30 03 13 PDF
30 03 13 PDF
30 03 13 PDF
TO CC.
1.00 2.00
Report No : Date :
Rev. 2
K. Surachead P. Worachart P. , Preecha K., Chotepong S., Aphichart S., K. Kawin T., Krisada B., Leartsak Ch., Deaunphen R.
WEATHER CONDITION 3.00 4.00 5.00 6.00 7.00 8.00 S 9.00 S 10.00 S Symbols Yesterday = 11.00 S 12.00 S 13.00 S Cloudy (C), 14.00 S 15.00 S 16.00 S 17.00 S 18.00 S
24.00
Sunshine (S),
MANPOWER REPORT Normal Time man hours Over Time man hours Normal Time man hours Over Time man hours
No.
Description
Total M/D
Total MH
No.
Description
Total M/D
Total MH
ENSURE INTERNATIONAL CO., LTD. A 1 2 3 4 5 6 7 8 9 10 11 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Foreman Welder Fitter Pipe Fitter Structure Helper Driver Scaffolder Fire wach man Insulation Safety Technic Qc Inspector Carpenter Mason Electrician Total A+B No. 1 2 3 No. 1 2 3 4 5 6 7 8 9 10 Griding M/C 4" Griding M/C 7" Activities (Yesterday) Install Steel Structure Trim Cooler Install Formwork Foundation Drum 03D018 Install Formwork For Pump 03P020A/B/C Remove sand Bag From Gutter Leveling For Drum 03D020 Fabrication Support Cylinder Installation Insulation For 05T009 Fabrication Pipe 24",28" 304H Shop Fabrication Steel Structure Area 03A 03B 03B 03B 03B Shop 05 Shop Shop Description Welding M/C 300 Amp. Unit ea ea ea Unit Set Set Set Set Set Set Set Set DB Kg. Q'ty 4 12 9 Q'ty 1 13 1 3 1 1 2 1 28 8835 No. 4 5 6 No. 1 2 3 4 5 6 7 8 Drill Generator Haib 5 T CONSTRUCTION ACTIVITIES Activities (Today) Install Steel Structure Trim Cooler Area 03A Unit Set Set Set Set Set Set Set DB Q'ty 1 13 26 1 3 1 1 28 No. 1 2 Activities (Tomorrow) Remove sand Bag From Gutter Fabrication Pipe 24",28" 304H Area 03B Shop Unit Set DB Q'ty 1 28 Project Manager Site Manager Site Engineer Safety Office QA/QC Manager Draftman Material Control Administrator Storekeeper Document Control Supervisor Direct 6 3 15 13 9 2 9 4 4 4 3 7 5 1 48 24 120 104 72 16 72 32 32 32 24 56 40 8 2 1 7 5 1 2 4 3 11 10 7 2 12 9 33 30 21 6 6 6 3 21 15 3 6 3 15 13 9 2 9 4 4 4 3 7 5 1 103 60 33 153 134 93 22 72 38 32 38 27 77 55 11 1,013 Description 2 1 1 4 Indirect 1 2 3 2 1 1 8 16 24 16 8 8 16 8 8 32 2 1 1 1 2 1 3 6 3 3 3 6 1 2 3 2 1 1 2 1 1 4 8 19 30 19 8 8 19 11 8 38 A 1 2 3 4 5 6 7 8 9 10 11 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Foreman Welder Fitter Pipe Fitter Structure Helper Driver Scaffolder Fire wach man Insulation Safety Technic Qc Inspector Carpenter Mason Electrician Total A+B Unit ea ea ea Q'ty 3 3 1 No. 7 8 9 Crane 55T. Crane 70T. Trailer Description Project Manager Site Manager Site Engineer Safety Office QA/QC Manager Draftman Material Control Administrator Storekeeper Document Control Supervisor Direct 6 4 15 14 9 2 9 4 4 4 3 7 5 1 48 32 120 112 72 16 72 32 32 32 24 56 40 8 6 4 15 14 9 2 9 4 4 4 3 7 5 1 106 Unit ea ea ea 48 32 120 112 72 16 72 32 32 32 24 56 40 8 848 Q'ty 2 1 2 4 Indirect 1 2 3 2 1 1 8 16 24 16 8 8 16 8 16 32 1 2 3 2 1 1 2 1 2 4 8 16 24 16 8 8 16 8 16 32
Install Steel Structur Cooling water Pipe Support 03A Install Formwork Foundation Cooling Water 03A Grouting Foundation Drum 03D018 Grouting Foundation For 03P020A/B/C Remove sand Bag From Gutter Installation Insulation For 05T009 Fabrication Pipe 24",28" 304H 03B 03B 03B 05 Shop
Page 1 of 1