Preamble
The RAILPAG (Railway Project Appraisal Guidelines) aim at providing a common framework for the appraisal of railway projects across the EU. They are the result of a similar harmonisation exercise as that carried out under TINA (Transport Infrastructure Needs Assessment) for transport projects in general in the Accession countries in 1999. The TINA Guidelines were adopted by the UN-ECE 1 in 2003. The guidelines have been prepared following an initiative of the European Investment Bank. The EIB has received financial support from the European Commission (DGTREN) and technical support from experts representing DGTREN, other international financial institutions (IFIs) and the key associations of the rail industry, integrated in a Steering Committee. This report has mainly been carried out by the services of the EIB and has benefitted from some background work carried out by CENIT, Center for Innovation in Transport of the Universitat Politcnica de Catalunya, Barcelona, Spain, and Dr. Nils Bruzelius. This report is intended to be the first step towards a comprehensive harmonised methodology for appraisal of rail investments in the EU and, eventually, in countries of the European Neighbourhood area. To further develop this framework, the EIB will continue to work closely with the European Commission, the other institutions that have participated in this exercise and other interested parties. EIB will maintain an internet site (www.railpag.com) where updated versions of the Guidelines and new appraisal tools as well as other relevant documents, on-going research and comments will be posted. The objective is to achieve, in the medium term, a consensus on a harmonised detailed appraisal procedure that would be used by project promoters to present their projects to the European Commission and to the IFIs for funding and, eventually, by planning services of public administration, rail infrastructure managers, rail companies and their consultants as a continuously updated reference to guide their appraisal work.
1 United Nations Economic Commission for Europe Cost Benefit Analysis of Transport Infrastructure Projects, U.N. New York and Geneva, 2003.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
Table of contents
1 2 Introduction Appraisal procedures in the decision-making process for rail investments 2.1 The need for a new approach 2.2 The place of the various stakeholders in the process 2.2.1 Public administrations and infrastructure owners 2.2.2 Infrastructure managers 2.2.3 Regulator 2.2.4 Transport service operators 2.2.5 Users 2.2.6 Non-users 2.2.7 Other stakeholders 2.3 RAILPAG: an instrument for investment decision-making Appraising rail projects 3.1 General issues 3.1.1 The screening process 3.1.2 Establishing the appraisal context 3.1.3 Traffic forecasting 3.1.4 Definition of alternatives 3.1.5 Environmental, social and cohesion aspects 3.1.6 The systemic view Financial and economic analyses 4.1 The financial analysis 4.2 Cost-benefit analysis 4.2.1 Investment costs 4.2.2 Benefits for users and operators 4.2.3 Calculation of safety benefits 4.2.4 Values for vehicle operating costs (VOCs) 4.2.5 Externalities 6
10 12 13 13 14 14 14 14 15 15 15 18 20 20 20 21 22 24 25 28 30 31 33 33 34 34 35
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
4.3
4.2.6 Taxes and subsidies Particular aspects relevant to rail projects 4.3.1 Capacity and bottlenecks 4.3.2 Appraisal period, project life and residual values 4.3.3 Discount rate
35 35 35 36 37 40 42 42 43 43 44 44 46 48 48 50 52 55 56 58 60 62 83 130 158
The RAILPAG approach to project appraisal 5.1 Ensuring the quality of cost-benefit analysis 5.2 Presenting re-distribution impacts 5.2.1 Effects and stakeholders 5.2.2 SE cells 5.2.3 Non-monetisable effects 5.2.4 Thresholds Applying RAILPAG 6.1 General concepts 6.2 The appraisal framework 6.2.1 Distributional aspects. Filling the SE Matrix 6.2.2 From CBA to SE cells 6.3 Comparative analysis
Annexes A. B. C. D. E. F.
External costs Useful life of specific railway components SE cells Case studies References Members of the Steering Committee
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
Introduction
Introduction
The RAILPAG (Railway Project Appraisal Guidelines) respond to the need for EU-harmonised procedures for the socio-economic and financial appraisal of rail projects following the latest developments in the sector, especially where supra-national financing is under consideration. Indeed, the methods used in the various member states are often tied to the domestic vision of rail transport characterised by integration of infrastructure and service operators, strong public intervention and lack of competition, and tend to obey to short-term political purposes rather than long-term socioeconomic objectives. In some cases the evaluation manuals2 have not been updated for many years. There is a common agreement that available appraisal guidelines are not sufficiently adapted to the new context of liberalisation, separation of infrastructure and operations, increased accountability and EU-wide integration of railways. These guidelines address the key factors that should be taken into consideration in appraising rail investments. They are based on a wide body of literature and EU-sponsored research on transport project evaluation, albeit with a practical approach. They do not pretend to establish rigid criteria, but rather to provide indications leaving the door open to future modifications and developments in the form of manuals or dedicated software. A major objective of this work is to highlight the knowledge gaps existing in the sector and the need for specific research to fill them. In this sense the RAILPAG Guidelines can be seen as a follow-up of the more general TINA Guidelines produced in the context of the Transport Infrastructure Needs Assessment (TINA) exercise, fine-tuned for railway projects. As the TINA Guidelines (simply referred to as TINA from now on), which are widely used for transport projects, notably in the new Member States, tackle the basic issues of socio-economic and financial appraisal, only complementary and/or railway specific aspects will be addressed in detail here. Project appraisal is a crucial tool for those decision-makers, both in the public and private domains, responsible for the development of the transport system. The latest evolution of railways in Europe is giving rise to important consequences in the way decisions are made in the sector. It is thus important to show the situation of the various stakeholders and the processes leading to decisions in order to begin to establish proper guidance on how appraisal information must be presented. The second chapter deals with this complex issue. The following chapter gives indications on how to carry out a CBA adapted to the particular conditions of rail projects. RAILPAG proposes a deepening of the typical CBA as described in TINA to provide some guidance regarding both the more general aspects, such as the preparatory work (scenario building, demand forecasts, project alternatives definition, etc.), and the economic analysis. It focuses on those elements that are most relevant for rail projects and on the criteria and parameters to be used in the economic analysis, which should be correctly specified and harmonised at the European level. For complex or/and larger projects, the distributional effects of an investment are an important component for decision makers. The re-distributional matters are becoming even more important for rail project in the new regulatory setting. Chapter 6 illustrates how the results of the CBA can be presented in a way that facilitates the understanding of the consequences of the project, based on a stakeholders/effects (or SE) matrix. The SE matrix provides an indication of the economic and financial implications for the various stakeholders and of the weight taken by the different costs and benefits.
2 Evaluation is used as synonymous to appraisal. When carried out after project execution will be referred to as ex-post evaluation.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
The document includes two annexes (A and B) with tables providing indicators and values that are considered particularly relevant. Annex C consists of general comments followed by a set of fiches on key matrix cells. Annex D shows 10 case studies, reflecting a whole range of rail investments, which can be used to illustrate their practicality. Finally, Annex E provides some references, mostly referring to specific EU documents or research projects and Annex F includes the composition of the Steering Committee members. All these annexes should be completed and improved in the following phases of development of the Guidelines, notably with the contribution of sector professionals. RAILPAG have been developed under a rapidly changing legal set-up for railways in Europe. It is possible that some of the comments made or examples used become obsolete in the next few years. The guidelines have been designed, however, to accommodate the expected evolution of the sector. On the other hand, as will be clearly shown throughout this publication, it should only be considered as a first step towards more detailed methodological documents and towards the development of improved appraisal tools, including specific guidance for the incorporation of the private sector in the financing of rail projects. It will also highlight the importance of better information on the sector and help to orient and prioritise research projects in the field of transport investment appraisal.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
Appraisal procedures
in the decision-making process for rail investments
10
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
11
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
11
2
2.1
Traditionally at least for the last half of the XX century, investment decisions in the rail sector have generally been taken by the Ministry in charge of railways in particular when projects were of some importance, or by the national rail company holding a monopolistic position in the provision of rail services. Quite often the responsible Ministry dealt only with rail or with other public transport modes, leaving roads and, in many cases, ports and airports, in the hands of other ministries. Even where transport infrastructure investment responsibilities were centralised, specific directorates for rail limited a proper multimodal vision and a harmonisation of appraisal procedures in the allocation of financial resources to the transport sector. Intimate relations between the public company and the supervisory authority have prevented proper scrutiny of investment proposals and led too often to misallocation of resources. This is certainly one of the explanations for the poor performance of the sector and decreasing market share in spite of investment levels well beyond its relative traffic volumes. Project appraisal, in this context, has often been carried out exclusively from a rail perspective, without taking into account proper scenarios meaning that the evolution of competing modes has been disregarded and forecasts have frequently been too optimistic, with an integrated view that facilitated the transfer of the project benefits between different components of the system3 and including constraints that were not always economically justified4. In some countries, appraisal procedures and practice have evolved rapidly. But all too often old biases remain due to a lack of control of the administration over rail companies, from which many investment proposals originate. This could lead to cost estimates well below real figures and to an inflation of benefits to justify them. It could also move in the opposite direction, and there is a tendency for rail companies to be technologically driven and over-design projects or to add components that are not really needed. These distortions have prevailed in a context of increasingly complex financing mechanisms where, for example, national companies have at times been asked to invest directly in infrastructure in order to disguise public debt, thus reducing the potential for rational decision-making in the sector. The consequences in terms of inefficiency due to poor appraisal and decision-making have not been established, although some major rail projects have been the focus of much attention5. In spite of the recognition of the problems, very little has been done to improve old appraisal practices. The need to update them also comes from the changing structure of the sector, pushed by the reform packages endorsed at Community level in an attempt to stabilise the market share of the rail mode that has been declining for decades. Balancing the weight of the different transport modes and, in particular, favouring the development of sustainable modes of transport such as rail transport, is one of the key priorities of the European Commission. Thus this political preference should be supported by appropriate evaluation tools able to justify the selection of projects and the use of public funds in rail projects.
3 From infrastructure to operations, between different parts of the network, from investment to maintenance, etc. 4 Most typical were the use of specifications favouring local manufacturers of rolling stock or other dedicated material or protecting employment in the rail companies. 5 Eurotunnel, among those privately financed, and many public sector projects have suffered impressive cost overruns.
12
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
2.2
An investment in the rail sector represents costs and benefits for a wide range of institutions, companies and individuals. Actual flows of cash constitute the basis for the financial assessment of the project. Most stakeholders (infrastructure managers, service operators, users, etc.) could claim a net financial profit or loss and it is also possible to formulate a global financial profitability for the project based on the addition of all the cash-flows. The financial analysis will look not only at this global profitability, which should give a good indication of the sustainability of the project 6, but also, in some cases, at its split among the various stakeholders, which will allow the analyst to better understand the redistribution of the financial impacts from the project. However, some costs and benefits, while relevant for one or the other stakeholder are not marketable and/or are externalities that do not affect the financial flows of the project. These are essential in the socio-economic evaluation, which includes both a CBA, for those aspects that can be somehow monetised, and an analysis of impacts, not included in the CBA, that may be quantified or not, but which affect some stakeholders and should also be considered in the appraisal. It is thus very important to identify the various stakeholders, in particular in view of the organisational changes taking place in the European Union:
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
13
2.2.3 Regulator
Between owners and managers (and, logically service operators) there is a need for a regulator. This is a most important player in the system, and will certainly influence decision-making. However, the financial impacts of an investment on the regulator are usually negligible and it will thus not be considered as a stakeholder in the appraisal. If necessary, it could be included in the cash-flows of the corresponding government.
2.2.5 Users
Users of both rail and alternative modes are the critical components in the financial (as enduse payers) and socio-economic analysis (as they will obtain most of the benefits not included in the cash flows: travel time savings, safety and comfort improvements, etc.). Curiously enough, being poorly organised, rail users usually have a very modest influence in decision-making, their interests being mostly defended by the public administrations, local governments, trade unions, neighbourhood associations, etc. On the other hand, traditional CBA deals adequately with user costs and benefits, although, as will be seen later, some specific factors of particular relevance to railways (i.e. reliability or comfort) require further refinement.
14
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
2.2.6 Non-users
Non-users are essentially affected by externalities, notably environmental and social. They are not easy to quantify but can have an important weight in decision-making. Concerns about the external impacts of projects should be expressed through the public enquiries foreseen in the Environmental Impact Assessment (EIA) procedures. Although this mechanism should provide enough headway for finding adequate solutions for these impacts in the definition of the project, quite often there are interest groups (in favour or against the project) that will place their position regarding the project firmly in the political arena. Both for decision-making and to provide an adequate response to potential political conflict, it is thus important to signal in the appraisal the impacts on non-users, trying to quantify and monetise them as much as possible.
7 In particular when there is inadequate competition in the contractor and suppliers market.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
15
16
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
17
Appraising
rail projects
3.1
General issues
The initial necessary condition for a good appraisal is to correctly establish the scale and scope of the project and, therefore, the amount of effort reguired for its assessment, and the framework in which it will be carried out. If the appraisal framework is not adapted to the objectives of the exercise or has theoretical flaws, the results can never be correct and could lead to the wrong decisions. Most of these framework conditions are addressed in TINA. Here the discussion will concentrate on those conditions more directly linked to the rail system.
3.1.1
As indicated in TINA, it is convenient, notably in the investment programming context, to carry out a screening process prior to the pre-feasibility and feasibility analysis of specific projects. The following is an adaptation of the TINA checklist of the screening process although for railway projects: Check that all individual projects are adequately defined in terms of objectives, alternatives (including reference baseline), interoperability conditions, etc. Identify the broad performance of the projects and make a preliminary ranking relative to a small number of key indicators. In many instances, the rail sector uses key minimum/ maximum ratios such as investment/minute saved, etc. that can be a quick means for rejecting projects that are not feasible. Ensure that, for demand-driven projects, the effects on the users, such as increased comfort, reduced time, etc. go beyond perception thresholds. If users can not properly perceive the effects of the project, it will not affect their behaviour and its economic benefits are likely to be very low. Projects that cannot produce improvements beyond these threshold values should be systematically questioned. Ensure that benefits are not dependent on complementary projects (in the same corridor, or elsewhere on the network) also being implemented. If there is dependency, it should be clear whether the linked projects are part of the investment under consideration or whether they can be assumed to be carried out both in the do-minimum and project scenarios. Assess whether there are particular barriers to implementation (physical, ecological, political, etc.).
A simple global assessment based on how the proposal responds to these issues should be able to reduce the number of candidate projects for consideration in the investment programme.
20
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
the viability of the investment. In general, the scenario building exercise is based on macroeconomic forecasts supported by specialised national and international organisations. They will signal the global trends in which the transport project is expected to thrive and are critical for demand forecasts. For large projects, however, there are also transport specific aspects that could affect the project performance. Some are technological; others are linked to behavioural and market aspects; and some others will depend on regulatory and political features. TINA doesnt pay much attention to the appraisal context but, since rail has a modest market share and is undergoing extraordinary changes, the scenarios being considered in the appraisal process are of particular relevance to projects in the sector. So, it is recommended to make a summary description of the context in which the project will develop. The complexity of this scenario-building will depend on the cost and timing of the project and may include: Economic, political and social aspects: Macroeconomic forecasts must be aligned with political developments (e.g. the integration of new member countries or the impact of the European Neighbourhood policy) and social trends (including demographics, a change in attitude towards railways, the spatial distribution of activities, tourism, logistics, etc.). Technological aspects: To be able to compete, rail has to take advantage of new technologies that are quickly being absorbed by competing modes. Advances in construction (e.g. in tunnelling techniques), energy and environment (e.g. fuel cell technologies) and in traffic control (e.g. using telematics and the location possibilities of GPS/Galileo systems) will certainly affect all transport modes during the life of any major rail project. So, new technological developments should be considered in the scenarios. In certain cases, the possibility of the implementation of new concepts (e.g. maglevs) should also be taken into account. Regulatory aspects: The EU political agenda includes important changes in the present structure of railways. The impacts of the first two packages are starting to be felt. The evaluator must analyse the possible implications of liberalisation and other imposed changes. Predictable developments in the transport sector that would significantly influence the railway sector such as charging principles in other modes of transport, major infrastructure development plans in competing modes, etc.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
21
8 To avoid this, either proprietary or commercial software for demand analysis is recommended. But ultimately the issue is who does the modelling and controls the assumptions. 9 The best mode or combination of modes to achieve the objectives, so any rail solution should stand up against other modal options. 10 SEA Directive No. 2001/42/EC. 11 In most rail companies, maintenance and renewal operations usually follow pre-established patterns for the track, the electrification and signalling components and the rolling stock.
22
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
by the comparison exercise, which will depend on the phase within the process and the size of the project. When the appraisal exercise indicates that some options are quite similar, additional precision may be necessary to discriminate between them. Sometimes an alternative is simply an extension or improvement of another. In this case, if the basic alternative is acceptable, it is the additional investment that must be appraised to see if it is justified: The reference case will exceptionally be this basic alternative instead of the do-minimum12 . Comparison may become more complex when several interlinked projects are proposed. As network effects (see point 3.1.6) are particularly important in railways, the implementation of related projects and their timing can have important effects on the profitability of the whole investment programme. One way to handle such cases is to carry out appraisals of the bunched investment and of each of its individual components, to reach an optimal project selection and their implementation period. In practice this is quite difficult and an individual appraisal of each project, taking into account the proposed timetable, is recommended. It is, however, extremely important to avoid double counting through the inclusion of the same network benefits in all separate schemes. This can only be achieved if the technical and traffic studies are detailed enough to account for the effects of the implementation of the different projects in terms of capacity, level of service and user response. In the design of rail projects the traditional view has often been to consider investments leading to a continuous piece-meal improvement process rather than options representing a major change in a part of the network. This is due to the integrated character of the rail system that often prevents the spreading of advantages (notably those derived from innovation) to the whole network. Speed restrictions or old electrification and signalling systems on a section can, for instance, make inefficient the deployment of modern rolling stock on an upgraded connected section. Typically, for instance, investments to increase the maximum speeds (e.g. from 140 km/h to 160 km/h) have been distributed over the whole network. The development of high-speed services and a more aggressive view of the role of railways (for instance, in developing rail-air transport intermodality) are changing this approach and some experts argue that, for specific cases including some urban projects, only high-cost/high-performance alternatives are able to make railways competitive and represent adequate value for money. The definition of alternatives must, in any case, take into account the implications for the whole transport system and, for large projects, even the wider effects on the territory. The general equilibrium of the economy will not be addressed here. However, this could be relevant for transport plans or for some major investments, but then specific analytical tools may have to be developed. The partial equilibrium context adopted means that the comparison of alternatives must be based on the principle that resources not used for the project would be used elsewhere in the economy and produce similar impacts on financial or economic transfers (for instance on generic taxation such as VAT or profit taxes or on employment generation). In some cases the comparison of technical options should be complemented with an appraisal of different operational setups. In particular, the private participation in the financing of infrastructure (in EU railways it would always be through a public-private partnership) would certainly be reflected not only in important differences in the financial flows, but possibly in the technical definition, the investment and maintenance costs, fares and demand for services and, as a consequence, in the economic profitability of the project.
12 In some exceptional cases the additional investment might make a project feasible for which the basic alternative is poor. If so, the full investment is the real alternative to be analysed.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
23
24
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
at the national or regional levels could also be included in the appraisal. There is no clear procedure for including these political components in the appraisal, but the SE Matrix, with their distinction of stakeholders, provides a means to identify them.
15 Of course, they could be negative if some affected sections were becoming congested and additional traffic could contribute to increasing average costs.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
25
26
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
27
Financial
and economic analyses
4
4.1
The financial analysis in TINA is simply presented as the cash-flow impacts of the project on specific organisations affected by the project including:
Without going into all the specific elements, that must be included in the financial analysis, some key issues should be recalled here: Taxes: Ideally all cash flows, including project-specific taxes such as VAT, should be included in the financial appraisal. However, the net impact of indirect taxes will often be minor and difficult to calculate. It is therefore recommended to exclude VAT from the appraisal except for large infrastructures or for projects generating a substantial amount of new traffic paying VAT17. In such cases the tax flows between administrators may be relevant in the financial structuring of the project. Operating costs: In calculating operating costs all items that do not give rise to an effective monetary expenditure must be excluded, even if they are items normally included in company accounting. In particular the following items must be excluded: Depreciation and amortisation; Any reserves for future replacement costs; Any contingency reserves, because uncertainty of future flows is taken into consideration in the risk analysis.
Revenues: As regards the revenue side, railway projects normally generate their own revenue. Expected revenue will be determined by traffic forecasts and fares. As mentioned above, revenues as well as operating expenditure should be net of VAT. It is worthwhile signalling here that pricing in railways is sometimes politically established, with little relation to actual costs (marginal or average) for the specific service. It is not easy to foresee the evolution of rail pricing policy, but it is important to study its potential impacts on the projects revenues. Subsidies (transfers from other authorities, etc.) should be considered separately from operation revenues and properly accounted for as pure financial transfers. In the railway sector a thorough study of the financial implications of the project, based on the observation of the financial transfers between the various stakeholders is becoming important, as the investor may be different from the body that will own and/or operate the infrastructure. As different stakeholders may have contradictory interests, it is necessary to grasp the expected implications of
16 Prepared for the European Commission, DGREGIO. 17 When there is little new traffic, VAT related to operation (which includes the impacts on competitive modes) is usually marginal compared to other cash flows in the appraisal. So, in general, only VAT on new investments and maintenance and new revenues would be included.
30
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
the investment on their financial performance or, essentially, what are the redistribution effects on the finances of the various players. So, investment grants (even if they are in the form of subsidised loans), operating subsidies for public service obligations, etc. must be included in the financial analysis. They should be adequately allocated between stakeholders if redistribution effects are to be analysed.
