Sample Schedule (5 Storey)
Sample Schedule (5 Storey)
Sample Schedule (5 Storey)
Activity Name
Original Duration 1 2 3 4 5 6 7 8 9 10 11 12 13
Month 14
15
16
17
18
19
20
21
22
23
24
25
26
27
GENERAL WO WORKS
MOBILIZATION AN D P REPERATORY WORKS
PRE-0010 PRE-0020 PRE-0030 PRE-0040 PRE-0050 PRE-0060 Mobilization Installation of Temp. Site O ffices and Facilities Pre-Construction Survey and Site Setting Out Geotechnical Soil Investigation Demolish Existing Building and Site Clearance Install Tower Cranes 62 55 5 18 31 27 Mobilization Installation of Temp. Site O ffices and Facilities Pre-Construction Survey and Site Setting Out Geotechnical Soil Investigation Demolish Existing Building and Site Clearance Install Tower Cranes
CONSTRUCTION CONSTRUCTIO
STRUCTURAL WORKS
SUB-0000 SUB-0005 Start Structural Works Finish Structural Works 0 0 Start Structural Works Finish Structural Works
SUBSTRUCTURE SUBSTRUCTU
PILING WORKS WOR SUB-0010 Exacavate to Platform Level for Bored Piling Operation SUB-0015 SUB-0020 SUB-0030 SUB-0040 SUB-0050 SUB-0060 SUB-0070 SUB-0080 Mobilization of Drilling Rigs (by Sub-Contractor. Bored Piling Operation and Pile Test Excavate up to Bottom of Pile Caps Trimming and Treatment of Pile Heads Fill/Compact Working Platform for Secant Piling Operation Secant Pile Retaining Walls Construct Capping Beam for Secant Pile Retaining Walls Parking Area - Install Suitable De-watering System (If Required) 12 12 60 30 30 12 40 40 16 Exacavate to Platform Level for Bored Piling Operation Mobilization of Drilling Rigs (by Sub-Contractor. Bored Piling Operation and Pile Test Excavate up to Bottom of Pile Caps Trimming and Treatment of Pile Heads Fill/Compact Working Platform for Secant Piling Operation Secant Pile Retaining Walls Construct Capping Beam for Secant Pile Retaining Walls Parking Area - Install Suitable De-watering System (If Required)
CAR PARKING AREA - BASEMENT 2 SUB-1010 Excavation Inside Cofferdam SUB-1020 SUB-1030 SUB-1040 SUB-1050 SUB-1051 SUB-1052 SUB-1053 SUB-1054 SUB-1060 SUB-1070 SUB-1080 Spray Gunite on Secant Pile Retaining Wall Surfaces Blinding and Waterproofing under Base Slab Water proofing on Retainin g Walls Construct Base Slab Construct Base Slab (Part 1) Construct Base Slab (Part 2) Construct Base Slab (Part 3) Construct Base Slab (Part 4) Construct Perimeter Walls, Inter nal Walls and Columns Construct Water Tank Walls and Columns (1st Lift) Construct Water Tank Walls and Columns (2nd Lift)
26 20 12 16 20 7 7 7 7 20 10 12
Excavation Inside Cofferdam Spray Gunite on Secant Pile Retaining Wall Surfaces Blinding and Waterproofing under Base Slab Water proofing on Retaining Walls Construct Base Slab Construct Base Slab (Part 1) Construct Base Slab (Part 2) Construct Base Slab (Part 3) Construct Base Slab (Part 4) Construct Perimeter Walls, Inter nal Walls and Columns Construct Water Tank Walls and Columns (1st Lift) Construct Water Tank Walls and Columns (2nd Lift)
Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone
Critical Milestone
AMAH-1
Revision
Checked
Approved
Activity ID
Activity Name
Month 14
15
16
17
18
19
20
21
22
23
24
25
26
27
Construct Beams and Deck Slab @ -2.55 Level Construct Beams and Deck Slab @ -2.55 Level (Part 1) Construct Beams and Deck Slab @ -2.55 Level (Part 2) Construct Stairways and Ramp (from -5.55 to -2.55 Level)
