This process offers benefits to the entire project team, ranging from focused planning and improved communication, to on-time successful completion and fewer callbacks. By Rebecca T. Ellis, P.E., LEED AP, CCP, CxA
ver the past century, and particularly over the past 25 years, many facilities design innovations have been implemented in order to enhance performance, protect occupant health and safety, reduce operating costs, and minimize negative impact on the environment. These innovations have led to increasingly complex or, at least, unusual building systems. How does one know that all of the complex features are working and/or are prepared to work when called upon after con-
struction is complete? Traditional design and construction industry processes have not kept pace with the evolving systems the industry is expected to deliver. Business-as-usual has been focused on equipment its selection and sizing (design), and its installation and startup (construction) with little or no attention being paid to how the individual pieces of equipment function together as systems. It is no longer the case that, just because every component is installed and energized, you have a proper-
ly functioning building system. The introduction of computerized controls and networked communication between components has resulted in a critical system element, which cannot be observed through a traditional site observation or punchlist process. Building systems commissioning is a process that has been developed to integrate into and fill this void in the traditional design and construction process. Commissioning is a systematic process of ensuring that building systems are designed, installed, integrated,
www.pmengineer.com
PMEngineer 41
ommissioning Act
ivities
Performance Requirements
Design Reviews
Q&M Planning
Commissioning Specication
Finish and tested to perform according to the design intent and the building owners operational needs. It is a process that enhances the quality assurance of a building project and requires an extended project team effort to realize the full benefits. construction and prior to owner occupancy. The following are some of the fundamental elements of commissioning in project chronological order: Prepare Commissioning Plan; Define owners systems performance acceptance criteria; Review design documents for compliance with acceptance criteria; Prepare commissioning specification section for bidding documents; Review shop drawings and equipment submittals for compliance with acceptance criteria; Observe installation for future maintenance and operations accessibility issues; Verify that equipment is installed and started per manufacturers recommendations; Provide appropriate time in the construction schedule for coordinating and executing system level activities such as air and water testing and balancing, controls programming and checkout, and inter-system communications; Verify functional performance of the systems and integrated systems to confirm final compliance with the acceptance criteria; Train owners staff in equipment maintenance and systems operation; Provide system-level operations documentation for future reference and training of owners staff; and Develop Re-Commissioning and/ or On-Going Commissioning plans for the owners execution throughout the life of the facility.
What is Commissioning?
Commissioning begins with the development of a project-specific Commissioning Plan. The Commissioning Plan is the roadmap for the commissioning process through pre-design, design, construction and occupancy of the facility. It lays out the roles and responsibilities for each team member during the various phases of the project, identifies the systems to be commissioned, and defines the level of rigor for each system. It establishes expectations early so there are no surprises later in the project for any team member. The commissioning process is facilitated by a Commissioning Professional (also known as a Commissioning Authority or Commissioning Agent). However, commissioning is a team sport and a primary role of the Commissioning Professional is that of a coach. The team is comprehensive and includes the owners project and operations staff, the design team and construction team. Very simply, commissioning helps the project team understand the owners performance goals and is a step-bystep process for successfully achieving and verifying those goals at the end of
42 PMEngineer
November 2008
issioning Activities
Commissioning Plan
Performance Requirements
Design Reviews
Commissioning Specication
Finish
were rarely selected for the rigors of the commissioning process. That is because most traditional plumbing systems dont score high on the previously noted five-question criteria test: 1. Where have problems consistently occurred on past projects? Sure, there have been plumbing system failures and/or malfunctions in new buildings, but the plumbing systems are not what keep owners up at night worrying about whether or not they will function when a project is complete. 2. What are the risks of system malfunction after occupancy/beneficial use? Probably the biggest plumbing system risk in a new building is a pipe failure or leak that could cause serious collateral damage to the building. Again, this has occurred in the past, but it is not common. Because it is such a big risk, the traditional project delivery process includes pressure testing all piping; and that, for the most part, helps to mitigate most potential problems. 3. What are the political implications of poor system performance? This is a criterion that may qualify typical plumbing systems for commissioning in some building types. For example, in a public sports arena, what would be the result of a systemic problem with toilet operation? In a private fitness center, what would be the result of a lack of hot water or timely hot water delivery? 4. How easily would deficiencies be found without commissioning? Other than an insidious hidden leak, most plumbing system deficiencies become evident very quickly as people find automatic faucets and flushes that dont work; low water pressure; insufficient hot water; etc. A building owner does not need to pay a professional to
search out and find these types of deficiencies. 5. How many parties are involved in design and construction of a single system? With the exception of a few electrical connections, plumbing systems have historically been the responsibility of a single subcontractor. If there are problems with plumbing, there has not been much discussion about who is responsible for correcting them. The above questions historically resulted in building owners choosing to commission only the following plumbing systems, if they chose to commission plumbing at all: Domestic water heaters and recirculation pumps; Sump pumps; and Sewage ejector pumps.
