Inspection Request Form For Diaphragm Wall
Inspection Request Form For Diaphragm Wall
Inspection Request Form For Diaphragm Wall
Unless otherwise approved,this inspection request form shall be submitted during the daily morning meeting among LTA,Contractor and QP(S) Contractor: Project: SAMWOH CORPORATION PTE LTD SK E&C To: LTA
NO:
ER296-CONSTRUCTION AND COMPLECTION OF SENTOSA GATEWAY TUNNEL FROM TELOK BLANGAH ROAD TO KEPPEL ROAD / KAMPONG BAHRU ROAD/ LOWER DELTA ROAD AND ASSOCIATED ROAD WIDENING WORKS INTERCHANGE
Date: Time:
The work described below has been inspected by our supervisory personnel and is complete and ready for your inspection. A checklist is attached overleaf. Location Checked and Requested By: Chainage Activity Drawings Used for Construction Other Description Contractor's PM Name & Signature
The meeting noted that the information provided by the Contractor is adequate/not adequate*. QP(S) may proceed *delete where appropriate Request Rejected
QP(S) Name&Signature/Date
The above process for request for inspection of work by Contractor and approval by QP(S) is noted. ___________________________________ LTA's representative/date/time
No:
Location:
Description of Works
Chainage:
Checked by Contractor Confirmed by QP(S)
16 17 18 19 20 21 22 23
Check verticality of panel Check calculated depth of penetration Check CWS joint/Water stop Check cut-off level of panel Check provision of couplers Check recess to form box-outs between the steel cages and the near face of the diaphragm wall Check sufficient temporary traffic devices if lane closure is required Others