4.2
Cost-benefit analysis
The economic analysis appraises the project contribution to the economic welfare of the whole society of the region, which is the political target of the project promoter. It does not contemplate the specific financial interests of the various stakeholders as is the case in the financial analysis. The concept of target population linked to a specific administrative area (urban area, region or country) is subject to discussion. It is clear that the distinction among users according to nationality or similar could be interesting for the decision-makers. However, discrimination among EU nationals is, in principle, against Community law and unacceptable for EU sponsored projects. So, the overall socio-economic benefits of the project should not make distinctions among users based on their particular nationality 18 . The socio-economic analysis is based on resource costs. For many items the market will provide good indications of these costs. However, some others, such as travel time, are not directly tradable. Non-marketable impacts for rail projects usually affect transport users and also non-users through externalities. For existing transport users, the benefit for society is estimated as the reduction of resource costs that the project will bring (some of them, being non-marketable, are estimated using a value based on willingness to pay 19). For generated traffic, as there is no prior reference to the willingness to pay of the new users, an estimation of the demand curve is necessary. This explains the need to apply the rule of the half when their benefits are compared with those of existing users. The final objective of CBA is to see the impact of the investment on society as a whole, calculated simply by summing up its impact on individuals. Usually a single value (IRR, NPV, CBR) provides the main indication of the projects quality. The distributional analysis will complement this indicator with quantitative and qualitative markers, associated to specific stakeholders, allowing for a more refined global assessment of the project than the traditional CBA. The CBA process can be illustrated as in Figure 1. The following items should be included in the economic analysis: Investment costs; Changes in: Maintenance and operating costs of the infrastructure; Vehicle Operating Costs; Journey times; Safety;
18 It is possible, however, to use this factor positively. For instance the European interest of a project could be related to its integration features and adopt the % of non-national users as a policy indicator. In some cases, a realistic assessment of users value of time may need to consider disaggregation in categories, which could include nationality. 19 The willingness to pay values might be adapted through social values (or shadow values) to take into account global social and economic aspects that are not reflected in users behaviour.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
31
4
Figure 1.
Inputs from Transport Forecasting and Modelling (multimodel passenger and freight ows, journey times, costs)
CBA Scope
Investment costs
Costs and benefits for the investment period and selected forecast years
Discounting
Aggregation
Present values
32
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
Following TINA, it seems useful to make some general recommendations on selected items that are particularly relevant for rail projects:
The basic measure of user benefit is the change in consumer surplus resulting from a change in the transport system. This requires to: Estimate the volume of travel by mode and trip category for each origin/destination pair. If the volume of travel is expected to respond to the change in network quality, both the volume with the change in place and the volume without the change need to be modelled or estimated for the base year and forecast for future years. Estimate the change in generalised costs of travel by mode and trip category for each origin/destination pair. This will include travel time savings, changes in money expenditure and improvements in convenience/comfort. Combine together the trip volume and cost change information so as to calculate the total user benefits over all origins and destinations.
The gains to the transport service providers or producer surplus due to a change in the supply curve produced by the project are taken into account through the variations in investment and operating and maintenance costs.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
33
20 Insurance should, in theory, cover all material damages and medical expenditure linked to accidents. 21 But the value of time savings must be excluded to avoid double counting! Attention must be paid, in particular, to lorry drivers time.
34
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
4.2.5 Externalities
Railway projects may have a considerable impact on the environment. In the case of the construction of a new line, environmental impact mitigation measures should be included in the project design and be part of the investment costs. In other cases, traffic may be transferred from more polluting modes of transport (road and air transport) to rail with positive impacts on the environment that should be included in the analysis (see, for illustration, Annex A for values proposed by INFRAS/IWW).
4.3
Some of the parameters to be considered in the financial and economic analyses are project related and particular reflections are needed for railway projects.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
35
36
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
Residual values are ideally valued as the discounted values of the costs and benefits in an indefinite time series. In this case, the impact of the length of the Operating Period is nil. The residual value is often calculated, however, as the non-depreciated part of the asset. To assume a depreciation method based on the replacement value means accepting that present market conditions will remain stable and that a replaced project will be, after its Operation Period, as competitive as it is today. This is linked to adequate maintenance and some minor upgrading expenditure to maintain the project at adequate standards. Under these circumstances a rather high residual value could be acceptable. Another option is to simply adopt a depreciation formula defining the residual value at any given year. The Operating Period should be shorter than the depreciation period of the main asset of the project (i.e. the infrastructure, for major projects). The depreciation formula is usually linear with time, but in many cases convex functions, notably for rolling stock, are used. A particular component requiring attention is the land purchased for the project. This component, at the end of its useful life, will probably keep its present value (in constant terms) or even increase it. In general a value between the present value in current and in constant terms would be used. Some research is needed to establish residual values for linear rights-of-way and for more adaptable plots such as those used for stations and facilities25. In summary, CBA calculations in the rail sector need to take into account the useful life spans of various assets. When structuring an appraisal, care should be taken to make a set of assumptions on renewals and residual values that is consistent with the appraisal period selected for the analysis. It is often convenient to place the end of the appraisal period at the end of the useful life of a major component of the investment.
25 The high value of some urban land owned by railways signals the interest of the proposed research.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
37
38
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
39
The RAILPAG
approach to project appraisal
5.1
Private sector stakeholders have clear financial profitability maximisation objectives. Goals and objectives for the public sector are much more difficult to establish. Classical economic theory assigns to the State the role of optimising the use of scarce resources for the welfare of society as a whole. Optimisation should be based on agreed objectives. These are not only difficult to establish, but also to define. Quantification of the project effects regarding objectives, which is very convenient for the comparison of alternatives, is the key technical challenge of socio-economic appraisal and requires a certain expertise, as has been shown in former chapters. However, the most difficult aspect of appraisal is probably how to integrate the available information regarding objective attainment to produce reasonable advice on the best option and on its qualities. CBA provides a measure of the efficiency of the investment for society. This covers the most important objectives of the appraisal. The other objectives, in particular redistribution effects and external impacts not properly included in CBA, should also be considered in decision-making and thus be part of the appraisal process. Multicriteria analysis was developed to solve this problem but there is no agreement on how to apply it and, in its present format, it is either too complex or too black box (all criteria are often merged into a single unclear figure). This has hindered the use of multicriteria analysis, which is often criticised as being a way of justifying political solutions. The RAILPAG solution is to extend CBA, in particular for large and complex projects, in order to: a) introduce the non-monetised aspects as simple indicators that generate awareness; b) facilitate the calculation of the maximum/minimum relative economic weight that these non-monetised project impacts should have to compensate their effects, and, in particular, c) to clarify how costs and benefits are distributed. This clarification of the effects of the project on the various stakeholders and the estimation of the expected financial transfers between them has become increasingly important with the new organisational setup. It is, in any event, information that could affect the investment decision.
5.2
CBA requires the estimation of the yearly impacts of the project in terms of costs and benefits. These are integrated in a single indicator (ERR, NPV, B/C ratio) allowing comparisons with benchmarks or an efficient distribution of budget. This information is usually handled using a spreadsheet that allows an easy calculation of the indicators. From the background support of CBA, if the spreadsheet is
42
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
STAKEHOLDERS SE MATRIX USERS TRANSPORT SERVICE OPERATORS INSURANCE CONTRACTORS INFRASTRUCTURE COMPANIES & SUPPLIERS MANAGERS NON USERS GOVERNMENT
properly organised, and provided that reliable data are available, it is relatively simple to obtain specific information on the effects of the project on the various stakeholders. A simple discussion of these effects should be included in the conclusions of the appraisal. For projects requiring a more refined distributional analysis, a SE Matrix (see Figure 2 for a simplified version) will be most useful. The SE Matrix takes advantage of the information that should be available for the traditional CBA, to present it in a way that relates effects (in the rows) and stakeholders (in columns) summarising the main economic and financial implications of the project and showing the transfers between stakeholders and the distribution of costs and benefits. It also incorporates markers for non-monetised effects and overall indicators of the profitability of the investment.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
43
5.2.3 Thresholds
The SE Matrix can be used to show valuable information on these non-monetised cells. In particular, it could easily be used to indicate the discounted cash (NPV) that it would be necessary to be globally assigned to all these elements (or to any sub-set of them) to ensure that the project reaches the established threshold of profitability. Alternatively (if the value is negative) it would show the reduction of benefits that these qualitative cells should have to lower the ERR of the project to the treshold. These values are extremely important to place the non-monetised impact in the appraisal (at least suggesting the order of magnitude they should have to influence the decision) and to eliminate an important element of subjectivity in the appraisal that has been particularly harming to rail projects26 . The next chapter explains in more detail the application process of RAILPAG. Annex D applies RAILPAG to several case studies.
26 It is not unusual to find justifications for rail projects based on environmental considerations that have not been quantified at all or compared with the CBA results.
44
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
45
Applying
RAILPAG
6
6.1
Applying RAILPAG
General concepts
Railway project appraisal needs a methodology that is simple and transparent, but able to respond to the current changing scenarios in the railway sector, and adaptable to the size and complexity of the project. RAILPAG aims at facilitating decision-making through an overall understanding of the projects effects and a simultaneous view of all the important issues at stake, whilst maintaining a rigorous approach that will take into account all the technicalities of the sector. The RAILPAG approach could be used for planning and programming exercises, including some screening processes, but is mostly focused on the appraisal of specific projects for which a rail solution is envisaged. The following comments on how to apply the Guidelines and the case studies showing how to do it in practice are mostly limited to specific rail projects. The RAILPAG appraisal process consists of three phases (see Figure 3): the first one is dedicated to defining the problem and choosing reasonable alternatives. The second phase, consists of a thorough CBA of these alternatives, supported by adequate demand studies (notably to establish forecasts for the project use and for competing options). It should also contain a discussion of the distributional effects of the project including, whenever it is appropriate, the elaboration of an SE Matrix for each do-something alternative. The last phase is dedicated to analysing each alternative and comparing them, expressing their relative values leading to recommendations for the decision-makers.
6.2
The definition of the projects objectives and its multimodal alternatives is a critical first phase. It is not possible to give indications on how to do this for the myriad of projects proposed in the rail sector. The technical quality and the creativity of the design team and its ability to envisage potential solutions outside the rail mode are critical for this phase, which is the most difficult to scrutinise by external evaluators. The second phase requires the elaboration of the CBA following the indications provided in TINA and those in chapter 3. If a SE matrix is considered necessary, the CBA should include the calculations needed to fill out the SE matrix for each of the alternatives selected in the first phase. Thus, if the SE matrix must be produced, a first step in the CBA will always be the establishment of the main stakeholders and main effects to be taken into consideration.
48
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
Definition of alternatives
PHASE 1
General aspects
Do-minimum Alternative 0
Alternative 1
Alternative N
Scenarios
PHASE 2
Financial analysis
Socio-economic analysis
External effects
PHASE 3
Preference map
Non-monetised effects
DECISION
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
49
Applying RAILPAG
6.2.1 Distributional aspects. Filling the SE Matrix
It is recommended that some consideration be given to the distributional impacts of the project. For small investments, a simple assessment may be sufficient. For large and/or complex projects, the elaboration of a SE Matrix should be envisaged. The SE Matrix for a specific investment will, in general, further divide effects and stakeholders to produce a more detailed version of the basic matrix in Figure 2, adapted to the specificities of the project. Figure 4 provides a kind of maximum division of the SE Matrix, which includes all the relations that are potentially relevant for a rail project. For each specific case, this matrix will be adapted (reduced) to those effects and stakeholders that are really relevant for the case. Only some of the cells in the SE Matrix will have a noticeable impact on the appraisal. Figure 5 indicates those that a priori could be active, i.e. cells that are relevant because the relationship between stakeholder and effect represents a significant socio-economic or financial incidence. Active cells vary from one project to another, and also the criteria to define their contents (the effect for the stakeholder: a NPV or a colour and/or a comment). A main recommendation of RAILPAG is to carefully analyse the stakeholders, the effects and their relationship in order not to overlook any relevant factor in the CBA. In any case, it is more prudent to assume that irrelevant cells will be active ones than the contrary situation. The estimation of the cell values usually requires a rather complicated modelling exercise. The economic appraisal heavily depends on the traffic demand. Unfortunately very often both studies are being carried out independently. This creates inefficiency and often induces errors. It is strongly recommended that the market analysis contemplates the various alternatives and also the potential impact of changes in fares, in particular for the rail mode. The appraisal team should also be able to run the demand models to observe the likely impacts of changes in the alternatives that might not have been considered in the forecasting exercise. Usually the CBA, with the calculations leading to the various NPVs that have to be inserted in the SE Matrix, is carried out using a spreadsheet. This type of working environment is particularly useful and the case studies provide examples of how to carry out the CBA in a systematic way. RAILPAG may be further developed in the future through some specific software tools. In the meantime the appraisal team will have to prepare ad-hoc spreadsheets (or equivalent) to produce the values in the matrix. In the CBA there are effects that only have financial implications, such as fares27, which will appear in the cells of the disbursing stakeholders as negative and in the cells of those receiving the cash flows as positive. As they are pure transfers in economic terms, the total value of the effect (in the row totals of the right hand) should be zero. Actually the zero sum of these financial transfers is an important check of the quality of the matrix. Some effects, such as the value of travel time savings, are purely economic, as they are not marketable. They will appear in the relevant cells with the proper sign and provide a total economic benefit or cost estimation. Finally some cells will have to be split to provide both the financial NPV component and the economic NPV for the part that is not covered by the cash-flow. The economic value for the stakeholder will be the addition of the two components and will be reflected in the columns total, whilst the row with the financial transfers will have a zero total28.
27 The cost of collecting and managing them are normally included in the global operation costs. 28 See, for example, the treatment of safety benefits in case study 6.
50
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
INSURANCE COMPANIES
SE MATRIX
Freight
Rail manager 1
Rail Operator 1
Rail Operator 2
Rail manager 2
Superstructure
Infrastructure
Other modes
Rolling stock
Other modes
REGIONAL
REGIONAL
Freight
EFFECTS
Fares Travel time
Pax
Pax
NATIONAL
LOCAL
LOCAL
USER SERVICE
Reliability of service Comfort Convenience Safety / accidents (economic / financial) Consumer surplus (new traffic) Fees
DIRECT
Vehicle operating costs Operating personnel Facilities operations Overhead management -HQ Subsidies Taxes Land value Infrastructure Superstructure
OPERATION
INVESTMENT
INDIRECT
Stations & terminals Garage & repair facilities Rolling stock (vehicles) Residual value Taxes
ASSETS
MAINTAINANCE (ROUTINE)
EXTERNAL EFFECTS
ENVIRONMENTAL
TERRITORIAL DEVELOPMENT
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
51
EU
...
...
Applying RAILPAG
A major problem in project appraisal is the difficulty of translating into monetary terms some effects that are essentially qualitative. The use of the colour code proposed by RAILPAG makes it possible to raise the awareness of the decision-maker on those aspects that have not been integrated into the cash-flow analysis. In general, cells with NPVs will have no colour, although they can be used when certain socio-economic aspects cannot be reflected in the financial or in both the financial and the additional economic component29. This subjective appraisal of non-monetisable impacts is carried through to the total NPV for the stakeholder and the effect in question. This means that the total in the corresponding row and column will also have a colour. When there are several coloured cells in a row or column, the addition of colours will have to be translated into a single colour for the total through a subjective exercise by the evaluator. This presentation is suited to eliminate some of the appraisal biases that have been affecting rail project appraisals, such as the use of the environmental friendliness of the mode or the positive effects on job creation to justify poor projects. A recommended way of dealing with important nonquantified effects is to estimate in the CBA, and then indicate in the SE Matrix, the NPV that should be added to (or subtracted from, when the effects are negative) the total benefits, to reach the desirable minimum ERR for the project. This value would give an indication threshold for the acceptable total of non-quantified costs and benefits. It could also be done for a specific cell, although, in this case, it might be necessary to compare the cell value with the totals in the row and column for the cell or with other cells estimating similar effects30. As for other methodological refinements, the appraisal team will need to balance the time and effort burden of collecting and treating data against the value of the additional information produced. In conclusion, the SE Matrix: a) provides valuable information, within the cells, on the individual SE relationships; b) the row and column totals allow identification of the relative importance of each type of effect (both financial and economic) and the relative impact of the project on each stakeholder, making it possible to analyse its distributional aspects; c) the standard indicators (NPV, ERR and B/C ratio) and the colour code give an assessment of the overall profitability; and, finally, d) the indications on the value to be given to non-monetised impacts to be able to affect the feasibility of the project provide a reference on those aspects that are most difficult to include in the appraisal. The information summarised in the SE Matrix thus provides an integrated picture of the consequences of the project. Information on socio-economic, including non-monetised, and financial aspects facilitates a comprehensive appraisal of the qualities of the project. On the other hand, presentation of the financial analysis will help the understanding of redistribution effects which are critical, notably in the context of Public Private Partnerships (PPPs), where global risk analyses heavily depend on an adequate distribution of risks and rewards. It should be noted, however, that PPP structures are likely to introduce a number of additional stakeholders with complex -and sometimes conditional- financial relationships based on risk coverage arrangements.
29 There is obviously a risk of double counting when some effects are given partially monetary values and partially qualitative marks. The evaluator should explain the mark when necessary. The double-counting risk is not dissimilar to those found in other methods, which do not provide the same easily readable indicators. 30 It is possible to deal with the question in a more systematic way. For instance, the number of cells with different colours could be given a weight (for instance 1, 2, 3) and see how big should be the single cell value to achieve the desired ERR and then observe the logic of this value, multiplied by the weight, for the various effects.
52
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
INSURANCE COMPANIES
SE MATRIX
Freight
Rail manager 1
Rail Operator 1
Rail Operator 2
Rail manager 2
Superstructure
Infrastructure
Other modes
Rolling stock
Other modes
REGIONAL
REGIONAL
Freight
EFFECTS
Fares Travel time
Pax
Pax
NATIONAL
LOCAL
LOCAL
USER SERVICE
Reliability of service Comfort Convenience Safety / accidents (economic / financial) Consumer surplus (new traffic) Fees
DIRECT
Vehicle operating costs Operating personnel Facilities operations Overhead management -HQ Subsidies Taxes Land value Infrastructure Superstructure
OPERATION
INVESTMENT
INDIRECT
Stations & terminals Garage & repair facilities Rolling stock (vehicles) Residual value Taxes
ASSETS
MAINTAINANCE (ROUTINE)
EXTERNAL EFFECTS
ENVIRONMENTAL
TERRITORIAL DEVELOPMENT
EU
...
...
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
53
6
CELL CLASSIFICATION
USERS RAIL LINES ALTERNATIVE MODES TRANSPORT SERVICE OPERATORS RAIL
Applying RAILPAG
Figure 6. Cell expansion program.
STAKEHOLDER
STAKEHOLDERS
CONTRACTORS & SUPPLIERS
Financial transfer
INFRASTRUCTURE MANAGER RAIL NON USERS (external)
cell
GOVERNMENT
PASSENGERS
INSURANCE COMPANIES
SE MATRIX
Freight
Rail manager 1
Rail Operator 1
Rail Operator 2
Rail manager 2
Superstructure
Infrastructure
Other modes
Rolling stock
Other modes
REGIONAL
REGIONAL
Freight
NATIONAL
LOCAL
EFFECTS
Fares Travel time
Pax
Pax
LOCAL
EFFECT
DESCRIPTION: NPV of incremental fare that railway use rs have to pay. It is to divide them amo often necessary ng existing, diverted and generated use rs. CALCULATION: Ideally, for each of the three types of passengers: i) - Fare (/passe ngerkm) x Trac with this fare (pas sengerkm) Considering di erent fares Alternatively: ii) -Average fare (/p assengerkm) x Tra c (passengerkm) The fare revenue from the do-minimum case (existing trac) to be deducted. SOME VALUES: 0.12 (conventional line) to 0.25 (high-sp eed line) /passen from Spanish case ger/km (data ) CRITICAL ISSUES: Demand forecast s (see chapter Ge neral Aspects). Sop forecasting models histicated trac are needed, in part icular under yield management. REMARKS:
USER SERVICE
Reliability of service Comfort Convenience Safety / accidents (economic / nancial) Consumer surplus (new trac) Fees
DIRECT
OPERATION
Operating personnel Facilities operations Overhead management -HQ Subsidies Taxes Land value Infrastructure Superstructure
INDIRECT
USER SERVICE
FARES
INVESTMENT
Stations & terminals Garage & repair facilities Rolling stock (vehicles) Residual value Taxes
ASSETS
MAINTAINANCE (ROUTINE)
EXTERNAL EFFECTS
ENVIRONMENTAL
TERRITORIAL DEVELOPMENT
project and the do-minimum alternative goes against the expected sign (i.e. it could be that some impacts that are usually positive, such as time savings, become negative for some users). Some of these positive NPVs in the CBA are directly transferred to the matrix. To facilitate the task, a colour code has been used: blue for the NPVs keeping the sign and red for those requiring a change of sign. The pure financial transfers are also indicated using numbers of a different colour or different style in the title of the effect in the CBA. RAILPAG provides some specific indications on how to produce the values for the SE cells. In Annex C, a fiche for the most relevant SE cells is provided, giving guidance on how to introduce the effect on the stakeholder in the appraisal. The fiches are organised using the same general layout in order to manage information more efficiently. There are several labels for identification of the referenced cell and the following points: description of the effect and the related stakeholder, units used to quantify the effect, some values as a reference, relative importance and other remarks. The RAILPAG website will allow quick access to the specific fiche for each cell, as depicted in Figure 6, which shows the standard contents as applied to fares and rail passengers. These fiches will be continuously updated using
54
RA I LPAG
EU
...
...
It is recommend ed to use method of calculation (i) distribution by clas and consider ses (business class, etc.), season tickets Fares quantied & discounts. here usually incl ude transport and when safety is a maj insu rance, except or issue for the proj ect. Taxes (i.e. VAT separately. ) are considered The total of addition al fares paid by use rs (thus a negativ be found as a pos e number) must itive value in the corresponding cell revenues for operato for additional rs.
