The Second Penang Bridge
The Second Penang Bridge
The Second Penang Bridge
Presented by: Dato Prof. Ir. Dr. Ismail bin Mohamed Taib Managing Director, Jambatan Kedua Sdn Bhd
Topics Covered
Introduction
Ferry Service
Then Now
Began operations in 1920, making it the oldest ferry service in Malaysia. The iconic ferries ply between the Seberang Perai in mainland and Penang Island.
Today the ferry still continue its services which connects Sultan Abdul Halim ferry terminal in Butterworth to Raja Tun Uda ferry terminal at Weld Quay in George Town in Penang Island.
The idea to build a bridge linking the island and mainland was mooted by the late Tun Abdul Razak, the second Prime Minister of Malaysia in 1960s.
The construction was carried out during the premiership of YAB Tun Dr Mahathir bin Mohamad, the fourth Malaysian Prime Minister in 1982. The 13.5km (8.5km over water) bridge was officially opened to traffic on September 14, 1985.
The bridge widening initiatives were undertaken to accommodate the increase in traffic volume which has reached its maximum capacity of 120,000 vehicles per day.
The project which started in December 2005 was completed in August 2009.
The Second Penang Bridge (24km total length and 16.9km over water) when completed will be the longest in Southeast Asia connecting Batu Kawan on the mainland and Batu Maung on the island.
Project Alignment
Existing Penang Bridge
Legend:
Existing Penang Bridge North South Highway (PLUS) Package 1&2 Package 3 Marine Bridge Land Expressway
8.4 km
NAVIGATIONAL SPAN
2+
3+
+0 13
. 00
0. 1+ 00 0. 00 0.
00 0.
4+ 00 0.
PULAU AMAN
6+ 00
5+ 00 0.
7+00
0.
8+000
9+000
0.
10+ 000
23
11
+0
+0
00
22+
00 .
12 +0 00 .
000
.
.
000 21+
20+00
19+00
14 +0 00 .
18+00
17+00
15+00 0.
16+00 0.
0.
0.
0.
0.
PLANNING STAGE
Traffic Demand
The traffic demand on the existing bridge has been increasing since its opening in 1985. Traffic projection without Second Crossing: 2000 97,200 vehicle per day 2010 140,400 vehicle per day 2020 163,400 vehicle per day
Due to a tremendous increase of motorcycle traffic utilising the bridge, it has brought about declining in the bridges level of service enforcing the motorist into intolerable traffic condition.
Both the ferry service and existing widened Penang Bridge will imminently not be able to cater for the traffic demand hence, a Second Crossing is needed to continuously support the economic development of the Penang State in addition to providing a smooth and safe driving facility.
163,400
After widening
120,000
Maximum capacity at existing bridge Actual / Projected capacity x without Second Penang Bridge Projected capacity with Second Penang Bridge
116,500
103,800
80,000
2000
2010
2020
Year
Feasibility Study
The feasibility study was carried out with the objectives :
To investigate the technical and economic Feasibility of the alternative alignments
To prepare the necessary documents for loan facilities purposes To prepare an Implementation Programme (IP) as well as a report on Preliminary Environmental Impact Assessment
To investigate the financial viability of tolling the proposed crossing
Alternative Alignments
Northern Route
Mid-Channel Route
Southern Route C
Feasibility Study
1.
Alternative Alignments:
Northern Route Linking the Penang Outer Ring Road (PORR) at Bagan Jermal on the island with Butterworth Outer Ring Road (BORR) at Bagan Ajam on the mainland. The total length of crossing is 9.2km. Restricted by the Royal Malaysian Air Force (RMAF) aviation requirement. Hence, only immersed tube tunnel can be considered for the main crossing. Mid-Channel Route Linking Georgetown with the Butterworth-Kulim Expressway (BKS). The total length is 8.3km long crossing which include the 2.4km long undersea tunnel. Immersed tube tunnel is considered due to part of the straits is subjected to the movements of exceptionally high cargo vessels. Building a bridge structure will further constraint the waterway. Southern Route C Linking Bayan Lepas Expressway at Batu Maung on the island with Batu Kawan on mainland and ended at North South Expressway at KM 154. This alternative involves a 24km long crossing in which 16.9km crosses the Straits of Penang and 7.1km long connecting road.
