HTS Rotating Machines 050303
HTS Rotating Machines 050303
HTS Rotating Machines 050303
1 1
Contents
Enabling Technologies Applications
Magnets Power Cables FCL and Transformers Rotating Machines
Future
2 2
Enabling Technologies
Status of Wire: Superconductors
Discovered in 1911 Perfect conductors of electricity Require cryogenic cooling Low Temperature Superconductor (LTS) metallic wires used in MRI near 4 K New, ceramic HTS material discovered in 1986 HTS requires less cooling
operation at >77K at low field 30-40K in motor applications < 1/10 the energy required for 4K refrigeration
3 3
Enabling Technologies
Wire Architectures
Generation I Generation II
Bi2Sr2Ca1Cu2O 0.010
Y1Ba2Cu3O
0.16
Second Generation Goal: Form-Fit-Function replacement at same performance, with 2-5x lower cost
4 4
Enabling Technologies
1G HTS Wire Fabrication Process
Powder Production Sealing in Billet Deformation Deformation
Rolling
Heat Treatment
5 5
Enabling Technologies
Status of Wire: Generation I
c-axis
z
Performance ~ 15,000 A/cm2 (insert) Strain Tolerance > 0.2% (design for 0.015%) Field
Bi2223 Gen I
abr
abt
Fatigue Tolerant Temperature ~35K Other Factors - 100% tested Laminated Bi2223
Filaments Silver
Status
6 6
Enabling Technologies
Coated Conductor Fabrication Process
Substrate Production
Buffer Deposition
YBCO Formation
Enabling Technologies
Status of Wire: Future Developments
Generation II Wires can be manufactured by low cost processes Form Fit Function replacement for Generation I wire
Superconductor Coating Buffer Layer Alloy Substrate
8 8
Enabling Technologies
Leading in HTS Wire Manufacture
Worlds first commercial HTS wire plant
now in operation
77 K
5
70 K
64 K
50 K
35 K
20
20 K
35
2
50 64 70 77
0 0 0 .5 1 1 .5 2 2 .5
Enabling Technologies
Cooling the New Superconductors
COTS Refrigerators
Relative Cost of Cooling
LTS
0
HTS
20
Temperature, Kelvin Scale
40
60
80
Enabling Technologies
Refrigeration
High Capacity Single Stage GM Cooler
Cold Head
Winding operating temperature ~ 20-40K provides optimal cost/performance balance. Gifford McMahon cryocooler output at 30 K has improved by nearly a factor of 4 over the past 5 years. MTBF of similar GM coolers exceeds 9 years
Vacuum Flange
CryoMech
Cold Head
610mm
Compressor
Gas Lines To Cold Head 762mm
12 12
HTS Transformers
13 13
Waukesha/SuperPower Objectives
14 14
Other Programs
Other transformer programs are;
- CAS/TBEA (China) - BHEL (India) - Condumex (Mexico)
15 15
HTS Magnets
16 16
17 17
20 20
Environmental Compatibility
Underground Placement No Electromagnetic Field Thermally Independent of Environment Nitrogen Cooling Fluid (Inert) No Oil
AC High Capacity VLI Cables XLPE Cables AC CURRENT 1000A 2000A 3000A 4000A 5000A
22 22
Physical Characteristics
Length 610m HTS Conductor Length 128km Cold Dielectric Design
Hardware Deliverables
Three 610m long Phase Conductors Six 161kV Outdoor Terminations & Accessories One 161kV Splice One Refrigeration System + Pulse Tube System
Commissioning - 2005
Worlds First Installation of a Transmission Voltage HTS Cable in the World
23 23
24 24
25 25
138 kV
30 MVA 15 kV
IPP
Bus-tie FCL
FCL Assembly
CB
LIMITER
RT RESISTANCE
LIMITER
CABLE
CABLE
28 28
Test
1999
2000
2001
2002
2003
2004
Advantages: 2-4x reduced size/weight, 2x better efficiency, 2-4x higher reactive power, high overload, low noise
29 29
30 30
31 31
HTS in DC rotor field only Rotor is vacuum insulated Refrigeration in the stationary reference
frame
Cooler Module
Current Leads Vacuum chamber Multi-Layered Insulation
Copper Litz armature (>room temp) Low reactance due to large air-gap Removal of iron teeth plus ~zero rotor
I2R yields high efficiency
Housing
PM & Conventional
32 32
33 33
Stator Cooler 3%
High efficiency even at low loads with a very small refrigeration power
34 34
Industrial Motors
AMSC 5000hp, 1800-RPM Motor List of Parameters
The motor is 97.7% efficiency 1/3 reduction in volume compared to the industry standard 40% reduction in losses compared to the industry standard
List of parameters Motor output List of parameters Motor output 5000 hp (nominal, tested to 7,000 HP transient, and 5900 HP maximum steady state) 1800 rpm 4 6.6 kV 97.7 % 0.99 23.2 inches 8.8 Henry 156 Amps 0.10 Ohm 333 Amps -17.069 deg 0.32 pu 0.32 pu 0.27 pu 0.173 pu 0.173 pu 0.031 sec
Speed Pole number Line voltage Full load efficiency Operating power factor - leading Straight length of machine HTS field inductance HTS field current Stator resistance Stator current Load angle at full load D-axis synchronous reactance Q-axis synchronous reactance D-axis transient reactance D-axis subtransient reactance Q-axis subtransient reactance Stator short circuit time constant
37 37
Industrial Motors
KERI 100 HP Motor System
Photograph showing the 100hp HTS motor in the test bed. The cooling system with the G-M cryocooler is located in the right side.
