DZS 387 3
DZS 387 3
DZS 387 3
i (h) i (h)
U U =
DZS 387-3: 2009
22
o
Harmonic order
1
1,4
2
< 5
5 to 10
> 10
The apportioned harmonic voltage distortion is given by the equation below (for MV loads).
Individual consumer voltage emission level:
t
i
U(h)HV MV h U U(h)i
) L (
_
S
S
T L E
) (
=
where
E
U(h)i
is the individual consumer maximum emission at the PPC;
T is the transformer ratio from HV to MV;
L
U(h)MV
is the enterprise MV planning level for harmonic voltage h;
L
U(h)HV
is the enterprise HV planning level for harmonic voltage h;
S
i
is the consumers maximum demand;
S
t
is the installed capacity.
The maximum current apportioned to the consumer is then given by dividing the allocated voltage
contribution by the specific network harmonic impedance at the point of common coupling (PCC).
Stage 3: Exceptional cases
Stage 3 acceptance of a load is based on considerations such as the presence of other local loads
that do not generate harmonics, and the fact that supply capacity might not be taken up for a long
time in the future. Subject to these considerations, higher harmonic levels can be allowed.
E.3 IEEE harmonic apportioning
The harmonic distortion limits at the point of common coupling in IEEE-519 are given in table
E.4.
Table E.4 IEEE voltage distortion levels
Bus voltage at PCC
kV
Individual voltage distortion
%
Total harmonic distortion
(THD)
%
s 69 3,0 5,0
> 69 s 161 1,5 2,5
> 161 1,0 1,5
For periods shorter than 1 h the limits in table E.4 may be exceeded by up to 50 %.
The IEEE standard specifies maximum current injection levels for loads connected to the various
voltage levels. These are given in table E.5.
DZS 387-3: 2009
23
Table E.5 IEEE current distortion limits (120 V to 69 kV)
Maximum harmonic current distortion as a percentage of I
L
Odd harmonics (even harmonics limited to 25 % of those below)
I
SC
/I
L
11 11 to 17 17 to 23 23 to 35 35 TDD
< 20
20 < 50
50 < 100
100 < 1000
> 1000
4,0
7,0
10,0
12,0
15,0
2,0
3,5
4,5
5,5
7,0
1,5
2,5
4,0
5,0
6,0
0,6
1,0
1,5
2,0
2,5
0,3
0,5
0,7
1,0
1,4
5,0
8,0
12,0
15,0
20,0
Where
I
SC
is the maximum short circuit current at PCC;
I
L
is the maximum demand (MD) load current at PCC (averaged MD over 12 months).
Table E.6 IEEE current distortion limits ( 69 kV to 161kV)
Maximum harmonic current distortion as a percentage of I
L
Odd harmonics (even harmonics limited to 25 % of those below)
I
SC
/I
L
11 11 to 17 17 to 23 23 to 35 35 TDD
< 20
20 < 50
50 < 100
100 < 1000
> 1000
2,0
3,5
5,0
6,0
7,5
1,0
1,75
2,25
2,75
3,5
0,75
1,25
2,0
2,5
3,0
0,3
0,5
0,75
1,0
1,25
0,15
0,25
0,35
0,5
0,7
2,5
4,0
6,0
7,5
10,0
Where
I
SC
is the maximum short circuit current at PCC;
I
L
is the maximum demand (MD) load current at PCC (averaged MD over 12 months).
Table E.7 IEEE current distortion limits ( 161kV)
Maximum harmonic current distortion as a percentage of I
L
Odd harmonics (even harmonics limited to 25 % of those below)
I
SC
/I
L
11 11 to 17 17 to 23 23 to 35 35 TDD
< 50
> 50
2,0
3,0
1,0
1,5
0,75
1,15
0,30
0,45
0,15
0,22
2,50
3,75
Where
I
SC
is the maximum short circuit current at PCC;
I
L
is the maximum demand (MD) load current at PCC (averaged MD over 12 months).