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
6.3
Comparative analysis
Finally, the third phase consists of the analysis of the alternatives, to establish their overall socio-economic and financial implications, including the expected redistribution impacts. For this comparative analysis the global indicators will obviously be critical. A major issue arises when the best option in socio-economic terms shows financial feasibility difficulties or unbalanced results for specific stakeholders. This could affect the ranking of alternatives or the elimination of feasible options that do not comply with a benchmark. This link between socio-economic and financial analysis, as well as the link between performance indicators and risk, are left for future developments of RAILPAG. In most cases the comparison among various alternatives will allow the selection of a preferred alternative or a maximum of two or three acceptable options. For them a more detailed analysis of the different aspects and the trade-offs between effects/stakeholders in the alternatives could be necessary. In some cases a sensitivity analysis 30 would be required to assess the robustness of the different options. The final selection of the recommended alternative (or alternatives, if no clear conclusion could be reached) could be performed using some relatively sophisticated mechanisms such as Preference Maps, or simply through a careful explanation of the motivation behind the proposal. In any case, it is recommended to make a complete and detailed revision of the SE Matrix for the proposed solution, to ensure that no mistakes have been made, and to improve its presentation to the decision-maker. The selection process described above could be simplified if, for technical reasons, there is only one alternative to the do-minimum option. Then a single SE Matrix should provide the indications for the feasibility or not of the project.
30 The use of Monte Carlo simulations for some key parameters could be appropriate, but in most cases the observation of the impact on the results of up and down variations (i.e. of 10-20%) of the variable or parameter in question will be sufficient.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
55
Annexes
A
Figures from INFRAS / IWW 2004
External costs
[Euro / 1000 pkm] Accidents Noise1) Air Pollution Climate Change High Climate Change Low2) Nature & Landscape Up-/Downstream3) Urban Effects Total EU 174) 30.9 5.2 12.7 17.6 2.4 188.6 1.3 20.7 8.3 16.0 3.8 11.7 32.4 5.1 13.2 16.5 0.8 3.9 6.9 6.2 0.4 1.8 2.4 46.2 22.3 4.2 10.0 23.7
[Euro / 1000 tkm] 35.0 32.4 86.9 57.4 4.8 4.9 38.3 12.8 7.6 7.4 42.8 16.9 0.0 3.2 8.3 0.0 8.9 15.6 0.0 0.0 14.1 4.3 6.5 7.1 38.5 16.9
3.2 235.7
37.7 226.3
67.2 250.2
17.9 271.3
Remarks: 1) The modal differences in noise costs are directly related to the national noise exposure databases used and thus might be subject to different ways of noise exposure measurement. Average climate change costs for the low scenario (for information only, values not used to calculate total costs). Climate change costs of up- and downstream processes are calculated with the shadow value of the Climate Change High Scenario. Total average costs calculated with the climate change high scenario. Noise costs for freight trains might be under-estimated as the simplified traffic assignment procedure applied did allocate most freight trains to daytime traffic.
2)
3)
4) 5)
58
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
59
With regard to track superstructure equipment, its lifespan depends largely on the volume of traffic sustained and speed. Representative values are shown in the next table; the component having the shortest life is the ballast, which requires partial renovation without changing rails or sleepers.
60
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Regarding rolling stock, the expected life depends on the speed characteristics of the material and the type of service it is assigned to.
Rolling stock
Type of vehicle Freight wagons for conventional lines Freight wagons for both conventional & high-speed lines Passenger cars for long distance and regional services Passenger cars for suburban and metropolitan services Motor train unit Locomotives for services in conventional lines Locomotives for services in high-speed lines Cars for high-speed lines Top speed Speed under 100 km/h Speed over 100 km/h Speed over 120 km/h Speed under 120 km/h Speed under 120 km/h Speed under 200 km/h Speed over 200 km/h Speed over 250 km/h Years* 40 30 25 15 15-25 25 20 15
*Some internal elements, such as the interior of passenger cars, may have a shorter service life. This may mean refurbishing a vehicle before the end of its service life.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
61
SE cells
This annex contains fiches referring to the key cells in the SE matrix, providing a description of the link between the relevant stakeholder and the effects, and guidance on how to introduce the cell information in the appraisal. There are essentially six types of cells: Financial cells, which contain the NPV of the expected cash-flows for effects representing the use of scarce resources, for which market prices adequately reflect their value for society. The financial and economic values can be assumed to be identical. Investment and maintenance costs fall within this category. Financial transfer cells, which reflect pure cash-flow transfers between stakeholders. Their total economic value (reflected in the row total) is nil. Fares and taxes are typical for this category. Economic cells for which there is no market price for the effect, but which can be given an economic value. Travel time savings are a typical example of this. Economic and financial cells are in fact divided cells, with a financial transfer component and an economic component necessary to produce the true economic cost for society of the effect. Accident costs for users often fall into this category, as insurance (a financial transfer between transport users and insurance companies) will cover only a part of the social cost of accidents. The economic supplement, in the second sub-cell, should include the users and public expenditure and the moral damages (suffering, etc.) that are not covered by the insurance premia. This category also allows for the use of shadow prices when considered necessary by the evaluator. Dividing the cell into two components indicates the importance of the socio-economic bias introduced in the CBA. Quantified socio-economic cells include those economic cells for which it is possible to quantify the effect but the evaluator does not have the possibility to make a proper economic estimation of it. The information in the cell could, for instance, refer to the diminution of pollutant emissions, which could be estimated in average tonnes/year, given that the economic value of the various pollutants is under discussion. The figures should be provided in the cell along with a colour indicating the relative importance given to the effect. Non-quantified socio-economic cells, due to lack of quantitative information or simply of factual data. If the effect is considered relevant, a subjective appraisal through a colour code is recommended to avoid disregarding it in the appraisal. It could be interesting to provide figures regarding the amount of NPV that would be necessary for this effect to change the weight of the overall results (for instance, to reach an ERR of 5%). The fiches will certainly depend on the cell category. In the first four cases, they will contain indications on how to obtain the NPV, with general comments on financial and economic aspects, reference values that could guide the calculation, an identification of the critical issues that the evaluator must deal with and other relevant remarks. When the SE relationship cannot be monetised (cases 5 and 6), some comments are provided on how to incorporate it in the matrix (through quantification, when possible, and a colour code). The NPV calculations are part of the CBA supporting the SE matrix presentation. The CBA must always refer to the comparison of the alternative being analysed with the do-minimum option, so the cells must indicate the discounted value of the difference in the specific effect considered for the stakeholder in question. The fiches are not supposed to provide all the information required to make the calculations in most rail projects. This could be the object of future appraisal manuals. In RAILPAG only general guidance is provided, mostly referring to the approach to be adopted so that theory and practice are balanced for maximum efficiency.
62
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
The following SE matrix indicates those cells for which specific fiches could be particularly useful to guide the evaluators. They are expected to be fully developed during the RAILPAG process, for which this document is just a first step. The eventual aim of these fiches is to develop into a type of appraisal manual for rail projects. However, to be able to provide the detailed information necessary for a Europe-wide standardised reference manual it is necessary to carry out an important exercise of research and data gathering that falls outside the scope of the present exercise. The fiches in this annex are thus only provided as indications of the type of content that can be expected in the future. The reader should check the web site www. railpag.com for updates.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
63
C
USERS RAIL LINES ALTERNATIVE MODES
SE cells
INSURANCE COMPANIES
SE MATRIX
Freight
Rail manager 1
Rail manager 2
Rail Operator 1
Rail Operator 2
Superstructure
Infrastructure
Other modes
Other modes
Rolling stock
REGIONAL
REGIONAL
EFFECTS
Fares Travel time
NATIONAL
Freight
LOCAL
LOCAL
Pax
Pax
USER SERVICE
Reliability of service Comfort Convenience Safety / accidents (economic / financial) Consumer surplus (new traffic) Fees
DIRECT
Vehicle operating costs Operating personnel Facilities operations Overhead management -HQ Subsidies Taxes Land value Infrastructure Superstructure
OPERATION
INVESTMENT
INDIRECT
Stations & terminals Garage & repair facilities Rolling stock (vehicles) Residual value Taxes
ASSETS
MAINTAINANCE (ROUTINE)
EXTERNAL EFFECTS
ENVIRONMENTAL
TERRITORIAL DEVELOPMENT
64
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
EU
...
...
STAKEHOLDER
PASSENGERS
RAIL LINES USERS
EFFECT
DESCRIPTION: NPV of incremental fare that railway users have to pay. It is often necessary to divide them among existing, diverted and generated users. CALCULATION: Ideally, for each of the three types of passengers: i) - Fare (/passengerkm) x Traffic with this fare (passengerkm) Considering different fares Alternatively: ii) -Average fare (/passengerkm) x Traffic (passengerkm) The fare revenue from the do-minimum case (existing traffic) to be deducted. SOME VALUES: 0.12 (conventional line) to 0.25 (high-speed line) /passenger/km (data from Spanish case) CRITICAL ISSUES: Demand forecasts (see chapter General Aspects). Sophisticated traffic forecasting models are needed, in particular under yield management. REMARKS: It is recommended to use method of calculation (i) and consider distribution by classes (business class, etc.), season tickets & discounts. Fares quantified here usually include transport and insurance, except when safety is a major issue for the project. Taxes (i.e. VAT) are considered separately. The total of additional fares paid by users (thus a negative number) must be found as a positive value in the corresponding cell for additional revenues for operators.
USER SERVICE
FARES
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
65
C
Financial transfer cell
SE cells
STAKEHOLDER
FREIGHT
EFFECT
DESCRIPTION: NPV of incremental fare that freight shippers will have to pay to the rail operator. It is often necessary to divide shippers among existing, diverted and generated users. CALCULATION: Ideally, for each of the three types of shippers: i) - Fare (/tkm) x Traffic (tkm) Considering different freight types (in some cases tariffs are not related to weight, but rather to TEU or other) Alternatively: ii) -Average fare (/tkm) x Traffic (tkm) SOME VALUES:
USER SERVICE
FARES
0.08 to 0.12 /tkm (data from Spanish case) CRITICAL ISSUES: Demand forecasts (see chapter General Aspects). It is difficult to estimate future traffic, as it depends on a really competitive market that is very much affected by unforeseeable conditions (i.e. fuel prices, tolls, transit limitations, etc.). It is even more difficult to foresee income from freight, as fares are often dependent on client conditions, even for the same type of freight. For projects aimed at diverting traffic from road to rail, this cell is critical and very difficult to estimate. Sensitivity analyses are then unavoidable. REMARKS: If demand cannot be distributed by freight types, method of calculation (i). If better precision is required, method (ii) will be applied, considering distribution by types. Fares quantified here include transport and insurance (this component is marginal in most cases). Taxes considered separately.
66
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
PASSENGERS
EFFECT
DESCRIPTION: NPV of the fares that diverted users are avoiding in the original mode (usually bus or air transport) CALCULATION: i) -Average fare (/passxkm) x Diverted traffic (passxkm) SOME VALUES: 0.12 to 0.15 /passxkm (bus) (data from Spanish case) 0.10 (low cost) to 0.30 / passxkm (regular plane) (data from Spanish case)
USER SERVICE
FARES
CRITICAL ISSUES: Demand forecasts (see chapter General Aspects) and determination of average fares (as it is usually not worthwhile to go into detailed analysis of diverted traffic). Confronted with the new competition due to the project, the supply of service and fares of alternative transport modes may change. The forecasting difficulties may justify a rather simplistic approach (such as average fares). REMARKS: If diverted traffic is very important, more detailed forecasts and sensitivity analyses are recommended. Fares quantified here include transport and insurances. Taxes should be considered separately if they are specifically included in the cell for rail fares for diverted rail users.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
67
C
Financial transfer cell
SE cells
STAKEHOLDER
OPERATORS
EFFECT
DESCRIPTION: NPV of additional income obtained by operators for services offered. CALCULATION: These incomes must correspond to the amounts paid by users, without taxes. CRITICAL ISSUES: The same as for users fares REMARKS: Insurance could be treated separately if safety impacts are particularly relevant. Taxes circulating through the operators (VAT paid by users) are not included here.
68
RA I LPAG
USER SERVICE
FARES
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
INSURANCE COMPANIES
EFFECT
DESCRIPTION: NPV of the insurance fees paid by users. If necessary, columns for different modes can be established. CALCULATION: Insurance premia differential between the proposed alternative and the dominimum. Train and airfares usually incorporate an insurance component that goes to the insurer. This amount, multiplied by the difference in the number of users, will provide the yearly amounts to be included in the calculation of the NPV. In the case of road traffic a project will usually not affect the payment of the users, but a reduction in road accidents will have positive financial effects on insurers (see accidents-insurer cell). SOME VALUES:
USER SERVICE
FARES
In most cases a percentage of the fare will be sufficiently precise. Information on the weight of insurance in fares is not well known to evaluators and should be publicised. CRITICAL ISSUES: Demand forecasts (see chapter General Aspects) REMARKS: The column on insurance can often be excluded, as the financial impact of projects is negligible, except for safety-oriented schemes. In such cases (see the elimination of rail-road crossing case study) it is recommended to include it, paying attention to the consideration of this item in the fare to avoid double counting. In any case, this is considered a transfer, although it can be argued that insurance premia require resources to be managed. This can be considered irrelevant in the context of a rail project appraisal, even for most safety oriented projects.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
69
C
Financial transfer cell
SE cells
STAKEHOLDER
EFFECT
TAXES
OPERATION
The better known indirect taxes are VAT (% of expenditure falling on final consumer) and local taxes for some constructions. For taxable cash flows that will be similar with and without the project (i.e. VAT on diverted users), it is advisable to exclude taxes altogether, as they will not affect results in a noticeable way. CRITICAL ISSUES: Revenue forecasts and tax evolution. REMARKS: If these taxes are split among authorities and the issue is relevant (to show contributors and beneficiaries) all columns must be shown. Row total for taxes must be zero, as they are considered a transfer (although it can be argued that there is a cost of raising public money, but this is a complex discussion see main text on cost of public money).
70
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
Economic cell
PASSENGER
RAIL LINES USERS
EFFECT
DESCRIPTION: NPV of the value of the reduction of travel time for the passengers using rail services with project. CALCULATION: Saved time in comparison with do-minimum: In general, three types of traffic should be distinguished (they could be separated into three different columns): Existing traffic: modifications in travel time for current rail users remaining in the mode Diverted traffic: modifications in total travel time between the original mode and the new mode. If travel time is increased (as is sometimes the case for road to rail diversion) the value would be negative.
TRAVEL TIME
USER SERVICE
Generated traffic: as there is no trip for the do-minimum alternative, all benefits for users are considered in the consumer surplus estimate (see corresponding SE cell). Time savings may evolve during the life of a project due to road congestion or other reasons. If they are due to improvements requiring investment (for instance new rolling stock), this should be included in the investment figures. Value of time saved: For existing and diverted trips, the corresponding composition of traffic (i.e. business, commuter and leisure trips, with each having a different value of time) is used to calculate a weighted average value of time (/passhour) that is multiplied by the time savings in hours. It is recommended to take into account both a change in the composition of traffic (so the average value of time changes over the years) and an evolution of the value of time to take into account the improvement of living standards. SOME VALUES: Reference is often made to average wages. See references. CRITICAL ISSUES: Value of time (see chapter General Aspects).
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
71
C
Economic cell
SE cells
STAKEHOLDER
FREIGHT
EFFECT
DESCRIPTION: NPV of the value of the reduction of travel time for freight using rail services with project. CALCULATION: Saved time in comparison with do-minimum: As for passengers. Value of time saved: It is essential to distinguish between the value of time savings (VTS) of existing and diverted traffic. VTS for existing rail traffic is purely related to the value of freight usually low value for captive rail traffic), whilst diverted road traffic, for instance, must consider the higher value of the cargo and, in particular, the value of time of the driver (and other staff in the lorry), to be calculated at full salary cost. For other modes (maritime or inland navigation, air transport) only the different value of freight could be an issue. CRITICAL ISSUES: Value of time (see chapter General Aspects). REMARKS: Freight travel times should be measured door-to-door. They are difficult to establish as logistic chains depend on many variables. Forecasting models are difficult and not very reliable. On the other hand as train freight services tend to be very slow, reliability becomes more important than travel time. It is thus recommended to spend effort on this cell only when improvement of freight traffic is a main objective of the project. In general this cell is only relevant when there is an important diversion from road traffic (due to the value of time of the driver).
72
RA I LPAG
TRAVEL TIME
USER SERVICE
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
Economic cell
PASSENGER
EFFECT
DESCRIPTION: NPV of the value of the reduction of travel time for passengers affected by the project and using other transport modes. CALCULATION: Saved time in comparison with do-minimum: It will essentially be due to a reduction in congestion due to traffic diversion to rail. There is an argument, in this case, about the possibility of generating additional traffic in the mode as it becomes more attractive. If these effects could be important in the CBA (project in rail to solve a congestion problem in road or air transport), traffic forecasts should take all this into account and distinguish the various types of generated traffic in the appraisal. It is important to pay attention to car occupancy if traffic is measured in vehicles. SOME VALUES(*): Must be consistent with those used for diverted car traffic. (*) There is plenty of data available to set values for travelling with different modes, as well as for walking and waiting. There is, on the other hand, not so much empirical evidence for determining VOT to reflect congestion and unreliability. Wardmans analysis (published in Transportation Research 2001) suggests a mark-up of about 50% when travelling during peak hours. This mark-up may well reflect both congestion (less comfort) and poorer reliability. CRITICAL ISSUES: Value of time (see chapter General Aspects). REMARKS: The effects produced by the elimination of bottlenecks must be considered (see chapter General Aspects). Due to changes in demand, operators of alternative modes can modify supply, which could affect saved time for users.
TRAVEL TIME
USER SERVICE
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
73
C
Economic cell
SE cells
STAKEHOLDER
FREIGHT
EFFECT
DESCRIPTION: NPV of the value of the reduction of travel time for freight affected by the project and using other transport modes. CALCULATION: See similar cell for passengers and general comments on travel time freight users. CRITICAL ISSUES: Value of time (see chapter General Aspects). REMARKS: The effects produced by reduced congestion tend to be less important in slower vehicles. This cell is often of minor importance.
74
RA I LPAG
TRAVEL TIME
USER SERVICE
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
Socio-economic cell
PASSENGERS
EFFECT
RELIABILITY OF SERVICE
Reliability is an important concept for rail services and has proved to be an essential component of their competitiveness. However, there is no standard definition commonly accepted and there are severe difficulties in establishing the differences in reliability between two situations (with project and do-minimum, for instance). The coefficient of variation (standard deviation divided by the mean) of travel times or simpler indicators such as % of trains delayed more than x minutes, would give a quantified estimate of reliability that could be introduced in the cell. SOME VALUES: The economic value of reliability or its relation with travel time values have not been properly studied. Even if quantified, a subjective evaluation (through the colour code) will probably be necessary, if this is considered a substantial aspect of the projects benefits. CRITICAL ISSUES: Determination of the distribution of delays with and without the project. REMARKS: Some operators warrant punctuality and return a part of the fare if there is any delay. This fact could be included in the cell as a pure financial transfer. Research is needed to link the characteristics of the infrastructure with reliability and to establish economic values for improvements in this quality.
USER SERVICE
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
75
C
Economic and financial cell
SE cells
STAKEHOLDER
PASSENGERS
RAIL LINES USERS
EFFECT
DESCRIPTION: NPV of changes in the value of accidents suffered by passengers. CALCULATION: The difference between the alternatives for the economic: [Risk of mortal accidents (number of deaths/passkm) x Valuation deceased (/deceased) x Traffic (passkm)] + [Risk of serious accidents (number of serious casualty/passrkm) x Valuation serious injuries (/serious casualty) x Traffic (passkm)] +
SAFETY / ACCIDENTS
[Risk of minor accidents (number of slight casualties/passkm) x Valuation slight injuries (/slight casualty) x Traffic (passkm)] + [Risk of pure-damage accidents (number of accidents/passkm) x Average valuation damages (/slight casualty) x Traffic (passkm)] Note: damage to users goods (cars) included in accident costs; external damages in separate cell and the financial part: Insurance compensation for the same amount of deaths, serious injuries and slight injuries SOME VALUES: From EU manuals or similar, providing a global view on the value of life and limb. For insurance compensations, information from sector associations. CRITICAL ISSUES: Quantification of risks (through statistic studies) and valuation of deceased, seriously injured and slightly injured. REMARKS: There is a financial part corresponding to compensations and equivalent to the amount that insurance companies pay for this concept, in a percentage laid down by law and contracts among those stakeholders. The economic component includes non-compensated economic costs (including suffering) for transport users.
76
RA I LPAG
USER SERVICE
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
OPERATORS
EFFECT
SAFETY / ACCIDENTS
CALCULATION: Valuation of material damages + interruption of the service meaning loss of income - Insurance compensation SOME VALUES: Accident risks for different types of operation should allow comparison of expected accidents with project and in the do-minimum case. The cost of the standard accident for both operations and the % covered by insurance are also necessary. This part would represent a transfer with the insurance companies, and the rest an economic cost to be absorbed by the operator. The cell could be divided into two parts, if these two parts differ substantially. CRITICAL ISSUES: Quantification of accidents (through statistic studies). REMARKS: Users are usually covered by separate insurance.
USER SERVICE
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
77
C
Economic and financial cell
SE cells
STAKEHOLDER
EFFECT
SAFETY / ACCIDENTS
[Risk of mortal accidents (number of deaths/passkm) x Valuation deceased (/deceased) x Traffic (passkm)] + [Risk of serious accidents (number of serious casualty/passrkm) x Valuation serious injuries (/serious casualty) x Traffic (passkm)] + [Risk of minor accidents (number of slight casualties/passkm) x Valuation slight injuries (/slight casualty) x Traffic (passkm)] + [Risk of pure-damage accidents (number of accidents/passkm) x Average valuation damages (/slight casualty) x Traffic (passkm)] SOME VALUES: Needs a case-by-case assessment. CRITICAL ISSUES: Quantification of risks (through statistic studies) and valuation of deceased, seriously injured and slightly injured non-users. REMARKS: This is particularly important for specific safety projects such as elimination of rail-road crossings. In most cases the impact of rail projects on non-users is very small. The reduction in the number of pedestrian and cyclists that are run over as a consequence of road traffic transferred to rail could, only in special circumstances, be substantial.