Construct Beams and Deck Slab @ -2.55 Level (Part 1) Construct Beams and Deck Slab @ -2.55 Level (Part 2) Construct Stairways and Ramp (from -5.55 to -2.55 Level) Water proofing on Retainin g Walls Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.55 Level Construct Beams and Deck Slab @ +0.55 Level (Part 1) Construct Beams and Deck Slab @ +0.55 Level (Part 2) Construct Water Tank Roof Slab @ +0.55 Level Construct Stairways and Ramp (from -2.55 to +0.55 Level) Water Pr oofing to Water Tank External and Internal Surfaces Backfilling & Compaction Around Parking Aea to Finish Level Blinding and Waterproofing under Pile Caps Construct Pile Caps Water Pr oofing at the Sid es of Pile Caps Backfilling upto Bottom of Floor Slab Blinding and Waterproofing under F loor Slab Construct Basement Floor Slab Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.60 F.F.L. Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) Water Pr oofin g at External Surfaces of Perimeter Walls Backfilling & Compaction Around Basement Floor to Finish Level Construct Stairways and Ramp (from -3.25 to +0.60 Level)
CAR PARKING AREA - BASEMENT 1 SUB-2010 Water proofing on Retainin g Walls SUB-2020 SUB-2030 SUB-2031 SUB-2032 SUB-2040 SUB-2050 SUB-2060 SUB-2070 Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.55 Level Construct Beams and Deck Slab @ +0.55 Level (Part 1) Construct Beams and Deck Slab @ +0.55 Level (Part 2) Construct Water Tank Roof Slab @ +0.55 Level Construct Stairways and Ramp (from -2.55 to +0.55 Level) Water Pr oofin g to Water Tank External and Internal Surfaces Backfilling & Compaction Around Parking Aea to Finish Level
MAIN BUILDI BUILDING - BASEMENT FLOOR SUB-3010 Blinding and Waterproofing under Pile Caps SUB-3020 SUB-3030 SUB-3040 SUB-3050 SUB-3060 SUB-3070 SUB-3080 SUB-3081 SUB-3082 SUB-3083 SUB-3090 SUB-3100 SUB-3110 Construct Pile Caps Water Pr oofin g at the Sides of Pile Caps Backfilling upto Bottom of Floor Slab Blinding and Waterproofing under F loor Slab Construct Basement Floor Slab Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.60 F.F.L. Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) Water Pr oofin g at External Surfaces of Perimeter Walls Backfilling & Compaction Around Basement Floor to Finish Level Construct Stairways and Ramp (from -3.25 to +0.60 Level)
SUPERSTRUCTURE SUPERSTRUC
CAR PARKING AREA - GROUND FLOOR SUP-0010 Construct Lift Shaft, Pump Room and Medical Gas Room SUP-0020 SUP-0030 SUP-0040 Construct Columns at Service Block Area Construct Roof Slab at Sevice Block Area Construct Roof Parapet Wall s at Sevice Block Area 30 12 18 10 18 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 18 Construct Lift Shaft, Pump Room and Medical Gas Room Construct Columns at Service Block Area Construct Roof Slab at Sevice Block Area Construct Roof Parapet Wall s at Sevice Block Area Construct Internal Walls and Columns Construct Beams and Deck Slab @ +5.40 Level Construct Beams and Deck Slab @ +5.40 Level (Part 1) Construct Beams and Deck Slab @ +5.40 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +9.60 Level Construct Beams and Deck Slab @ +9.60 Level (Part 1) Construct Beams and Deck Slab @ +9.60 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +13.80 Level Construct Beams and Deck Slab @ +13.80 Level (Part 1) Construct Beams and Deck Slab @ +13.80 Level (Part 2) Construct Beams and Deck Slab @ +13.80 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +18.00 Level Construct Beams and Deck Slab @ +18.00 Level (Part 1) Construct Beams and Deck Slab @ +18.00 Level (Part 2) Construct Beams and Deck Slab @ +18.00 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +22.20 Level Construct Beams and Deck Slab @ +22.20 Level (Part 1) Construct Beams and Deck Slab @ +22.20 Level (Part 2) Construct Beams and Deck Slab @ +22.20 Level (Part 3) Construct Stairways Construct Internal Walls and Columns