missioning Activiti
es
Prefunctional Checklists
Commissioning Report
Finish rently being designed and installed in buildings. These include, but are not limited to: Rain water collection and use for flushing toilets, irrigation, and other non-potable applications; Gray water collection for flushing toilets, irrigation, and other non-potable applications; Solar water domestic water heating; Waste energy recovery for domestic water preheat; e.g., transferring heat from chiller condensers, boiler blowdown, boiler exhaust stacks, etc.; Irrigation system flow and pressure monitors; Sub-metering water consumption; Time-of-day scheduling of domestic water distribution; and Composting toilets. Each of the above systems, partially because of their unique nature and partially because of their inherent controls complexity, are excellent candidates for the commissioning process.
in which the entire project team can successfully achieve their operational, schedule, and budget goals. However, the greatest value from commissioning accrues to the facility owner through focused planning, documentation, and training for the on-going operation and maintenance of the new systems. The project team benefits from improved communication and coordination, on-time successful completion and turnover of the building to the owner, and far fewer callbacks after project completion. The owner receives a building that works at the time of occupancy, while the designers and contractors have a satisfied customer and a more profitable project. The owners facilities team takes over a building that they understand and in which they have confidence. They are also given the tools to successfully serve their customers the building occupants. Rebecca T. Ellis, P.E., LEED AP, CCP, CxA, is president of Questions & Solutions Engineering, Inc., located in Chaska, MN. Contact her at [email protected].
Summary
Commissioning offers a substantial benefit to the design and construction project by providing a framework
Codes
J U L I U S B A L L A N C O, P. E . , C P D
C i d from page 15 Continued f When you cannot come up with a technical reason for objecting to a code change, a testifier will normally say, We have had problems with the system. However, they are very careful to never tell you what those problems are. Typically, because they dont exist. As for separate primary and secondary systems, inspectors had nothing to do with these changes. The concept of separating the primary and secondary storm drainage was championed by the structural engineers to reduce the potential for roof collapse. However, ASPE worked with all stakeholders to develop a design that would provide sizing for both the primary and secondary roof drainage for any combined storm drain. The concept accounts for a hurricane factor where the system may need capacity for both primary and secondary. It was also pointed out that, prior to 1993, second46 PMEngineer
November 2008
ary drainage was not required by the code. All secondary drainage systems (many combined with primary) were voluntary systems added by the plumbing engineers. None of this mattered the pontificating carried the day. The code change was disapproved. I could tell that many in attendance were not pleased with the outcome of the hearings. But, the IPC and ICC process will live for another day. Like the Cubs, wait until next year, or in this case the 2012 International Plumbing Code. Julius Ballanco, P.E., CPD, is Editorial Director of PM Engineer and president of J.B. Engineering and Code Consulting, P.C. in Munster, IN. Ballanco is the current president of ASPE and a member of both ICC and the IAPMO. He can be reached by e-mail at [email protected].