Mc-7 and Mc-7 and Lateral Shy-1: Project Project Milestone

This document provides a work breakdown structure (WBS) layout for the MC-7 AND LATERAL SHY-1 project. It includes over 100 activities related to procurement, mechanical and civil works, electrical and instrumentation installation, and commissioning. The activities have start and finish dates ranging from December 2012 to November 2013.

Uploaded by

George Manuel
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views16 pages

Mc-7 and Mc-7 and Lateral Shy-1: Project Project Milestone

This document provides a work breakdown structure (WBS) layout for the MC-7 AND LATERAL SHY-1 project. It includes over 100 activities related to procurement, mechanical and civil works, electrical and instrumentation installation, and commissioning. The activities have start and finish dates ranging from December 2012 to November 2013.

Uploaded by

George Manuel
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID

Activity Name

Start 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 15-Dec-12 A 21-May-13 20-Jul-13 10-Aug-13 23-Sep-13

Finish 28-Nov-13 28-Nov-13 28-Nov-13 28-Nov-13

MC-7 AND LATERAL SHY-1


PROJECT MILESTONE
MC-7 REMAINING REMAIN MILESTONE
OLD SCOPE M MILESTONE CM-36 CM-44 CM-40 CM-38 CM-56 CM-58 CM-05 CM-10 CM-11 CM-51 CM-52 CM-53 CM-57 CM-55 CM-54 CM-26 CM-29 CM-47 CM-37 CM-45 CM-41 CM-39 CM-21 CM-32 CM-35 Start Installation Of Scrapers Start Installation Of Electrical And Instrument Cables & Wires Start Hydrotest Under Ground Piping Start Hydrotest Above Ground Piping Start Commissioning Of New Rerouted Pipes Schedule Completion Date Of All Facilities As Per Schedule "B" Paragraph #.9 Procurement Remaining Material Start Procurement Completion For Shy-1 & Petrorabigh(170-B1 & B2) Procurement Completion FOR 30" Lateral(170-B3) Partial M/C Of 26" Shy-Line To Support Commissioning Of Line Partial M/C Of 18" YRBETH-1 Line To Support Commissioning Of Line Partial M/C Of 6" YRBUT- 1 LIne To Support Commissioning Of Line Mechanical Completion Of MC-7 Demolition & Removal Of Original Pipelines Decommission Original Pipelines Complete Under Ground Piping 100% Of New Shy -1 Pipe Line W/Out Hydrotest Complete Under Ground Piping 100% Of New Petro Rabigh W/Out Hydrotest Complete Loop Check Complete Installation Of Scrapers Complete Installation Of Electrical And Instrument Cable & Wires Complete Hydrotest UnderGround Piping Complete Hydrotest Above Ground Piping Complete Above Ground Piping Sleepers Complete Above Ground Piping 100% Of New Shy-1 W/Out Hydrotest Complete Above Ground Piping 100% Of New Petro Rabigh Lines W/Out Hydrot

28-Nov-13 09-Dec-12 A 23-Jun-13 22-May-13 01-Oct-13 23-Sep-13 03-Jul-13 29-Oct-13 19-Nov-13 07-Oct-13 28-Jul-13 28-Jul-13 01-Oct-13 20-Oct-13 03-Sep-13 08-Aug-13 29-Sep-13 18-Jun-13 28-Jul-13 28-Jul-13 17-Jun-13 17-Jun-13 28-Nov-13 28-Nov-13 07-Jul-13 17-Jul-13 17-Jun-13 18-Jun-13 07-Aug-13 28-Nov-13 10-Oct-13 18-Jul-13 12-Sep-13 21-Nov-13

SHY-1 LATERA LATER L MILESTONE


NEW AMENDMENT AMENDM LM- 7 LM- 3 LM- 1 LM- 2 LM- 8 LM-11 LM- 5 LM- 6 LM- 9 LM-10 Partial Mechanical Completion 30" Shy -Lateral Up To NGL Fence Installation Of All Utilities FireWater Loop Inside The New SSD Fence Extension A Installation Of 3 Box Culverts Inside YNGLFC Installation of Above Ground Pipe Supports Final Tie-In Of Shy-1 Lateral @ NGL Final MCC Shy-1 Lateral & All Associated Works Electrical Work In the Scraper Trap Area Including Lighting Grounding,Cathodic P Completion Of 30" Shy -Lateral And Above Ground Piping Complete Hydrotesting Of 30" Shy-1 Lateral And Above Ground Piping @ YNGLF Complete Commissioning Of 30" Shy-1 Lateral

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID LM- 4

Activity Name Civil Work In The Scrap Trap Area Including SSD Fencing,Petrol Road And All As

Start

Finish 25-Jun-13

PROCUREMENT CONTRACTOR SUPPLIED MATERIALS (170 -B1-SHY-1) PROCUREME PROCUREMENT CONTRACTOR SUPPLIED MATERIALS (170-B2 -PETRO RABIGH) PROCUREME PROCUREMENT CONTRACTOR SUPPLIED MATERIALS (170-B3 -30" SHY-1 COMB PROCUREME

02-Jan-13 A 24-Dec-12 A 15-Dec-12 A 09-Dec-12 A 09-Dec-12 A 30-Mar-13 30-Mar-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 29-Jul-13 29-Jul-13 09-Dec-12 A 15-Dec-12 A 10-Dec-12 A 05-May-13 05-May-13 13-May-13 25-May-13 05-May-13 08-Jun-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 14-Apr-13 07-Apr-13 08-Apr-13 08-Apr-13 08-Apr-13 01-Jul-13 01-Jul-13 01-Jul-13 23-May-13 23-May-13 07-Jul-13 01-Jul-13 09-Dec-12 A 15-Dec-12 A 15-Dec-12 A 11-Aug-13

23-Jun-13 23-Jun-13 22-May-13 28-Nov-13 24-Nov-13 30-Mar-13 11-Aug-13 11-Aug-13 11-Aug-13 11-Aug-13 22-May-13 28-Jul-13 03-Jun-13 24-Jun-13 23-May-13 06-Jun-13 12-May-13 24-Jun-13 18-Jul-13 24-Apr-13 22-Apr-13 24-Apr-13 13-Apr-13 30-Jun-13 30-Jun-13 18-Jul-13 18-Jul-13 15-Jul-13 15-Jul-13 06-Jul-13 15-Sep-13 21-Jul-13 14-Aug-13

REMAINING WORKS OF ORIGINAL SCOPES


170-B1 INSTALLATION INSTA OF 26" U/G MAINLINE RE-ROUTE FROM (FROM 0KM TO ST)
REMAINING W WORKS FOR 170-B1 170-B1 000 Remaining Works For 170-B1 Start Milestone INSTALLATION 26" SCRAPER TRAP ( V73-D-010 ) INSTALLATIO MECHANICAL PIPING WORKS MECHANICA MC-7 239 MC-7 295 MC-7 275 MC-7 240 MC-7 265 MC-7 250 MC-7 249 MC-7 280 MC-7 285 MC-7 270 MC-7 290 Work Permit Valves Installation for 26" Scraper Trap Spools Installation for 26" Scraper Trap Spools Fabrication for 26" Scraper Trap Installation for 26" Scraper Trap Hydrotest Valves & Spools for 26" Scraper Trap Work Permit Install 8" & 4" U/G RTR Oily Water Sewer Install 8" & 4" U/G Fire Water Supply Install 3" Utility Water Line Install 10", 8" & 4" U/G RTR Fire Water Supply

INSTALLATION OF UTILITY LINES @ SCRAPER TRAP AREA INSTALLATIO

INSTALLATION OF 26" U/G MAINLINE RE-ROUTE FROM (FROM 0KM TO ST) INSTALLATIO CIVIL & STRUCTURAL STR WORKS MC-7 019 MC-7 060 MC-7 030 MC-7 020 MC-7 069 MC-7 070 MC-7 109 MC-7 110 MC-7 141 MC-7 145 MC-7 142 MC-7 134 MC-7 135 MC-7 165 Work Permit Laying Riprap Stones @ Sta -2+651 Installation Of Markers Install Flange /LDS Enclosure & Crash Barrier Work Permit Thrustboring @ TAMA Highway Work Permit Tie-in @ TAMA Highway Area Work Permit Pipe Weld/Radiography/Girth Weld Coating for 26" A/G Pipe Installation Of 24" A/G By-Pass Line Scraper Area Work Permit Trench Excavation for Electrical/Grounding & Communication Loop Checking for Elect./Grounding & Comm.