MAIN BUILDI BUILDING - GROUND FLOOR SUP-1010 Construct Internal Walls and Columns SUP-1020 SUP-1021 SUP-1022 SUP-1023 SUP-1030 Construct Beams and Deck Slab @ +5.40 Level Construct Beams and Deck Slab @ +5.40 Level (Part 1) Construct Beams and Deck Slab @ +5.40 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - 1ST FLOOR SUP-2010 Construct Internal Walls and Columns SUP-2020 SUP-2021 SUP-2022 SUP-2023 SUP-2030 Construct Beams and Deck Slab @ +9.60 Level Construct Beams and Deck Slab @ +9.60 Level (Part 1) Construct Beams and Deck Slab @ +9.60 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - 2ND FLOOR SUP-3010 Construct Internal Walls and Columns SUP-3020 SUP-3021 SUP-3022 SUP-3023 SUP-3030 Construct Beams and Deck Slab @ +13.80 Level Construct Beams and Deck Slab @ +13.80 Level (Part 1) Construct Beams and Deck Slab @ +13.80 Level (Part 2) Construct Beams and Deck Slab @ +13.80 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - 3RD FLOOR SUP-4010 Construct Internal Walls and Columns SUP-4020 SUP-4021 SUP-4022 SUP-4023 SUP-4030 Construct Beams and Deck Slab @ +18.00 Level Construct Beams and Deck Slab @ +18.00 Level (Part 1) Construct Beams and Deck Slab @ +18.00 Level (Part 2) Construct Beams and Deck Slab @ +18.00 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - 4TH FLOOR SUP-5010 Construct Internal Walls and Columns SUP-5020 SUP-5021 SUP-5022 SUP-5023 SUP-5030 Construct Beams and Deck Slab @ +22.20 Level Construct Beams and Deck Slab @ +22.20 Level (Part 1) Construct Beams and Deck Slab @ +22.20 Level (Part 2) Construct Beams and Deck Slab @ +22.20 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - 5TH FLOOR SUP-6010 Construct Internal Walls and Columns
Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone
Critical Milestone
AMAH-1
Revision
Checked
Approved
Activity ID
Activity Name
Original Duration 1 2 3 4 5 6 7 8 9 10 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 8 9 8
Construct Beams and Deck Slab @ +26.40 Level Construct Beams and Deck Slab @ +26.40 Level (Part 1) Construct Beams and Deck Slab @ +26.40 Level (Part 2) Construct Beams and Deck Slab @ +26.40 Level (Part 3) Construct Stairways
15
16
17
18
19
20
21
22
23
24
25
26
27
Construct Beams and Deck Slab @ +26.40 Level (Part 1) Construct Beams and Deck Slab @ +26.40 Level (Part 2) Construct Beams and Deck Slab @ +26.40 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +30.60 Level Construct Beams and Deck Slab @ +30.60 Level (Part 1) Construct Beams and Deck Slab @ +30.60 Level (Part 2) Construct Beams and Deck Slab @ +30.60 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +34.80 Level Construct Beams and Deck Slab @ +34.80 Level (Part 1) Construct Beams and Deck Slab @ +34.80 Level (Part 2) Construct Beams and Deck Slab @ +34.80 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +38.30 Level Construct Stairways
MAIN BUILDI BUILDING - 6TH FLOOR SUP-7010 Construct Internal Walls and Columns SUP-7020 SUP-7021 SUP-7022 SUP-7023 SUP-7030 Construct Beams and Deck Slab @ +30.60 Level Construct Beams and Deck Slab @ +30.60 Level (Part 1) Construct Beams and Deck Slab @ +30.60 Level (Part 2) Construct Beams and Deck Slab @ +30.60 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - 7TH FLOOR SUP-8010 Construct Internal Walls and Columns SUP-8020 SUP-8021 SUP-8022 SUP-8023 SUP-8030 Construct Beams and Deck Slab @ +34.80 Level Construct Beams and Deck Slab @ +34.80 Level (Part 1) Construct Beams and Deck Slab @ +34.80 Level (Part 2) Construct Beams and Deck Slab @ +34.80 Level (Part 3) Construct Stairways
