Aia, Bim Implamentation Guide, Aiab085571
Aia, Bim Implamentation Guide, Aiab085571
Aia, Bim Implamentation Guide, Aiab085571
CURT Owner Member Companies Abbott Laboratories Air Products & Chemicals, Inc. Alstom Power, Inc. Ameren American Electric Power AT&T Barrick Gold Corporation Baxter Healthcare Corporation Boeing Company BP p.l.c. Caterpillar Inc. Chevron Constellation Energy The Dow Chemical Company DTE Energy Duke Energy DuPont Dynergy Generation Eli Lilly and Company Exelon Corporation ExxonMobil Chemical Company FirstEnergy Corporation General Electric Company Honda of America Mfg., Inc. Intel Corporation Johnson & Johnson Linde Process Plants The McGraw-Hill Companies Merck & Co., Inc. Mirant Corporation NRG Energy NV Energy Ontario Power Generation Praxair, Inc. Progress Energy PSEG Power, LLC The Procter & Gamble Company Salt River Project Shell Global Solutions (U.S.), Inc. Siemens Energy Southern Companies Suncor Energy Sunoco TECO Tampa Electric Company Tennessee Valley Authority Tyco International U.S. Architect of the Capitol U.S. Army Corps Of Engineers U.S. Department of State U.S. Federal Bureau of Prisons U.S. General Services Administration U.S. NNSA/DOE
Associate Member Companies Aker Construction AMEC Bechtel BMW Constructors EMCOR Group Inc. Fluor Corporation Jacobs Engineering Group KBR Rudolph/Libbe Companies The Shaw Group, Inc. Skanska USA Turner Construction Company URS Washington Division Vulcan Industrial Contractors
Association Associate Members American Institute of Architects (AIA) American Institute of Steel Construction (AISC) Associated Builders and Contractors (ABC) Associated General Contractors of America (AGC) The Association of Union Constructors (TAUC) Design Build Institute of America (DBIA) Finishing Contractors Association (FCA) Mechanical Contractors Association of America (MCAA) National Association of Women in Construction (NAWIC) National Center for Construction Education and Research (NCCER) North American Contractors Association (NACA) National Electrical Contractors Association (NECA) Sheet Metal & Air Conditioning Contractors National Association (SMACNA)
Notice:
The purpose of this publication is to make available to industry the results of research and common owner practices. The information is provided solely for the individual consideration and education of The Construction Users Roundtable (CURT) members and the industry. The publication does not necessarily represent the views of every CURT member company on this topic. The booklet is offered as an informational publication only. CURT intends only to synthesize current thought and trends concerning the topic. Neither CURT nor its committees make any warranty as to the completeness of the materials. Readers are encouraged to further research the topic before relying exclusively on these materials. Each CURT member and other readers of these materials are free, acting in their own discretion and perception of business self-interest, to reject or adopt the recommendations in whole or in part. Adoption and/or reliance upon these recommendations are strictly voluntary. The Mission of CURT is to promote cost effectiveness for owners doing business in the United States by providing aggressive leadership on issues that will significantly improve project engineering, maintenance, and construction processes, thereby creating value for the owners.
Contents
1.0 2.0 3.0 4.0 5.0 6.0
Page
Intent .................................................................................. 1 Initial Steps and Assessments ............................................ 2 Project Pre-Planning .......................................................... 6 Design and Construction .................................................. 21 Operations and Maintenance............................................ 29 References ........................................................................ 34
1.0 Intent
This publication is for owners who want to implement Building Information Modeling (BIM). Because each project and each owners enterprise is inherently different, there is no fully developed, off-the-shelf, one-size-fits-all solution for BIM implementation. This publication serves as a practical guide to help owners develop a BIM implementation process that best suits each owners situation and needs. The paper is divided into three broad phases of project life cycle (Project Pre-Planning; Design & Construction; Operations & Maintenance) so that an owner can contemplate employing BIM processes at any time. In each phase, the publication follows a chronological process and provides both step-wise guidance on activities and key questions that owners need to ask themselves (and their team members) to ensure that the processes and desired outcomes realistically align with resources and capabilities. This publication is the product of the CURT Process Transformation Committee and has been developed with input and contributions from CURT members, architects, contractors, subcontractors, and fabricators, all with BIM experience. This group believes that owners have a unique opportunity to positively influence the adoption of BIM across the industry and continually improve the BIM implementation process.
Lower total installed cost? Produce better designs? Assist with project budgeting and pricing? Reduce claims or litigation? Improve deliverable times? Improve decision-making processes through better visualization and what-if scenarios? Improve construction outcomes? Prevent knowledge loss from construction to operations? Create digital turnover documents? Perform Operations and Maintenance? All of the above?
Answers to the above questions will assist the owner in forming an appropriate approach to BIM for various project types.