THRUSTBORING @ TAMA HIGHWAY THRUSTBOR

26" U/G MEC MECH PIPING WORKS

26" A/G MEC MECH PIPING WORKS

ELECTRICAL /GROUNDING & COMMUNICATION

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 150 MC-7 160 MC-7 170 MC-7 140 MC-7 179 MC-7 180 MC-7 216 MC-7 205 MC-7 190 MC-7 215 MC-7 235 MC-7 200 MC-7 225 MC-7 9212 MC-7 9233 MC-7 9231 MC-7 9232 MC-7 9226 MC-7 9225 MC-7 9213 MC-7 9223 MC-7 9224 MC-7 9228 MC-7 9229 MC-7 9230 MC-7 9242 MC-7 9237 MC-7 9089 MC-7 9103 MC-7 9123 MC-7 9113 MC-7 9093 MC-7 9209 MC-7 9090 MC-7 9219 MC-7 9192 MC-7 9195 MC-7 9194 MC-7 9196

Activity Name Install UG/Control Cable from Operator Shelter to Substation Grounding Installation for Operator Shelter, Scraper Area to NGL Backfilling for Electrical/Grounding & Communication Area Lighting for Scraper Area Work Permit Trench Excav.,Splice Point SP-XX1 to SP-XX2 for Comm. Outside YERP Termination Works/Loop Checking for Comm. Outside YERP Splicing Both Ends SP-XX1 To SP-XX2 for Comm. Outside YERP Laying of Fiber Optic Cable for Comm. Outside YERP Install Metallic Warning Tape for Comm. Outside YERP Install Cable Marker for Comm. Outside YERP Continuity Test for Comm. Outside YERP Backfilling for Comm. Outside YERP Work Permit Name Plate & Tagging for Cable & Conduts @ 26" Scraper Area Install ZV-517A/ZV-516A/ZB-921B 26" Shy-1 Install ZV-516A/ZV-517A/ZB-921B 30" PXXX1-9CS9P Install TI-101/TE-101 Install PT-101 & PT-103 Install PI-XX3 on 26" Shy-1 Install PI-XX2 on 2" Equalizing line Install PI-XX1 on 4" PXXX8-9CS9P Install Limit Switch on Emerg. Shutd. Va ZV-516/517 Install Limit 12" Bypass line ESVa ZV-516/517 Install XS-102 & 104 ON 26" SHY-1 Fire Alarm System Installation @ 26" Scraper Area Analog Digital Junction Box Installation @ 26" Scraper Area Work Permit Trenching Inst Cable Shutdown Cabinet to Air Surge Drum @ 26" Scraper Area Trenching Inst Cable FJB-02CJB-001 to Marshalling Rack @ 26" Scraper Area Trenching Inst Cable FJB to AJB -001 & to LCP516/517 @ 26" Scraper Area Trenching for MOV not Include Main Trench Petro Rabigh @ 26" Scraper Area Termination All Installation Cables @ 26" Scraper Area Survey Layout & Markings @ 26" Scraper Area Loop Checking @ 26" Scraper Area Lay Inst Cable PC-0003/0004/0005/0231/0232 Sub. to MOVs @ 26" Scraper Are Lay Inst Cable Cable FJB-02CJB-001 to Marshalling Rack @ 26" Scraper Area Lay Inst Cable Cable FJB to AJB -001 & to LCP516/517 @ 26" Scraper Area Lay Inst Cable Cable AJB-001/DJB-001 to RTU Marsha. Cab. @ 26" Scraper Ar

Start 28-Jul-13 03-Aug-13 14-Aug-13 21-Jul-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 24-Jul-13 17-Jul-13 21-May-13 22-Jul-13 28-Jul-13 23-May-13 09-Feb-13 A 12-Aug-13 12-Aug-13 24-Aug-13 21-Aug-13 24-Aug-13 17-Aug-13 15-Aug-13 12-Aug-13 13-Aug-13 14-Aug-13 19-Aug-13 19-Aug-13 20-Aug-13 26-Aug-13 24-Aug-13 14-Aug-13 14-Aug-13 19-Aug-13 26-Aug-13 22-Aug-13 15-Aug-13 07-Sep-13 14-Aug-13 14-Sep-13 02-Sep-13 02-Sep-13 02-Sep-13 02-Sep-13

Finish 12-Aug-13 11-Aug-13 28-Aug-13 05-Aug-13 30-Jul-13 10-Jun-13 28-Jul-13 22-Jul-13 16-Jul-13 24-Jul-13 30-Jul-13 17-Jul-13 03-Jul-13 29-Aug-13 27-Aug-13 24-Aug-13 26-Aug-13 18-Aug-13 17-Aug-13 13-Aug-13 14-Aug-13 15-Aug-13 19-Aug-13 19-Aug-13 21-Aug-13 29-Aug-13 27-Aug-13 15-Sep-13 25-Aug-13 01-Sep-13 28-Aug-13 21-Aug-13 12-Sep-13 20-Aug-13 15-Sep-13 03-Sep-13 03-Sep-13 03-Sep-13 03-Sep-13

COMMUNICATION WORK OUTSIDE YERP COMMUNICA

INSTRUMENT INSTALLATION @ 26" SCRAPER AREA INSTRUMEN

INSTRUMENT CABLE INSTALLATION @ 26" SCRAPER AREA INSTRUMEN

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 9193 MC-7 9204 MC-7 9143 MC-7 9154 MC-7 9155 MC-7 9160 MC-7 9170 MC-7 9180

Activity Name Lay Inst Cable & Accesso. Shut. Cab. to Air Surge Drum @ 26" Scraper Area Install Local Shut Down Cabinet 02-LCP-517A @ 26" Scraper Area Conduitting/Stubups & Sealing @ 26" Scraper Area Work Permit Stockfiling of Backfilling Materials for E & I @ Scraper Area Hauling Fill Sand for E & I @ Scraper Area Hauling Fill Marl for E & I @ Scraper Area Grading/Leveling & Compaction for E & I @ Scraper Area

Start 02-Sep-13 04-Sep-13 26-Aug-13 04-Sep-13 04-Sep-13 04-Sep-13 05-Sep-13 08-Sep-13 09-Sep-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 29-Dec-12 A 30-Mar-13 13-Apr-13 27-Apr-13 30-Jan-13 A 09-Dec-12 A 27-Apr-13 27-Apr-13 05-Jun-13 07-May-13 13-May-13 27-Apr-13 05-Jun-13 03-Jan-13 A 27-Apr-13 03-Jan-13 A 16-May-13 09-May-13 02-May-13 12-May-13 27-Apr-13 18-May-13 19-May-13 29-Apr-13 28-May-13 06-May-13 06-May-13 15-Jun-13 07-May-13 26-Jun-13

Finish 03-Sep-13 05-Sep-13 01-Sep-13 10-Sep-13 05-Sep-13 08-Sep-13 09-Sep-13 10-Sep-13 29-Jun-13 07-May-13 31-Jan-13 A 11-Apr-13 25-Apr-13 07-May-13 12-Feb-13 A 10-Jan-13 A 27-Jun-13 23-Jun-13 12-May-13 04-Jun-13 06-May-13 27-Jun-13 02-Jun-13 03-Jan-13 A 16-May-13 11-May-13 08-May-13 15-May-13 28-Apr-13 18-May-13 27-May-13 01-May-13 02-Jun-13 29-Jun-13 19-Jun-13 12-May-13 29-Jun-13

BACKFILING WORKS FOR E & I @ SCRAPER AREA

MODIFYING E EXISTING OPERATOR SHELTER NEAR SCRAPER AREA CIVIL/STRUCTURAL WORKS CIVIL/STRUC MC-7 299 MC-7 310 MC-7 315 MC-7 330 MC-7 340 MC-7 320 MC-7 300 MC-7 354 MC-7 390 MC-7 360 MC-7 370 MC-7 355 MC-7 380 MC-7 399 MC-7 400 MC-7 820 MC-7 730 MC-7 720 MC-7 790 MC-7 700 MC-7 830 MC-7 840 MC-7 710 MC-7 850 MC-7 404 MC-7 580 MC-7 406 MC-7 671 Work Permit Install Tie Beam for Operator Shelter Install Slab On Fill for Operator Shelter Install Roof Beam & Suspended Slab for Operator Shelter Install Parapet for Operator Shelter Install Column for Operator Shelter Install Column Foundations for Operator Shelter Work Permit Roof Slab Water Proofing for Operator Shelter Plumbing Works & Water Supply for Operator Shelter Interior Finishing for Operator Shelter Install CMU Wall for Operator Shelter Exterior Finishing for Operator Shelter Work Permit Survey Lay Out & markings Submit RFI Prior to Conc. for Pad PACU-1 Rebar Installation for Conc. Pad PACU-1 Rebar Cutting & Bending Hauling Of Rebar for Conc. Pad PACU-1 Form Works for Conc. Pad. PACU-1 Excavation for Conc. Pad PACU-1 Concreting for Pad PACU-1 Concrete Curing for Pad PACU-1 Base Preparation & Lean Conc. for Pad PACU-1 Backfilling /Levelling & Compaction By Layer for Pad PACU-1 Work Permit (Access) Termination All Power Cable Grounding @ Operator Shelter Power Line Conduiting Lighting /Switches & Outlets @ Operator Shelter Loop Checking @ Operator Shelter