2.
3.
Feasibility Study
Conclusion
The alignment of Southern Route was finally chosen by YAB Tun Dr Mahathir Bin Mohamad, the fourth Prime Minister of Malaysia. The decision was to promote socio-economics development in the south that would provide a balance across the Penang State.
Package 1 : Main Navigation Span & Substructure & Foundation Works for Approach Spans. Package 2: Superstructure Works of Approach Spans.
60.0
52.0
8-Nov-08 8-Nov-13
8-Nov-08 8-Mar-13
51.1
24.0 31.0 28.0 14.0 12.0 12.0 24.0
8-Jun-09
8-Sep-13
19-May-10 18-May-12 28-Jun-10 27-Jan-13 19-May-10 18-Sep-12 1-Nov-11 31-Dec-12 9-Oct-12 9-Sep-12 9-Sep-11 8-Oct-13 8-Sep-13 8-Sep-13
18
JKSB issue Letter of Offer (LOO) to Contractors including Employers Requirements (Need Statement) Contractors submit technical & financial proposal
JKSB issue Letter of Acceptance (LA) Contractor submit design brief & work programme
Contractor submit the preliminary drawings Contractor submit detailed drawing & method statements
Construction stage
Employers Requirements
A key feature of design and build contracts is the document commonly known as the employers requirements or need statements which is drawn up by the employer and provides the outline design.
The Employers Requirements set out the project needs in terms of specification, function and performance of the project required and if applicable will also define planning and any other restrictions.
Condition of Contract
Technical Proposal
Drawings
Letter Acceptance Employers Requirements Contractors proposal Contract Sum Analysis (CSA) Form of Design Guarantee Form
Project Specifications
Due to time constraint to complete and to open the bridge for the traffic by end of 2013, a fast-track strategy was crucial.
Design and Build contract is a combination of
all (running parallel), depending on the size, scope, and complexity. divided into 2 types:
Due to stringent Project timeframe , most of the major Project Scopes will be implemented on a Fast Track Basis
Nov 08 Oct 08
Sep 13
Nov 13
TIME
Design Completed
Construction Drawings Completed
Construction Completed
Project
Package 1 Main Navigation Span and Substructure and Foundation Works of Approach Span.
o
o o o o o
Contractor : China Harbour & Engineering Construction Ptd Ltd Date of Site Possession : 8 Nov 2008 Date of Completion : 8 March 2013 Completion Period : 52 Months Contract Amount : RM2.2 billion Work Progress : 63.81%
Contractor Date of Site Possession Date of Completion Completion Period Contract Amount Work Progress : UEM Builders Ltd : 8 Jun 2009 : 4 June 2013 : 48 Months : RM1.55 billion : 29.69%
14
16
Package 1, 2 & 3
Package 1 & 2
Package 1, 2 & 3
CONTRACTORS
CONSULTANT
(DESIGN REVIEW & SUPERVISION)
EIA CONSULTANT
R-SYNC Tech. Resources Ptd. Ltd.
EIA CONSULTANT
DR. Nik & Associates Ptd. Ltd.
CONSULTANT (DESIGNER)
EIA CONSULTANT
YES Enviro Services Ptd. Ltd.
The primary advantage of design and build contracts is that this form of arrangement leaves the employer with a single point of responsibility for any problems, whether design or construction.
27
Employer s Requirement (ER) ER was introduced by JKSB to outline the scope of Design & Build (D&B) Contract for general, contractual & technical requirements and contractor shall comply with all the requirements within the stipulated time up to as well as defect liability period. Independent Checking Engineer (ICE) ICE is appointed by JKSB for the following scope of works to ensure the specific clients requirements & high quality of work are delivered: Review design input parameters adopted to confirm on fundamental design issue Review & comment design brief & final design report Prepare design check report & certification Verify & endorse progress payment Audit construction works Design & Build Contractors Contractors hold most of the responsibility for the design, construction and supervision of the project
28
Conventional Contract
Conventional Contract is adopted for Package 3 (Land Expressway Portion) with the value of RM 750 million.
The objectives are:
to give the opportunity to local/Bumiputera Contractor/Consultant to participate in such prestigious project to expose local Contractor/Consultant in executing mega project to encourage transfer of technology
DESIGN STAGE
2008 24 km
16.9 km
- Main bridge
Cable-stayed bridge with beam and slab deck Box girder bridge
- Approach bridge
- Approach bridge
Second Penang Bridge 2-lane dual carriageway with dedicated 3m motorcycle lane Traffic Loading to UK BD 37/2001, 45 units HB unguided
Seismic design: 475 year event -Ground peak acceleration: 0.1773 g 2500 year event - no collapse -Ground peak acceleration: 0.3261 g
Seismic design: 475 year event -Ground peak acceleration: 0.075 g 2500 year event - no collapse
Structural concrete design to CP110: 1972 No specific durability requirements Normal concrete
First Penang Bridge Estimated Concrete Strength: Spun pile : 50 N/mm2 Pile cap : 30 N/mm2 Pylon : 40 N/mm2 I-Beam : 40 N/mm2 Slab : 30 N/mm2
Second Penang Bridge Estimated Concrete Strength: Spun pile : 80 N/mm2 Pile cap : 40 N/mm2 Pylon : 50 N/mm2 Box girder : 55 N/mm2
Expansion joint at every 5 or 6 spans (275m or 330m) Degree of compaction for earth embankment: 100%
Settlement criteria for earth embankment: 367 mm in 5 years Pavement IRR Index: Not specified
Settlement criteria for earth embankment: 100 mm in 5 years Pavement IRR Index: 2m/km
Design Features
16.9km 7.1km Dual 2 lanes traffic + emergency lane + 1 motorcycle lane each direction.
Cast in-situ Cable-Stayed Bridge P24 to P27 = 117.5m + 240m + 117.5m = 475m. Height Clearance: 30m Navigation Channel: 150m
P0 to P24 = 24 span x 55m = 1,320m. P27 to P292 = 265 span x 55m = 14,575m. Height Clearance : Low Piers: 6m High Piers: 6m to 21.6m Pre-cast Prestressed Segmental Box Girder = 8,092 nos.
Superstructure
34
Project Packages
PENANG ISLAND (BATU MAUNG)
PULAU JEREJAK
P24-P27
13
0 +0
0.
0.
P0
PACKAGE 3A
2+ 00 0.
.
3+ 0 00
4+ 00 0.
PACKAGE 3C
PULAU AMAN
5+ 0 00 .
6+ 00 0.
7+00 0 .
8+000 .
9+000 .
10+ 0 00 .
23
11 + 00 0.
1 2+ 00 0.
0 +0
0 00
22+
0.
.
21+
20+00
P292
17+00
000
19+00
14 + 00 0.
18+00
15+00 0.
16+00 0.
0.
0.
0.
0.
Design Concept
Scope of D&B Packages
117.5m
m NGVD
240m
m NGVD
117.5m
m NGVD
m NGVD
NGVD
m NGVD
m NGVD
m NGVD
m NGVD
P024
m NGVD
P025 P026
m NGVD
P027
Design Concept
14400 7300
29800
3000
Horizontal Split
m NGVD
Approach Span
(Cross Section)
37
Design Concept
MAIN NAVIGATION SPAN Foundation Bored piles adopted for main and end piers at thick layer of dense sand and silty clayey below 45m of seabed level.
Total 66 pts. of 2.0m and 2.2m dia Bored Piles with average length of 120m.