All load sizes are catered for by the above tables, and therefore a staged approach is not adopted.
It should be noted that the tables have been calculated assuming a linear network impedance (i.e.
resonance conditions due to line and cable capacitances, or shunt capacitors are not taken into
consideration).
E.4 Common features and differences
The common features and differences between the IEC and the IEEE standards are summarized
below.
DZS 387-3: 2009
24
E.4.1 Common features
The common features are:
a) point of common coupling;
b) current emission levels;
c) worst case normal operating network impedance (IEEE = 1 h); and
d) compatibility cannot be guaranteed.
E.4.2 Differences
The differences are:
a) harmonic percentage levels;
b) IEC planning levels;
c) IEC staged approach;
d) IEEE linear impedance vs. IEC actual impedance;
e) IEC actual upstream distortion; and
f) IEC installed capacity vs IEEE short circuit ratio.
DZS 387-3: 2009
25
ANNEX F
(informative)
A METHODOLOGY FOR ASSESSING CONTRACTUAL EMISSION LEVELS
BASED ON THE IEC APPORTIONING PROCEDURES
F.1 OVERVIEW
Not all loads are large enough to have a significant impact on the voltage distortion levels. For
this reason a staged approach is used to differentiate the complexity of the studies to be undertaken
when calculating emission levels. This staged approach and the contractual implications are
described in this annex.
The criteria used to determine which stage categorization (stage 1, stage 2 or stage 3) a consumer
qualifies for are set out in table F.1.
Table F.1 Consumer categorization
Stage PCC voltage Load maximum
demand
Load maximum
demand as a percentage
of mini-mum designed
opera-ting three-phase
PCC fault level
Method of acceptance
1 < 132 kV < 25 MVA** < 1 % Accept
2 < 132 kV < 25 MVA** > 1 % Apportion
3 > 132 kV > 25 MVA Special analysis
NOTE. Care should be taken where capacitors or underground cables are involved.
The concept of risk allocation also needs to be considered in stage 3. This is illustrated in figure
F.1.
}
}
}
Normal STAGE 2 flicker allocation
Concession based on technical
motivation and no additional risk
(e.g. other large customers do not
generate flicker)
Concession with risk transferred to customer
STAGE 3
STAGE 2
Figure F.1 Risk allocation under stage 3
Figure F.2 indicates the type of contractual clauses that specify the emission levels.
Stage 3: Specific contractual limits are specified. These may be time-graded or linked to specific
network conditions. Two possible stage 3 limits can be developed:
DZS 387-3: 2009
26
a) technically justifiable limits (i.e. where it can be shown that higher emission levels can be
allowed because of specific local network conditions. The risk of exceeding the planning
levels shall be shown to be low, and the fair allocation of emission to other consumers
should not be negatively impacted).
b) concessionary limits (i.e. higher limits which have the risk of exceeding the planning
levels in the short or long term). In this case the enterprise shall stipulate under what
conditions the emission levels will be allowed. The consumer shall table procedures to
reduce emission levels in the event of these conditions occurring. In this case the risk is
transferred contractually to the consumer.
STAGE 2
STAGE 3
Standard
contractual
clauses
Load too small to
impact PCC levels
Specific
contractual limits
Load emission evaluated
w.r.t. total emission from
other loads
START
Specific
contractual limits
and specified
conditions
Load emission evaluated
w.r.t. total emission from
other loads and specific
local conditions
(special study)
(standard tables)
(standard procedure)
Design mitigation
strategy to reduce load
emission or network
sensitivity
(special study)
exceeds
Stage 1
exceeds
Stage 2
exceeds
Stage 3
STAGE 1
Figure F.2 Load emission evaluation procedure
In figure F.2 exceeds implies that the consumer emissions will exceed those allowed or that the
consumer defaults to the next stage because of size and voltage connection.