EXTERIOR /INTERIOR /I FINISHING WORKS

CONSTRUCT CONCRETE PAD PACU-1 @ OPERATOR

ELECTRICAL & HVAC @ OPERATOR SHELTER

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 490 MC-7 420 MC-7 405 MC-7 610 MC-7 410 MC-7 590 MC-7 480 MC-7 510 MC-7 570 MC-7 500 MC-7 470 MC-7 670

Activity Name Install Wall Mounted Exaust Fun & Wiring @ Operator Shelter Install Switches , Outlets & Utility Boxes @ Operator Shelter Install Power Panel Board @ Operator Shelter Install Power Line to PACU-1 @ Operator Shelter Install Power Cable Wiring /Cabling @ Operator Shelter Install Pacu-1 Equipment Outside Operator Shelter Install Lighting Fixtures ,Outlets & switches @ Operator Shelter Install Grounding Transformer & Panel Board @ Operator Shelter Install Grounding Rad & Test Station All Loc. @ Operator Shelter Install Grounding Cable Around Shelter Building @ Operator Shelter Install Dry Type Transformer Inside Store Room @ Operator Shelter Install Condensation Drain Near PACU-1 @ Operator Shelter

Start 05-Jun-13 27-May-13 07-May-13 22-Jun-13 09-May-13 19-Jun-13 01-Jun-13 10-Jun-13 12-Jun-13 08-Jun-13 29-May-13 24-Jun-13 16-Jan-13 A 16-Jan-13 A 16-Jan-13 A 25-Jun-13 16-Jan-13 A 25-Jun-13 20-Jul-13 20-Jul-13 20-Jul-13 22-Jul-13 20-Jul-13 25-Jul-13 04-Aug-13 30-Jul-13 10-Aug-13 10-Aug-13 10-Aug-13 12-Aug-13 17-Aug-13 14-Aug-13 16-Sep-13 16-Sep-13 16-Sep-13 24-Sep-13 02-Oct-13 24-Sep-13 28-Sep-13 07-Oct-13 12-Oct-13 16-Sep-13

Finish 08-Jun-13 29-May-13 09-May-13 24-Jun-13 27-May-13 22-Jun-13 05-Jun-13 12-Jun-13 15-Jun-13 10-Jun-13 01-Jun-13 25-Jun-13 23-Jul-13 23-Jul-13 23-Jul-13 24-Jun-13 06-Jul-13 19-Aug-13 08-Aug-13 25-Jul-13 22-Jul-13 30-Jul-13 08-Aug-13 04-Aug-13 19-Aug-13 12-Aug-13 14-Aug-13 19-Aug-13 17-Aug-13 24-Nov-13 15-Oct-13 01-Oct-13 06-Oct-13 01-Oct-13 01-Oct-13 10-Oct-13 15-Oct-13 23-Sep-13

CIVIL WORKS/FENCE WORKS & MARL ROAD @ SCRAPER AREA CIVIL/STRUCTURAL WORKS CIVIL/STRUC MC-7 504 MC-7 521 MC-7 505 MC-7 520 Work Permit Scraper ReceIver Area Paving Installation of Air Surge Drum Fdns. (2 Units) @ Scraper Area Install Platforms of V73-D-010 @ Scraper Area

HYDROSTATIC TESTING OF SHY-1 HYDROSTATI HYDROTESTING OF 26" MAIN LINE (FROM 0KM TO ST) HYDROTEST MC-7 529 MC-7 540 MC-7 530 MC-7 541 MC-7 561 MC-7 551 MC-7 549 MC-7 550 MC-7 560 MC-7 572 MC-7 562 Work Permit Water Filling for Hydrotest of 26" Main Line Line Cleaning Works for Hydrotest of 26" Main Line Hydrotesting Of Line for 26" Main Line Drying Of Line for Hydrotest of 26" Main Line Dewatering Of Line for Hydrotest of 26" Main Line Work Permit Water Filling for Hydrotest of 24" By-Pass Line @ Scraper Area Hydrotest Process of 24" By-Pass Line @ Scraper Area Drying Of Line for Hydrotest of 24" By-Pass Line @ Scraper Area Dewatering Of Line for Hydrotest of 24" By-Pass Line @ Scraper Area

HYDROTESTING OF 24" BY-PASS LINE @ SCRAPER AREA HYDROTEST

PRE-COMMISSIONING & FINAL COMMISSIONING FOR 170B1 @ SCRAPER AREA PRE-COMMIS PRE-COMMISSIONING AT SCRAPER AREA PRE-COMMI MC-7 563 MC-7 565 MC-7 595 MC-7 575 MC-7 585 MC-7 605 MC-7 615 MC-7 564 Work Permit Pre-Commissioning Of Shy-1 MOV's @ Scraper Area Pre-Comm.Shut Down System @ Scraper Area Pre-Comm.Of Transmiters ,SPI,PI, & Gas Detec.Syst. @ Scraper Area Pre-Comm.Lighting System ,Functional Test @ Scraper Area Pre-Comm.Communication System @ Scraper Area Pre-Comm. HVAC System Operator Shelter @ Scraper Area Loop Checking All Elect & Instrument @ Scraper Area

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID

Activity Name

Start 23-Sep-13 23-Sep-13 15-Oct-13 09-Oct-13 23-Sep-13 03-Oct-13 28-Sep-13 21-Oct-13 21-Oct-13 24-Oct-13 21-Oct-13 05-Nov-13 05-Nov-13 28-Oct-13 23-Oct-13 07-Oct-13 07-Oct-13 07-Oct-13 07-Oct-13 12-Oct-13 12-Oct-13 14-Oct-13 16-Oct-13 16-Oct-13 12-Oct-13 13-Oct-13 13-Oct-13 13-Oct-13 14-Oct-13 13-Oct-13 13-Oct-13 15-Oct-13 09-Dec-12 A 30-Mar-13 30-Mar-13 09-Dec-12 A 23-Apr-13 23-Apr-13 30-Apr-13 23-Apr-13 07-May-13 07-May-13

Finish 20-Oct-13 20-Oct-13 15-Oct-13 28-Sep-13 09-Oct-13 03-Oct-13 24-Nov-13 31-Oct-13 28-Oct-13 12-Nov-13 24-Nov-13 04-Nov-13 03-Nov-13 21-Oct-13 21-Oct-13 10-Oct-13 13-Oct-13 13-Oct-13 15-Oct-13 21-Oct-13 17-Oct-13 14-Oct-13 30-Oct-13 30-Oct-13 21-Oct-13 28-Oct-13 28-Oct-13 30-Oct-13 28-Nov-13 30-Mar-13 01-Aug-13 06-May-13 06-May-13 29-Apr-13 01-Aug-13

PRE-COMMISSIONING OF 26" U/G MAINLINE (FROM 0KM TO ST) PRE-COMMI MC-7 624 MC-7 629 MC-7 628 MC-7 625 MC-7 627 MC-7 626 MC-7 634 MC-7 655 MC-7 635 MC-7 675 MC-7 685 MC-7 665 MC-7 645 Work Permit Ready for Trail Run for Pre-Commissioning of 26" Main Line Nitrogen Purging for Pre-Commissioning of 26" Main Line Dewatering for Pre-Commissioning of 26" Main Line Bolt Tighting for Pre-Commissioning of 26" Main Line Air Drying for Pre-Commissioning of 26" Main Line Work Permit (Access Inside Plant) Walk Thru & Sign PMCC for Final Comm. of 26" Main Line Walk Thru & Punchlisting for Final Comm. of 26" Main Line Prepare & Submit QC Documents for Final Comm. of 26" Main Line Prepare & Submit Close Out Report for Final Comm. of 26 " Main Line Prepare & Submit As Built for Final Comm. of 26" Main Line Complete Exceptional Items for Final Comm. of 26" Main Line

FINAL COMMISSIONING COMM OF 26" U/G MAINLINE (FROM 0KM TO ST)

DEMOLITION OF EXISTING SHY-1 SCRAPER TRAP AREA DEMOLITION WORKS MC-7 429 MC-7 430 MC-7 445 MC-7 455 MC-7 465 MC-7 485 MC-7 475 MC-7 440 Work Permit Shutdown Of Existing Pipelines @ Shy-1 ST Removal Of Valves @ Shy-1 ST Removal Of Spools @ Shy-1 ST Removal Of ScraperTrap @ Shy-1 ST Removal Of Pipe Supports @ Shy-1 ST Install Blind Flange To Existing Line @ Shy-1 ST Degasing of Pipelines,Spools @ Shy-1 ST

DEMOLITION REMOVAL EXISTING SHY-1 PIPELINE ACTIVITIES A AFTER SHUTDOWN AT SHY-1 MC-7 449 MC-7 461 MC-7 450 MC-7 460 MC-7 471 Work Permit Transport Cut Pipes To Laydown Yard @ Shy-1 ST Removal Of Existing Pipeline @ Shy-1 ST Cutting Of Dismantled Pipeline To Joints @ Shy-1 ST Backfilling Works @ Shy-1 ST

170-B2 AT PETRO P RABIGH (FROM ST TO NGL)


170-B2 AT PETRO PE RABIGH REMAINING WORKS START 170-B2 000 170-B2 Remaining Works Milestone INSTALLATION PETRO RABIGH 18" & 6" LINES INSTALLATIO CIVIL/STRUCTURAL WORKS MAINLINE CIVIL/STRUC MC-7 567 MC-7 600 MC-7 568 MC-7 619 Work Permit Laying Of RipRap Stones @ Sta.-2+651 Fabricate of P/L Enclosure / Markers and Installation Work Permit

CIVIL/STRUCTURAL WORKS @ TIE-IN KM 0.020 & KM 0.139 CIVIL/STRUC

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 620 MC-7 630 MC-7 639 MC-7 640 MC-7 650 MC-7 660 MC-7 679 MC-7 695 MC-7 680 MC-7 690

Activity Name Structural Steel Installation @ Km 020 & Km 139 Install Type -1 Fence @ Km 020 & Km 139 Work Permit Spool Fabrication for 18" U/G Pipe Pipe Weld ,Gerth Weld Coating,Lowering(Remaining) for 18" U/G Pipe Completion Of 18" A/G By Pass Line @ Km. 0.00 Work Permit Tie-In All Existing Facilities & Crossing for 6" U/G Pipe Pipe Weld,Gerth Weld Coating ,Lowering (Remaining) for 6" U/G Pipe Completion Of 6",4",10"AG Bypass @ Km. 0.00

Start 07-May-13 16-Jul-13 02-Jan-13 A 02-Jan-13 A 02-Jan-13 A 17-Jan-13 A 30-Mar-13 09-Dec-12 A 09-Dec-12 A 01-Jul-13 09-Dec-12 A 30-Mar-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 30-Mar-13 10-Apr-13 09-Dec-12 A 15-May-13 09-Dec-12 A 13-May-13 13-May-13 21-Aug-13 07-Sep-13 14-Aug-13 29-Jul-13 15-Jul-13 16-Jun-13 03-Aug-13 13-May-13 15-Jan-13 A 29-Jan-13 A 29-Jan-13 A 23-Jul-13 20-Jul-13 06-Jul-13 25-Jun-13 11-Jul-13 17-Jul-13 30-Jun-13 29-Jan-13 A 13-Apr-13

Finish 13-May-13 01-Aug-13 09-Apr-13 24-Jan-13 A 30-Jan-13 A 09-Apr-13 03-Jul-13 03-Jul-13 26-Jan-13 A 09-May-13 09-Sep-13 20-May-13 09-Apr-13 17-Apr-13 01-Jan-13 A 20-May-13 08-Jan-13 A 09-Sep-13 07-Sep-13 09-Sep-13 21-Aug-13 03-Aug-13 27-Jul-13 15-Jul-13 14-Aug-13 16-Jun-13 29-Oct-13 24-Jul-13 24-Jul-13 22-Jul-13 14-Jul-13 08-Jul-13 16-Jul-13 18-Jul-13 06-Jul-13 01-Feb-13 A 29-Oct-13

U/G 18"ETHANE 18"ETHA MECH PIPING MAINLINE WORKS

U/G 6"BUTANE 6"BUTA MECH PIPING MAINLINE WORKS

SUBSTATION-150 @ SCRAPER TRAP SUBSTATION CIVIL/STRUCTURAL & PLUMBING WORKS CIVIL/STRUC MC-7 739 MC-7 760 MC-7 770 MC-7 740 MC-7 780 MC-7 750 MC-7 799 MC-7 851 MC-7 861 MC-7 841 MC-7 821 MC-7 811 MC-7 810 MC-7 831 MC-7 800 Work Permit Roof Slab Water Proofing @ Substation Ramp & WalkWays @ Substation Interior Finishing @ Substation Install 8" RTR Sewer & Plumbing Lines @ Substation Exterior Finishing @ Substation Work Permit Test ,Splicing & Termination Medium Volts Power Cables @ NGL 150A To 150B Loop Checking @ Substation Installation Of Medium Volts Transformer,4.16 KV 1000KVA @ Sub Sta.Area Installation Of Lighting Fixtures @ Substation Installation Of Electrical Devices @ Substation Installation Of Electrical CableWires @ Substation Installation Of A/C Units @ Substation Cable Tray Installation Inside Substation

ELECTRICAL & HVAC FOR SUBSTATION

INSTALL 18" & 6" SCRAPER TRAPS (170-B2) CIVIL WORKS WORK @ 18" SCRAPER LAUNCHER FACILITIES (K98-D-0001E) MC-7 887 MC-7 941 MC-7 931 MC-7 911 MC-7 888 MC-7 912 MC-7 921 MC-7 891 MC-7 889 Work Permit Site Clearing @ 18" Scraper Launcher Removal Of Forms for Containment Slab @ 18" Scraper Launcher Rebar Works for Containment Slab @ 18" Scraper Launcher Installation Of Platforms @ 18" Scraper Launcher Formworks for Containment Slab @ 18" Scraper Launcher Concreting Works for Containment Slab @ 18" Scraper Launcher Compaction Of Base-Containment Slab @ 18" Scraper Launcher BackFill All Fdns. @ 18" Scraper Launcher

PIPING WORKS WOR @ 18" SCRAPER LAUNCHER

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 899 MC-7 900 MC-7 910 MC-7 925 MC-7 920 MC-7 969 MC-7 999 MC-7 998 MC-7 971 MC-7 996 MC-7 997 MC-7 995 MC-7 990 MC-7 0999 MC-7 1000 MC-7 1010 MC-7 1220 MC-7 1020

Activity Name Work Permit Spool Fabrication @ 18" Scraper Launcher Scraper Trap Installation @ 18" Scraper Launcher Installation Of Valves @ 18" Scraper Launcher Installation Of Spools @ 18" Scraper Launcher Work Permit Site Clearing @ 6" Scraper Launcher Removal Of Forms for Containment Slab @ 6" Scraper Launcher Installation Of Platforms @ 6" Scraper Launcher Formworks for Containment Slab @ 6" Scraper Launcher Concreting Works for Containment Slab @ 6" Scraper Launcher Compaction Of Base-Containment Slab @ 6" Scraper Launcher Backfill All Fdns. @ 6" Scraper Launcher Work Permit Spool Fabrication @ 6" Scraper Launcher Scraper Trap Installation @ 6" Scraper Launcher Installation Of Valves @ 6" Scraper Launcher Installation Of Spools @ 6" Scraper Launcher

Start 13-Apr-13 13-Apr-13 14-Oct-13 17-Oct-13 17-Oct-13 15-Jan-13 A 15-Jan-13 A 30-Jul-13 27-Jul-13 09-Jul-13 18-Jul-13 24-Jul-13 30-Jan-13 A 15-Jan-13 A 13-Apr-13 13-Apr-13 13-Apr-13 19-Oct-13 20-Oct-13 20-Oct-13 09-Dec-12 A 27-Apr-13 27-Apr-13 27-Apr-13 09-Dec-12 A 09-Dec-12 A 10-Jan-13 A 20-Dec-12 A 26-Dec-12 A 10-Dec-12 A 09-Dec-12 A 30-Mar-13 18-Jan-13 A 04-Apr-13 04-Apr-13 23-Apr-13 04-Apr-13 07-May-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 28-Apr-13

Finish

28-Apr-13 16-Oct-13 26-Oct-13 29-Oct-13 01-Aug-13 01-Aug-13 29-Jul-13 17-Jul-13 23-Jul-13 25-Jul-13 14-Feb-13 A 06-Feb-13 A 29-Oct-13 28-Apr-13 20-Oct-13 28-Oct-13 29-Oct-13 22-May-13 14-May-13 14-May-13 23-Apr-13 02-Feb-13 A 20-Jan-13 A 22-Jan-13 A 31-Jan-13 A 06-Feb-13 A 23-Apr-13 03-Feb-13 A 22-May-13 06-May-13 22-Apr-13 22-May-13 31-Aug-13 12-Jun-13 21-May-13

CIVIL WORKS WORK @ 6" SCRAPER LAUNCHER FACILITIES (K99-D-0001)

PIPING WORKS WOR @ 6" SCRAPER LAUNCHER

1.2.2.6 CIVIL W WORKS FENCE/ROADS MARL ROAD WITHIN YGP PRECASTING OF LIGHT WEIGHT FDNS MC-7 1459 MC-7 1460 MC-7 1489 MC-7 1490 MC-7 1510 MC-7 1550 MC-7 1530 MC-7 1540 MC-7 1500 MC-7 1560 MC-7 1569 MC-7 1580 MC-7 1570 MC-7 1585 Work Permit Installation of Precast Light Weight Fnds. for Area Lighting Work Permit Installation of Air Surge Drum Fdns. @ Scraper Area Install Transformer Pad @ Substation Area Install Transformer Fire Wall @ Substation Area Install Concrete Pad PACU-Unit-2 @ Substation Area Install Concrete Pad PACU-Unit-1 @ Substation Area Install Acid Containment & Valve Box @ Substation Area Backfilling Works @ Scraper Area Work Permit Install Type -III Fence Around Tranformer Pad @ Substation Area Excavation Works for Fence Around Trans. Pad @ Substation Area Backfilling Trench & Fnds Around Substation Area

CAST IN PLACE PLA CONCRETE STRUCTURES (FROM ST TO SUBSTATION AREA)

INSTALLATION FENCE AROUND TRANS. PAD & BACKFILLING @ SUBSTATION AREA INSTALLATIO

ELECTRICAL AND INSTRUMENTATION WORKS (FROM ST TO NGL) ELECTRICAL (FROM ST TO NGL) MC-7 1029 MC-7 1060 Work Permit Trenching For Cable Lines from ST to NGL

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 1920 MC-7 1030 MC-7 1230 MC-7 1930 MC-7 1050 MC-7 1040 MC-7 1069 MC-7 1080 MC-7 1070 MC-7 1089 MC-7 1090 MC-7 1111 MC-7 1121 MC-7 1110 MC-7 1100 MC-7 1118 MC-7 1120 MC-7 1150 MC-7 1200 MC-7 1130 MC-7 1140

Activity Name Termination Works from ST to NGL Pre-casting Of Various Fnds. For Electrical (Remaining) from ST to NGL Power Cable Laying from ST to NGL Loop Checking from ST to NGL Installation Of Fnds. & Fabricated Items from ST to NGL Excavation For Various Fnds. from ST to NGL Work Permit Installation Of Lighting Fixtures @ Scraper Area Installation Of Electrical Devices @ Scraper Area Work Permit Trenching Works for Instrumentation from ST to NGL Termination Works for Instrumentation from ST to NGL Loop Checking for Instrumentation from ST to NGL Instruments Installation from ST to NGL Instrument Cable Installation from ST to NGL Work Permit Trenching Works for Communication from Substation to NGL Termination Works for Communication from Substation to NGL Loop Checking for Communication from Substation to NGL FOC Cable Laying for Communication from Substation to NGL Backfilling Works for Communication from Substation to NGL

Start 04-Jun-13 09-Dec-12 A 23-May-13 10-Jun-13 27-Apr-13 29-Dec-12 A 04-Jun-13 04-Jun-13 04-Jun-13 04-Jun-13 01-Jan-13 A 01-Jan-13 A 01-Jan-13 A 09-Jun-13 26-Jun-13 05-Jun-13 03-Jun-13 12-Dec-12 A 12-Dec-12 A 12-Dec-12 A 16-Jun-13 23-Jun-13 09-Jun-13 16-Jun-13 09-Dec-12 A 02-Jan-13 A 02-Jan-13 A 02-Jan-13 A 30-Apr-13 27-Apr-13 16-Feb-13 A 12-May-13 15-Dec-12 A 15-Dec-12 A 15-Dec-12 A 05-Jan-13 A 29-Dec-12 A 29-Dec-12 A 08-Jan-13 A 03-Jan-13 A 29-Dec-12 A 30-Jan-13 A

Finish 10-Jun-13 17-Jan-13 A 04-Jun-13 12-Jun-13 06-May-13 03-Jan-13 A 31-Aug-13 31-Aug-13 16-Jun-13 27-Jun-13 02-Jun-13 25-Jun-13 27-Jun-13 16-Jun-13 13-Jun-13 24-Jun-13 08-Jun-13 22-Jun-13 24-Jun-13 15-Jun-13 22-Jun-13 25-Aug-13 19-May-13 24-Apr-13 12-May-13 08-May-13 11-May-13 19-May-13 26-Jun-13 26-May-13 26-Jun-13 18-Jul-13 22-Jun-13 23-May-13 05-May-13 18-Jul-13

LIGHTING @ SCRAPER AREA

INSTRUMENTATION (FROM ST TO NGL) INSTRUMEN

COMMUNICATION (FROM SUBSTATION TO NGL) COMMUNICA

1.2.2.4 INSTALLATION INSTAL OF UTILITY LINES @ SCRAPER TRAP AREA U/G UTILITY LINE INSTALLATION MC-7 1159 MC-7 1160 MC-7 1180 MC-7 1170 MC-7 1171 MC-7 1181 MC-7 1189 MC-7 1190 MC-7 1210 MC-7 1239 MC-7 1255 MC-7 1250 MC-7 1240 MC-7 1265 Work Permit Trenching Works for U/G RTR Line @ Scraper Area Laying U/G 6" RTR Oily Water Line @ Scraper Area Laying U/G 4' Fire Water Supply FW-XXXX-12 FEOU @ Scraper Area Install Air Surge Drum (2 Units) @ Scraper Area Backfilling Works for U/G RTR Line @ Scraper Area Work Permit Spool Fabrication for 16" A/G Pipe Coating & Installation of A/G 16" Lateral Pipe (Ethane) Work Permit Installation of Bent Supports of 8" R/L Installation of 8" R/L Foundations Excavation Works of Bent Support for 8" R/L Backfilling Works for Fdns. of 8 " R/L

16" A/G ETHANE ETH LATERAL PIPING INSTALLATION (FROM ST TO NGL)

CIVIL WORK WORKS FOR 8" RELIEF LINES (FROM ST TO NGL)

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID

Activity Name

Start 09-Dec-12 A 09-Dec-12 A 11-Aug-13 11-Aug-13 09-Dec-12 A 15-Jan-13 A 29-Dec-12 A 29-Dec-12 A 29-Dec-12 A 09-Dec-12 A 09-Dec-12 A 13-Dec-12 A 23-Dec-12 A 09-Dec-12 A 07-Jul-13 07-Jul-13 16-Jul-13 07-Jul-13 22-Jul-13 16-Jul-13 25-Aug-13 31-Jul-13 23-Sep-13 31-Jul-13 15-Sep-13 08-Oct-13 08-Oct-13 31-Oct-13 26-Oct-13 08-Oct-13 20-Oct-13 14-Oct-13 19-Sep-13 19-Sep-13 12-Oct-13 06-Oct-13 19-Sep-13 01-Oct-13 25-Sep-13 07-Oct-13 07-Oct-13 29-Oct-13

Finish 25-Aug-13 25-Aug-13 25-Aug-13 18-Aug-13 22-Apr-13 27-May-13 27-May-13 01-Jul-13 01-Jul-13 01-Jul-13 10-Jun-13 29-Sep-13 29-Sep-13 16-Jul-13 05-Aug-13 17-Jul-13 31-Aug-13 03-Aug-13 29-Sep-13 06-Aug-13 28-Nov-13 05-Nov-13 05-Nov-13 30-Oct-13 14-Oct-13 26-Oct-13 20-Oct-13 17-Oct-13 17-Oct-13 12-Oct-13 25-Sep-13 06-Oct-13 30-Sep-13 04-Nov-13 04-Nov-13

PIPING WORKS WOR FOR 8" R/L (FROM ST TO NGL) MC-7 1259 MC-7 1281 MC-7 1280 MC-7 1270 MC-7 1260 MC-7 1309 MC-7 1310 MC-7 1319 MC-7 1330 MC-7 1340 MC-7 1320 Work Permit Installation Of Depressurized Heater for 8" R/L Installation Of 8" R/L Spools Installation Of 8" -RL-10139-ISDOP Fabrication Of Spools for 8" R/L Work Permit 6" A/G Butane Piping Fabrication & Installation (6"-10086-9CAIP) Work Permit 2" A/G UW-10235-12CGOU & 2"10236-12CGOU (Fab. & Inst.) 2" A/G UA-10225-12CGOU Utility Air (Fabrication & Installation) 2" A/G Nitrogen Supply Line (Fabrication & Installation)

6" A/G BUTA BUTANE LINE LATERAL PIPING INSTALLATION (FROM ST TO NGL)

2" INPLANT LINE NITROGEN/UTILITY AIR (FROM ST TO NGL)

1.3.2.2 HYDROTESTING HYDRO PETRO RABIGH LINES HYDROTESTING (FROM 0KM TO NGL) HYDROTEST MC-7 1589 MC-7 1600 MC-7 1590 MC-7 1640 MC-7 1630 MC-7 1620 MC-7 1610 MC-7 1615 Work Permit Hydrotesting 6" Butane U/G Main Line P/L from 0KM to ST Hydrotesting 18" Ethane U/G Main Line P/L from 0KM to ST Hydrotest For 8" RTR Line from ST to NGL Hydrotest 8" Relief Line from ST to NGL Hydrotest 2" Lines from ST to NGL Hydrotest 16" A/G Lateral from ST to NGL Hydrotest 6" A/G Lateral from ST to NGL

PETRO RABIGH RABIG (MCC) & FINAL COMMISSIONING(170B2) PRE-COMMISSIONING OF 18" U/G MAIN LINE FROM (0KM TO ST) PRE-COMMI MC-7 1634 MC-7 1639 MC-7 1638 MC-7 1635 MC-7 1637 MC-7 1636 MC-7 1649 MC-7 1661 MC-7 1660 MC-7 1650 MC-7 1652 MC-7 1651 MC-7 9302 MC-7 9292 Work Permit Ready for Trail Run for Pre-Commissioning of 18" Main Line Nitrogen Purging for Pre-Commissioning of 18" Main Line Dewatering for Pre-Commissioning of 18" Main Line Bolt Tighting for Pre-Commissioning of 18" Main Line Air Drying for Pre-Commissioning of 18" Main Line Work Permit Ready for Trail Run for Pre-Commissioning of 6" Main Line Nitrogen Purging for Pre-Commissioning of 6" Main Line Dewatering for Pre-Commissioning of 6" Main Line Bolt Tighting for Pre-Commissioning of 6" Main Line Air Drying for Pre-Commissioning of 6" Main Line Work Permit Ready for Trail Run for Pre-Commissioning of 8" Lateral Line

PRE-COMMISSIONING OF 6" U/G MAIN LINE FROM (0KM TO ST) PRE-COMMI

PRE-COMMISSIONING OF 8" A/G LATERAL LINE (FROM ST TO NGL) PRE-COMMI

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 9282 MC-7 9252 MC-7 9272 MC-7 9262 MC-7 1669 MC-7 1674 MC-7 1673 MC-7 1670 MC-7 1672 MC-7 1671 MC-7 1653 MC-7 1655 MC-7 1665 MC-7 1695 MC-7 1676 MC-7 1675 MC-7 1685 MC-7 1654 MC-7 1704 MC-7 1705 MC-7 1725 MC-7 1785 MC-7 1795 MC-7 1755 MC-7 1715

Activity Name Nitrogen Purging for Pre-Commissioning of 8" Lateral Line Dewatering for Pre-Commissioning of 8" Lateral Line Bolt Tighting for Pre-Commissioning of 8" Lateral Line Air Drying for Pre-Commissioning of 8" Lateral Line Work Permit Ready for Trail Run for Pre-Commissioning of 16" Lateral Line Nitrogen Purging for Pre-Commissioning of 16" Lateral Line Dewatering for Pre-Commissioning of 16" Lateral Line Bolt Tighting for Pre-Commissioning of 16" Lateral Line Air Drying for Pre-Commissioning of 16" Lateral Line Work Permit Pre Commissioning Of Peto Rabigh MOV's Pre Comm.Of Transmitters ,SPI,PI & Gas Detec.System Pre Comm.HVAC System Substation Pre Comm. Shut Down System Pre Comm. Lighting System Functional test Pre Comm. All Equipment Inside Substation Loop Checking All Elect .& Instrument

Start 23-Oct-13 07-Oct-13 19-Oct-13 13-Oct-13 06-Oct-13 06-Oct-13 28-Oct-13 22-Oct-13 06-Oct-13 17-Oct-13 12-Oct-13 15-Sep-13 16-Sep-13 18-Sep-13 29-Sep-13 02-Oct-13 16-Sep-13 09-Oct-13 24-Sep-13 06-Nov-13 06-Nov-13 06-Nov-13 10-Nov-13 14-Nov-13 16-Nov-13 12-Nov-13 09-Nov-13 19-Oct-13 19-Oct-13 19-Oct-13 22-Oct-13 27-Oct-13 28-Oct-13 24-Oct-13 21-Oct-13 05-Nov-13 05-Nov-13 05-Nov-13 09-Nov-13 13-Nov-13 14-Nov-13

Finish 29-Oct-13 13-Oct-13 23-Oct-13 17-Oct-13 03-Nov-13 03-Nov-13 28-Oct-13 12-Oct-13 22-Oct-13 16-Oct-13 16-Oct-13 25-Sep-13 06-Oct-13 09-Oct-13 23-Sep-13 16-Oct-13 01-Oct-13 15-Sep-13 28-Nov-13 18-Nov-13 26-Nov-13 26-Nov-13 27-Nov-13 24-Nov-13 28-Nov-13 10-Nov-13 30-Oct-13 07-Nov-13 07-Nov-13 09-Nov-13 05-Nov-13 10-Nov-13 27-Nov-13 17-Nov-13 25-Nov-13 25-Nov-13 26-Nov-13

PRE-COMMISSIONING 16" A/G LATERAL LINE (FROM ST TO NGL) PRE-COMMI

PRECOMMISSIONING - SUBSTATION PRECOMMIS

FINAL COMMISSIONING COMM OF U/G 18" MAIN LINE (FROM 0KM TO ST) Work Permit(Inside Plant) WalkThrough & Punchlisting for Final Comm. of 18 " Main Line Walk Thru.& Sign PMCC for Final Comm. of 18" Main Line Prepare & Submit QC Documents for Final Comm. of 18" Main Line Prepare & Submit Close Out Reports for Final Comm. of 18" Main Line Prepare & Submit As Built for Final Comm. of 18" Main Line Complete Exceptional Items for Final Comm. of 18" Main Line

FINAL COMMISSIONING COMM OF U/G 6" MAIN LINE (FROM 0KM TO ST) MC-7 10272 Work Permit(Inside Plant) MC-7 10212 WalkThrough & Punchlisting for Final Comm. of 6 " Main Line MC-7 10232 Walk Thru.& Sign PMCC for Final Comm. of 6" Main Line MC-7 10252 Prepare & Submit QC Documents for Final Comm. of 6" Main Line MC-7 10262 Prepare & Submit Close Out Reports for Final Comm. of 6" Main Line MC-7 10242 Prepare & Submit As Built for Final Comm. of 6" Main Line MC-7 10222 Complete Exceptional Items for Final Comm. of 6" Main Line FINAL COMMISSIONING COMM OF A/G 8" LATERAL LINE (FROM ST TO NGL) MC-7 9852 MC-7 9792 MC-7 9812 MC-7 9832 MC-7 9842 Work Permit(Inside Plant) WalkThrough & Punchlisting for Final Comm. of 8" Lateral Line Walk Thru.& Sign PMCC for Final Comm. of 8" Lateral Line Prepare & Submit QC Documents for Final Comm. of 8" Lateral Line Prepare & Submit Close Out Reports for Final Comm. of 8" Lateral Line

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 9822 MC-7 9802

Activity Name Prepare & Submit As Built for Final Comm. of 8" Lateral Line Complete Exceptional Items for Final Comm. of 8" Lateral Line

Start 11-Nov-13 07-Nov-13 04-Nov-13 04-Nov-13 04-Nov-13 07-Nov-13 12-Nov-13 13-Nov-13 10-Nov-13 06-Nov-13 19-Sep-13 19-Sep-13 19-Sep-13 16-Oct-13 12-Oct-13 26-Sep-13 07-Oct-13 02-Oct-13 21-Oct-13 19-Nov-13 31-Oct-13 10-Nov-13 19-Sep-13 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 09-Dec-12 A 29-Dec-12 A 11-Jun-13 25-May-13 13-Jan-13 A 29-Dec-12 A 20-May-13 20-Apr-13 09-Dec-12 A 15-Jun-13 18-May-13 05-Jan-13 A 05-Jan-13 A 19-Jan-13 A 28-Apr-13

Finish 23-Nov-13 27-Nov-13 25-Nov-13 16-Nov-13 24-Nov-13 24-Nov-13 25-Nov-13 21-Nov-13 23-Nov-13 28-Nov-13 28-Nov-13 19-Oct-13 14-Oct-13 29-Sep-13 09-Oct-13 05-Oct-13 29-Oct-13 28-Nov-13 07-Nov-13 17-Nov-13 24-Sep-13 28-Nov-13 28-Nov-13 28-Nov-13 17-Jun-13 17-Jun-13 13-Jun-13 18-Apr-13 31-Mar-13 05-Jun-13 16-May-13 30-Mar-13 17-Jun-13 20-May-13 18-Jun-13 11-May-13 27-May-13

FINAL COMMISSIONING COMM OF A/G 16" LATERAL LINE (FROM ST TO NGL) MC-7 10132 Work Permit(Inside Plant) MC-7 10072 WalkThrough & Punchlisting for Final Comm. of 16" Lateral Line MC-7 10092 Walk Thru.& Sign PMCC for Final Comm. of 16" Lateral Line MC-7 10112 Prepare & Submit QC Documents for Comm. of 16" Lateral Line MC-7 10122 Prepare & Submit Close Out Reports for Comm. of 16" Lateral Line MC-7 10102 Prepare & Submit As Built for Final Comm. of 16" Lateral Line MC-7 10082 Complete Exceptional Items for Comm. of 16" Lateral Line 1.2.2.5 DEMO DEMOLITION & REMOVAL @ PETRO RABIGH AFTER SHUTDOWN SHUT AT PETRO RABIGH MC-7 1349 MC-7 1390 MC-7 1389 MC-7 1360 MC-7 1380 MC-7 1370 MC-7 1430 MC-7 1445 MC-7 1442 MC-7 1444 MC-7 1350 Work Permit Scraper Trap Removal, 6" Scraper Trap Removal, 18" Installation Cup East & West Portion Install Blind Flange @ 6" Petro Rabigh Lines Install Blind Flange @ 18" Petro Rabigh Lines Demolition of Scraper Traps Fnds Demolition of Petro Rabigh Pipelines Demolition of Electrical / Instrumentation at Scraper Area Demolition of Electrical / Instrumentation @ Pipe Lines Degasing OF 18" & 6" Petro Rabigh Lines

AMENDMENT WORKS (LATERAL LINES) AMENDME


170 B3-30" SHY-1 S COMBINED LATERAL (FROM ST TO NGL)
INSTALLATION INSTALLATIO 170-B3 000 MC-7 1689 MC-7 1766 MC-7 1745 MC-7 1710 MC-7 1700 MC-7 1735 MC-7 1720 MC-7 1690 MC-7 1765 MC-7 1730 MC-7 1759 MC-7 1770 MC-7 1780 Remaining Works Start (For 170-B3) Work Permit Inside Plant Reinstate Disturbed Roads, (2 Loc.) @ Culvert #1 & (1 Loc.) @ Culvert #2 Rebars for Slab, (2 Loc.) @ Culvert #1 & (1Loc.) @ Culvert #2 Rebars for Base & Column, (2 Loc.) for Culvert #1 Inside NGL Lean Concrete, (2 Loc.) for Culvert #1 Inside NGL Formworks for Slab, (2 Loc.) @ Culvert #1 & (1 Loc.) @ Culvert #2 Form Works for Base & Column, (2 Loc.) for Culvert #1 Inside NGL Excavation Works, (2 Loc.) for Culvert #1 Inside NGL Concreting Works for Slab, (2 Loc.) @ Culvert #1 & (1 Loc.) @ Culvert #2 Concreting Works for Base & Column, (2 Loc.) for Culvert #1 Inside NGL Work Permit Inside Plant Installation Of Pipe Sleepers Inside NGL Installation Of Fabricated Structural Supports Inside NGL (LM-1)(3)BOX CULVERTS (INSIDE NGL) (LM-1)(3)BO

(LM-2) INSTA INSTALLATION OF ABOVE GRND PIPE SUPPORTS (INSIDE NGL)

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 1760 MC-7 1790 MC-7 1859 MC-7 1860 MC-7 1871 MC-7 1891 MC-7 1881 MC-7 1870 MC-7 1869

Activity Name Excavation Works for A/G Pipe Support Inside NGL Backfilling Works for A/G Pipe Support Inside NGL Work Permit Sumpit Installation Of U/G 8" Utility Line Installation Of U/G 12" Utility Line Installation Of U/G 10" Utility Line Installation Of U/G -4"Utility LIne Delivery of RTR Pipes, Aramco

Start 05-Jan-13 A 21-May-13 29-Apr-13 29-Apr-13 29-Apr-13 18-Jun-13 07-Jul-13 27-Jun-13 09-Jun-13 01-May-13 29-Dec-12 A 20-Apr-13 20-Apr-13 02-Jun-13 25-Apr-13 28-Apr-13 21-Apr-13 25-Apr-13 21-Apr-13 20-Apr-13 29-Dec-12 A 29-Dec-12 A 13-Jan-13 A 26-Jan-13 A 31-Dec-12 A 02-Jan-13 A 06-Jan-13 A 30-Mar-13 30-Mar-13 30-Mar-13 13-Apr-13 21-Apr-13 20-Apr-13 20-Apr-13 17-Jul-13 26-Sep-13 17-Aug-13 23-Jun-13 28-Jul-13 17-Aug-13 12-Sep-13 20-Apr-13

Finish 23-Apr-13 18-Jun-13 17-Jul-13 08-May-13 27-Jun-13 17-Jul-13 07-Jul-13 18-Jun-13 25-Jun-13 25-Jun-13 25-Jun-13 01-May-13 02-Jun-13 28-Apr-13 01-May-13 08-May-13 25-Apr-13 30-Apr-13 30-Apr-13 24-Apr-13 28-Apr-13 29-Apr-13 30-Apr-13 01-May-13 11-Apr-13 24-Apr-13 01-May-13 10-Oct-13 27-Jul-13 10-Oct-13 12-Sep-13 17-Jul-13 21-Aug-13 22-Aug-13 26-Sep-13 19-Jun-13

(LM-3) UTILITY UTILI PIPING /CIVIL & STRUCTURAL WORKS (FROM ST TO NGL)

(LM-4) CIVIL & LIGHTING WORKS @ SCRAPER TRAP AREA PERIMETER LIGHTING WORKS MC-7 2449 MC-7 2480 MC-7 2500 MC-7 2470 MC-7 2460 MC-7 2490 MC-7 2451 MC-7 2450 MC-7 1909 MC-7 2400 MC-7 1910 MC-7 2110 MC-7 2380 MC-7 2390 MC-7 2419 MC-7 2420 MC-7 2430 MC-7 2440 MC-7 2309 MC-7 2330 MC-7 2410 MC-7 2360 MC-7 2320 MC-7 2340 MC-7 2350 MC-7 2370 MC-7 2310 Work Permit Termination Works for Perimeter Lighting @ Scraper Area Site Clearing for Perimeter Lighting @ Scraper Area Power Cable Laying Works for Perimeter Lighting @ Scraper Area Installation of Lighting Pole @ Scraper Area Installation of lighting Devices @ Scraper Area Installation of Fdns.for Perimeter Lighting @ Scraper Area Excavation Works for Perimeter Lighting @ Scraper Area Work Permit Installation Of Fabric Wire & Gates @ Security Fence Install Line Post & Gate Fnds. @ Security Fence Formworks for Concrete Channel @ Security Fence Concreting for Concrete Channel @ Security Fence Backfilling Works @ Security Fence Work Permit Base Coarse Preparation for Patrol Road Asphalt -Binder Coarse for Patrol Road Ashpalt-Wearing Coarse for Patrol Road Work Permit PC Termination for E & I from ST to NGL Loop Checking for E & I from ST to NGL Installation Of Fiber Optic Cable & Devices for E & I from ST to NGL Inst. of Power Cable, Fixtures, Devices & Equipments for E & I from ST to NGL Inst. of Instrument Cables & Devices for E & I from ST to NGL IC Termination for E & I from ST to NGL FOC Termination for E & I from ST to NGL Excavation Works for E & I from ST to NGL

INSTALL SECURITY SE FENCE

CONSTRUCTION OF PATROL ROAD CONSTRUC

(LM-5) ELECTRICAL ELEC & INSTRUMENTATION (FROM ST TO NGL)

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID

Activity Name

Start 15-Dec-12 A 20-Dec-12 A 15-Dec-12 A 22-Dec-12 A 14-May-13 27-May-13 03-Jun-13 20-May-13 09-Dec-12 A 09-Dec-12 A 03-Jul-13 19-Jun-13 29-Dec-12 A 13-Jul-13 13-Jul-13 03-Aug-13 18-Jul-13 01-Aug-13 13-Jul-13 22-Jul-13 25-Jul-13 29-Jul-13 05-Aug-13 04-Aug-13 08-Aug-13 08-Aug-13 03-Sep-13 17-Aug-13 01-Sep-13 27-Aug-13 25-Aug-13 29-Aug-13 22-Aug-13 10-Sep-13 07-Sep-13 08-Aug-13 14-Sep-13 26-Sep-13 06-Nov-13 29-Oct-13 26-Sep-13 26-Sep-13

Finish 08-Jul-13 22-May-13 16-Jun-13 18-Jun-13 01-Jul-13 08-Jul-13 25-Jun-13 13-Jul-13 13-Jul-13 07-Jul-13 02-Jul-13 07-Aug-13 05-Aug-13 22-Jul-13 05-Aug-13 18-Jul-13 25-Jul-13 29-Jul-13 01-Aug-13 07-Aug-13 06-Aug-13 12-Sep-13 05-Sep-13 21-Aug-13 02-Sep-13 28-Aug-13 26-Aug-13 31-Aug-13 24-Aug-13 12-Sep-13 09-Sep-13 17-Aug-13 28-Nov-13 14-Nov-13 14-Nov-13 06-Nov-13 29-Oct-13 29-Oct-13