38
Design Concept
MAIN NAVIGATION SPANS Substructure
Steel Fender
i) Easy to construct, hence shorter construction period ii) Compact thus does not restrict the navigation passageway
iii) Low impact on the environment and existing hydrological condition due to its relatively small size
Design Concept
MAIN NAVIGATION SPANS
Substructure Total pilecap : 4 nos Pilecap size (P25 & P26): 48.1m x 17.5m x 6m Pilecap size (P24 & P27): 42.7m x 10.6m x 4m
Design Concept
MAIN NAVIGATION SPAN
Superstructure Cable Stayed Bridge
The cable stayed bridge design is adopted for its advantages in the aspects of performance, construction methodology, project duration and cost competitiveness.
The main navigation is a 3-span twin tower fan-type cable stayed bridge of continuous rigid beam and slab deck with span arrangement of 117.5m + 240m + 117.5m and to be erected by the balanced cantilever method.
Design Concept
SUPERSTRUCTURE FEATURES Type of Structure: prestressed concrete beam and slab deck
The pylon concrete grade: 50 N/mm Main beam: table shape section (2 side web and 1 top flange)
Typical beam height : 2.8m Deck slab thickness : 28cm The main beam concrete grade: 55 N/mm
Design Concept
APPROACH SPAN
Foundation
Prestressed Precast Concrete Spun Piles designed where the overlaid deposit is thick 40m length for each pile total 5166 pts of 1.0m dia Spun Piles with average penetration length of 55m adopted at deep water area Total 368 pts of 1.6m dia Steel Piles with average length of 80m applied at the shallow water and thin deposit area Total 80 pts of 1.5m dia Bored Piles
Bored piles
Design Concept
APPROACH SPAN
c) Spun pile - Faster, prefabricated allows longer length with less joint - Efficient mass to strength ratio - Piles can be withstand higher tension forces which make them suitable for cater wind load & earthquake problem
44
Design Concept
APPROACH SPAN Foundation
Prestressed precast concrete spun piles Out of total of 292 piers, 248 piers or 85% adopted prestressed precast concrete spun piles.
Advantages:
Suitable for the Project by dredging at the thick overlaid deposit area. Dredging is also carried out to allow for the transportation of materials and movement of marine traffic.
More competitive on cost compared to steel piles or bored piles. Available locally from pile manufacturers and Installers. Easy to install in marine environment.
Able to safely withstand ship impact forces via raking piles. Does not involve usage of expensive steel casing.
Fast construction. One piling machine can complete 1 pier in 5 days compared to bored piles area which takes about 6 months to complete one pier with 2 RCD drilling machines based on the same number of quantity.
45
Design Concept
APPROACH SPAN Substructure
Pile caps, Columns and Crossheads are
Total no of Piers 289 nos at Approach The sections and shapes of the pile caps,
columns and crossheads are designed to enhance constructability, construction time and aesthetically pleasing.
46
Design Concept
APPROACH SPAN Superstructure Segmental Box Girders
The precast segmental box girder is designed as a continuous single twin box of 14.08m width,
4.0m length and 3.20m depth structure with match cast joints, multiple shear keys and prestressing tendons.
This type of box-girder was selected because of its size that does not require extensive casting
facilities, special heavy lifting equipment and storage as compared to a precast full-length box girder.
The design of the segments is repetitive which allows the same formwork to be used The depth is maintained constant to present aesthetically consistent soffit line. Total 7 types of Segmental Box Girder are designed for each span.
47
Construction Stage
Construction Methods
Dredging Activities
PULAU PINANG
PULAU JEREJAK
BATU MAUNG TEMPORARY JETTY
LEGEND
Dredging works for 270m width Temporary Navigational Channel Total volume 11 million m of Dredged Materials
+0 13
. 00
0. 1+ 0 00 . 00 0.
00 0.
0.
4+ 00
5+ 0 00 .
7+00 0.
0.
8+000 .
9+000 .
10+ 0 00.
0.
23
11 +0 0
00 . 1 2+ 0
+0 . 00
22+ 000
RSA
20+00
000
19+00
14 +0 00 .