McGraw Hill 2009 SmartMarket Report, The Business Value of BIM http://www.nibs.org/index.php/bsa/newsevents/news/Entry/mcgrawhillconstructionsmartmarketreport2009
insights of all participants to reduce waste and optimize efficiency through all phases of design, fabrication, and construction. Integrated Project Delivery principles can be applied to a variety of contractual arrangements and Integrated Project Delivery teams will usually include members well beyond the basic triad of owner, architect, and contractor. At a minimum, though, an Integrated Project includes tight collaboration between the owner, the architect, and the general contractor ultimately responsible for construction of the project, from early design through project handover. 2 In its simplest form, IPD can be a non-contractual agreement between parties to collaborate. An owner who requires designers and constructors to reconcile design documents with construction means and methods to produce spatially coordinated installation documents will achieve better outcomes, regardless of the contract method used. While the statements above might seem to contradict the traditional arms length relationship between design and construction, traditional delivery methods have always included design review of installation shop drawings before construction begins. An integrated approach improves collaboration and communication; reduces cost-bearing requests for information (RFIs); and improves outcomes.
Technology Capabilities
Software and Interoperability
Decide between a proprietary software format and an open standard. Some owners have a great deal of legacy data in formats that must be maintained, while others are more willing to accept an open standard deliverable such as the Industry Foundation Class (IFC); each has certain benefits and detriments. An open standard, if acceptable, will result in a greater ability to maintain data accessibility over time. Mandating a proprietary single software solution may limit the number of qualified designers and contractors but improve internal post-construction data use. Selection of proprietary solutions reduces data accessibility as the solution provider (software developer) makes future version changes, or files format changes. Sustainability and retrieval of digital information over time is an imperative to life-cycle uses of BIM. Software programs come and go and so do digital file formats. For digital data to remain retrievable over time, procedures for archiving and updating must be in place. 3
o o o o o o o
Do you have adequate trained staff for the task? What (if any) outside resources will you rely on? Who will manage the data at each stage? What is the final deliverable? How will information be used after construction? Where will it reside? Who will maintain it? Listed below are some processes that benefit from a BIM-enabled project delivery method and may assist with answering the questions above.
o o o o o o o o o o o o o o o
Enterprise planning Project planning Programming Proof of performance Consideration of design alternatives Cost and schedule evaluation Visualization studies Permitting Design and construction Sales and leasing Commissioning Portfolio management Tennant build-out Future building additions and alterations Facility Management
Consider the following for inclusion in your BIM execution plan: o o o o o o o o o Portfolio management group spatial planning and programming enabled with a BIM. Scenario-based planning and implementation. Space utilization, phasing plans, etc. Enterprise financial area / purpose, other business lines. Team structure. Roles. Responsibilities. Information handoff. Reliance on data at certain stages.
Potential Participants
Consider your market. Analyze availability of qualified potential team members within the project locale, and assess the technical maturity of the region. This knowledge may influence the information entered in or produced from the model. Is the BIM expertise youll require to achieve your desired implementation strategies and goals available in your geographical area / region? If not, can you acquire it effectively elsewhere? Some regions have talent available on a consulting basis that can provide expertise where needed.
10
How will the design team, construction team, consultants, and subcontractors embrace the use of BIM? Are their attitudes about BIM aligned with your project and company goals? Positive, can-do attitudes ensure success, whereas reluctant partners may try to prove BIM does not work. Are your existing project consultants and constructors BIM capable? If they have not used BIM, are they willing and able to transition to a BIM process? If they have been contemplating a move to BIM, their enthusiasm may help foster project success. Will you consider exploring new relationships with new team members who have demonstrated BIM expertise? BIM users would rather work with strangers who know BIM than with friends who dont. A majority of users (between 55% and 74%, depending on the discipline) gave high value to other team members on a project having BIM experience. This displaces the traditional favorite, previous experience working together, which scored only 42%. Additionally, when asked to rate factors that would most enable improved ROI, 66% of BIM users gave a high score to more external firms with BIM skills. This shows that adoption needs to accelerate to meet demand. 5 Developing the RFQ / RFP It is critical that the owner develop a clear understanding of potential team members experience with BIM. Determine whether they have proven experience or merely a BIM-formarketing (BIM Wash) presentation. Careful review of experience and qualifications, along with a well-written RFQ, will clarify the respondents capabilities and qualifications. Below are some sample questions to ask yourself and prospective RFP recipients.
11
The RFP should clearly reflect your BIM goals and intent and should communicate your expectations of the BIM team. It must focus on the necessary skills and processes required for successful BIM implementation. A focus on value-added vs. first cost is strongly recommended (see CURT WP 1003 for more information regarding costs. 6) A best-value analysis will guide an owner through the process of defining the roles, responsibilities, and capability requirements for collaboration partners. The RFP should outline performance metrics for the project and define exactly how success is measured. Consider the following metrics and goals:
o o o o o o o o
Alignment with your business corporate metrics Milestone dates Safety expectations Sustainability goals (energy performance, rating system compliance, etc.) Number of RFIs and change orders Definition of value and measurement of achievement Schedule Budget
12
o o o
o o
Quantity take-offs (greater accuracies in material quantity estimates) