Studies prove that most projects, especially large ones, do not end successfully. You might think that companies would be happy to just have their project finish with some degree of success. However, in spite of the odds, organizations also expect projects to be completed faster, cheaper, and with higher quality. The only way that these objectives can be met is through the use of effective project management processes and techniques. Consider the size, complexity, and other characteristics of your project, and build the right project management processes to manage and control your project. Theres a common saying among project managers: Plan the work and work the plan. In essence, that is the key to successful project management. You must first plan out the project and then monitor and control the execution of the program work. This is a step-by-step best practices guide, which uses a migration from Microsoft Exchange 5.5 to Exchange 2000 as an example.
Copyright 2003 CNET Networks, Inc. All rights reserved. To see more downloads and get your free TechRepublic membership, please visit http://techrepublic.com.com/2001-6240-0.html.
Planning
Its hard to overestimate the importance of proper planning for a project such as an Exchange migration. In general, project failures can most often be traced back to deficiencies in the planning process. There are three major deliverables from the project planning process: the project definition, the workplan, and the project management procedures.
Project definition
Best practice: Plan the work by utilizing a project definition document.
There is a tendency for IT infrastructure projects to shortchange the planning process, with an emphasis on jumping right in and beginning the work. This is a mistake. The time spent properly planning the migration will result in reduced cost and duration and increased quality over the life of the project. The project definition is the primary deliverable from the planning process and describes all aspects of the project at a high level. Once approved by the customer and relevant stakeholders, it becomes the basis for the work to be performed. The project definition should include the following: Project overview: Why is the Exchange migration taking place? What are the business drivers? What are the business benefits? Objectives: What will be accomplished by the migration? What do you hope to achieve? Scope: What features of Exchange 2000 will be implemented (i.e., e-mail, chat, instant messaging, conferencing)? Which departments will be converted? What is specifically out of scope? Assumptions and risks: What events are you taking for granted (assumptions), and what events are you concerned about? Will the right hardware and infrastructure be in place? Do you have enough storage and network capacity? Approach: How will the migration project unfold and proceed? Organization: Show the significant roles on the project. Identifying the project manager is easy, but who is the sponsor? It might be the CIO for a project like this. Who is on the project team? Are any of the stakeholders represented? Signature page: Ask the sponsor and key stakeholders to approve this document, signifying that they agree on what is planned.
Copyright 2003 CNET Networks, Inc. All rights reserved. To see more downloads and get your free TechRepublic membership, please visit http://techrepublic.com.com/2001-6240-0.html.
Project workplan
After the project definition has been prepared, the workplan can be created. The workplan provides the step-by-step instructions for constructing project deliverables and managing the project. You should use a prior workplan from a similar migration effort as a model, if one exists. If not, build one the old-fashioned way by utilizing a work-breakdown structure and network diagram.
Copyright 2003 CNET Networks, Inc. All rights reserved. To see more downloads and get your free TechRepublic membership, please visit http://techrepublic.com.com/2001-6240-0.html.
Monitor the schedule. Identify activities that have been completed during the previous time period and update the workplan to show they are finished. Determine whether there are any other
Copyright 2003 CNET Networks, Inc. All rights reserved. To see more downloads and get your free TechRepublic membership, please visit http://techrepublic.com.com/2001-6240-0.html.
Cost By Month and Variance 25000 20000 Dollars 15000 10000 5000 0
J an Feb M ar April Variance Y TD
Budget Actuals
If these situations occur, raise visibility through risk management, and put together a plan to proactively ensure that the project stays on track. If you cannot successfully manage through the problems, raise an issue.
Copyright 2003 CNET Networks, Inc. All rights reserved. To see more downloads and get your free TechRepublic membership, please visit http://techrepublic.com.com/2001-6240-0.html.
Manage risk
Risks refer to potential events or circumstances outside the project teams control that will have an adverse impact on the project.
Manage issues
In spite of your best efforts at risk management, all projects of any size and complexity will have issues arise that need to be dealt with and resolved. If you have not done as good a job managing risks, chances are you will have more issues to deal with than you might have otherwise.
Copyright 2003 CNET Networks, Inc. All rights reserved. To see more downloads and get your free TechRepublic membership, please visit http://techrepublic.com.com/2001-6240-0.html.
Conclusions
A migration from Exchange 5.5 to Exchange 2000 may be very lengthy and costly to your organization. There are always complexities in dealing with newer technology and ensuring that all the pieces integrate together. There are also challenges in implementing infrastructure with as little impact on your customers as possible. All of these challenges can be overcome through a proper mix of planning, monitoring, controlling, and executing. The planning, monitoring, and controlling aspects are where project management processes and techniques are needed. Resist the urge to jump straight into the execution. Proper planning and management of the migration effort will take more time up front but will be more than rewarded with efficiencies and savings throughout the rest of the project. Remember the project management best practices: Plan the work by utilizing a project definition document. Create a planning horizon. Define project management procedures up front. Look for other warning signs. Ensure that the sponsor approves scope-change requests. Guard against scope creep. Identify risks up front. Continue to assess potential risks throughout the project. Resolve issues as quickly as possible.