18+00
17+00
15+00 0.
16+00 0.
0.
0.
0.
0.
Construction Methods
Construction Sequence of Bored Piling
Building Platform
Casing Installation
50
Construction Methods
MAIN NAVIGATION SPANS Substructure Steel Fender
Fabrication : Factory Dongguan Yin Ji Heavy Industry Con. Ltd Maximum dimension of Steel Fender (Main Pier P25 & P26) : 8.6m 9.1m. Maximum dimension of Steel Fender (Transition pier P24 & P27): 8.69.1m.
Installation Sequence For Steel Fenders - Main Pier P25 & P26
Installation Sequence For Steel Fenders - Transition Pier P24 & P27
Construction Methods
Construction Sequence of Pilecaps
Construction Methods
Construction Sequence of Pilecaps Contd
Construction Methods
MAIN NAVIGATION SPANS
Superstructure
Slip form is a self-climbing formwork that once set up as a desired-shaped wall to be built, it ascends continually to the height of the structure.
Slip form system is used for the construction of pylon and piers which are more than 8m height.
Each lift will be 4m ~ 5m height Working platform will be provided at the top of the formwork system Slip form system provides high speed of erection (works execution speed increases) and as a result, rapid completion of the project There is no need to dismantling or re-assembling.
54
Construction Methods
MAIN NAVIGATION SPANS
Superstructure
55
Construction Methods
Deck Works Construction using Cantilever Method
Stage 1 Construct piers and pylons
Construction Methods
Deck Works Construction using Cantilever Method Contd
Stage 4 and onwards The process is repeated until all the cables and decks are installed.
Construction Methods
Traveler form for deck
58
Construction Methods
APPROACH SPAN
Pilecap Construction
Insitu construction is ruled out due to high cost and time requirements of cofferdam. Precast Concrete Shells are adopted for:
Precast Concrete Shells are used as a formwork for second layer casting and permanently incorporated into the pile cap 6 pieces of Precast Concrete Shell are required for each pilecap. Total of 3,468 nos of Precast Concrete Shell will be used Casting and Curing are carried out in the Casting Yard Transported to temporary jetty and delivered to worksite by barge. Two casting yards have been establish for overall production Total 27 sets of precast mould are used which consist of 18 sets of 9m dia. and 9 sets of 10m dia.
Construction Methods
APPROACH SPAN
Substructure
Two stage construction of pilecap
The pilecap is designed in accordance to method
of precast concrete shell which is designed to act as permanent formwork for the 2nd layer pile cap construction. Both casting to be carried out during low tide condition
60
Construction Methods
APPROACH SPAN
Substructure
Steel formwork
The bridge consists of 578 nos. of Piers i.e. P0(L/R) to P292 (L/R) Piers are classified as Low (max height 6m) and High Piers (> 6m to
21.6m) from top of pile cap to top of crosshead - using self climbing formwork.
modules installed, cast, removed and installed for the next layer. Process is repeated until crosshead level is reached.
61
Construction Methods
APPROACH SPAN
Superstructure
Due to requirements of the project and launching speed, short line match-casting method is used for precasting of segmental box girder. Segments are being cast similar to cast of any structure via moulds to specific shapes and dimensions Main components of the segments are reinforcement bars and concrete. Segment cast is allowed to cure prior to opening of moulds section Similar process is being adopted for casting of next segment in the exception that frontal side of the next segment shall be cast against the previous cast segment. This term is match casting. The shear keys act as the interlocking shapes between the two segments.