For the contract negotiations with any new consumer or evaluation of an existing consumer, the
above three stages of acceptance should be followed as set out in F.2.1 to F.2.3.
F.2 ACCEPTANCE CRITERIA
F.2.1 Acceptance dependent on the network minimum designed operating three-phase fault level stage
1 assessment
A load connected at a voltage of less than 132 kV and less than 25 MVA in rating, may
immediately be connected to a PCC if the maximum designed loading is less than 1 % of the
minimum designed operating three-phase PCC fault level.
The apportioned emission limits for flicker, unbalance and voltage harmonics are given in table
F.2.
DZS 387-3: 2009
27
Table F.2 Standard apportionment for stage 1
assessment
Power quality and reliability
parameter
Apportionment
Short term flicker P
st
= 0,35 minimum
Voltage unbalance 0.5%
Voltage total harmonic distortion 1%
The rapid voltage change emission limits are given in table F.3.
Table F.3 Rapid Voltage Change Emission Limits
Number of changes per
hour
U
dyn
/U
n
(%)
(see note)
r MV/LV HV
r < 1 4.00 3.0
1 < r s 10 3.00 2.5
10 < r s 100 2.00 1.5
100 < r s 1000 1.25 1.0
NOTE Where
AU
dyn
is as defined in F.3.3.1; and
U
n
is the actual r.m.s. voltage.
F.2.2 Acceptance as per prescribed proportioning guideline stage 2 assessment
For loads exceeding 1 % of the minimum designed operating three-phase PCC fault level, rated
below 25 MVA and connected at a voltage below 132 kV, the different PQR compatibility levels
will be apportioned based on the ratio of the load rating and installed capacity under the minimum
designed operating three-phase PCC fault level, according to a fixed procedure as given in F.3.
F.2.3 Acceptance per detailed special impact assessment stage 3 assessment
For large, single, distorting loads such as arc-furnaces, traction, static var compensators, mine
winders, etc., or loads connected at a voltage of 132 kV and above or loads larger than 25 MVA in
rating, a fixed procedure would not be sufficient to ensure compatibility with the network. Each
such installation should be planned and designed individually on a case-by-case basis for both the
enterprise and the consumer.
For example, detailed studies are undertaken to investigate the effects of allocating larger flicker
emission levels to the consumer. Where such larger allocations are made, the contract will specify
the conditions under which these higher levels are allowed. Typical conditions that might exist in
the contracts include the absence of consumer complaints, reduction of emission levels under
certain network or generation contingencies, and the availability of existing compensators or
filters.
The implication is that the consumer needs to balance the cost of achieving the allocated levels,
and the risk of the conditions in the contract not being met.
F.3 APPORTIONING PROCEDURE
F.3.1 Harmonics
DZS 387-3: 2009
28
F.3.1.1 Harmonics Stage 2 assessment
It is not a simple process to determine what the effect of upstream voltage distortion is at a specific
PCC without switching off all the loads at the PCC. A general equation is defined, based on
thorough experimental measurements, for the summation of harmonics or reduction of
compatibility levels at a specific busbar due to upstream harmonics:
| |
a
1
us h
a
pcc h
a
(new) pcc h
0,7
_
, ,
,
V V V = (F1)
where
V
h,pcc(new)
is the new percentage voltage planning level of harmonic number h at the PCC;
V
h,pcc
is the percentage voltage planning level of harmonic number h at the PCC;
V
h,us
is the percentage upstream harmonic voltage of number h at the PCC;
a is 1 for harmonics 3, 5, 7;
a is 1,4 for harmonics 11, 13;
a is 2 for harmonics > 13 and other than mentioned above.
This equation therefore gives a method for reducing the set compatibility levels at the PCC due to
upstream harmonics. Where upstream harmonics are totally stochastic (i.e. no coincidence) as
commonly found in large transmission networks with no direct consumers, a value of a = 2 is
typically used in all cases.
