnar B. rnason for the technical data and support. I would also like to
thank my employer, KenGen under the directorship of Mr. Edward Njoroge for granting me the
opportunity to attend the training programme.
Special thanks go to all my family members, especially my wife and son for their moral support.
Above all, I would like to sincerely thank the Almighty God for good care, protection and guidance
during the six months training in Iceland.
NOMENCLATURE
A = Cross-sectional area (m
2
);
a = Cross-sectional area for casing ID (m
2
);
b = Weight of bentonite per 100 kg of cement (kg);
csg = Casing;
d = Slurry density (kg/l);
Di = Inside diameter (mm);
Do = Outside diameter (mm);
e = Volume of cement hydration water in relation to cement (l);
g = Acceleration due to gravity (9.81 m/s
2
);
H = Fluid column height (m);
p = Weight of perlite per 100 kg of cement (kg);
P
p
= Pumping pressure (N/m
2
);
P
h
= Hydrostatic pressure of cement slurry (N/m
2
);
r = Weight of retarder per 100 kg of cement (kg);
s = Weight of silica flour per 100 kg of cement (kg);
v = Slurry yield (l);
I
shoctuck
= The cement volume left inside the casing below the float collar
I
uthoIc
= The cement volume in the open hole below the guide shoe
I
opcnhoIc
= The cement volume in the annulus between the casing and the hole wall
(up to the previous casing shoe).
I
csg
= The cement volume in the annulus between the casing and the previous casing
I
cxccss
= The excess added for the uncertainity of the open hole volume
I
s
= Total slurry volume,.
Wc = Casing weight (N);
W
d
= Weight of fluid inside casing (N);
X = Amount of water per kg of silica (l);
Y = Amount of water per kg of silica (l);
Z = Amount of swelling water per kg of bentonite (l);
= Fluid density (kg/m
3
).
REFERENCES
API, 2009: Hydraulic fracturing operations well construction and integrity guidelines (1
st
edition).
API Publishing Services, Washington, API guidance document HF1, 32 pp, website:
http://www.energyindepth.org/wp-content/uploads/2009/03/API-HF.pdf.
Berndt, M.L., and Philippacopoulos, A.J., 2002: Incorporation of fibres in geothermal well cements.
Geothermics, 31, 643-656.
Bourgoyne Jr., A.T., Millheim, K.K., Chenevert, M.E., and Young Jr., F.S., 1991: Applied drilling
engineering (2
nd
printing). Society of Petroleum Engineers, Richardson, Texas, 508 pp.
Bett 130 Report 10
Bush, G., and O'Donnell, K., 2007: Global cementing best practices (Rev. 1). Occidental Oil and Gas
Corp., Global Drilling Community, 65 pp.
CaseTech International, Inc., 2010: Cementing methods and equipment. CaseTech International, Inc.,
website: www.scoretrinidad.com/downhole-tools/CASETECH_BROCHURE.pdf, 53 pp.
Crook, R., 2006: Cementing. Chapter 9 in: Lake, L.W., and Mitchell, R.F. (eds.), Petroleum
engineering handbook, vol. II: Drilling engineering. Society of Petroleum Engineers, Richardson,
Texas, 369-431.
Drilling and Completion Committee, 1995: Primary and remedial cementing guidelines. Drilling and
Completion Committee, Alberta, Canada, 17 pp.
Gabolde, G., and Nguyen, J.P., 2006: Drilling data handbook (8
th
edition). IFP publications, Editions
Technip, 541 pp.
Gaurina-Medimurec, N., Matanovic, D., and Krklec, G., 1994: Cement slurries for geothermal wells
cementing. Rudarsko-Geolosko-Naftni Zbornik, 6, 127-134.
Hernndez, R., and Bour, D., 2010: Reverse-circulation method and durable cements provide
effective well construction: A proven technology. Proceedings of the 35
th
Workshop on Geothermal
Reservoir Engineering, Stanford University, Stanford, California, 4 pp.
Heriot-Watt University, 2010: Drilling engineering. Heriot-Watt University, Depm. of Petrol. Eng.,
website: www.4shared.com/document/8oA1j29G/Heriot-Watt_University_-_Drill.html, 539 pp.
Hole, H.M., 2008: Geothermal well cementing. Petroleum Engineering Summer School, Dubrovnik,
workshop 26, 6 pp.
Iverson, B., Maxson, J., and Bour, D., 2010: Strength retrogression in cements under high-
temperature conditions. Proceedings of the 35
th
Workshop on Geothermal Reservoir Engineering,
Stanford University, Stanford, California, 8 pp.
Kabinoff, K.B., Ekstrand, B.B., Shultz, S., Tilghman, S.E., and Fuller, D., 1992: Determining
accurate bottomhole circulating temperature for optimum cement slurry design. Society of Petroleum
Engineers Western Regional Meeting, Bakersfield, California, 8 pp.
Kutasov, I.M., and Kagan, M., 2002: Procedures to correct temperatures for deep offshore well. Oil
and Gas Journal, 100-49, 56-61.
Nelson, E.B. (ed.), 1990: Well cementing. Schlumberger Educational Services, Texas, 487 pp.
Niggemann, K., Samuel, A., Morriss, A.V., and Hernndez, R., 2010: Foamed cementing geothermal
13 3/8" intermediate casing. Halliburton, NGP 61-22, 11 pp.
Ogbonna, F.J., 2009: The secondary effects of lignosulfonate cement retarder on cement slurry
properties. ARPN J. Eng. & Appl. Sci., 4-9, 7 pp.
Rabia, H., 1985: Oilwell drilling engineering: principles and practice. Graham & Trotman, London,
322 pp.
Rabia, H., 2001: Well engineering and construction. Entrac Consulting, 789 pp.
Shyrock, S.H., and Smith, D.K., 1982: Methods of combating lost circulation during drilling and
casing cementing. In: Geothermal Resources Council Special Report No. 12, 67-80.
Thrhallson, S., 2010: Geothermal drilling technology. UNU-GTP, Iceland, unpublished lecture
notes, 41 pp.
Weatherford (publ.), 1986: Cementing program. Weatherford.