What Is Nominated Contractor
What Is Nominated Contractor
What Is Nominated Contractor
12
WHAT IS NOMINATED CONTRACTOR DEFINITION OF NOMINATED SUB-CONTRACTOR In the Contract, nominated Sub-contractor means a Sub-contractor: (a) Who is stated in the Contract as being a nominated Sub-contractor, or (b) Whom the Engineer or Employer, under Clause 13 [Variations and Adjustments], instructs the Contractor to employ as a Sub-contractor subject to Sub-Clause 5.2 [Objection to Notification]. In general Nomination is the process by which the Employer nominates, selects or approves who will perform a subcontract or specialist trade role ("NSC"). The NSC then enters into a sub-contract with the Main Contractor ("MC"). It is a means for the Employer to retain some control over the selection of specialist contractor or supplier without necessarily becoming directly involved in detailed contractual arrangements with the specialist. WHY EMPLOYER NOMINATE SUB-CONTRACTOR
Nomination is used because there are benefits for the Employer in using the system. The key benefit for the Employer is control over the choice of, and performance required from, NSC. Above all, the Employer reserves to itself the choice of subcontractor.
FIDIC Red Book 4th In its Conditions of Contract for Works of Civil Engineering Construction (4th ed. 1987) ("Red Book 4th"), FIDIC recognizes that the failure of NSC to perform can have serious consequences for both MC and the Employer. Therefore, it is important to ensure that MC approves of the subcontractor and is prepared to collaborate with him. Thus, MC need not employ just any NSC. He need not employ anyone:
Against whom he has reasonable objection; or Who refuses to enter into a subcontract which: is back-to-back with the main contract; and Which indemnifies MC in respect of NSC's breaches, and against the negligence of his workmen and misuse of any Temporary Works
Where, however, if the NSC has been appointed in advance of the Contract date, the right to object may be more limited, provided that appointment was notified to MC beforehand and no objection was made or highlighted as a likely reaction to formal nomination.
REJECTION OF NSC BY MC There are several grounds for reasonable objection: 1. 2. 3. 4. financial standing Profession / Potential technical competence reliability
NSC MUST COMPLY FOR THE FOLLOWING IN THE AGREEMENT WITH MC 1. Accept equivalent responsibilities or obligations consistent with those undertaken by MC. 2. Indemnify MC against liabilities, claims and damages arising from defaults of NSC on the same terms as MC's indemnity to the Employer. 3. Accept liability for reasonable delay damages. 4. Accept MC payment terms, subject to retention and set-off or counterclaim. ABREACTIONS MAY FACE MC BY USING NSC If MC does cannot secure a suitable amendment of the provisions of the Red Book 4th or SIACC, he may be faced with insufficient description of NSC Works, other than perhaps the inclusion of a provisional sum in the Bill of Quantities. 1. The true nature of the NSC Works and its effect on programming often is only made apparent once the nomination occurs, which may be late on in MC's own Works and certainly after the terms of the main Contract have been settled. 2. MC may not have a fair opportunity to consider his power of objection to the nomination and/or to make constructive suggestions with regard to an alternative proposal. 3. When the NSC will be placed after MC is selected, then Sub-clause 59.2 provides the necessary veto right. When, however, NSC will be in place before the main contract tender process, a prudent tenderer will seek full details of the NSC and of the subcontract terms and conditions.
Clause58.2A
If the Contractor suffers delay and/or incurs costs by reason of the issue of an instruction pursuant to sub-clause 58.2 in circumstances where the work, goods, materials, plant or services, and/or the timing of the said instruction for the execution or supply thereof (as the case may be) were, in the reasonable opinion of the Engineer, not foreseeable by an experienced contract, the Engineer shall after due consultation with the Employer and the Contractor determine: (a) (b) any extension of time to which the Contractor is entitled under Clause 44, and The amount of such costs, which shall be added to the Contract Price, and shall notify the Contractor accordingly, with a copy to the Employer.
a. Equivalent responsibilities or obligations consistent with those undertaken by MC. b. Indemnities against liabilities, claims and damages arising from defaults of NSC in the same terms as MC's indemnity to the Employer. c. CAR insurance capped no lower than the potential liability of MC arising from design fault. d. Bonds in stipulated form. NSC has to proof his financial Status e. MC has the right to evaluate the pre-qualification of NSC
CONCLUSION 1. Nomination is a risky process for MCs, and it is open to abuse by Employers and their consultants. 2. Contractors should, therefore, tread carefully when nomination is being proposed in MEGA construction projects. 3. No special protection to MCs with regard to NSCs. So, every opportunity must be taken to negotiate changes to the standard NSC provisions in the corresponding sub-contracts. 4. At least from 2-3% additional percentage to be added for the risks of using NSC. (complete Risk analyses will give the actual assessment)