Oee Exercise Result: Please Perform This Analysis For All Key Processes
Oee Exercise Result: Please Perform This Analysis For All Key Processes
OEE Analysis- (Uses data that can be gathered from a sample production run)
Please perform this analysis for all key processes. (Note: White cells must be filled in, Shaded cells are calculated fields)
Operating pattern and machine data: A. Shifts/day B. Hours/shift C. Minutes/shift D. Planned downtime: lunch, breaks (minutes/shift) Note: If tag relief is used, enter 0 E. Total planned production time/shift (minutes) F. Total planned production time/day (minutes) G. Days/week H. Total planned production time/week (minutes) Sample production run data: I. Total minutes run J. Total breakdown time + time for minor set-ups and adjustments (minutes) K. Total number of parts made (good + bad) L. Total good parts (first time through only- do not include parts that were re-processed or reworked) M. Total bad parts N. Actual cycle time (sec/part) Other data: O. Planned cycle time-the one used for capacity planning (seconds/part) P. Projected time per changeover (minutes) Q. Projected changeovers per shift R. Projected downtime: changeover time/shift (minutes) S. Projected downtime: (breakdown time+time for minor set-ups and adjustments)/shift (minutes) T. Total projected unplanned downtime/day (minutes) OEE calculation U. Equipment Availability: V. Performance Efficiency W. Quality Rate: X. OEE: Capacity analysis Y. Planned uptime (hours/day) Z. Planned uptime (days/week) AA. Planned rate of production (parts/minute) AB. Theoretical production capacity per day AC. Theoretical production capacity per week AD. Weekly Demand AE. Weekly Parts Available for Shipment AF. Daily Demand (DPV) AG. Daily Parts Available for Shipment AH. Percent above/below DPV Percent above/below DPV for bottleneck operation (Minimum value of AH) What are the process assumptions for yield, OEE, and first-run capability?
Process 8
Process 9
Process 10
Process 8
Process 9
Process 10
=P x Q This should agree with field J = (R + S) x A Process 1 =(F-T)/F =O / N =L / K =U x V x W x100 Process 1 = F/60 =G = 60/O = Y x 60 x AA = AB x Z = AC x X = AD/Z = AB x X = (AG-AF)/AF x 100 -10.29% Process 2 Process 2
Process 8
Process 9
Process 10
Process 8
Process 9
Process 10
Consequences: 1) ALERT in WERS 2) Interim-PSW (Capacity) 3) Communicate Interim-PSW (Capacity) with status "YELLOW" to STA engineer 4) Always attach OEE analysis to PSW coversheet when PSW is submitted!