KERI
Korea Electrotechnology Research Institute
38 38
39 39
36 MW HTS
500
400
300
A
200 CRYSTAL 100
al c tu
n ve on
op vel En r o ot lM na ti o
QE2
HTS Advantage
HTS Advantage
GRANDEUR HTS
HTS
0 0 20
Source: MSCL
0 0 10 20 30 40 50 60 70 80 90 100
40
60
80
100
Pow e r (MW )
Source: MSCL
Power (MW)
HTS motor volume advantages are impressive over a broad range of ratings
40 40
Helium Make-up
GM-1A GM-1B
Cooler Module
865 mm
GM-2A
GM-2B
Reliability with degraded mode capability is achieved through redundant components and design for maintenance
41 41
Coil Manufacture
Completed Stator
43 43
44 44
Full torque at speed Limited Structureborne Noise Data Operation on a Drive ONR Accepted motor shipped to CAPS on 22 July 2003
5 MW HTS Motor
45 45
Initial heat run conducted on September 19, 2004 Motor delivered 5 MW at 230 RPM Stator attained steady-state temperature
47 47
48 48
Hoeganaes, TN
51 51
Utility Applications
SuperVAR Prototype Project Description
Similar to a conventional synchronous machine but with better performance
Developed an 8 MVA prototype SuperVAR machine for testing on TVA grid TVA is partially supporting the prototype development TVA has ordered 5 production units subject to successful testing of the prototype - rated 10 MVA at 13.8kV
Rating Voltage Ambient Temp Losses 8 MVAR 13.8 kV line to line -30o to +40oC 1.5% rating at 8MVA Including 30kW 480V auxiliary power
Utility Applications
Major SuperVARTM Condenser Systems
Refrigeration Systems
25 feet
53 53
Utility Applications
Machine Performance on Grid
Machine has been installed on TVA grid in Hoeganaes, TN Was synchronized with the grid on 10 October 2004 - Verified VARS capability from 8 MVARS to + 8 MVARS Machine has been experiencing transients due to the arc furnace operations It is supplying various levels of MVARS to the system depending on the type of arc furnace burn cycle
7.00E+06
Output (VArs)
4.00E+06
3.00E+06
2.00E+06
1.00E+06
0.00E+00 2:31:12 PM
2:38:24 PM
2:45:36 PM
2:52:48 PM
3:00:00 PM
3:07:12 PM
3:14:24 PM
3:21:36 PM
3:28:48 PM
3:36:00 PM
3:43:12 PM
54 54
Time (Seconds)
Time (Seconds)
55 55
56 56
57 57
Cryogenic cooling system maintenance procedures are well established in MRI and high vacuum industries 58 58
Installation Considerations
Most electrical and mechanical interfaces are similar to conventional synchronous machines Installation is similar to conventional machines for the following components:
- Prime mover - Stator and stator cooling - Exciter
Stator Cooler Cryocooler Compressors
Mechanical Operation
Similar to conventional machines
Stator cooling is the same as conventional machines Bearings are conventional roller or sleeve type Cryocoolers employ cold heads and helium compressors Cryocooler maintenance and service procedures are well established in the industry Each compressor has a charcoal filter that is replaced at 2-year interval Cooler can be shutdown for short period of time without having to stop the machine Compressors are water cooled and require 5 liter/min water flow with inlet pressure of 2 bar at 5-25oC.
- Air-cooled compressors can also be specified
- Control field current in response to AVR or a command from the operator - Coil voltages and currents - Coil temperature - Current lead temperature Cryocooler temperature Compressor helium pressure and flow rates Compressor temperature Compressor cooling water temperature and flow rate
Future
62 62
63 63