Erection Report Lot178 Week 1

The document provides a weekly report of the progress made in erecting a mining machine over 10 days. It details the percentage completion of various assembly tasks each day such as installing frames, assembling crawler links, cleaning components, and installing platforms and electrical systems. By the end of the tenth day, the swing rack and boom were installed, and work was 30% complete on installing lights and 80% complete on connecting the boom lube system.

Uploaded by

juangomezsan
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views10 pages

Erection Report Lot178 Week 1

The document provides a weekly report of the progress made in erecting a mining machine over 10 days. It details the percentage completion of various assembly tasks each day such as installing frames, assembling crawler links, cleaning components, and installing platforms and electrical systems. By the end of the tenth day, the swing rack and boom were installed, and work was 30% complete on installing lights and 80% complete on connecting the boom lube system.

Uploaded by

juangomezsan
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Erection Report Lot 178 Week 1

Date of Report: Customer: Machine Model: Serial Number: Location: Erector Engineer:
Friday August 3, 2012 Field assembly day: 1 Crew Shift: Day 12 hours Work complete: Position, clean and prepare truck frame, 50% Position, clean and prepare crawler frames, 50% Position, clean and prepared revolving frame, 30% Inventory material, 15% Assemble crawler links, 25%

August 13, 2012 Quadra 7495 H 141477 Sierra Gorda, Chile Walter Villar Prez

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Saturday August 4, 2012 Field assembly day: 2 Crew Shift: Day 12 hours Work complete: Assembly crawler links first set, 50% Clean and prepared truck frame, 75% Clean and prepared crawler frames, 100% Clean and prepared swing rack, 50% Inventory material, 30% Clean and prepare special bolts, 100%

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Sunday August 5, 2012 Field assembly day: 3 Crew Shift: Day 12 hours

Work complete: Installed left hand crawler frame, 100% Installed and adjusted the crawler frame bolts LH, 50% Assembly crawler links first set, 75% Clean components

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Monday August 6, 2012 Field assembly day: 4 Crew Shift: Day 12 hours

Work complete: Install right side crawler frame, 100% Install and adjust the crawler frame bolts RH, 50% Install and adjust the crawler frame bolts LH, 100% Clean and prepare high voltage collector rings, 100% Prepare boom Clean and prepare components

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Tuesday August 7, 2012 Field assembly day: 5 Crew Shift: Day 12 hours

Work complete: Install high voltage collector rings, 30% Install and adjust the crawler frame bolts RH, 100% Positioning crawler frame over crawler belt Check and mark cables, 25% Prepare DPT1 and DPT2, 75% Install and adjust the crawler frame bolts RH, 100%

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Wednesday August 8, 2012 Field assembly day: 6 Crew Shift: Day 12 hours

Work complete: Assemble crawler belts second set, Positioned truck-crawler frame on crawler link Clean and prepare revolving frame, 30% Clean and prepare utilitarian room base, 50% Clean and prepare lube room base, 50%

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Thursday August 9, 2012 Field assembly day: 7 Crew Shift: Day 12 hours

Work complete: Install platforms, ladders and handrails on boom, 25% Clean and prepare swing rack, 100% Clean and prepare boom point sheave, 50% Prepare and install DPT1 and DPT2, 50%

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Friday August 10, 2012 Field assembly day: 8 Crew Shift: Day 12 hours

Work complete: Install and connected crawler belt, 50% Install and weld ballast box plates, 10% Clean and prepare boom point sheave, 100%

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Saturday August 11, 2012 Field assembly day: 9 Crew Shift: Day 12 hours

Work complete: Install and connected crawler belt, 100% Install and adjust swing rack, 50% Install boom point sheave, 100% Install and welded ballast box plates, 15% Clean components Install and connected boom lube system, 30%

Av. Pedro Aguirre Cerda 11776, Antofagasta Chile. Fono +56 55 434900

Sunday August 12, 2012 Field assembly day: 10 Crew Shift: Day 12 hours

Work complete: Install and adjust swing rack on truck frame, 100% Install boom platforms, 80% Install DPT1 and DPT2, 100 Install light system on control room roof, 30% Install and connected boom lube system, 80%