Where the upstream levels are so excessive that the PCC limit is reduced by more than 50 %, then
stage 3 assessment is required.
This available distortion shall now be distributed fairly amongst all new consumers to be
connected at the PCC. The only applicable parameters known when connecting a new consumer
or evaluating an existing one at the PCC are the installed capacity at minimum designed operating
3 phase fault level (MVAi) and the consumer notified maximum demand (MVA
md
). Using these
parameters for proportional allocation at the PCC the following equation is used:
a
1
i
md
pc(new) h, p h,
MVA
MVA
(
= V V (F2)
where
V
h,p
is the maximum percentage proportional voltage of harmonic number h for the
new consumer;
V
h,pcc(new)
is the percentage voltage planning level of harmonic number h at the
PCC;
a is as previously described (see F.3.1.1).
DZS 387-3: 2009
29
This equation allows for a fair distribution of allowable harmonic voltage distortion by all
connected consumers at the PCC. It also makes provision for the connection of future prospective
clients, ensuring that the total allowable distortion capabilities of the PCC be used to their full
capacity once all consumers are connected. The minimum value accepted will be 0.1 % even if
lower values are calculated.
Where the addition of a new apportioned consumer (as above) causes the busbar compatibility
level to be exceeded, for instance, due to existing consumers connected in the past without
sufficient limitations on their allowable pollution levels, the enterprise will be responsible for
ensuring proper network compatibility, taking cognizance of the fact that the supply impedance is
highly non-linear under resonance conditions.
To obtain the proportioned harmonic current injection by the specific consumer, the following
equation can be used assuming a linear supply impedance:
h X
V
I
,
sup
p h,
p h
= (F3)
where
I
h,p
is the allowable apportioned harmonic current injection of the specific
consumer;
h is the harmonic number;
V
h,p
is the percentage upstream harmonic harmonic voltage;
X
sup
is the 50 Hz minimum designed operating three-phase fault level supply
impedance as calculated below:
fl
2
line
sup
MVA
V
X = (F4)
where
V
line
is the PCC line voltage in volts and MVA
fl
the minimum designed operating
three-phase fault level.
This equation therefore allows calculation of the proportional distortion current injection allowed
by each consumer connected at the PCC, assuming a linear supply impedance. It shall, however,
be emphasized that whenever capacitor banks or long underground cables are present on either
side of the supply transformer, great care should be taken in applying the above equations, as
possible resonant conditions can exist at characteristic harmonic frequencies which would cause
the supply impedance to be extremely non-linear at that frequency.
NOTE. The harmonic number at which a capacitor bank is in resonance with the supply (series or parallel) is
approximately given by:
cap
sc
Mvar
MVA
~ h (F5)
DZS 387-3: 2009
30
with MVA
sc
being the different network three-phase operating fault levels and Mvar
cap
the
capacitor bank three-phase rating.
If this frequency is close to frequencies of existing harmonics or harmonics of the proposed
installation, specialist analysis is required, rather than a simplistic approach. The above equations
may, however, be used to give an indication of proportional projection but an in-depth system
impact study would be required to ensure proper operation.
Where the specific nature of distorting loads is known, the above proportioning can be relaxed
under some circumstances by dividing I
h,p
by the factor in the table F.4 below. The resulting
current can be used in supply contracts.
Table F.4 Diversity factors
Type and operating conditions of multiple harmonic generators Typical
diversity
factors
Controlled or uncontrolled converters when a single converter provides 60 % or more of
the arithmetic total of the harmonic currents of all the equipment in the installation
1,00
Uncontrolled converters (rectifiers) 0,90
Controlled converters operating on co-ordinated duty cycles (fair probability of
coincidence)
0,75
Controlled converters operating independently with unco-ordinated duty cycles (low
probability of coincidence)
(a) s 3 converters
(b) > 4 converters
0,60
0,50
A single arc-furnace providing more than 60 % of the arithmetic total harmonic current of
the installation
1,00
Multiple arc-furnaces each providing less than 60 % of the arithmetic total harmonic
current of the installation
0,75
F.3.1.2 Harmonics Stage 3 assessment
In the case where
a) the consumer supply voltage is greater than 132 kV and equal to 132 kV, or
b) the size of the consumer load is bigger than 25 MVA, or
c) long cables or capacitor banks are absent from either side of the supply transformer,
a linear supply impedance can no longer be assumed.