78
RA I LPAG
USER SERVICE
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
EFFECT
SUBSIDIES
CALCULATION: The real amount of subsidies arriving to the beneficiaries could have to be increased by the expenditure for the public agencies giving them (this would be a resource cost to be included if there is a differential between alternatives). CRITICAL ISSUES: Subsidies (except if concomitant public expenditure is very big) are pure financial transfers). It must be shown if the project allows reduced subsidies somewhere else in the system (for instance, in other public transport modes).
OPERATION
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
79
C
Economic and financial cell
SE cells
STAKEHOLDER
INFRASTRUCTURE MANAGER
DESCRIPTION: NPV of the differential investment to be carried out by the infrastructure manager. Economic costs are included here. CALCULATION: The economic costs can be established as the contract cost for the rail manager (if he is doing the investment). This would include a normal profit for manufacturers and constructors, that can be estimated as a certain percentage (5 to 15%) of the investment. If the profit is exceptional or it is important to indicate it, a separate column for the construction company must be envisaged and a reasonable economic cost plus a transfer to the company included in the matrix. Taxes are considered separately. SOME VALUES: Case-by-case. CRITICAL ISSUES: Proper design and pricing. Key element in the appraisal. REMARKS: Inside this concept of investment is included the cost of land: it is transference between Government and non-user. It is calculated through the price of expropriation. It is important to separate this cost when expropriation is a major cost component. The tax issue is particularly important here. See discussion on cost of public money.
EFFECT
80
RA I LPAG
INVESTMENT
ASSETS
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
STAKEHOLDER
EFFECT
MAINTENANCE (ROUTINE)
ASSETS
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
81
C
Quantified socio-economic cell
SE cells
STAKEHOLDER
EFFECT
82
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Case studies
This annex presents different case studies, reflecting a whole range of rail investments, which have allowed the improvement of the RAILPAG Guidelines and can now be used to illustrate their practicality:
D
Page 86 92 98 100 102 104 110 116 124 126
Case Study 1 Line upgrading Case Study 2 Line renewal Case Study 3 Bottleneck removal Case Study 4 Interoperabillity Case Study 5 Line electrification Case Study 6 Level crossing elimination Case Study 7 Link to terminal Case Study 8 Rail terminal development Case Study 9 Line closure Case Study 10 Construction of a new high-speed rail line
The spreadsheets, which may be updated in the future, can be download from the webside (www. railpag.com). Some other case studies will be added through the RAILPAG website to this first selection, notably with the contribution of sector professionals All spreadsheets contain the corresponding SE Matrix for illustration purposes. In simple cases a discussion on re-distribution impacts should be sufficient to complete the appraisal.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
83
Line upgrading
2.
Technical characteristics of current situation The distance between A and B by rail is at present 200 km, and the time of travel is 2 hours; the railway is only used by passengers. The two places are also connected by road, with travellers making on average 230 km door-todoor. There is no congestion on the road in the do-minimum situation.
3.
Project description The investment provides new sections (some of them including tunnels) where the old layout was poor and increases the radius of some curves. It reduces the distance between A and B to 180 km by railway and results in a travel time saving of 30 minutes.
4.
Demand A comprehensive forecasting model, covering mainly road and rail, has been used. Before the investment, on an average day, there are 2000 rail journeys and 4000 journeys by car between the two towns. The composition of types of journeys is the same on both modes, viz. 75% private and 25% business trips. The occupancy of a car is 1.7 persons, on average. If the project is carried out, then there will be 700 additional journeys by train, of which 400 will be diverted from car transport and 300 will be genuinely new traffic. Demand is expected to have a modest growth during the first 10 years and remain constant thereafter.
5.
Costs Investment The investment is costed at 250 million exclusive of VAT. The investment, to be made full in year zero, will have a 40 year life span and a residual value of 50%. In the do-minimum situation there is a need for reinvestment, mostly in track renewal and electrification in order to allow the current level of service to be retained, estimated at 50 million , excl. of VAT. It is also expected to have a life of 40 years, with a residual value of 20%. Maintenance and operation Maintenance cost of the track is assumed to be determined by a fixed amount (11000 per km/ year) plus a variable amount related to train production (0.25 /train x km). Maintenance costs are reduced in the project on account of the reduced distance.
84
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Train operating costs are also reduced on account of reduced distance, but there are more trains, due to increased patronage. Additional traffic involves some additional costs (sales, etc.) per passenger, estimated at 0.2 /pass. Track charges Revenues from track charges (3 /train x km) are paid to the rail manager. The increase in the number of trains outweighs the reduction in distance, so the rail manager will receive additional (even if very modest) income.
6.
Benefits The method used identifies and measures all the changes in consumers and producers surpluses that the project gives rise to. In addition, effects on the fiscal balance of the government are taken into account and valued and external effects are also measured and valued. User benefits The benefits for the existing traffic are, in this case, assumed to be due entirely to time savings, with no improvements in comfort, reliability or other service characteristics. The train fare for the journey is assumed to be the same with and without the project, so the financial cash flow between the existing rail users and the operator is not modified. There is diverted traffic from road to rail due to the perceived reduction in generalised costs. The benefit for society from diverted users is measured as the difference between the resource costs of their travel by road (time, operating costs and accidents) and the cost of rail transport (time, accidents and the cost of producing the rail trip, which is included in the operating costs of the rail line) plus the differences in externalities. In this case, the potential costs or benefits related to different quality of service between road and rail, such as comfort, reliability, etc. are not included. The value of the change in the surplus for generated traffic, for which the minimum willingness to pay for the trip was not known, is measured from the surplus of existing traffic with the rule of the half. External effects The CBA should take full account of the external effects produced by the project due to changes in modal split and generated traffic. The external effects include, in this case, not internalised (insurance-covered) accident costs, noise and gas pollution and global warming effects. The project is assumed not to have any additional external effects such as railway accidents, as their frequency is negligible. The reduction in train x km due to the shorter distance and same number of trains/day, will have positive impacts on emissions as a consequence of less energy consumption. Positive external effects (reduction of emissions and non-covered accident costs) due to reduced number of car trips are included. The negative impacts are due to the construction works and the occupation of land for the new layout. These are relatively minor and mitigated by the measures required by the EIA and included in the project investment cost.
7.
Results of Economic analysis The project shows a reasonable economic rate of return, at 5.8%, which could justify the investment. As most benefits are due to time-savings, the profitability of the project is most sensitive to the value of travel time. The suitability of the value adopted (for instance, with good information on the purpose of travel) must be ensured. The robustness of the investment cost estimate is also critical to ensure the feasibility of the project.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
85
Line upgrading
8.
Results of Stakeholder analysis The case demonstrates that rail improvement projects could have a very negative impact on rail managers if they charge operators purely on train x km. The reduction in distance finally represents a reduction in revenue for the infrastructure manager. The rail operator is also making a loss on the project in spite of a major improvement of the service, increase in users and reduced travel distance. This is an indication of excessively low fares (which have been assumed to remain constant, although in the traditional fare calculation system based on distance it could even be reduced in spite of providing better service) or high operating costs. Essentially, in this case, rail users are the main beneficiaries of the project, along with some external effects that would benefit those suffering from road traffic and the population at large (greenhouse effect). On the other hand it will create some nuisances for those living close to the railway and also affect the landscape. The impacts on the national government are very modest if its allocations to the rail manager are not included.
9.
Comments The case could be further refined taking into account a more complex demand situation and more complex funding schemes, but it is useful to indicate that, to balance the stakeholders impacts, there is a need to have a relatively flexible (and complex) fare and track charges policy.
86
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s
A n n e x e s
ECONOMIC EVALUATION NPV INVESTMENT & MAINTENANCE; m Rail infrastructure Project cost to Rail manager Investment; project economic cost VAT revenue to National govt Residual value; project (50% end of period) Cost to Rail manager; do-min Investment; do-min; economic cost VAT revenue to National Govt Residual value; do-min Net investment: financial cost to Rail manager Net investment cost (econ) Net VAT revenue to National government Net residual value Maintenance cost to Rail manager Total financial cost Total economic cost BENEFITS; thousand Users Train users Existing traffic Travel time savings Diverted traffic from cars Reduction in car operating costs Travel time savings Safety improvements Additional revenue for train operator Reduction in petrol taxes Generated traffic User benefit Additional revenue for train operator Additional VAT Service providers Train operator Additional operating costs Impact on revenues Track charges Externalities Reduction in emissions (cars) Total economic benefits Economic benefits-costs 289.16 127.62 ERR = 5.8% 0.00 -200.00 9.67 9.82 9.95 10.10 17.15 132.28 Rate 3.00% Year 1
40
290.0 250.0 40.0 38.3 58.0 50.0 8.0 3.1 232.0 200.0 32.0 35.3 -3.2 193.5 161.5
290.0 250.0 40.0 0.0 58.0 50.0 8.0 0.0 232.0 200.0 32.0 0.0 0.0 232.0 200.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -0.15 -0.2 -0.2
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 -0.15 -0.2 -0.2
0.0 0.0 0.0 125.0 0.0 0.0 0.0 10.0 0.0 0.0 0.0 115.0 -0.13 -115.1 -115.1
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
87
Line upgrading
Supporting information for economic evaluation Costs Indirect tax factor Residual value after 40 years Maintenace cost per km; thousand /year Marginal maintenace cost per train x km Share financed by rail manager Track charges per train x km Demand Rail users before Rail users after Net rail traffic gain Transferred from cars Generated traffic Production Trains per year before Trains per year after Distance present, km Distance after; km Train-km before; million Train-km after; million Consumers surplus data Distance for road to train passengers Travel time savings for existing rail users Travel time savings for road to train travellers Value of travel time; commuter Value of travel time; business Value of travel time; leisure Average value of time Growth in VOT pa Car occupancy Reduction in accident costs Operating costs Costs per additional users (sales, etc.); million Train operating cost; per train x km Investment in train sets; annuity; 000 Operating costs car per pass x km Fuel taxes
2% growth 10 years
6570 7300
6570 7300
7300 8395
1.31 1.46
1.31 1.46
1.46 1.68
14.24
28.05
0.05
0.05
0.06
88
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Rail users
Generated traffic
Rail oper.
Rail manager
National gvt
ECONOMIC VALUE
RA I LPAG
Travel time
190.8
Safety
OPERATION Track charges 13.7 82.2 -115.5 -57.4 23.3 -8.9 -55.6 113.0 -14.4 -13.7
Fares
Residual value
Taxes
Infrastructure maintenance
Air pollution
Climatic change 100.1 15.1 11.2 -207.2 17.6 127.6 ERR = 5.8%
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ECONOMIC PROFITABILITY
190.8
89
Line renewal
2.
Technical characteristics of current situation Track on parts of the line between A and B is more than thirty years old, and traffic is very dense. In the absence of investments, it would be necessary to scale up maintenance significantly, yet it would still be necessary to impose speed restrictions on parts of the line in the near future and these sections would gradually grow in number and length, and would likely have significant cost and revenue implications for rail operations; The track on the B to C section is approaching 30 years, and unless investments are made sometime in the future, maintenance costs would increase significantly and it would be necessary to impose speed restrictions on sections of the line, and these sections would gradually grow in number and length.
The do-minimum case represents, in principle, the minimum investments required to keep the A-B and B-C sections of the line open to traffic at current speeds and capacity. They include some major maintenance works.
3.
Project description The project comprises the upgrading of the permanent way of the 187 km double-track section A to B (including 11.5 km of new alignment) and of the 159 km single-track section B to C, allowing an overall speed increase from 140 km/h to 160 km/h and even to 200 km/h on some parts of the line. The capacity of the single track section is estimated at about 80 trains/day and of the double track section at about 200 trains/day. In the project situation, it is assumed that high-speed train services, requiring adapted rolling stock, will be introduced.
4.
Demand Passengers The data in Table 1 reflect million single trips. Year 1 is the first year of investment, and the new services will be introduced in year 8. Table 1: Passenger forecast; million trips per annum Year A-B; project case A-B; do-minimum case B-C; project case B-C; do-minimum case 2 7.6 7.6 2.1 2.1 6 7.9 7.9 2.2 2.2 7 7.9 7.9 2.2 2.2 8 9.1 7.9 2.7 2.2 16 10.1 7.9 3.0 2.2 37 13.4 7.9 4.0 2.2
1 Whilst the data used in this example are assumed to be reasonable, they should not be applied to a real situation, for which the analyst should obtain relevant data.
90
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
The forecast of passengers travelling with high-speed trains are set out in Table 2. Table 2: Forecast of traffic on high-speed trains; million trips per annum Year A-B B-C 8 2.20 0.57 16 2.45 0.65 37 3.27 0.90
Train plan and train production Based on these demand forecasts, as well as the capacity of the trains, the train plan in Table 3 is assumed to apply: It reflects an average load factor of 80%. The average distance travelled by high-speed passengers is estimated to be 170 km on the A-B line and 150 km on the B-C line. An average trip with a long distance train is 135 km between A and B and 150 km between B and C. The capacity of a high-speed train is 280 passengers, while a long-distance train with 5 passenger cars can accommodate 450 passengers. Trips on the A-B and B-C lines may be part of the same journey. Table 3: Future train plans and train production Year A-B Project LD HS Total A-B Do-min. B-C Project LD LD HS Total B-C Do-min. LD 27 27 54 41 16 7 23 16 0.93 0.41 1.34 0.93 451 138 589 451 8 1.84 1.84 3.68 896 625 1521 30 30 60 41 18 8 26 16 16 2.05 2.05 4.10 2.80 1.04 0.46 1.50 0.93 995 694 1689 1360 508 157 665 451 40 40 80 41 24 11 35 16 37 2.73 2.73 5.46 2.80 1.39 0.64 2.03 0.93 1327 925 2252 1360 677 216 893 451 Trains M km M g.t.km Trains M km M g.t.km Trains M km M g.t.km
5.
Costs Investments Infrastructure The investment expenditures in infrastructure in the two alternatives during years 1 to 8 are set out in the cost-benefit table. The investments are assumed to have a residual value of 10% after the end of the entire project period, assumed to be 38 years, 8 of investment and 30 years of operation. Some investments are made also in year 8, i.e. during the first year of the new services. Rolling stock A high-speed train costs about 12.2 million and a complete 5-wagon long-distance train costs about 8.7 million. The initial locomotives and rolling stock investment, and its replacement, are introduced in the CBA as annuities calculated by assuming an 8% real rate of interest and a 25 year technical life. This method is adopted in view of the fact that the trains on the lines A-B and B-C are part of a large fleet of trains used in the whole rail network. Maintenance and operating costs These costs reflect only additional routine maintenance of the rails and catenary, as the other routine maintenance costs are assumed to remain at a similar level and major maintenance needed in the do-minimum alternative are included in the investment. In the project case incremental costs for the additional traffic have been calculated on the basis that each gross tonne-km gives rise to additional maintenance cost at 0.002.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
91
Line renewal
Train maintenance and operating costs The operating costs (personnel, energy and maintenance) are reflected in Table 4. Table 4: Assumptions used to calculate train costs Capital cost million per train and year LD HS 0.51 0.78 Operating cost /km 5.74 6.26 Utilisation of a train average km per day 400 700
6.
Benefits The economic analysis is a conventional one. The change in the consumers surplus takes into account the improvement of the quality of service (speed, comfort and convenience). The rule of the half has been applied, in this case, both to generated and diverted traffic (assumed to be 60% and 40% of the new traffic). The utility of the project for diverted traffic is estimated as the fare plus half of the time savings to existing rail users (the estimated surplus). This approach is used due to the lack of precise information on the trips (and their cost) of those changing modes, so the rule represents an acceptable proxy for the real economic benefits (the fare is a proxy for the foregone car operating costs). The reduction in fuel taxes from diverted cars (note that there is no effect on freight traffic) is (roughly) estimated from the number of diverted pass x km. The rail manager is paying value added taxes to the National Government. The rail operator is assumed to pay track charges to the rail manager. To be noted is that rail users pay a surcharge for using the high-speed train services. This charge must be inferior to the value of saved time plus the additional comfort and convenience offered by the high-speed services. Also to be noted is that the effects to remaining road users of traffic diverted from road to rail are not reflected in the analysis. This reflects the assumption that, at present, there is no congestion on the roads. The project produces some positive external effects due to the diversion of car traffic to rail, mitigated by some additional costs incurred by rail in the form of additional emissions and accidents due to additional traffic and higher speeds. Time savings The following country specific values of time are used: Business: Commuting: Leisure: 22 /h 9 /h 5 /h
When calculating the value of time savings, adjustment has been made to consider expected future growth in real incomes. The values of time are assumed to increase by 1.5% p.a. during the period years 1 to 8 and by 1.0% p.a. between years 9 and 37. On the A-B line it is estimated that about 25% of the trips are on business, 25 % is in commuting, and 50% on leisure. The total demand on the B-C line is composed of 15% business trips, 25% commuter trips and 60% leisure trips. When calculating the value of time savings for the A-B line, the average time saving is assumed to be 18 minutes. For the B-C line the average time saving has been estimated at 15 minutes. The same assumptions apply to generated and diverted traffic. Revenues The average revenue per km in long-distance traffic is assumed to be 0.07. It is expected that a surcharge of about 15% will be imposed on passengers travelling by high-speed trains. It is further assumed that the surcharge on the A-B and B-C lines will generate 0.013 per passenger-km, and that this additional charge will be implemented in a way - and through market segmentation - that it has marginal effect on the demand for travel (and therefore can be ignored for the purposes of economic analysis).
92
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Track charges It is assumed that the rail operator has to pay a 0,003 non-taxed charge per gross tonne-km to the rail manager for use of the track. Accidents and emissions In the project case, additional economic costs will be incurred by the additional train traffic in the form of accidents and emissions, of the order of 0.17 per train-km for accidents and 0.0004 per gross tonne-km for emissions. The additional rail accidents will be borne by the rail operator (as its insurance premium is related to its train x km). The external component of reduced road accidents are estimated from pass x km of diverted traffic (the internal component is included in the consumer surplus).
7.
Results of Economic analysis The project shows a modest rate of return, close to 5%, that would require in depth analysis of the various parameters, notably through sensitivity analysis, to ensure that the project is economically feasible. Considered discount rate was 5%.
8.
Results of Stakeholder analysis The main beneficiaries are the rail passengers and the rail operator. The rail manager incurs losses about equal to the net investments that must be made. The track charges just cover the variable maintenance costs for the line.
9.
Comments This investment is highly dependent on the following: the investment required in the do-minimum alternative increase in demand on account of the improved services the values of time used. There is hence a special need to ensure that the technical definition of the project is the most suitable (analysing other renewal possibilities), and also that forecasts and values of time are reasonable.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
93
94
Rate 5% 2 378 322 56 0 234 199 35 0 144 123 21 0 0 144 123 185 158 216 184 261 222 150 128 176 150 125 107 -29 -24 -29 -24 -28 -24 -27 -23 -99 -95 485 413 72 0 299 255 44 0 185 158 27 0 0 512 436 76 0 296 252 44 0 216 184 32 0 0 521 444 77 0 261 222 39 0 261 222 39 0 0 380 324 56 0 230 196 34 0 150 128 22 0 0 329 280 49 0 153 130 23 0 176 150 26 0 0 154 131 23 0 29 25 4 0 124 106 18 0 1 0 0 0 0 29 25 4 0 -29 -25 -4 0 1 0 0 0 0 29 25 4 0 -29 -25 -4 0 1 0 0 0 0 29 25 4 0 -29 -25 -4 0 1 0 0 0 0 29 25 4 0 -29 -25 -4 0 2 0 0 0 217 29 25 4 144 -29 -25 -4 73 3 3 4 5 6 7 8 9 10 20 30 38 348 296 52 0 176 150 26 0 172 146 25 0 0 172 146
Year 1
RA I LPAG
INVESTMENT & MAINTENANCE; m Rail infrastructure Project cost to Rail manager Investment; project economic cost VAT revenue to National govt Residual value; project (10% end of period) Cost to Rail manager; do-min Investment; do-min; economic cost VAT revenue to National Govt Residual value; do-min Net investment: financial cost to Rail manager Net investment cost (econ) Net VAT revenue to National government Net residual value Maintenance cost to Rail manager 2544 2167 377 34 1691 1441 251 23 853 726 126 11 13 854 728
400 190 23 160 46 327 240 42 3 78 14 256 1 478 20 20 3 23 700 -27 0 -146 0 -123 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -158 0 0 0 0 0 0 0 0 -184 0 0 0 0 0 0 0 0 -222 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -128 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -150
32 8 1 7 2 13 10 2 0 6 1 13 0 23 1 1 0 1 41 -65
33 8 1 7 2 15 11 2 0 6 1 14 0 24 1 1 0 1 43 67
33 9 1 8 2 16 12 2 0 6 1 15 0 26 1 1 0 1 45 69
36 17 2 15 4 30 22 4 0 7 1 23 0 44 2 2 0 2 64 87
40 27 3 22 6 46 33 6 0 8 1 33 0 64 3 3 0 3 86 109
43 36 4 29 8 61 44 8 0 9 2 42 0 82 4 4 1 4 106 201
Line renewal
BENEFITS; million Users Train users Existing traffic Travel time savings Diverted traffic from cars Utility (surplus + fare) Safety improvements (external) Additional revenue for train operator Reduction in petrol taxes Generated traffic User benefit Additional revenue for train operator Additional VAT Additional accidents costs rail users Incremental revenues; high-speed trains Additional VAT Service providers Train operator Additional operating costs Add. accident costs borne by rail operator Impact on revenues Track charges External effects (positive) External effects rail; emissions External effects road; reduced emissions
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ERR = 4.8%
Rail users
Generated traffic
Rail oper.