WORK BATCHING SHOP PLANT OPERATION CENTRE LAB SEGMENT STORAGE AREA 1 & 2
OFFICE
567m
298m
Construction Methods
APPROACH SPAN
Superstructure
SBG Casting Requirements
Method of casting
Concrete volume
Steel Reinforcement
Total moulds
Daily output
21 moulds
14 nos/day (at peak)
Casting Cycle
Total casting duration
3 days/bay
28 months
63
Construction Methods
Methods of Segmental Box Girder Casting Shortline Casting (Match Cast)
Perfect Match
Construction Methods
SBG Casting Sequence
Concreting of SBG
Construction Methods
APPROACH SPAN
Launching of SBG using Span by Span Method Features and Advantages
Construction Methods
APPROACH SPAN
Launching Requirements
Total Marine Bridge Span
Total launching gantry Total segments required Plant storage capacity Plant daily output
578 spans
4 nos. 84 nos/wk 750 nos 12~14 nos/day
Overall Planning A dedicated jetty is also built near the precast factory to facilitate the delivery of SBG to the bridge via sea barges.
There will be 4 barges carrying 5 numbers
are 1 type P1, 1 Type P2, 2 Type S1, 2 Type S2, 2 Type D1, 5 Type S3 and 1 Type S3A.
Construction Methods
Segment Transportation Procedure
Approaching, berthing and mooring at Jetty
68
Construction Methods
Mooring Barges At The Erection Fronts Anchor Handling Tug Boat disengage from working barge
69
Construction Methods
Launching Sequence
Offloading of segment from Barge
70
Construction Methods
Launching Sequence contd
- Segments have been installed to form a full span - First stage Post Tensioning & Incremental Load Transfer to form simply supported span
- Release hanger bars and remove lifting beams after the span supported on the temporary support on pier - Launch Main Girder to next pier
72
Introduction
Sustainable development is an enduring balanced approach to economic activity, environmental responsibility and social progress.
73
Conventional
Fisheries
Overview Fisheries Industry in Penang
There are 17 fishing villages on the island and 14 fishing landing point on the main land. In 2007, marine fisheries catch in Penang amounted to 37,774 tonnes worth RM 218.9 million.
75
Fisheries
Location of Fisheries Landing Points Location of Cage Culture Farms
76
an Independent Consultant to monitor the Fisheries Impact Assessment (FIA) for this project. Fanli had earlier completed the base line study in 2007 for the Fisheries Department. To assess on the impact of construction activities on fishing, cockle farming To advise for such measures as necessary To propose the mitigation measures
77
Research by Lund University in Sweden has discovered that the Oresund Bridge connecting Denmark and Sweden have improved the Marine Environment in 10 years since it was built.
In the Second Penang Bridge, aquatic life such as algae and fishes are found around the driven piles.
They become food for fish like the Longfin Bannerfish (Heniochus acumiratus), Rock Grouper (Epinephelus fasciatomaculosus) and White Cheeked Monocle Bream (Scolopsis vosmeri) and the local udang lipan (Stomatopod Crustacean).
The dredging activities have to be carried out due to shallow water conditions at certain portions of the bridge alignment which affect the barges movement for piling, pier and launching activities. The estimated amount of spoil to be dredged is 11,000,000 m3.
Dredging Works
81
C L
Sea Water Level Sea Bed Level -3.0m ACD 1:5 -3.5m ACD 1:5 1:5 Barges Navigation
Channel (BNC)
60m 270m
170m
Main Dredged Channel (MDC)
40m
Note: National Geodetic Vertical Datum (NGVD) Admiralty Chart Datum (ACD) (+0.00 NGVD = +1.72m ACD)
82
o
o
o
o
TSS mapping via satellite imagery Marine water quality monitoring at disposal site Marine water quality monitoring along transportation on route Composition of dredged materials Bathymetric survey at disposal site Final Environmental Audit Garmin GPS Receiver ( Model GPSMAP 76 CSx)
83
Equipment used:
o
Disposal Area
84
All sampling locations generally recorded a significant decrease in TSS level compared to the baseline level. This shows that the spoils disposal activities are being carried out in a proper manner.
Above baseline TSS level at station W18 may be caused by surface run-off originated from northern coastline.