From the actual system impedance that is obtained by system simulation studies, the current
injection levels are calculated by:
h
p h,
p h,
X
V
I = (F6)
where
I
h,p
is the allowable apportioned harmonic current of number h at the PCC (in
amperes);
DZS 387-3: 2009
31
V
h,p
is the percentage harmonic voltage emission of number h at the PCC allocated to
the new consumer (in volts);
X
h
is the maximum supply impedance of number h at the PCC for any normal
operating condition (in ohms).
The maximum supply impedance of number h at the PCC for any normal operating condition,
such as a line out of service, is determine by system simulations at all the applicable harmonic
orders. A set of curves is produced for various normal operation conditions. From this set of
curves the highest impedance value for each harmonic order is selected.
Figure F.3 shows an example of a network harmonic impedance simulation.
Figure F.3 Example of a harmonic impedance plot
F.3.2 Unbalance
The emission levels B
A
for a specific consumer are calculated using the following equation:
2
installed
MD
2
2
background
2
limit A
A
_
S
S
UB UB B = (F7)
where
UB
limit
is the planning limit;
UB
background
is the existing background unbalance level in the supply network;
S
MD
is the consumer notified maximum demand in MVA;
S
installed
is the installed capacity of the network in MVA.
0
20
40
60
80
100
120
140
160
1 3 5 7 9 11 13 15 17 19 21 23 25
Harmonic number
Simulation 1
Simulation 2
Simulation 3
linear impedance
DZS 387-3: 2009
32
F.3.3 Flicker
F.3.3.1 Rapid voltage changes
Although no minimum standards for limiting rapid voltage changes are given in ZS 387-1, the
concept is introduced in this part of ZS 387 because the flicker emission requirements for
consumers do not sufficiently limit the possible larger changes in voltage magnitude at lower rates
of change. In order to introduce limits on large rapid voltage changes emission limits can be
introduced at the PCC.
Figure F.4 shows the definition of a rapid voltage change.
AU
dyn
AU
c
r.m.s. voltage
Time
Figure F.4 Definition of a rapid voltage change
NOTE. A decrease in voltage is illustrated. The voltage could also increase as a result of a rapid voltage change.
where
AU
c
is the steady state r.m.s. voltage change;
AU
dyn
is the dynamic r.m.s. voltage change.
The r.m.s. voltages are calculated using a 20 ms window and sliding this 20 ms window at 10 ms
intervals.
The emission limits for rapid voltage changes are given in table F.3.
Flicker is typically caused by a.c. arc-furnaces or welding equipment that are remotely connected,
i.e. one arc-furnace consumer per specific PCC.
For a.c. arc-furnace operation, P
st
is linear with respect to the magnitude of the voltage depressions
giving rise to it.
The summation of flicker from independent sources is as follows:
3
1
3
new st
3
background st tot st
) ( P P P + = (F8)
where
P
st
background
is the existing flicker at the PCC;
DZS 387-3: 2009
33
P
st
new
is the new furnace predicted flicker.
Where existing remotely connected consumers are in dispute over their proportional contributions
at a specific PCC, the following equation can be used to determine the contribution using fault
levels at the respective PCCs, for example, the effect of a furnace at B on the PCC where furnace
A is connected, as shown in figure F.5.