Rail manager
National gvt
ECONOMIC VALUE
RA I LPAG
Travel time
400.2
Safety
-2.9
OPERATION Track charges -19.6 -255.6 -159.9 45.7 -41.7 9.6 -239.8 477.7 19.6
Fares
-78.1
Taxes
-13.6
Residual value
Taxes
Infrastructure maintenance
Emissions
ECONOMIC PROFITABILITY
305.7
98.6
45.2
201.6
-834.6
20.2
136.0
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
95
Bottleneck removal
2.
Technical characteristics of current situation When forecasting traffic consecutive to the removal of a bottleneck, it is important to consider the capacity constraints on the rest of the network. The growth of traffic on the section selected for appraisal may be constrained by capacity on distant points of the network in a way which is not apparent in the existing situation. Often, several bottlenecks must be removed at the same time or in rapid sequence to achieve the desired traffic growth. The project analyst must make sure that the next most critical bottleneck has been identified and does not prevent the envisaged traffic growth.
3.
Project description A bottleneck will typically be associated with congestion. Small deviations to train plans (train delays) will result in the need to readjust train schedules significantly. A removal of the bottleneck will hence often have significant repercussions on reliability. The improvement in reliability will affect the costs of the rail operators, and these savings could be significant but difficult to trace and measure. Improvement in reliability will also lead to shorter travel times and so to an improvement in the welfare of travellers over and above average time savings. These improvements will have to be valued separately and accounted for in the analysis, otherwise the real benefits of the project will not be covered. On the other hand attention must be paid not to double-count time savings under the reliability label.
4.
Demand The removal of serious capacity constraints may allow for the introduction of new strategies to serve the market on the part of rail operators. The investments may e.g. allow the introduction of new rail services which are better integrated from both an operating and the travellers point of view. There is therefore a need to consider new approaches to the supply of rail services and to evaluate their impact on costs, as well as their impact on demand and on user benefits.
5.
Costs Investments in the removal of a clearly identified single bottleneck can often be expected to yield high economic returns, but also to be financially beneficial for the train operators. Financial profitability could be more elusive for the infrastructure manager unless specific track access charges can be considered.
96
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
97
Interoperability
2.
Technical characteristics of current situation Operation benefits: Interoperability will allow for reduced costs of locomotives and rolling stock, which could benefit from standardisation and scale economies (see point 5). In addition, in many cases, the rotation of trains may be shortened allowing for reduced investments in train sets as well as reduced operating costs.
3.
Project description Network effects (non quantified): Some of the effects of an interoperability project could not be translated into specific elements within the project boundaries, as they are diffuse and may occur in parts of the network located far from the geographical location of the project itself. It could also affect overhead costs of the companies. Indeed, these aspects are those that have justified the EU interoperability regulations, which often require additional investments that are included in the CBA. Not taking into account all the benefits of these additional costs would bias the appraisal. It is therefore recommended to include them, even if, at this stage, it can only be in a qualitative way, in the SE matrix. There is a specific line for this and, lacking data, a colour code could be used. If this is a major qualitative impact of the project, the amount of benefits needed to reach a desirable rate of return could be used to appraise if they are reasonable.
4.
Demand If interoperability is introduced on a larger scale, and involving several countries, it may be necessary to evaluate the impact of reduced travel times by way of an econometric demand model to properly account for the impact on competing modes of transport and to take into account network effects.
98
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
5.
Costs Fewer standards will strengthen competition between suppliers of rolling stock as well as train control equipment. Also, manufacturers will be able to produce longer series and thereby achieve cost reductions through economies of scale. These benefits are very difficult to capture, but cautious assumptions about possible cost reductions over time may be employed as a possible measure of these benefits.
6.
Benefits A new train control system will likely also show higher performance than the existing one, in effect allowing for a higher capacity on the lines where it is installed. The higher capacity is a benefit, which has to be evaluated although this may be difficult. The marginal cost of expanding the capacity of the system could possibly be used as a measure. To obtain a proxy of this cost it will be necessary to calculate the average incremental cost, i.e. what it would cost to expand the capacity of the existing line with conventional technology, e.g. by adding a track, and then divide by the number of train services this would allow for as a maximum.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
99
Line electrication
2.
Technical characteristics of current situation Electrification does not preclude the operation of some diesel traction on certain sections of electrified lines, which certain operators may prefer for some rail services if the cost of changing traction is not justified by operating cost savings for some short distance services.
3.
Project description If the conversion to electrification is on a large scale, and involving a large part of the network it may be necessary to evaluate the impact of reduced travel times by way of an econometric demand model to properly account for the impact on competing modes of transport.
4.
Demand Electrification will result in lower emissions of noise and air pollutants It is to be noted, however, that modern diesel electric trains are becoming much cleaner and more silent than older ones, which will have to be taken into account. Furthermore, the analyst should consider not only gross emissions but their actual impact. While the impacts on global warming do not depend on the location of the emission source, local and regional impacts obviously do.
5.
Costs Electrification may allow for the introduction of a different type of train, e.g. comprising a complete train set, which may be better suited to demand. As a consequence, additional time and operating cost savings may be achieved.
6.
Benefits Electrification can be a source of productivity for operators when it is justified by sufficient traffic flows on significant portions of networks. In financial terms, the outcome for operators and infrastructure manager will depend on the arrangements for the purchase of track access and energy and the actual level of the related charges.
100
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
101
2.
Technical characteristics of current situation Level crossing between a 2 lane country road and a single track rail line protected by centrally controlled automatic barriers that are closed for 2 minutes for every train passage. It requires a speed reduction of the trains (time loss of 0.2 minutes) and implies an average time loss of 1 minute for stopped road traffic. Road vehicles also suffer from the crossing in terms of comfort and additional operating costs (fuel spent 0.08 litres per stopped vehicle and some damage due to braking, vibrations, etc. that has not been considered). In the do-minimum scenario this situation will continue.
3.
Project description Construction of a bridge over the rail line, which represents the least cost solution for separating road from rail traffic.
4.
Demand Road traffic: ADT: 400 cars and 100 trucks. 75% of traffic during 12 peak hours. No pedestrians or buses. Rail traffic: 20 trains/day (80% passenger and 20% freight); 90% during 12 peak hours. Traffic growth (per year): Trains 1%; cars 3%; trucks 4%. Hypothesis: Demand is not affected by the project.
5.
Costs Investments The total estimated cost of the proposed new bridge is 150 000 . It will be built during the first year of the project life and will be paid by the infrastructure manager (40%) and the regional government (60%), as the project will be of benefit to both road and rail users/operators. The project is assumed to have a residual value of 40% of its original asset cost after 20 years 2.
1 Whilst the data used in this example are assumed to be reasonable, they should not be applied to a real situation, for which the analyst should obtain relevant data. 2 See discussion on residual values in the main text.
102
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Maintenance and operating costs In the do-minimum scenario: Barriers are assumed to require some manning from the control centre and specific attention from staff, assumed to be 20% of a full-time job for the infrastructure manager valued at 10000 /year1. They also involve power consumption and specialised maintenance (including communication system). Rail track in crossings also need special maintenance. All this has been assumed to have a cost of 1000 /year. In the project scenario: All do-minimum maintenance and operating costs are eliminated, but the road administration will face some additional maintenance costs (assumed to be approx. 2% of investment cost: 3000 /year).
6.
Benefits In addition to the elimination of operating costs for the barriers and specific costs of level crossing maintenance, the benefits are due to: a) time savings from vehicles not being stopped (value of time: 12/h car and 20 /h truck) and increased speed of trains (this represents a time saving that has been valued at 3 / hour per passenger; it is assumed that a passenger train has 100 passengers on average). b) reduced operating costs of stopped vehicles (no impact on trains considered) 2. c) improved comfort for all road users (0.02 /vehicle) d) increased safety both for road and rail users, the value of which has been calculated based on the following assumptions: Probability of death/ severed injured/ slightly injured in level crossings Cost of fatal accident/severely injured/slightly injured Accidents Estimated average cost borne by insurance companies 50% of average cost per road accident 100% of costs to train operators 10% of average cost per road accident 5.1510-7/6.5010-7/1510-7 accident/vehicles / day
1 Whilst the data used in this example are assumed to be reasonable, they should not be applied to a real situation, for which the analyst should obtain relevant data. 2 See discussion on residual values in the main text.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
103
7.
Results of the Economic analysis The cost/benefit analysis carried out is synthesised in the annexed table. Costs are essentially due to investment and maintenance. The values in the economic analysis table reflect the NPV (at 5% discount rate) of the flows associated with the various items considered in the cost/benefit analysis. It can be seen that economic benefits come mostly from travel time savings and safety improvement, although other components are also relevant, mostly operating costs. Non-quantified benefits (improved reliability and environmental externalities) are all positive. A sensitivity analysis shows that increasing the train users value of time for marginal savings could have quite an impact. Doubling the value time for rail passengers (to 6/h), would make them the main beneficiaries and total profitability would rise above 17%. In certain projects like this one, with small impacts on train schedules, it would be wise to analyse carefully both the real time improvements of the service and the value that could be placed on time savings. It is important to carefully evaluate accident risks and the value to be placed on reduced number of accidents.
8.
Results of Stakeholder analysis The values in the Stakeholder row are relevant to show who benefits the most from the project and who pays. In this case the regional government is taking most of the burden whilst the national government is obtaining some net gain through tax revenues. Insurance companies appear as major beneficiaries of the project (free riders). The table shows how some of the economic cost and benefits can only be partially reflected in financial cash flows. For some stakeholders, however, the benefits (i.e. travel time savings) are not reflected in financial cash flows. The measure of stakeholder impact on the rail manager and rail operator in the bottom row reflect the financial impact on the rail businesses, independently of any subsidies (i.e. as if no regional subsidies were received, in this case) or expenditure by other stakeholders (for instance, for road maintenance). In this case a strong negative value indicates that subsidies are necessary to avoid that the economic benefits of the project imply a financial loss for the rail system. It is also interesting to observe that, in the case of safety, the project will produce savings for the insurance company, which is assumed to keep the same level of income from road users and rail operators with the project. Road users will not benefit from the compensations insurance companies would have to pay without the project due to accidents (negative cash flow for users) but will benefit from the economic value of accident reductions, which is assumed to be, in this case, twice the amount of the insurance compensations. For the rail operator and users (no severe injuries are assumed for them) it is assumed that insurance will cover the whole amount of damage, established at 10% of road economic costs. A similar procedure has been applied for taxes, which have certainly a financial impact on stakeholders.
9.
Comments The analysis indicates a reasonable project, at 13% economic rate of return, with benefits distributed among users, essentially paid by a public authority (the regional government) and an important free rider, the insurance companies, that could be requested to contribute to finance level crossing elimination.
104
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ECONOMIC EVALUATION NPV COSTS Investment cost (fin.) Rail manager contribution Taxes paid by rail manager Regional authority Taxes paid by regional auth. Investment; project economic cost Taxes Residual value Maintenance road Total nancial cost Total economic cost BENEFITS Value of time savings VTS cars VTS trucks VTS train users Comfort improvement Safety improvements cars Operating costs saved Operating costs saved cars value Taxes saved cars Operating costs saved trucks value Taxes saved trucks Op. costs rail infrastructure Central operation Op & maint (barrier & rail) Safety rail (50/50 users & operator) Financial benets rail sector Economic benets Financial benets-costs Economic benets-costs Rate 3.00% Year 0 181500 66000 6600 99000 9900 165000 16500 0 0 181500 165000
1 0
2 0
3 0
20 0
181500 66000 6600 99000 9900 165000 16500 36543 53559 144957.4 182016.3
0 0 0 3600 0 3600
0 0 0 3600 0 3600
0 0 0 3600 0 3600
125202 20313 10157 94733 71193 125211 6446 2763 3683 691 921 47054 32176 14877 12521 47054 384634 -97904 202618 ERR = 11.7%
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -181500 -165000
7375 984 492 5898 3760 6068 312 134 179 33 45 3000 2000 1000 607 3000 20977 3000 17377
7494 1024 512 5957 3872 6313 325 139 186 35 46 3020 2020 1000 631 3020 21504 3020 17904
7391 1034 517 5840 3988 6374 328 141 188 35 47 3040 2040 1000 637 3040 21607 3040 18007
10062 2005 1002 7055 6400 12357 636 273 364 68 91 3392 2392 1000 1236 3392 33788 69392 96188
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
105
20
20
24
400 100
412 103
424 106
437 109
701 175
4% trains trains 16.18 16.83 17.00 4.05 4.21 4.25 0.27 0.28 0.28 0.07 0.07 0.07 5.39 5.44 5.33
10 20 3 2 0.2
min min
Time saving 1 min due to speed restriction on rail crossing (no benefits included for rail operation)
Operating cost of veh. stopped 0.02 Fuel taxes per veh. stopped 0.03 Consumption of veh. stopped 0.08 Fuel cost 0.3 Taxes 0.4 Comfort improvement 0.02 Accident rates and values Acc/IMD*Tr/day Fatal 0.000000515 Injury 0.00000065 Slight inj. 1.50E-06 Number of accidents involving trains 1.00E-07 Assume part of train accidents/road Assume part operator cost covered insurance Assume part user cost covered insurance Operating staff Financing: regional authority subsidy Taxes on construction (national) 0.2
Per car*train (train) 0.05833 10% suffered by users and operator 50% 100% employeesassuming one addit. operator of control centre per 5 crossings 60% 10%
106
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
Rail users Road freight Insurance Local gvt Regional gvt National gvt Rail oper. Rail manager Local non user
Road pax
ECONOMIC VALUE
Travel time
94733
20313
Reliability
Comfort
71193
Safety
Financial
-3130
-62605
Economic
6261
125211
2763
Operating personnel
Taxes (fuel)
3683
ASSETS -66000 36543 -6600 14877 -9900 -53559 16500 -99000 -165000 36543 0 -38681
Infrastructure
Residual value
Taxes
Infrastructure maintenance
Air pollution
Climatic change 11768 0 71996 10996 -162459 11896 202618 ERR = 11.7 %
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
FINANCIAL PROFITABILITY
97863
160557
107
Link to terminal
2.
Technical characteristics of current situation The airport is 65 km away from the centre of A and 80 km from B. Without the project, the majority of the travellers, including employees at the airport, would make use of bus services. Taxis and cars are also used for accessing the airport. In the do-minimum situation, road transport is assumed to expand to accommodate increasing demand over time without additional investment. Should roads be expanded, it is assumed to be mostly due to non-airport traffic, so a conservative approach (no positive impact on the road traffic) is assumed.
3.
Project description The project involves a dual rail track linking up the airport with a main existing railway line running to A. After passing under the airport, the railway links up again with the existing railway line towards B (80 km from the airport), creating a detour of 15 km for through long-distance - trains on the main railway line. This existing line will be partly upgraded in order to allow for the new high-speed services to the airport and a part of the central station in A will be upgraded to allow for dedicated platforms for the high-speed train services to the airport, paid for by the public rail manager. The project further envisages that the airport train services will be exclusively provided by a 60-year rail concessionaire, on a BOT basis. The concessionaire will invest in all the dedicated facilities required by the airport services. The rail manager will only handle investments required for the through-train services, including one of the two links between the airport and the main railway line, i.e. the one that will be used only by long-distance services. Long-distance train operators will pay the same track charges. The bus service will be able to continue to provide transport in the project case in order to ensure competition, with the bus operators adapting their service to the new demand conditions.
4.
Demand The demand projections indicated that the airport would have 18.3 million passengers during the opening year of the new service, year 6 after an investment period of five years. This is expected to generate up to 6 million trips between A and the airport, of which the rail service would be able to catch 2,5 million during the first year of operation. The pricing policy proposed by the train operator meant that the bus service could continue retaining a substantial part of the market, alongside private car and taxi users. The total demand for travel is expected to increase by 1.5% every year. The growth of rail traffic should be higher, at about 2%. No generated traffic is envisaged, as traffic to the airport is assumed not to be dependent on the quality of its access. The project will have an impact on the modal choice of those travellers between the airport and B, but the effects of the old line improvement on through-train services is assumed to be negligible in terms of demand generation (conservative assumption).
108
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
5.
Costs
Investments Investments in the infrastructure to be paid for by the BOT operator are estimated at 585 million, exclusive of VAT. The BOT operator is assumed to have to reinvest 50 million (exc. VAT) for the years 25, 45 and at the end of the period in order to maintain the infrastructure in adequate condition and hand it over to the rail manager.The public investment in the new line is estimated at 86,5 million, to be paid for by the rail manager (plus three times 10 million along with the concessionaire). The initial investments are evenly spread over a period of 5 years; the appraisal period covers this period as well as a 60 year operation period. At the end of that period, the investments are assumed to have a 50% residual value. Maintenance and operating costs Maintenance costs of the track are assumed to be the responsibility of the rail manager, but will be partly paid for by the concessionaire through a fixed amount estimated at 1% of the investment cost. To provide the services, the BOT operator will initially require 7 train sets in total. Each set costs 7,2 million. These trains have a life of about 25 years. Additional trains are necessary to accommodate increasing demand. Thus, at the end of the concession period, the rail operator is assumed to have 16 train sets, representing a residual value of almost 16 million . Train operating costs consist of two components, one mainly determined by the number of train x km and the other by the number of passengers. During the first year of operation these costs are assumed to be 22.2 million . Subsidies In principle, no subsidies will be paid to the BOT operator.
6.
Benefits The calculated benefits focus on the effects for those who switch to the high-speed train service, and the change in the consumers surplus for these travellers, as well as the producers surplus of the high-speed service. The impacts on the remaining road traffic are ignored, although some congestion improvements could have been considered. User benefits and evaluation A simplified approach is used in order to determine the value of the user benefits. The base assumption is that in the absence of the rail service, those travelling between A and the airport would be going by bus, and essentially between the same two points. The train service, on average, implies a time saving of about 20 minutes, also taking into account frequencies of the rail and bus service. This time saving is the same for just about everyone travelling by rail. On the other hand, these travellers also face the payment of a fare about twice as high for rail than for bus, 13,3 to be compared with 6,7 . The train service additionally provides better reliability and a higher level of comfort than the bus service, since it is more spacious. For travellers between the airport and B, the time saved is 25 minutes, and the fares respectively 18 and 10 . Given the normal values of time applying to leisure travellers it is clear that they will not be attracted to the rail service. It will primarily attract those who travel on business, and then by air, and possibly some of those who travel to and from the airport for work purposes. at.The average value of time used for the traveller diverted to rail is 25 . All the switchers in addition gain in reliability and comfort equal to 1,2 per trip.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
109
Link to terminal
Producers surplus The producers surplus is measured in the traditional way, viz. gross revenues minus cost. There is a need to identify specifically the share of the revenues paid to the government in the form of VAT (6%). This issue requires a detailed financial analysis not carried out here. It is assumed that bus operators will adapt their supply to the new demand without noticeable loss. Externalities Externalities will have a negative component regarding the construction of the new line, that cannot be quantified. The positive impacts due to the reduction of emissions and noise of the reduced road traffic are included in the analysis.
7.
Results of Economic analysis The investment is economically sound and the ERR is robust. Values of time and train operating costs appear as important variables on the economic profitability of the project. Of course, the reliability of the investment estimates is also very relevant.
8.
Results of Stakeholder analysis The stakeholder analysis shows that although the government wishes to engage a BOT operator in order to reduce its investment in public infrastructure, the project could be implemented as proposed. Under the assumptions made, the BOT operator will not be making money. It would require higher volumes of traffic or some financial advantages (i.e. subsidies) to achieve breakeven. However, the risks faced by the BOT operator are fundamental since he is totally dependent on air traffic, which, in turn, is very much decided on by economic development in general. The BOT operator cannot protect himself against this kind of uncertainty; and for that reason he is likely to undertake an evaluation of the project at a much higher rate of discount than the one used in the economic analysis, i.e. 6%. Given the assumptions reflected in this example, the BOT operator would not participate in the project, unless able to recover a larger part of the consumers surplus, or by obtaining financial advantages such as reduced maintenance payments to the rail manager or direct subsidies.It is important to observe that the national government is obtaining financial benefits from the project (which are almost identical to the losses made by the rail manager). A detailed analysis of taxes, notably the real impact of VAT, would be needed to better assess the potential financial profitability for the rail concessionaire, but it appears obvious that, even though the project is economically profitable, the proposed BOT structure is not suitable.
9.
Comments Some factors that could improve the economic profitability of the project such as the effects of the through train rail services and the improved road traffic or its access to the airport, have not been considered. But, as they would only increase an already acceptable profitability, they are not particularly relevant in this case.