(LM-6) COMPLETION COMP OF 30" LATERAL AND A/G PIPE (FROM ST TO NGL) MC-7 1938 MC-7 1939 MC-7 1960 MC-7 1970 MC-7 1990 MC-7 2000 MC-7 1980 MC-7 2009 MC-7 2015 MC-7 2012 MC-7 2010 MC-7 2019 MC-7 2250 MC-7 2030 MC-7 2070 MC-7 2020 MC-7 2040 MC-7 2050 MC-7 2060 MC-7 2270 MC-7 2260 MC-7 2016 MC-7 2241 MC-7 2190 MC-7 2240 MC-7 2219 MC-7 2210 MC-7 2221 MC-7 2200 MC-7 2300 MC-7 2290 MC-7 2180 Work Permit Fabrication Of Spools Fabrication & Installation Of 6" Lateral (Blowdown Line) ,Valves & Fiitings Fabrication & Installation Of 2" UW (Utility Water),Valves & Fiitings Fabrication & Installation Of 2" PG (Purge Gas),Valves & Fiitings Fabrication & Installation Of 2" N (Nitrogen),Valves & Fiitings Fabrication & Installation Of 2" IA (Instrument Air),Valves & Fiitings Work Permit Inside Plant ( Access Permit) Installation Of 30" lateral Valves & Fittings Hydrotesting of Valves for 30" Lateral Lines Fabrication & Installation Of 30" Lateral lines Work Permit Inside Plant Tie-In For 8" RTR Fire Water Tie-In For 6' Blowdown Line Tie-In For 4" RTR Utility Line Tie-In For 30" Lateral Lines Tie-In For 2" Utility Water Line Tie-In For 2" Instrument Air Line Tie-In For 2 " Nitrogen Line Tie-In For 12" RTR Fire Water Tie-In For 10" RTR Fire Water Work Permit Inside Plant Hydrotest for 8" Utility Lines from ST to NGL Hydrotest for 6" (Blowdown Line) from ST to NGL Hydrotest for 4" Utility Lines from ST to NGL Hydrotest for 2" (Utility Water) from ST to NGL Hydrotest for 2" (Purge Gas) from ST to NGL Hydrotest for 2" (Nitrogen) from ST to NGL Hydrotest for 2" (Instrument Air) from ST to NGL Hydrotest for 12" Utility Lines from ST to NGL Hydrotest for 10" Utility Lines from ST to NGL Hydrotest 30" Lateral Line from ST to NGL

(LM-7)PARTIAL MECHANICAL COMPLETION 30" LATERAL (FROM ST TO NGL) (LM-7)PARTI

(LM-8) FINAL TIE-IN OF SHY-1 LATERAL (INSIDE NGL)

(LM-9) COMPLETE COMP HYDROTEST OF 30" LATERAL & A/G PIPING (FROM ST TO NGL)

(LM-10)PRE & FINAL COMMISSIONING (FROM ST TO NGL) PRE-COMMISSIONING (FROM ST TO NGL) PRE-COMM MC-7 1686 MC-7 1815 MC-7 1694 MC-7 1664 Pre Comm. Shut Down System Pre Comm. Lighting System Functional test Loop Checking Instrument Loop Checking Elect.

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 1663 MC-7 1679 MC-7 1684 MC-7 1682 MC-7 1680 MC-7 1683 MC-7 1681 MC-7 9362 MC-7 9352 MC-7 9342 MC-7 9312 MC-7 9332 MC-7 9322 MC-7 1809 MC-7 1814 MC-7 1813 MC-7 1810 MC-7 1812 MC-7 1811 MC-7 1774 MC-7 1775 MC-7 1825 MC-7 1845 MC-7 1855 MC-7 1835 MC-7 1805 MC-7 9502 MC-7 9442 MC-7 9462 MC-7 9482 MC-7 9492 MC-7 9472 MC-7 9452 MC-7 9572 MC-7 9512 MC-7 9532

Activity Name Issue Work Permit Work Permit Ready for Trail Run for Pre-Commissioning of 30" Lateral Line Nitrogen Purging for Pre-Commissioning of 30" Lateral Line Dewatering for Pre-Commissioning of 30" Lateral Line Bolt Tighting for Pre-Commissioning of 30" Lateral Line Air Drying for Pre-Commissioning of 30" Lateral Line Work Permit Ready for Trail Run for Pre-Commissioning of 2" Lateral Line Nitrogen Purging for Pre-Commissioning of 2" Lateral Line Dewatering for Pre-Commissioning of 2" Lateral Line Bolt Tighting for Pre-Commissioning of 2" Lateral Line Air Drying for Pre-Commissioning of 2" Lateral Line Work Permit Ready for Trail Run for Pre-Commissioning of 6" Lateral Line Nitrogen Purging for Pre-Commissioning of 6" Lateral Line Dewatering for Pre-Commissioning of 6" Lateral Line Bolt Tighting for Pre-Commissioning of 6" Lateral Line Air Drying for Pre-Commissioning of 6" Lateral Line Work Permit WalkThrough & Punchlisting for Final Comm.of 30" Lateral Line Walk Thru.& Sign PMCC for Final Comm. of 30" Lateral Line Prepare & Submit QC Documents for Final Comm. of 30" Lateral Line Prepare & Submit Close Out Reports for Final Comm. of 30" Lateral Line Prepare & Submit As Built for Final Comm. of 30" Lateral Line Complete Exceptional Items for Final Comm. of 30" Lateral Line Work Permit WalkThrough & Punchlisting for Final Comm.of 2" Lateral Line Walk Thru.& Sign PMCC for Final Comm. of 2" Lateral Line Prepare & Submit QC Documents for Final Comm. of 2" Lateral Line Prepare & Submit Close Out Reports for Final Comm. of 2" Lateral Line Prepare & Submit As Built for Final Comm. of 2" Lateral Line Complete Exceptional Items for Final Comm. of 2" Lateral Line Work Permit WalkThrough & Punchlisting for Final Comm.of 6" Lateral Line Walk Thru.& Sign PMCC for Final Comm. of 6" Lateral Line

Start 26-Sep-13 14-Sep-13 14-Sep-13 06-Oct-13 30-Sep-13 14-Sep-13 24-Sep-13 18-Sep-13 14-Sep-13 14-Sep-13 06-Oct-13 30-Sep-13 14-Sep-13 24-Sep-13 18-Sep-13 18-Sep-13 18-Sep-13 12-Oct-13 06-Oct-13 18-Sep-13 30-Sep-13 24-Sep-13 12-Oct-13 12-Oct-13 29-Oct-13 02-Nov-13 10-Nov-13 28-Oct-13 21-Oct-13 12-Oct-13 12-Oct-13 26-Oct-13 31-Oct-13 17-Nov-13 28-Oct-13 22-Oct-13 16-Oct-13 16-Oct-13 05-Nov-13

Finish

PRE-COMMISSIONING OF 30" LATERAL LINE (FROM ST TO NGL) PRE-COMM

10-Oct-13 10-Oct-13 06-Oct-13 18-Sep-13 30-Sep-13 24-Sep-13 10-Oct-13 10-Oct-13 06-Oct-13 18-Sep-13 30-Sep-13 24-Sep-13 16-Oct-13 16-Oct-13 10-Oct-13 24-Sep-13 06-Oct-13 30-Sep-13 21-Nov-13 12-Oct-13 28-Oct-13 13-Nov-13 20-Nov-13 21-Nov-13 16-Nov-13 13-Nov-13 28-Nov-13 12-Oct-13 28-Oct-13 09-Nov-13 17-Nov-13 28-Nov-13 13-Nov-13 07-Nov-13 28-Nov-13 16-Oct-13 02-Nov-13 20-Nov-13

PRE-COMMISSIONING 2" LATERAL LINE (FROM ST TO NGL) PRE-COMM

PRE-COMMISSIONING 6" LATERAL LINE/SS BLOWDOWN LINE (FROM ST TO NGL) PRE-COMM

FINAL COM COMMISSIONING OF 30" LATERAL LINE (FROM ST TO NGL)

FINAL COMMISSIONING COM OF 2" LATERAL LINE (FROM ST TO NGL)

FINAL COM COMMISSIONING OF 6" LATERAL LINE/SS BLOWDOWN LINE (FROM ST TO NGL)

MC-7 AND LATERAL SHY-1

Classic WBS Layout

22-Apr-13 13:17

Activity ID MC-7 9552 MC-7 9562 MC-7 9542 MC-7 9522 MC-7 2099 MC-7 2150 MC-7 2140 MC-7 2130 MC-7 2120 MC-7 2100 MC-7 2160 MC-7 2170

Activity Name Prepare & Submit QC Documents for Final Comm. of 6" Lateral Line Prepare & Submit Close Out Reports for Final Comm. of 6" Lateral Line Prepare & Submit As Built for Final Comm. of 6" Lateral Line Complete Exceptional Items for Final Comm. of 6" Lateral Line Work Permit Restoration of Damage Existing Marl & Asphalt Road Demollition ff Some Security Perimeter Lighting Demolition of Portion Of Existing Perimeter Fence Demolition of Existing Redundant Piping Inside YGP Demolition of Existing Pond (Including Fence) Demolition of Existing Foundations Demobilization, Cleaning & Clearing

Start 05-Nov-13 17-Nov-13 30-Oct-13 26-Oct-13 19-Nov-13 19-Nov-13 23-Nov-13 21-Nov-13 20-Nov-13 19-Nov-13 19-Nov-13 24-Nov-13 25-Nov-13

Finish 25-Nov-13 28-Nov-13 23-Nov-13 17-Nov-13 28-Nov-13 26-Nov-13 25-Nov-13 24-Nov-13 23-Nov-13 23-Nov-13 27-Nov-13 28-Nov-13

(LM-11)FINAL COMPLETION SHY -1 LATERAL (LM-11)FINA