MAIN BUILDI BUILDING - ROOF AND TOP ROOF FLOOR SUP-8040 Construct Internal Walls and Columns SUP-8050 SUP-8060 Construct Beams and Deck Slab @ +38.30 Level Construct Stairways
MASONRY WO WORKS
FINISHING WO WORKS
WOOD WORKS
CIV-5010 CIV-5020 CIV-5030
MEP WORKS
MEP-0000 MEP-0010 MEP-0020 MEP-0030 MEP-0040 Start MEP Works Chilled Water and Air Distribution System Install Galvanized Steel Sheet Rectangular Duct Works. Install Ventillation System Install Building Managemenrt System (BMS) 0 242 242 242 214 Start MEP Works Chilled Water and Air Distribution System Install Galvanized Steel Sheet Rectangular Duct Works. Install Ventillation System Install Building Managemenrt System (BMS)
Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone
Critical Milestone
AMAH-1
Revision
Checked
Approved
Activity ID
Activity Name
Original Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 92 61 61 61 242 242 242 137 92 92 92 92 92 92 242 242 92 76 76 242 242 242 245 92 92 199 199 242 242 242 242 242 90 184 184 184
Month 14
15
16
17
MEP-0050 MEP-0060 MEP-0070 MEP-0080 MEP-1010 MEP-1020 MEP-1030 MEP-1040 MEP-1050 MEP-1060 MEP-1070 MEP-1080 MEP-1090 MEP-1100 MEP-2010 MEP-2020 MEP-2030 MEP-2040 MEP-2050 MEP-3010 MEP-4010 MEP-4011 MEP-4020 MEP-4030 MEP-4031 MEP-4040 MEP-4060 MEP-4070 MEP-4080 MEP-4090 MEP-4100 MEP-4110 MEP-4120 MEP-4140 MEP-4150 MEP-4160
Install Air-Cooled Water Chillers and Pumps Install Fresh Air Handlling Units Roof Mounted Exhaust Fans Motor Control and Supply Distribution Panel Installation of Internal Cold Water Pipes, F ittings and Valves Installation of Internal Hot Water Pipes, F ittings and Valves Installation of Internal Drainage Pipes and Fittings Installation of Drain Water Pipes and Manholes Install CWS Transfer Pump Set Install of Electric Water Heaters Install HWS Circulation Pump Set & CWS Booster Pump Set Install Central Water F ilter in cl. Pipes, Filter Pumps Automatic Control Panel Install Water Tanks Including Related Piping Works Install Drainage Pump Set Install Fire Sprinkler System Install Fire Alarm and Fire Detection System Install FM-200 Clean Agent System Install Fire Water Pumps and Control Panels Install Portable Fire Extinguishers Installation Medical Gases Install Power/Lighting Cables, Supports & Trays Install Electrical Service to Mechanical Works Install Main and Sub Distribution Boards including MCC Install 1500KVA Dr y Type Transformer Install Stand by Generator Install Final Sub-Circuit, Fixtures and Accessories Install Lighting Fixtures Install Public Address & Voice Evacuation System Install SMATV System Telephone, Data (Structure Cabling) and CATV System Install Uninterruptable Power Supply (UPS) Install Earthing System Install Lightning Ptotection Install Nurse Call System Install IPTV System and Audio System Install CCTV System and Access Control System
18 19 20 21 Install Air-Cooled Water Chillers and Pumps Install Fresh Air Handlling Units Roof Mounted Exhaust Fans Motor Control and Supply Distribution Panel
22
23
24
25
26
27
CONVEYING SY SYSTEM
CON-0000 CON-0010 CON-0020 CON-0030 CON-0040 Start Installation of Conveying System Install Parking Lift Type (L3) Install Bed Lifts Type (L1) Install Passenger Lifts Type (L2) Install Service Lifts Type (L4) 0 60 183 183 183 Start Installation of Conveying System Install Parking Lift Type (L3) Install Bed Lifts Type (L1) Install Passenger Lifts Type (L2) Install Service Lifts Type (L4)
Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone
Critical Milestone
AMAH-1
Revision
Checked
Approved