110
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
Rail infrastructure Cost to Rail manager Investment; project economic cost VAT revenue to National govt Residual value of total project (50% end of period) Cost to Rail operator (concessionnaire) Investment; project economic cost VAT revenue to National govt 94,63 75,71 18,93 14,08 661,22 528,98 132,24 741,77 590,60 151,17 16,04 12,83 3,21 108,46 86,76 21,69 82,04 65,10 16,28 0,66 948,31 754,63 192,34 117,00 29,25 146,25 146,25 117,00 29,25 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 182,29 145,83 36,46 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 182,29 145,83 36,46 146,25 117,00 29,25 146,25 117,00 29,25 182,29 145,83 36,46 182,29 145,83 36,46 182,29 145,83 36,46 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 182,29 145,83 36,46 0,00 0,00 0,00 1,08 0,87 0,22 7,31 5,85 1,46 63,00 50,40 12,60 0,00 71,39 57,12 14,28 0,00 0,00 0,00 0,00 146,25 117,00 29,25 0,00 0,00 0,00 0,00 146,25 117,00 29,25 36,04 28,83 7,21 0,00 146,25 117,00 29,25 36,04 28,83 7,21 0,00 146,25 117,00 29,25 36,04 28,83 7,21 0,00 146,25 117,00 29,25 0,00 0,00 0,00 0,00 0,00 0,00 0,00
12,50 10,00 2,50 335,75 62,50 50,00 12,50 -260,75 -275,75 15,00 1,08 0,87 0,22 7,31 5,85 1,46 15,84 0,00 0,00 15,84 -236,52 -284,88 16,68
Total investment: financial cost Total investment cost (econ) VAT revenue to National government
Maintenance cost to Rail manager Normal maintenance costs (economic) VAT revenue to National govt Maintenance cost to Rail operator (conc.) Normal maintenance costs (economic) VAT revenue to National govt Rolling stock Cost to Rail manager Investment; project economic cost VAT revenue to National govt Residual value of train sets
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
111
112
ECONOMIC EVALUATION
BENEFITS; million
RA I LPAG
138,32 -256,76 374,14 59,86 -70,73 118,10 13,61 -327,49 492,24 73,47 -349,57 80,57 244,70 81,57 91,35 1026,12 349,06 81,57 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 -4,0 5,5 0,6 -18,5 22,8 3,4 -9,0 1,6 6,3 2,1 2,4 47,3 19,7 2,1 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 -14,5 17,3 2,8
0,00
0,00
0,00
0,00
0,00
5,8
24,9 -26,1 56,1 9,0 -7,2 17,7 2,0 -33,3 73,8 11,0 -86,4 27,2 60,5 20,2 22,6 155,2 35,5 20,2
USER SERVICE Train users Existing long-distance traffic Travel time savings Diverted traffic from bus Airport-A Fare paym. difference Travel time saving Comfort & reliability Airport-B Fare paym. difference Travel time saving Comfort & reliability Total Fare paym. difference Travel time saving Comfort & reliability Diverted traffic from cars Fare Travel time saving Operating costs saving (excl. petrol taxes) Petrol taxes Safety improvements (external) Total Additional revenue for train operator Loss of revenue for bus operator Reduction in petrol taxes
Link to terminal
Service providers Long-distance train operator Reduction in operating costs Rail operator (concessionnaire) Operating costs Sales costs Bus operator reduction in operating costs 29,23 409,38 21,31 349,06 -17,66 -9,63 126,68 87,85 1255,50 500,87 ERR = 7.7% 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0 -117,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0 -117,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0 -145,83
0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0 -145,83
0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0 -145,83
2,0 21,2 1,0 19,7 -0,9 -0,5 5,4 3,2 48,8 -8,3
2,0 48,6 3,2 35,5 -2,1 -1,1 21,4 17,5 241,4 526,3
External effects External effects rail; emissions global External effects rail; emissions local External effects road; reduced emissions global External effects road; reduced emissions local
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Economic benets-costs
RA I LPAG
Existing Road to Bus to Rail rail users rail users rail users concess.. Local non user National gvt
Bus operatorr
Rail manager
ECONOMIC VALUE
USER SERVICE Travel time 492,2 91,4 73,5 73,5 0,0 0,0 -430,7 349,1 -327,5 1026,1 0,0 -349,1 -81,6 29,2 0,0 0,0 -401,5 349,1 244,7 0,0 0,0 0,0 -529,0 14,1 -153,9 -86,8 -65,1 0,7 -9,6 87,9 238,2 -238,7 29,2 0,0 -112,9 78,2 -17,7 126,7 109,0
Discount rate: 5 %
138,3
80,6
711,1
Safety
91,4
OPERATION
Track charges
244,7
Fares
0,0
-349,6
Petrol taxes
81,6
Infrastructure
-604,7 14,1 0,0 -99,6 -65,1 0,7 -27,3 214,5 110,8 500,9 ERR = 7.7 %
Residual value
Taxes
Infrastructure maintenance
Rolling stock
Residual value
Emissions rail
Construction impacts
Emissions road
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ECONOMIC PROFITABILITY
138,3
148,6
113
2.
Technical characteristics of current situation At present a double track runs through A, but there is no station. A is served by bus, with services from the town centre to stations in B and C, nearby towns served by the same rail line.
3.
Project description The establishment of a station, comprising two platforms, a footbridge to connect the two platforms, a terminal building and parking areas, which would allow all trains to stop in A. It is assumed that all ordinary passenger trains (approx. one train in each direction every hour from early morning to late evening) would stop. This would result in 12 400 trains stopping at A on an annual basis. The existing bus services to B and C would be discontinued. Travel time for bus travellers between A and B will be reduced by 20 minutes and for those between A and C by 10 minutes. For simplicity reasons an average 15 minutes has been adopted. Car users diverting to the train are making, on average, 60 km (as they go far in the line) and their travel time will be increased by 13 minutes.
4.
Demand The new station will result in the transfer of all previous 90 bus passengers per day to the train services. In addition, each weekday an additional 60 passengers to and from A will be deviated from cars (occupation ratio 1.3) and 20 trips will be generated by the rail service. To estimate annual traffic, weekday traffic has been multiplied by 325, for a total of 48750. The number of through passengers on the ordinary passenger services before the new terminal is constructed is estimated at 400 000/year. Because of a loss of 2 minutes for the stop, through passengers are assumed to be reduced by 8000 on an annual basis. These passengers, spread over the line, are expected to divert to cars (with an average travel time improvement of 12 minute, but a car trip of 40 km). Bus fares (A to B or C) are, on average, 2 per trip. Equivalent train fares will be, on average, 3 per trip. Traffic is assumed to grow by 2% per year during the first 10 years and stay constant thereafter.
5.
Costs Investments The investment is costed at 2,06 million , plus indirect tax at 17%. It will be paid for by the rail manager. The project can be completed during one year, and no additional investments will be required thereafter. The residual value after 50 years is assumed to 50% of the original investment, due to good maintenance. As rotation time will be increased by 2+2 minutes, and there is additional patronage in the line, it is assumed that one new train set is necessary and will be sufficient for the duration of the project. This train must be replaced after 30 years. The replacement will have a residual value of 20% in year 50. The investment on this train set and the differences of the operating costs due to longer rotations should cover all additional costs for the train operator. The cost for the operator of a new train, is 3.6 million plus VAT.
114
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Maintenance costs The rail manager is assumed to face a maintenance cost of the new station of some 11 000 per year. Additional costs for the rail operator are assumed to be covered by additional revenues from commercial revenues made at the station. The annual cost of a train set maintenance is estimated at 0.1 million per year. Train and bus operating costs Two minutes additional time will require more train operating staff and energy. The marginal timerelated costs of train operation are estimated at 100 per hour. The savings in the annual bus operating costs have been estimated at 110 000 , which are now borne by the regional government, which only covers 45500 of the costs with bus fares. The impact of VAT on changes in operations and on train and bus fares is considered to be negligible overall. There are no impacts on track charges to the rail manager.
6.
Benefits The method used identifies and measures all the changes in consumers and producers surpluses that the project gives rise to. In addition, effects on the fiscal balance of the national and regional governments are taken into account and valued. External effects are not quantified in this particular case. It is implicitly assumed that the additional diverted passengers, which at present make use of car do not face congestion on the roads. The benefits to generated passengers are estimated using the rule of the half. The benefits of the project for stakeholders in the transport sector come from changes in resource costs for trip production and from changes in travel time, other potential benefits (comfort, reliability, etc.) are not considered. User benefits The bus users switching to rail are expected to make a gain of 15 minutes, whilst the generated traffic to and from A is assumed to make, on average, a gain which is half as large. Through passengers lose on average two minutes because of the stop at the proposed new station. The 8000 passengers who stop making use of the train services because of this delay, are expected to divert to cars (40 km and reduction of 12 minutes compared to the present situation). It is assumed that existing rail and bus traffic comprises 40% commuters, 10 % business travellers and 50% leisure trips. Car users diverting to rail and rail users diverting to car have a different composition and a higher value of time These compositions will remain constant. The weighted average value of time for these types of users is 8.2 and 9.6 , in year 0; the value of time is assumed to grow by 1.8% annually. Resource operation costs of cars are assumed to be 0.2 /km. Fuel taxes are estimated at 0.4 /km. Operators benefits The rail operator obtains additional revenues from incoming traffic and losses from traffic diverting due to additional travel time. Besides investment and additional maintenance for the new train set, it will have some additional costs due to longer trips and to the additional traffic (sales, etc.). The bus service will be eliminated with all its operating costs and subsidies. The regional government will strongly benefit from this. Externalities The elimination of the bus services will have substantial impacts on urban pollution (air an noise). The net reduction of car traffic will also have positive impacts. The new station may become a catalyst for urban development. This might have a positive impact if well-planned and focused on the use of the new public transport facility.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
115
7.
Results of Economic analysis The economic evaluation shows that the proposal is poor from an economic point of view. It is very sensitive to the number of future users. The modest number of bus users indicates that there is a poor demand for public transport. It could be interesting to study if proper marketing of available rail services would improve rail traffic forecasts.
8.
Results of Stakeholder analysis The stakeholder analysis shows that only the regional government stands to gain from the proposal. In addition, some of the rail users are, of course, winners, but their improvement drowns in the losses made by the through passengers.
9.
Comments This case quite clearly shows the opposing forces that some investments will give rise to in the railway sector. The station is in the interests of those who travel to and from A, as well as the regional government. Also, on account of the financing arrangements, substantial costs are not easily seen, and only borne indirectly by the public, often at a later date.
116
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ECONOMIC EVALUATION NPV INVESTMENT & MAINTENANCE; thousand Rail infrastructure Project cost to Rail manager Investment; project; economic cost VAT revenue to National govt Residual value; project (50% end of period) Cost to Rail manager; do-min Investment; do-min; economic cost VAT revenue to National Govt Residual value; do-min Net investment: financial cost to Rail manager Net investment cost (econ) Net VAT revenue to National government Net residual value Maintenance cost to Rail manager Cost to Rail manager; maintenance VAT revenue to National govt Rolling Stock Project cost to Rail operator Train set investment cost VAT revenue to National Govt Residual value Maintenance Total nancial cost Total economic cost 2412.3 2060.0 352.3 235.0 0.0 0.0 0.0 0.0 2412.3 2060.0 352.3 235.0 331.4 283.0 48.4 2412.3 2060.0 352.3 0.0 0.0 0.0 0.0 0.0 2412.3 2060.0 352.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.9 11.0 1.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.9 11.0 1.9 0.0 0.0 0.0 1030.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1030.0 12.9 11.0 1.9 Rate 3.00% Year 1
30
50
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
117
ECONOMIC EVALUATION NPV BENEFITS; thousand Users Train users Existing traffic Travel time losses Diverted traffic from bus Travel time savings Loss of revenue for bus operator Additional revenue for train operator Reduction in petrol taxes Diverted traffic from cars Reduction in car operating costs Travel time losses Additional revenue for train operator Reduction in petrol taxes Generated traffic User benefit Additional revenue for train operator Diverted from train to road Additional car operating costs Travel time savings Loss of revenue for train operator Additional fuel taxes Service providers Train operator Additional operating costs Impact on revenues Bus operation Reduction of operating costs Reduction of revenues Reduction of regional subsidy Externalities Reduction in emissions (-buses+cars) Total economic benets Economic benets-costs 1674.6 -441.0 ERR = 1.7% 0.0 -2063.6 144.6 103.5 42.3 27.6 -12.0 1007.6 Rate 3.00% Year 1
30
50
4895.9 2767.5 1793.8 2690.7 257.3 4631.4 1585.6 3010.4 1204.2 162.6 501.7 1509.6 723.7 1226.5 392.5
109.9 62.1 58.5 87.8 10.0 180.0 42.9 117.0 46.8 3.4 19.5 49.2 16.2 40.0 12.8
229.3 129.6 72.7 109.1 10.0 180.0 72.0 117.0 46.8 7.9 19.5 61.2 33.9 49.7 15.9
327.6 185.2 72.7 109.1 10.0 180.0 102.8 117.0 46.8 12.7 19.5 61.2 48.4 49.7 15.9
118
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Supporting information for economic evaluation Costs Indirect tax factor Cost of tax funding factor VAT on investments and maintenance Investment in the project alternative; net VAT; thousand Investment in the do-min alternative; net VAT; thousand Residual value after 50 years Maintenace cost of station; thousand Share financed by rail manager Demand Through rail users before Through rail users after Net loss of through traffic Transferred from bus Transferred from cars New traffic generated by station Total traffic through the station Production Departures per year Consumers surplus data Distance for train to road passengers Distance for road to train passengers Travel time saving for bus travellers Travel time losses for through travellers Travel time gains for train to road travellers Travel time losses for road to train travellers Value of travel time; commuter Value of travel time; business Value of travel time; leisure Average value time bus&train Average value time diverting road-train Growth in VOT pa Operating costs Costs per additional user (sales, etc.) Operating cost; per hour Investment in train set; annuity; 000 Operating cost of busservice; net 000 Operating costs car per pass x km Fuel taxes Bus operation fuel taxes Bus fare Train fare station users Train fare through users Train fare car to train users
2% growth 10 years
12410
12410
12410
km km h h h h /h /h /h
0.5 Bus & train 40% 10% 50% 8.35 8.50 9.98 10.16
11.5
14.26 17.04
20.37 24.34
0.3 euro
15.73 17 15
15.73 17 15
2 3 5 6
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
119
120
Rail users
Rail operator
Bus operator
Rail manager
RA I LPAG
USER SERVICE Travel time 2767.5 162.6 723.7 -2990.2 162.6 0.0 -1509.6 -1449.9 2830.3 3121.8 1380.4 0.0 0.0 0.0 -2060.0 235.0 -352.3 -283.0 -48.4 -5.1 -0.9 0.2 -2.6 0.9 48.4 352.3 -2060.0 235.0 0.0 -283.0 0.0 -5.1 0.0 0.2 -2.6
-4895.9
-1585.6
OPERATION
4631.4
Fares
ASSETS
Infrastructure
Residual value
Taxes
Infrastructure maintenance
Rolling stock
Taxes
Residual value
Externalities
ECONOMIC PROFITABILITY
-4895.9
3045.8
162.6
-1458.2
-2508.7
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
-441.0
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
121
Line closure
2.
Technical characteristics of current situation A key question to be considered up front is if the areas being served by the line are well served by other modes, ensuring good accessibility for freight as well as people, and at reasonable costs. If the answer to that question is yes, then the CBA will be fairly straightforward. It will have to focus on the costs savings to be attained by closing the line to be compared with the worsened conditions to be experienced by those who before closure will travel by rail but after a closure will have to use an alternative mode, e.g. bus or truck. These conditions will have to be evaluated based on time losses, effects related to regularity of service, additional cost related to the need to transfer to rail at some other place (comfort), additional costs of freight transport, etc. Additional external effects caused by road traffic may also have to be considered explicitly.
3.
Project description The network effects will have to be considered as closure of a line can have negative effects on the network as a whole.
4.
Demand Assume, on the other hand, that some communities along the existing railway line are not served well in the existing situation. Then it may be necessary to consider possible alternative investments that will have to be made in order to improve accessibility. This may involve extending a road or improving public transport. The costs for improving accessibility in case of a line closure must be considered in the CBA. If it turns out that not closing the railway line is the cheapest means for ensuring accessibility to the area served by the line, it may be necessary to also consider a subsidy (a PSO) to sustain the train services. If, on the other hand, it is concluded that the line should be closed but that improvement should be made to the alternative modes, it may be necessary to ensure expansion of e.g. a bus service by way of subsidies.
5.
Costs A further case to be considered is when some of the traffic is captive, normally freight, in the sense that it would disappear entirely from the market if the line is closed. A line closure is thus expected to lead to the concomitant closure of a factory or a mine as well. In principle, also in this case the line closure should be evaluated as before, but disregarding the captive traffic. If the conclusion is that the line should be closed, then before doing so it should be offered to the captive user to take it over. This is the easiest way to assess the actual willingness to pay by the captive user.
6.
Benefits A line closure will tend to improve the financial position of the rail manager and the rail operator. The users will typically face higher costs.
122
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
123
10
2.
Technical characteristics of current situation All the cities that will be linked by the new section of high-speed line are connected by conventional rail at the present time, and will be assumed to remain so in the reference case. In this alternative it is also assumed that investments would be made as usual in rolling stock and that reinvestments would be undertaken as required in order to minimise overall costs of the railway services. All these costs are reflected in the do-minimum alternative in the economic analysis.
3.
Project description The project is mainly greenfield and therefore includes a new double track, with associated right of way, for 155 km. In addition, 3 new railway stations will be constructed. The capacity of the new line is estimated at 200 trains per day. The existing rail network and services will remain, albeit be reduced, in the project case. The CBA of the project has been determined for a period of 37 years, reflecting a seven-year design and construction period and 30 years of operation. It is assumed that GDP grows on average by 2.5% p.a.
4.
Demand The annual rail passenger transport market served by the line is estimated at less than 3 million one-way journeys. The project is expected to have a significant impact on the market, resulting primarily from sharply reduced rail travel times (from 75 minutes to 100 minutes depending on the O/D). Based on earlier experience and by using econometric demand functions, the promoter has estimated that the project will result in a total growth in the number of one-way rail journeys of 100% in comparison with the case without the project. The change in demand reflects the assumption that the new line will capture a substantial part of the air transport market, attract part of the present road traffic and induce new traffic. After initiation of the high-speed services, the promoter expects that growth will be high for about 7 years, as experienced by other high-speed routes after opening of services. Eventually after 7 years growth is assumed to slow down and to be more or less in line with growth in GDP. Again, this pattern is demonstrated by existing high-speed lines, for which sustained growth has been experienced.
124
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
5.
Costs Investments The investment expenditures are set out in Table 1, for both the rail operator and the rail manager. Additional investments in rolling stock will have to be made by the rail operator in order to accommodate the increase in traffic. These investments are reflected in the analyses (25 years is assumed to be the economic life of the high-speed trains and other rolling stock). Table 1: Investment expenditures (EUR million) Rail manager Year 1 2 3 4 5 6 7 8 9 10 Maintenance and operating costs Operating costs have been estimated separately for the manager and the operator and are based on detailed assumptions about the various resources required in the with and without project case. The maintenance costs are about 84,100 EUR per kilometre and year and the operation costs are estimated to be 8,400 EUR per kilometer and year. In addition, every 20 years, 2,4 M EUR per kilometre will be needed for major renovations. The operation costs for rail operators are estimated to be 0.05 EUR per user-kilometer for high speed trains and 0.04 EUR per user-kilometer for trains running at around 250 km/h. The operating costs for the operator include the track charges and station charges to be paid to the manager and have been calculated in accordance with the basic principles applicable in the country for the setting of these charges. Track charges are per train-km and station charges per user. They vary with the type of train service, being higher for high-speed lines, with differences between those with high and low traffic. Infrastructure 2 28 29 492 279 312 307 99 62 93 Rail operator Rolling Stock
6.
Benefits User benefits and evaluation User benefits, i.e. changes in consumers surplus, are measured directly by way of the demand functions that are employed. The user benefits mainly reflect time savings made by traffic on the existing railway traffic, diverted traffic and generated traffic. The values of time implicit in the demand models are as set out in Table 2. It is assumed that real values of time grow at 1%, an assumption which is reflected in the calculations of the user benefits.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
125
10
Table 2: Average values of time Type Air Rail Private car Bus External effects The model takes full account of the external effects produced by the project due to changes in modal split and generated traffic. In addition, account is taken of the fact that diversion of traffic away from air transport and roads will result in less congestion on the roads. The quantitative impact thereof has been calculated by way of a separate analysis. The parameter values used are of the same nature and order of magnitude as those used by several European countries for evaluating external effects in the transport sector. /h 12 8 10 6
7.
8.
Results of Stakeholder analysis This project is characterised by substantial subsidies from the national government. The main beneficiaries are rail users in the form of time savings. Also the rail manager and rail operator will benefit from the project. The part of the public burdened by external effects will see its situation improved.
9.
Comments This project is highly sensitive to the demand forecast. It must therefore be viewed as risky, and would warrant additional analysis to shed further light on this particular aspect.