A from B B from A
Fault Level A Fault Level B
Furnace A Furnace B
Figure F.5 Example of interconnected PCCs
(
(
=
AfromB A
BfromA
B st cont st
FI
_
FL
FI
P P (F9)
where
P
st
cont
is the contribution of furnace B at A;
P
st
B
is the effect of furnace B acting alone at PCC B;
P
st
A
is the effect of furnace A acting alone at PCC A;
FI
BfromA
is the three-phase fault level infeed at B from A;
FL
A
is the three-phase fault level at A;
FI
AfromB
is the three-phase fault level infeed at A from B.
This equation will provide the apportioned flicker (P
st
) contribution of furnace B at PCC A. P
st
A
and P
st
cont
can then be summated as given in equation F8 to determine the total PCC Pst.
DZS 387-3: 2009
34
F.3.3.2 Flicker Stage 2 assessment
The emission levels P
st
A
for a specific consumer are calculated using the following equation:
3
installed
MDA
3
3
background st
3
limit t s A st
_
S
S
P P P = (F10)
where
P
st
A
is the effect of furnace A acting alone at PCC A;
P
st
limit
is the planning limit;
P
st
background
is the existing background flicker level in the supply network;
S
MDA
is
the consumer notified maximum demand in MVA;
S
installed
is the installed capacity of the network in MVA.
The minimum short-term flicker level apportioned to any individual MV or HV consumer is
P
st
95 (daily) = 0,35.
F.3.3.3 Flicker Stage 3 assessment
F.3.3.3.1 The following technically justifiable considerations exist:
a) for EHV and HV networks where it can be shown that the HV/LV attenuation ratio
HV st
LV st
LV/HV
(
P
P
R = ) is smaller than 1,0, the HV planning level can be increased to
(
LV/HV
limit st
0,8
R
P = ) with a maximum planning level of 1,0; and
where
R
LV/HV
is the HV/LV attenuation ratio;
P
st
LV
is the short term flicker level on the LV network;
P
st
HV
is the short term flicker level on the HV network;
P
st
limit
is the maximum value for the HV planning level for short term flicker.
b) where a consumer contributes directly to the cost of increasing the fault level of the
network, for example, by the installation of a new line which is only built for the purpose
of reducing flicker levels and increasing supply reliability. In this case the installed
capacity does not change in equation F10. The flicker emission level stays the same, but
is related to a higher fault level. If the enterprise in future uses this line for further load
growth, the additional loads might not substantially contribute to the flicker levels. In this
case the consumer has already paid for the right to the flicker capacity.
DZS 387-3: 2009
35
F.3.3.3.2 The following concessionary considerations exist:
a) where a large consumer (B) with low flicker emission levels exists at the PCC (and the probability
of this consumer becoming a flicker-producer is low), the flicker allocation of the consumer can be
distributed across the other consumers on a basis of:
3
installed
MDB MDA
3
3
background st
3
limit st A st
_
S
S S
P P P
+
= (F11)
where
P
st
A
is the short term flicker allocation for consumer A;
P
st
limit
is the short term flicker planning limit;
P
st
background
is the background short term flicker level in the supply network;
S
MDA
is the notified maximum demand of consumer A in MVA;
S
MDB
is the notified maximum demand of consumer B in MVA;
S
installed
is the installed capacity of the network in MVA.
b) where it can be shown that the attenuation ratio ) (
HV st
LV st
LV/HV
P
P
R = is smaller than 0.8, a higher
planning level than 1,0 may be considered. The risk of new MV and LV networks being
established with higher attenuation ratios shall be transferred to the consumer;
c) where a known long-term risk exists of a power station being closed, the consumer may be
allowed emission levels based on the higher fault levels with the power station in operation. The
risk of the closure of the station shall be transferred to the consumer; and
d) at the initial stage of furnace commissioning, problems might be experienced with the furnace or
the SVC compensator, or the type of product that initially needs to be processed results in higher
flicker emission levels than later normal operation. Where network conditions allow, the
consumer may be allocated higher flicker levels for a specific period of type, for example, 6
months after start-up.