INSPECTION REQUEST FORM FOR DIAPHRAGM WALL

Unless otherwise approved,this inspection request form shall be submitted during the daily morning meeting among LTA,Contractor and QP(S) Contractor: Project: SAMWOH CORPORATION PTE LTD SK E&C To: LTA

NO:

ER296-CONSTRUCTION AND COMPLECTION OF SENTOSA GATEWAY TUNNEL FROM TELOK BLANGAH ROAD TO KEPPEL ROAD / KAMPONG BAHRU ROAD/ LOWER DELTA ROAD AND ASSOCIATED ROAD WIDENING WORKS INTERCHANGE

Date: Time:

The work described below has been inspected by our supervisory personnel and is complete and ready for your inspection. A checklist is attached overleaf. Location Checked and Requested By: Chainage Activity Drawings Used for Construction Other Description Contractor's PM Name & Signature

The meeting noted that the information provided by the Contractor is adequate/not adequate*. QP(S) may proceed *delete where appropriate Request Rejected

INITIAL INSPECTION DECISION BY QP(S)


We have inspected the above referenced works and found them acceptable. You may proceed. However, please return the completed checklist upon completion of the remaining work. You cannot proceed. Please carry out corrective works as noted on the checklist and submit a fresh request for inspection. Other comments:

RTO/RE Name & Signature/ Date

FINAL INSPECTION DECISION BY QP(S)


_______________________________________

QP(S) Name&Signature/Date

work approved to start:_____________________ LTA

work completed on:_________________________

The above process for request for inspection of work by Contractor and approval by QP(S) is noted. ___________________________________ LTA's representative/date/time

CHECKLIST FOR DIAPHRAGM WALL


Date/Time:
S/No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Check setting out Check services plan Locate services with cable detector and digging trial trench Check soil sample at trench base and confirm by contractor's Professional Engineer Check certificate of fitness of excavating crane & service crane Check certificate of crane operator Check excavating crane and service crane located on firm bases Check cover blocks/spacers Check steel cage reinforcement Ensure cleanliness of excavated trench Provision of tremie pipe Quantity of ready-mix concrete : Check concrete grade Take slump test Take cube samples No of sets: Grade : Desired slump -----------------mm -----------------Reference: m3 ------------------

No:

Location:
Description of Works

Chainage:
Checked by Contractor Confirmed by QP(S)

16 17 18 19 20 21 22 23

Check verticality of panel Check calculated depth of penetration Check CWS joint/Water stop Check cut-off level of panel Check provision of couplers Check recess to form box-outs between the steel cages and the near face of the diaphragm wall Check sufficient temporary traffic devices if lane closure is required Others