126
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ECONOMIC EVALUATION NPV 2000 2001 2002 2003 2004 2005 2006 2007 2008 2010 2015 2025 2038
RA I LPAG
COSTS; million 2 2 0 0 0 0 0 0 0 0 0 2 2 0 0 0 0 0 0 2.5 2 27.6 28 29 29 492.1 492 278.9 279 311.6 312 379.2 369 206.5 192 28 28 0 4 0 0 0 0 29 29 0 5 0 0 0 0 492 492 0 79 0 0 0 0 279 279 0 45 0 0 0 0 312 312 0 50 0 0 0 0 369 307 62 49 10 0 0 0 192 99 93 16 15 0 0 0 0 0 0 0 0 0 12 21 0 33 0 0 0 0 0 0 12 23 0 35 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 30 0 42 0 0 0 0 0 14 0 14 0 2 0 12 43 16.2 70 28 28 0 4 0 0 29 29 0 5 0 0 492 492 0 79 0 0 279 279 0 45 0 0 312 312 0 50 0 0 369 307 62 49 10 0 192 99 93 16 15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 14 0 14 0 2 0 0 0 0 0 0 774 0 0 0 0 0 0 0 0 0 0 774 12 69 -774 -693
Project cost Investment economic cost Cost to rail manager Cost to rail operator (rolling stock) Taxes paid by rail manager Taxes paid by operator Residual value 0 0 0 0 0
Do minimum cost Investment economic cost Cost to rail manager Cost to rail operator (rolling stock) Taxes paid by rail manager & operator Residual value
Net investment cost Investment economic cost Cost to rail manager Cost to rail operator Taxes paid by rail manager Taxes paid by operator Residual value O&M cost for rail manager O&M cost for rail operator
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
1220 1578
127
128
10
ECONOMIC EVALUATION
BENEFITS; million
RA I LPAG
USERS Train users Time savings Operating costs Safety/Comfort Environmental externalities 244 44 0 0 NPV 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -2 0 -28 0 0 0 0 0 -29 0 0 0 0 0 0 -492 0 0 0 0 -279 0 0 0 0 -312 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -369 0 0 0 0 0 0 0 0 0 0 0 0 -192 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -7 15 4 2 18 55 78 16 11 1 10 16 2 31 21 1 117 84 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 1 0 0 0 -7 18 5 3 19 60 86 18 12 1 11 18 2 35 23 1 131 96 1 0 1 0 -7 26 7 4 23 76 108 22 16 1 14 22 3 45 29 1 175 133 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 29 9 5 7 35 10 5 8 51 15 8 7 83 25 9 1 0 1 0 -7 42 11 5 44 108 153 32 22 2 20 32 4 66 41 2 260 190 5 150 45 13 1 0 1 1 -5 77 21 7 79 167 237 49 34 3 32 49 7 105 63 3 428 1121 ERR = 6.8 % 57 501 150 63 0 11 0 5 3 0 -55 257 69 33 260 699 991 204 143 14 132 207 29 420 264 11 0 0 0 0 2000 0 0 0 0 2001 0 0 0 0 2002 0 0 0 0 2003 0 0 0 0 2004 0 0 0 0 2005 0 0 0 0 2006 0 0 0 0 2007 30 3 0 0 2008 31 3 0 0 2010 32 4 0 0 2015 31 7 0 0 2025 22 13 0 0 2038
Private vehicle users Time savings Operating costs Safety/Comfort Environmental externalities Bus users Time savings Operating costs Safety/Comfort Environmental externalities Air users Time savings Operating costs Safety/Comfort Environmental externalities Generated traffic
TRAIN OPERATOR Impact on revenue Impact on revenue From existing users From PV users From bus users From air users From generated traffic Additional VAT from generated traffic
AIR OPERATOR
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
BUS OPERATOR
1643 64
RA I LPAG
Rail users Air Generated traffic Rail manager Rail operator National GVT
Air operator
Bus operator
ECONOMIC VALUE
Travel time
244
57
Safety
150
Generated Traffic
OPERATION -276 420 257 -3 -29 132 -207 699 -264 -11 29 -420 -232 0 501 257 0 0
44
Track charges
501
Fares
-204
-143
VAT
ASSETS -1171 -99 66 -187 -98 99 13 403 25 -971 -111 -264 -11 99 232 -16 203 -1171 -99 66 0 -98 99 64
Infrastructure
Rolling stock
Residual value
Taxes
Infrastrucutre maintenance
ENVIRONMENTAL EXTERNALITIES
84
565
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
ERR = 6.8 %
129
References
This annex contains comments on relevant references prepared by CENIT and used as background for RAILPAG.
130
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
White Paper: European transport policy for 2010: time to decide Commission of the European Communities Commission of the European Communities
AUTHOR/S
EDITOR
YEAR
2001
SUMMARY The aim of this document is to analyse the main current problems existing in the European transport network and propose counter measures in order to improve it in terms of efficiency and sustainability. Nowadays, there is a growing imbalance among modes of transport in the European Union. The increasing success of road and air transport is resulting in worsening congestion, while, paradoxically, failure to exploit the full potential of rail and short-sea shipping is impeding the development of real alternatives to road haulage. A sign of this imbalance is that over the last 30 years an average of 600 km of railway lines have been closed each year in Europe, while at the same time the motorway network has increased by 1200 km a year. Of the thousands of kilometres of lines which have been closed to traffic, or even dismantled, there are branches and lines which today would have been extremely useful for coping with saturation on parts of the rail network. Railway infrastructure is no longer able to cope with the growth in traffic and, in recent years, more and more bottlenecks have formed in the vicinity of the largest conurbations, where trains of different types share the same infrastructure. Priority is given to passenger trains, with the result that goods consignors have lost confidence in the railways. Between 1970 and 1998 the share of the goods market carried by rail in Europe fell from 21.1% to 8.4% (down from 283 billion tonnes per kilometre to 241 billion), even though the overall volume of goods transported rose spectacularly. Because of congestion, there is a serious risk that Europe will lose economic competitiveness. The most recent study on the subject showed that the external costs of road traffic congestion are 0.5% of European Community GDP and will reach 1.0% by 2010, which entails 80 billion euros a year. In this context, rail transport is the strategic sector, on which the success of the efforts to shift the balance will depend. Revitalising this sector means competition among the railway companies themselves. The priority is to open up the markets, not only for international services, but also for cabotage on the national markets (to avoid trains running empty) and for international passenger services.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
131
References
The European Commission has been studying a package of measures which should restore the credibility, in terms of regularity and punctuality, of this mode in the eyes of operators, particularly for freight. Step by step, a network of railway lines must be dedicated exclusively to goods services so that, commercially, railway companies attach as much importance to goods as to passengers. This package will have to take into account tasks of general interest and economic and territorial cohesion, and will include: opening up the national freight markets to cabotage; setting high safety standards for the rail network, based on regulations established by an independent body and on a clear definition of the responsibilities of each player involved in order to ensure smooth operation of this market in which several operators will share the same stretches of the network; updating the Interoperability Directives to harmonise the technical requirements and provisions on use of all components of high-speed and conventional railway networks; gradual opening-up of international passenger services; promotion of measures to safeguard the quality of rail services and users rights; and creation of a Community structure for safety and interoperability.
Related to the above measures, Member States may introduce rates that take into consideration environmental costs and other external costs connected with accidents and congestion. The instruments for integrating infrastructure costs and external costs are, firstly, charging for infrastructure use, which is a particularly effective means of managing congestion and reducing other environmental impacts, and, secondly, fuel tax, which lends itself well to controlling carbon dioxide emissions. The European Commission plans to propose a framework Directive to establish the principles of infrastructure charging and a pricing structure for all modes of transport. The proposal, which leaves each Member State a wide scope in terms of implementation, will include a common methodology for setting price levels which incorporates external costs, and will specify the conditions for fair competition between modes
132
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
Going Trans-European. Planning and financing transport networks for Europe Mateu Turr
AUTHOR/S
EDITOR
Pergamon, Elsevier
YEAR
1999
SUBJECT
SUMMARY In this book we can find a profound reflection on the present state of European transport networks. The most important topical issues analysed are the planning and financing of European transport projects, taking into account subjects such as future challenges in Europe, the Community policy on transport infrastructure, the priority projects, etc. The new transport network framework proposed by Dr. Mateu Turr is based on the goals of efficiency, sustainability and cohesion. Specifically, he translates these general principles into more detailed objectives: a) integration of Member States action; b) integration between the infrastructure policy and other common policies; c) multimodal integration; and d) integration of the European, national, regional and local scales. To try to achieve these objectives, the author suggests quite a few different procedures. Some of them concern transport investment appraisal directly, e.g.: Applying the polluter pays principle and adequate payment mechanisms; Introducing global and long-term considerations in major transport infrastructure planning; Ensuring that environmental considerations have been adequately taken into account in decision-making on investment in transport infrastructure; Using the design and implementation of major transport investments to enhance social cohesion.
In chapter 7, the reader can find an excellent summary of the funding options of the TransEuropean transport projects, in relation to an important subject: the ideal level of co-operation between the public and private sector. Finally, the last themes analysed are the expected and needed improvements for the future of transport: in relation to European policy, investment financing, additional funds, the European Institutions, etc.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
133
E
TITLE AUTHOR/S
References
Transports: pour un meilleur choix des investissements Transports: for a better choice of investments Marcel Boiteux et al.
La Documentation Franaise
YEAR
1994
SUMMARY This document introduces the principles that must be considered when studying a new investment connected with transport. Nowadays, there are a large variety of methods and values as regards the benefits and costs that a new transport infrastructure entails. The document is focused on obtaining general tools that can be used for different modes of transport in order to evaluate and establish a comparison among the alternatives proposed. Not only do the internal costs have to be taken into consideration but also the external costs and the nature of the investment. As an example, the distribution of investments in the conventional network of SNCF, depending on their nature, is the following: 47% for maintenance investments; 30% for quality improvement; and 23% for safety.
Anyway, it is necessary to compare and contrast the present or future situation in which there is only the current transport infrastructure with the present or future situation considering the investments made and all of their consequences. In this process, the study has to take into account aspects such as traffic demand forecasts, shares of modes of transport, length of the journeys, safety conditions, comfort for passengers, external environmental costs (noise, vibrations, water pollution, air pollution), economic development and cost of the infrastructure. In order to define traffic demand forecasts for its high-speed lines, SNCF considers: passengers using the existing conventional railway line; passengers using planes, who are known by using a price-time model; and generated traffic and traffic from the road.
Finally, one of the most difficult parts in the process of evaluation investments is how to quantify effects that refer to quality. Some impacts (especially environmental ones) can be determined in terms of cost of avoidance, cost of repairs, indemnities and costs which society is willing to pay so as to reduce nuisance.
134
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
AUTHOR/S
Prof. Peter Mackie, Dr. Susant Grant/Muller, Mr. John Nellthorp and Prof. Alan Pearman
TINA Secretariat Commission of the European Communities TINA Secretariat University of Leeds
YEAR
1999
SUMMARY The Transport Infrastructure Needs Assessment (TINA) process was designed to initiate the development of a multi-modal transport network within the territory of the candidate countries for accession: Estonia, Latvia, Lithuania, Czech Republic, Slovakia, Hungary, Poland, Slovenia, Romania, Bulgaria, and Cyprus. This network development, which takes into account relevant work of the UN-ECE and previous analysis of the European Commission assisted by groups of experts from the Member States, should comply with the principles, objectives and criteria as set out in the guide for the development of a Trans-European Transport Network in the territory of the European Union (Decision No 1692/96/EC of the European Parliament and of the Council on Community guidelines for the development of the trans-European transport network). This study establishes a common methodology for project appraisal to be endorsed by international financial institutions. So it must be regarded a guide in order that TINA project proposals, for submission to the various international financial institutions and organisations by different states, can be selected and appraised. The use of a Framework approach is recommended, containing at its core a cost-benefit analysis of those elements that can justifiably be evaluated in monetary terms. The socio-economic cost benefit analysis was placed in the context of a necessary wider project and investment appraisal, which covers safety, environmental and policy-related aspects. The initial stages of the assessment methodology for publicly funded projects include the definition and initial screening of candidate projects. Screening should include ensuring that projects are adequately defined, identifying their board performance relative to main indicators, identifying other dependent projects and assessing barriers to implementation. For those projects that are carried forward to a formal appraisal, it is necessary to assess the effects or impacts on a key group of indicators such as transport system efficiency and safety, environmental impacts, wider policy impacts and financial implications. Comparing the state of these indicators in the do-minimum scenario with their state in the dosomething scenario assesses the effects of the project. In order to form this comparison it will be necessary to collect data and other relevant information relating to the indicators. The cost-benefit analysis, which forms the core of the assessment, is then calculated using both computed costs and benefits.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
135
References
Apart from that, the use of spreadsheet software is recommended because storing data in a relatively detailed form within a spreadsheet or similar would assist the sensitive testing process (on particular parameters or values), ease the updating of information and allow decision-makers to form comparisons more readily. The project analyses the context of the appraisal of a single project but concludes that the real world is more complex and, typically, that the decision-makers need to assure themselves that they have chosen the best of the available alternatives, and that the project is sufficiently high in the merit or ranking order to warrant funding. But, although the analysis must be capable of allowing for the existence of many project alternatives and should facilitate prioritisation, the task of weighing up the economic, environmental and policy impacts in order to determine ranking, rests with the decisionmakers themselves. Its not possible to undertake a complete appraisal of all the project alternatives because of the large number of combinations of routing, alignment, layout and capacity. However, and especially where strategic routing options exist, the full appraisal of a few alternatives should be undertaken so as to demonstrate that the preferred option is superior, not just to the do-minimum but to the available alternatives. This should help to minimise the risk of over- or under design. For large projects, where many technical choices exist, such as bridges and tunnels, many alternatives may need to be evaluated. But a full comparison between the project alternatives will be needed based on each of the criteria listed in the appraisal framework, in theory. In practice, however, it is likely that for several of the impacts, the performance of the project options will be similar or identical so that in comparing alternatives, it should be possible to focus on the aspects in which the project alternatives differ. These are likely to be in cost-benefit analysis plus any location specific effects of particular alternatives (loss of heritage, natural assets, opportunities created, etc.) In terms of cost-benefit analysis, the decision taker should consider whether the net differences in user benefit, revenue and operating costs justify the additional capital outlay for each project alternative. The analysis should list the alternatives in ascending order of capital cost and show the incremental Net Present Value (NPV) for each increment of capital outlay thus showing a a form of incremental analysis. But, usually not all the acceptable projects can actually be funded. In this situation, prioritisation becomes important. So, in terms of project appraisal and conditions of capital rationing, its recommended that some form of explicit prioritisation or ranking exercise be undertaken between the projects being considered. The key indicator for this will be the cost-benefit- ratio (CBR) of projects because this is the indicator of benefit per unit of capital cost, obtained for each project. But a single indicator will not take into account important differences between projects and will be an incomplete measure. A more complete approach will require the decision-maker to balance or trade-off the performance of the project in terms of the cost-benefit, environmental and wider policy dimensions with information and support of the socio-economic analysis.
136
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
Metodologia per a lavaluaci dalternatives dinversi en transport pblic Methodology for the appraisal of public transport investment options
AUTHOR/S
Autoritat del Transport Metropolit Autoritat del Transport Metropolit Universitat Autonoma de Barcelona
YEAR
1998
SUMMARY The aim of this study is the elaboration of a methodology for planning the investments of the Autoritat del Transport Metropolit, an organisation that regulates the public transport in the metropolitan area of Barcelona (Spain). This study is included in the Master Plan of Public Transport Infrastructures 2001-2010. The public investment project appraisal allows the PTA to know which is the most beneficial project for the whole community or for a group. This is a very difficult task for transport investments because of the generation of several, different and difficult to calculate costs and benefits. The main benefit of transport investments used to be the time saving aspect but there are other impacts that can be important such as environmental externalities or safety. There are several methodologies for evaluating projects. Some of them are very well known for instance, cost-benefit analysis but there are other useful ones that have had less exposure e.g., the achievement of objectives matrix. Apart from that, these methodologies consider not only different sorts of costs and benefits but also different valuations and aggregations of them. Six appraisal methods were compared: investment financial appraisal; cost-benefit analysis; multicriteria analysis; cost-effectiveness analysis; achievement of objectives matrix and threshold analysis. The analysis of these six methods led to an elimination of the less useful ones when analysing a public transport investment alternative appraisal in the metropolitan area of Barcelona and the study used the most apposite methods, which are the multi-criteria analysis and the cost-benefit analysis. The fact that both methodologies have their benefits and problems led to the formulation of a mix model in order to make the best use of the benefits and avoid any disadvantages. Besides this, availability of the data is another possible handicap that must be taken into account. This mix method appraises with a cost-benefit analysis all the impacts (in monetary terms or not, depending on the availability of good data). Basically, the features in monetary terms are the investment costs, the operating costs and maintenance costs and non-monetary impacts with monetary value in the metropolitan area of Barcelona are variation in travel time, variation in safety and some environmental externalities such as air pollution or noise.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
137
References
First of all, it appraised the economical efficiency of projects. It has got an important weight but there are other factors related to the viability of the operators and social equity that must be taken into account. The incorporation of these indicators in the appraisal process is done by multi-criteria analysis. Afterwards, five criteria are used in a multi-criteria analysis: social economic profitability, appraised by the cost-benefit analysis (internal economic rate of return); private economic profitability, appraised by the cash-flow of the operator (net present value); increase in potential accessibility, in terms of the increase in the number of inhabitants served; increase in the supply of public transport, comparing the value of the indicators based on daily public transport trips and people served with and without project; and equity, that shows if the new situation leads to a more equal distribution of the resources for the whole of society or not.
The proposed method of aggregation can synthesise the impact of projects in a quantitative way. It has got three important benefits: its simple application, its easy interpretation and the possibility of obtaining a complete ranking of all the projects to be appraised. So, the final result will be a global index of the social need for every project.
138
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
Manual de evaluacin de inversiones en ferrocarriles de va ancha Manual of wide-gauge railway investment appraisal Direccin General de Infraestructura del Transporte Ministerio de Transporte, Turismo y Comunicaciones
EDITOR
YEAR
1987
Direccin General de Infraestructura del Transporte Ministerio de Transporte, Turismo y Comunicaciones Profitability of railway investments
SUMMARY At the end of the 1980s and the beginning of the 1990s in Spain a new impetus was given to the financing and construction of rail infrastructure. In that socio-political framework the Ministerio de Transportes, Turismo y Comunicaciones promoted the elaboration of the Manual de evaluacin de inversiones en ferrocarriles de va ancha. The main objective of this document is to measure the contribution from each investment project in relation to the objectives defined by the government; going beyond the purely financial investment in appraisal of infrastructure projects. For the analysis of the different railway investment projects it proposes an evaluation of the aforementioned on three different levels (including the option of not investing at all): Financial evaluation: It outlines a balance, by means of typical indicators, between expenses and revenues during the service life of the public work. It is based on real prices, including taxes and subsidies. Economic evaluation: Costs and profits are compared, for real market value (excluding taxes and subsidies). Social evaluation: The fundamental aspect to keep in mind is social fairness. Looking at themes such as the impact on the environment, the effect on the growth of employment or energy consumption is also included.
The most remarkable quality in the proposed procedure is that it is compact, practical and selfsufficient, so that it only requires a periodic upgrading of the indexes. Also, it outlines a control method of the effectiveness of the investment once the project is executed and in operation. In spite of the obvious advantages of the document, there exists, however, some limitations for the use of this methodology in a European environment. On the one hand it should be pointed out that the method is set up from a local point of view. It is also programmed assuming that there is only one owner of the infrastructure, who is also the agent and the operator.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
139
References
It establishes the convenience of carrying out (or not) certain investments in railways but it does not include an analysis of investments in other transport modes. It does not consider, in a general way, the external effects of transport. The social and environmental effects considered are not always translated into monetary terms.
Finally, and to conclude, the analysed document proposes a procedure to evaluate investments in railways that is normative, specific, self-sufficient and easy to review periodically; but whose layout is local (both geographically and in terms of transport modes) and it also suffers from a lack of the externality concept.
140
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
Effets Externes du Transport External Effects of Transport S.P. Mauch and W. Rothengatter
AUTHOR/S
YEAR
1994
International Union of Railways, UIC Universitt Karlsruhe Institut fr Wirtschaftspolitik und Wirtschaftsforschung, IWW External effects
SUMMARY This document analyses in a systematic way the issues involved in the incorporation of externalities in the socio-economic evaluation of transport projects. There were analysed, and quantified absolute and relative costs of air pollution as well as noise and global warming for the different transport modes. Although the results provided in this paper are quite old, the methodology of obtaining them and the differences of rates between countries has still got great value. According to the obtained results and regarding air pollution, external costs were in the range of 0,3% to 1% of GDP for the seventeen UE studied countries (EUR 17). Average relative costs for passenger transport in EUR 17 were highest for cars and aviation and significantly lower for railways (about 6 and 5 ECU/1000 pass-km for cars and aviation respectively, and about 2 ECU/1000 pass-km for railways). In the domain of freight transport, average relative costs were highest by far for aviation (about 26 ECU/1000 ton-km), followed by road transport (13 ECU/1000 ton-km). Shipping on inland waterways and rail showed significantly lower values (about 4 and 1 ECU/1000 ton-km respectively). Annual noise costs of transport added up to 0,65% of the GPD on average in EUR 17. In terms of relative costs, EUR 17 average relative costs for passenger transport are 4,5 ECU/100 pass-km for cars, 4,2 ECU/1000 pass-km for buses and 3,1 ECU/1000 pass-km for rail transport and the EUR 17 average noise costs for freight transport are 12,7 ECU/1000 ton-km for road transport and 4,7 ECU/1000 ton-km for rail transport. In relation to the climate change, it can be concluded that overall prevention costs represent about 0,7% of GPD for EUR 17. For passenger transport, relative costs are highest for aviation (below 10 ECU/1000 pass-km), but are also high for cars (about 6 to 7 ECU/1000 pass/km). Values are slightly below 3 ECU/1000 pass-km for buses and rail. Apart from that, airfreight transport (about 50 ECU/ 1000 ton-km) showed the highest value and railways freight transport (about 1 ECU/1000 ton-km), the lowest.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
141
E
TITLE AUTHOR/S Pierre Vilain
References
Harmonising Parameter. Values in Transport Project Appraisal: The Values of Time and Safety* Foot note: This document has been recently updated.
YEAR
1996
SUMMARY It recommends a consistent methodology, quantitative measures of profitability and validity as indicators of a projects worth in the evaluation of transport projects. But, a consistent methodology implies using consistent parameters, to the greatest extent it is possible to estimate them. So, this document presents recommended parameter values for EU member countries, as main inputs into the standard cost-benefit analyses conducted at the EIB in the case of transportation projects, namely the value of time savings and the value of safety. The value of time is by far the most important variable used in appraising transport projects. About the valuation of travel time, this report says that: The value of working time for a traveller should be equal to the average gross wage in that country. Values for non-working time should be valued as a proportion of net wages. On average, these represent about 35% and 25% of the gross wage.
This paper also provides a methodology for estimating the growth in the value of time, because it increases with real wages. For appraisals, it is proposed to use an annual growth rate of 1,5% for the real value of time in all the EU countries. However, in Spain, Portugal, Ireland and Greece, it is recommended to use a growth rate of 2% a year in the short and medium term and 1,5% after 2005. It is also recommended to keep the proportional relationship of working time to non-working time in member countries constant over time. Apart from that, the value of time could be expected to vary according to the mode of transport. Their concept of the value of time includes a disutility of transport (except arguably in the case of working time), and this would also tend to vary with the mode of transport. The value of time could also be expected to vary according to regions within a country. Regions will differ in their income levels based on such factors as industry mix, the degree of specialisation in production and the existence of other externalities in production due to an urban environment. So, national values outlined in the tables of results should be altered to reflect particularly significant regional differences.