88
Marine Water Quality during construction of load out jetty River Water Quality Air Quality Noise Level Discharge from Sedimentation Ponds Discharge from Septic Tank
89
Generally, suspended solids and turbidity values were below the baseline conditions although the values showed fluctuations
(DOE) requirements, ERE Consulting Group Ptd. Ltd. is appointed by JKSB as an Independent EIA Auditor/Consultant for the overall project.
Check the implementation of environmental mitigation measures Review environmental monthly report Review methodology, sampling and testing Identify potential environmental issues and recommend the mitigation measures
92
PACKAGE 2
Dredging Work Silt curtain was erected and maintained properly
PACKAGE 3A
Generator set was placed in containment area
PACKAGE 3B
Skid tanks and diesel drums was placed in containment area
Embodied energy is the total amount of energy required for the processes of extraction, processing, construction, and disposal of a material
The design of Segmental Box Girder is optimized by adopting higher reinforcement ratios and less concrete with a higher strength concrete High performance concrete with silica fume and pfa cement is used to give the durability required
Effective use of embodied energy; designs to be efficient and reduce waste
94
95
damage criteria for a 500 years return period. In addition to this, a requirement of no collapse criteria for the most credible earthquake (2500 years return period) was also introduced. First Penang Bridge was design on a similar requirement.
spun piles at the approach bridge of Package 1 could only cater for the 500 years return period earthquake. No plastic hinge forms as required for no collapse criteria of 2500 years return period.
HDRB Layout
HDRB Section
Considering the current progress of works, it was decided that a change of bridge bearing system shall be the best solution. The original Pot Bearing system has to be replaced with High Damping Rubber Bearing to provide an effective seismic isolation system. Elastomeric bearing have a low embodied energy per m of the bridge deck.
HDRB Prototype testing - Shear Test for 240 mm displacement
97
Tun Abdul Razak Research Centre (TARRC) at Brickendonbury, United Kingdom, a laboratory of the Malaysian Rubber Board (MRB).
98
98
HDRB provide a simple and economical isolation system. It possesses the low horizontal stiffness needed and are capable of safely withstanding the large horizontal displacements imposed during an earthquake. The bearing was design to meet two set of action as per below:
o
o
SLS non-seismic actions conformance with BS5400 SLS non-seismic actions simultaneous with a 2500year return period seismic event conformance with EN15129
99
ISSUES
Ship Impact Load Assessment Further assessment was also carried out on the ship impact load criteria to ascertain that the bridge could withstand any accidental ship impact. Additional Soil Investigations Soil investigations for design does not reflect the actual soil condition causing several incidents of broken pile heads, piles driven shorter than the design length and drilling bit broken inside the bored holes. Additional soil investigations was conducted to ascertain the profile and conditions of soil below seabed level.
Note: The above issues have initially affected the completion of the marine bridge portion. However, it has now been resolved and the construction is moving forward for the completion in September 2013 with the commitment to achieve highest standard quality of works.
Load Test for Stone Column Compliance test that was carried out failed to comply with the specification criteria. Consultant was directed to review their design and ensure that no sliding failure during construction and no settlement after completion occurs.
previous SI works is
Thus, the contractors are required to conduct additional soil investigation works to confirm the existing SI. Other Non Compliance Issues Several materials were tested to the Project specification and were found to be non compliant. (e.g pipe culvert, sand and spun piles). JKSB have rejected the materials which do not meet the Project requirements as we are committed to produce the highest quality of works. Note: Since the activities at land expressway works are not critical, JKSB is confident and committed to ensure the Project is delivered with the highest standard of quality and meets the target completion of September 2013.
Conclusion
Despite its implementation in a fast track manner, the Penang Bridge Second Crossing is being constructed to the highest quality, considering health, safety, cost, sustainability and environmental conservation. The Second Penang Bridge when completed will be the longest bridge in Malaysia and South East Asia when it opens for traffic in 2013.
105
View of the Segmental Box Girder (SBG) Storage at Casting Yard with Production Line in Background
* JKSB acknowledges the assistance of CHEC & UEMB for the preparation of this presentation.