142
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
For non-member countries (not available in tables), it is encouraged that all value of time estimates be based, to the greatest degree possible, on wage data. The short and medium-term growth rate of the value of time should reflect expected economic growth rates considerably above those forecast for member countries. On the other hand, values for safety improvements would ideally be based on an individuals own evaluation of these improvements. Unfortunately, the empirical results of estimation of individual valuations for reduction risk, yield divergent results. So, while an individuals risk evaluation may take into account the effects of her/his death or injury, it is likely that the wider social cost (which would include, for example, lost human capital) is not taken into account. According to these considerations, a hybrid cost of fatalities is proposed, composed of two different costs. The first is the human capital cost the value of which is based on several variables and is different across EU countries. The second is the average human suffering cost, equal for all EU countries in its base value, but adjusted for variations in purchasing power. This value is estimated from an average of official values from member states for human suffering and material damages used in project evaluation. The annual growth rates of these values should be the same as used for the value of time.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
143
E
TITLE AUTHOR/S (Coordinator)
References
External costs of transport in Europe (EXTERNE) P. Bickel, S. Schmid, W. Krewitt, R. Friedrich European Commission DG Transport & Energy
EDITOR
YEAR
1996 - 1997
INSTITUTIONS INVOLVED
European Commission DG Transport & Energy Institute for Energy Economics and Rational use of Energy (IER) Institute of Occupational Medicine Ltd Association pour la Recherche et le Dveloppement des Mthodes et Processus Industriels National Technical University of Athens AEA Technology Plc Institut National de lEnvironnement Industriel et des Risques Vrije Universiteit Amsterdam Universit Commerciale Luigi Bocconi Energy externalities in transport
SUBJECT
SUMMARY Within ExternE Transport a new methodology for quantifying energy-related environmental externalities of transport based on a bottom-up approach was developed. This methodology allows the calculation of marginal external costs of different transport activities in a detailed and consistent way, considering operation and the life cycle of the transport modes. Energy-related impacts and associated costs resulting from transport activities are assessed using the impact pathway approach, which was developed in the ExternE Project. The impact pathway is the sequence of events which links a burden to an impact. The main stages of the impact pathway are: emission modelling, dispersion modelling, estimation of physical impacts using exposure-response functions and, finally, the monetary valuation of impacts. The methodology was applied to a variety of case studies in different countries, giving a European-wide overview of site-specific results. The technologies assessed cover passenger and goods transport with road, rail, and waterway transport. It can be concluded that health impacts dominate the damages quantified in this study; in particular, mortality due to primary (PM2.5) and secondary particulates (nitrates, sulphates). Carcinogens, which were expected to play an important role due to their high specific toxicity, proved to be of much lower importance compared to the particles. It was found that the population density around a road is a key parameter for the magnitude of impacts, particularly for diesel fuelled vehicles. This effect is caused mainly by the importance of the primary particles for the total damage. With respect to the occurring site-specific damages, three main categories of locations could be identified: agglomerations, urban areas, extra-urban areas.
144
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
The external costs due to airborne pollutants and greenhouse gases quantified in the different case studies were between 0.005 to 0.051 ECU/pkm (passenger kilometre) for petrol cars fitted with three way catalyst, depending on the location (low value for extra-urban areas, high value for agglomerations). For diesel cars the range quantified was 0.020 to 0.375 ECU/pkm (extra-urban areas - agglomerations). Damages due to up- and downstream processes (fuel production, production, maintenance and disposal of vehicles and infrastructure) were quantified to about 0.007 ECU/pkm for a car. Quantified external costs of passenger trains ranges from 0.001 to 0.007 ECU/pkm (electric and diesel train respectively). For electric and diesel goods trains the range quantified was 0.001 to 0.009 ECU/tkm (tonne kilometre), compared to about 0.040 to 0.300 ECU/tkm for heavy goods vehicles (different sizes and locations).
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
145
E
TITLE (TENASSESS) AUTHOR/S (Coordinator) Dr. Liana GIORGI
References
EDITOR
YEAR
1996 - 1999
INSTITUTIONS INVOLVED
European Commission DG Transport & Energy Interdisciplinary Centre for Comparative Research in the Social Sciences Halcrow Fox INRETS PLANCO Consulting GmbH SYSTEMA IVTB ERRI TRT UKO NEA NEI LESEC ICCR-London UWCC Decision process in transport policy
SUBJECT
SUMMARY The research project Policy assessment of trans-european networks and common transport policy acronym TENASSESS was financed by the European Commission within the framework of the 4 th PCRD on transport. Its main objectives were: 1. To provide a preliminary policy assessment methodology related to decision making on transport infrastructure investments and service evaluations; more specifically, the aim is to develop a methodology that could be utilised in the assessment of different solutions. 2. To provide a comprehensive policy assessment of the European Common Transport Policy (CTP) with a view to evolving recommendations that may assist its further development and implementation. 3. To provide input and data for further or parallel research on the subject. The general focus of the project was on the decision making process in transport policy. It is considered that transport policy is complex as it is characterised by decisions that must consider lots of interests from different groups and actors. In this research, special attention was paid to possible conflicts between different measures or objectives observed in the different geographical scales of concurrence (european, national, regional). 146
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
AUTHOR/S (Coordinator)
EDITOR
YEAR
1996 - 1999
INSTITUTIONS INVOLVED
European Commission DG Transport & Energy Marcial Echenique & Partners National Technical University of Athens Institute for Transport Studies, University of Leeds Planco Consulting Institut National de Recherche sur les Transports et leur Scurit (INRETS) Facults Universitaires Catholiques de Mons Technical University of Denmark; LT-Consultants, Finland; Gruppo CLAS The Interdisciplinary Centre for Comparative Research in the Social Sciences Modelling socio-economic impacts of new strategic transport initiatives
SUBJECT
SUMMARY The broad aim of EUNET was to develop a comprehensive method for modelling and assessing the socio-economic impacts of new strategic transport initiatives. There were four main strands to the work: The development of a new regional economic/transport modelling method, with the emphasis on research to extend the input-output framework which is at the heart of the approach. Recommendations on costs, prices and values to feed into the assessment process, including the development of a set of standardised European values for use in assessments. Development of an assessment method and prototype assessment software, which can be linked to the regional economic/transport model, including the incorporation of accessibility analysis and the specific treatment of uncertainty. Application of the model and assessment tool to demonstration examples which can be linked to three demonstration models. The three demonstration examples cover the Trans-Pennine area of Northern England, the Baltic region and Greece.
The study includes a Costs values and prices in appraisal section aiming to provide a full set of values for the EUNET appraisal tool. Impacts which have been considered include direct impacts (such as time savings), environmental impacts, and socio-economic impacts (e.g. on employment).
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
147
References
There were three main tasks on the issues surrounding appraisal values, and a fourth task to construct a database of transport costs, as follows: to review current appraisal practice for major transport projects across member states. Information on member states current use of formal CBA (Cost-Benefit Analysis) and MCA (Multi Criteria Analysis) methods was gathered by the project partners and recorded in a series of Country Reports. Detailed information was requested on the scope of appraisals the range of impacts included, which were monetised and how those monetary values had been derived. to identify the key issues to be addressed in developing the appraisal values for EUNET and to agree the approach. to prepare for each impact a common definition, units of measurement and accompanying monetary values where appropriate, using the information gathered through the Country Reports. to obtain operating cost data, by mode for each Member State where available, and develop a vehicle operating cost database.
It was decided that a European value set and a Country-Specific value set were necessary in EUNET. Although it could be argued that the philosophy underlying CBA implied the need to use local values (the values for the people actually affected by a project), projects of European significance will need to be appraised within a common framework for European Institutions to determine funding allocation issues. On the other hand, Member States may wish to appraise projects using a similar framework, though with values relating to country-specific objectives. The list of impacts has been finalised using material from the country reports and the assessment works proposals for the framework variants. The key direct impacts have been defined and a set of EU and country specific values derived. The assessment methodology developed within the EUNET project was expected to be innovative, but also to provide a functioning and practical product within the three years of the project. Overall, the proposed EUNET assessment framework has three main steps: Decision tree: what are the project objectives, what criteria should be used to assess it and how are they connected Weighting: prioritisation of the criteria in the appraisal Evaluation and ranking: utilisation of criteria, weights and structure to meet the objectives.
148
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
Strategic Assessment of Corridor Developments, TEN Improvements and Extensions to the CEEC/CIS CODE-TEN
The Interdisciplinary Centre for Comparative Research in the Social Sciences European Commission DG Transport & Energy
YEAR
1996 - 1999
INSTITUTIONS INVOLVED
The Interdisciplinary Centre for Comparative Research in the Social Sciences IFP, Denmark VTT Technical Research Centre of Finland Systema Systems Planning & Management Consultants s.a. Cesur Planco Consulting TRT Transporte e Territorio Institute for Transport Studies Halcrow Fox Incertrans WEUG KTI CTC Engineering SCCTP Tallinn College of Engineering Scenario development
SUBJECT SUMMARY
The general aim of the CODE-TEN project was to assist with decision-making in the complex environment of contemporary transport geography characterised by the new concept of corridor. It applies the scenario approach in order to elaborate consistent images of the future that combine information on the socio-economic development, policy development and infrastructure planning. These are, in turn, subjected to impact assessment in order to reveal the effects or consequences of specific strategies. The specific aims of CODE-TEN are: 1. Compilation of an information and political database about the development of trans-European corridors within a global & long term perspective; 2. Elaborate scenarios for future development of CEEC/CIS countries affecting transport demand Economy, Integration, Population & Policy Strategy; 3. Comparative analysis of the temporal and spatial impacts of socio-economic parameters on the development corridors; 4. Compile studies and indicators related to the environmental effects on European regions; 5. Develop a methodology for the assessment of transport policy and large-scale projects; 6. After this methodology development, define and develop political support tools aimed at improving the interaction between political instruments and corridors / networks; 7. Make recommendations for transport policy.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
149
E
Corridor I: Corridor II: Corridor IV: Corridor V: Corridor VII: Corridor IX: Corridor X: Corridor: Zone MSS:
References
Different case studies were considered: Warszawa Riga Tallinn Helsinki Via Baltica; Berlin Warszawa Minsk Moscou Nizny Novgorod; Berlin Prague Vienne Budapest Sofia Constanta / Thessaloniki; Venise Trieste / Koper Budapest Kiev; Danube waterways; St.. Petersburg Helsinki Stockholm Copenhague; Salzburg Ljubljana Zagreb Beograd Thessaloniki; Lisbonne Madrid - Paris; Zone de transport courte distance dans la Mditerrane (Mediterranean Short-sea Shipping).
As a result, the study provided: Scenario development Development of scenarios up to the year 2015 for socio-economic development, integration and policy developments; Transport Information system Development of a comprehensive information system on a CD-ROM on 30 European countries providing information on politics, regionalised socioeconomic data, regionalised road information, foreign trade, transport costs behavioural and resource costs, networks and maps; In-depth corridor studies I, II, IV, V, VII, IX, X, the Mediterranean short sea shipping and the Lisbon-Madrid-Paris trans-European link; Development of infrastructure strategies based on priorities developed by combining the policy performance of projects with the degree of adaptability of projects to the national policy goals; Traffic flow estimations and assignments based on the development of the various scenarios and corridors up to the year 2015; Impact assessment of the various corridor development alternatives on accessibility, environment and socio-economic factors.
150
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Monitoring Assessment and Evaluation Scheme for Transport Policy options in Europe MAESTRO Dr. Laurie PICKUP
EDITOR
YEAR
1998 - 1999
INSTITUTIONS INVOLVED
Transport & Travel Research Ltd Arise - European Economic Interest Grouping Technical Research Centre of Finland Netherlands Economic Institute Beratung und Planung im Verkehrswesen Gmbh Salford University Business Services Limited Universit degli studi di Roma La Sapienza Gestionnaires sans Frontires Romania Center of Interdisciplinary System Research AEA Technology Plc University of Leeds Systems Planning and Management Consultants S.A. University of Twente Barcelona Tecnologia S.A. European Transport and Telematics Systems Ltd. Project appraisal
SUBJECT
SUMMARY MAESTROs aim is to provide practical advice on the selection, design and evaluation of transport-related pilot projects, to play a supporting role in the current 4 th Framework Programme, and to assist with the preparation for future Programmes. In doing so, MAESTRO expects to strengthen the link between pilot projects and their contribution to identifiable policy aspects, thus bridging the gap between theoretical knowledge and practical applications and providing a synthesising role for pilot projects within the RTD Transport Research Programme. The MAESTRO project identifies the following main goals: to conduct a review of existing evaluation methodologies, and assess their value in relation to policy objectives; to develop a Maestro methodology for the selection, design and evaluation of pilot and demonstration projects within the Transport RTD workplan; to develop evaluation procedures to be incorporated into the MAESTRO methodology; to play a supporting advisory role in the Transport RTD programme in the setting up and establishment of all pilot and demonstration projects; based upon the MAESTRO methodology, to produce practical guidelines for the selection, design and evaluation of pilot and demonstration projects in the Transport RTD workplan.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
151
E
TITLE Acronym PROFIT EDITOR
References
European Commission DG Transport & Energy Netherlands Economic Institute (NEI) National Technical University of Athens The University of Leeds STRATEC University of North London Transek PPP promoting and advising
YEAR
2000 - 2001
INSTITUTIONS INVOLVED
SUBJECT
SUMMARY PROFIT looked at options to bridge the gap between the financial profitability of TEN projects and their socio-economic rentability by facilitating and promoting public-private-partnerships (PPP) to finance and operate TEN projects. The project has: developed a structured methodology for assessing the PPP potential of a TEN project, based on financial attractiveness and socio-economic costs and benefits; defined and assessed the network effects in TENs; established an Expert Group consisting of private companies and government bodies in PPPs, which will function as a consultative body for the project; provided a user friendly and easy-to-use tool (handbook) to make a quick-scan of the PPP potential of a TEN or other infrastructure project.
152
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
Integrated Assessment of Spatial Economic and Network Effects of Transport Investments and Policies IASON
Tavasszy, Lorant A.
EDITOR
YEAR
2001
SUMMARY The IASON project (Integrated Appraisal of Spatial economic and Network effects of transport investments and policies) intended to provide the Commission with an assessment framework and procedures for the evaluation of transport policies and investments, and to produce new insights for assessments by studying spatial impacts of transport investments and policies.
For that purpose IASON has: 1. introduced a comprehensive but practical assessment framework for the evaluation of indirect effects; 2. used a set of EU level models for quantifying spatial and socio-economic impacts of transport investments and policies; 3. provided a methodology for the analysis and measurement of network effects and Community added value of TENs; 4. built up and maintained a discussion platform, and 5. provided recommendations for inclusion of indirect impacts in cost benefit analysis and the development of supporting tools and databases.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
153
E
TITLE Acronym AUTHOR/S (Coordinator) EUROPE-TRIP
References
EDITOR
YEAR
1997 - 1999
INSTITUTIONS INVOLVED
Ferrovie Dello Stato - Societ di Trasporti e Servizi per Azioni Steer Davies ang Gleave Ltd. Hgskolan Dalarna British Railways Research Limited DSB Consult Statens Jrnvgar Societ Nazionale per il Trasporto Combinato Strada-Rotaia The Foundation for Scientific and Industrial Research at the Norwegian Institute of Technology Universit degli studi di Roma Tor Vergata Universit degli studi di Genova Universidade de Santiago de Compostela European Railway Planning Optimisation
SUBJECT
SUMMARY Main objectives: The EUROPE-TRIP (briefly TRIP Transportation Railways Integrated Planning) is part of a wider initiative referred to as EUROPE (European Railway Optimisation Planning Environment) supported within the EU RDT Programme. TRIP addresses the higher part of the rail planning process and aims to assist the management of infrastructure by providing a comprehensive model to represent the short and medium/long term planning of the railway system, taking into account the evolution of the European market and transport policies. TRIP implements the specific transportation facets of the EUROPE programme, in order to: a. define a business planning model of the rail system, focused on the management of infrastructure; b. analyse the market structure and find mechanisms to define how the infrastructure must coordinate with the transport companies in providing access-to-track; c. determine the cost of using the infrastructure; d. evaluate the methods for assessing the capacity of rail lines, with particular reference to European corridors. The project follows an experimental approach so as to engineer the Directive principles and incorporate a market game approach to simulate the behaviour of market operators, via management science and game theory algorithms. It provides a basis to determine a standard cost model for the EU Railways, in order to address track pricing and other investment policies. In addition it will use simulation as a leading tool in assessing the rail lines capacity, taking a European corridor as case study (i.e. Italy-France-UK). Finally the project aims to develop a prototype software model in order to demonstrate the research concepts and provide a tool to better disseminate its final results. 154
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
EDITOR
European Commission DG Transport & Energy University of North London Netherlands Economic Institute Technische Universitt Dresden University of Pardubice T.M.T. Pragma S.R.L. Socially necessary railways
YEAR
1997 - 1999
INSTITUTIONS INVOLVED
SUBJECT
SUMMARY The SONERAIL project examines the role of socially necessary railways, i.e. those railways, which under EC regulations 1191/69 and 1893/91 cannot be provided on a commercial basis and may therefore be financially supported by a Member State. The overall workplan consisted of four main tasks as follows: Task 1: Establish the current situation with respect to definitions used and evaluation criteria applied along with the development of an evaluation methodology for socially necessary railways which can be applied to other passenger services. This will form the basis for the next stages; Task 2: Apply the developed evaluation methodology to specific passenger services with the aim of testing this methodology and utilising it to provide information about the performance of the selected passenger services; Task 3: Identify and assess future European operations scenarios which will contribute to narrowing gaps between supplied and demanded service level for different dimensions of service level (including a range of policy options regarding socially necessary railways and other passenger modes); Task 4: Provide conclusions and recommendations on best practice operations of socially necessary railways in terms of optimal operations scenarios for reducing the gap between supplied and demanded service levels for different dimensions of service.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
155
E
TITLE AUTHOR/S NEI and CPB
References
Netherlands Economic Institute (NEI) Central Planning (CPB) Netherlands Economic Institute (NEI) Infrastructure planning
YEAR
Up to 2002
SUMMARY The specific aim of the OEEI programme was to achieve greater uniformity among policymakers and researchers on appropriate calculations of the economic pay-off of large-scale transport infrastructure projects. In recent years many Dutch economic research institutes have worked on the research programme on the economic effects of infrastructure (OEEI). It was initiated by the Ministries of Transport and Economic Affairs after discussions on the benefits of various major transport infrastructure projects. This large-scale research programme has produced about ten reports, which are integrated into this guide for cost-benefit analysis. These reports are primarily aimed at large projects. For smaller projects some effects (such as indirect effects) were not examined, or not as extensively as for large projects. Some conclusions of this initiative are: A thorough and complete cost-benefit analysis is an indispensable tool in evaluating transport infrastructure projects. For large projects, the indirect economic effects (effects on clusters) should be explicitly taken into account, as the reasons for such projects usually involve strategic considerations; In assessing costs and benefits of infrastructure projects, it is important to include the possible benefits of flexible investment strategies, which are stable to very different developments of economic growth, reactions of competitors and other key determinants of the results. Moreover, uncertainties should be taken into account by adding a (project-specific) risk premium to the discount rate; The OEEI research program has resulted in a broad consensus among research institutes on the importance of cost-benefit analysis in the evaluation of major infrastructure projects and on the outlines of the way in which such analysis needs to be made. It has been an important step towards improving the scientific basis for decisions on infrastructure.
156
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
TITLE
Kosten-batenanalyse van HSL-Oost infrastructuur Cost benefit analysis of high speed rail infrastructure Henri Dijkman, Carl Koopmans and Martin Vromans CPB Netherlands bureau for economic policy analysis
AUTHOR/S
EDITOR
YEAR
2000
SUMMARY The Dutch government was considering the construction of a High Speed Rail (HSR) section, the HSL-Oost, between Utrecht and the German border, as a part of the HSR-link connecting Schiphol Amsterdam Airport with the German Ruhrgebiet. This working-paper presents a cost-benefit analysis of the construction of the railway section. The cost-benefit analysis (CBA) closely followed the guidelines for project evaluation that have been worked out by a number of economic research institutes within the OEEI project (CPB/NEI, 2000). The economic effects of this project appear to be rather small. This is due mainly to the limited savings in travel time. As a result, a new railway seems to be unprofitable in the circumstances analysed. The base-case, or no-build option, is preferable. In the base-case, many benefits can be reaped when high-speed rolling stock is used on conventional track.
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
157
F
NAME
Mr. Matthew Arndt Mr. Edward Calthrop Mr. Jos Carbajo Mr. Gerard Dalton Mr. Gunther Ellwanger(*) Mr. James A. C. Evans Mr. Christian Faure Ms. Kristina Geiger-Weichbrodt(*) Dr. Carl-Henrik Lundstrm(*) Ms. Susana Martins Ms. Catherine Prudhomme Ms. Sabine Simmross Ms. Maj Theander Dr. Mateu Turr (chairman) Ms. Ainhoa Zubieta(*)
(*)
Members who have contributed to RAILPAG but are not currently active
Many other people have contributed to the elaboration of this first phase of RAILPAG and to the publication of this book. The rapporteur wishes to express his gratitude, in particular to J. Dionisio Gonzlez Garca, Elizabeth McKell, Marc Bello, Daniel Cima and Manuel Fernndez Rivero. RAILPAG have also benefited from the advice of other transport economists under the management of Chris Hurst, Director for the Projects Infrastructure Department, and Jos Luis Alfaro, responsible for the appraisal of rail projects at the EIB.
158
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
RA I LPAG
R a i l w a y P r o j e c t A p p r a i s a l G u i d e l i n e s A n n e x e s
159
RAILPAG aim at providing a common framework for the appraisal of railway projects across the EU. These
guidelines have been prepared following an initiative of the European Investment Bank, with the support of the European Commission (DGTREN), international nancial institutions and key associations of the rail industry. They will be continuously updated through the website www.railpag.com.
European Commission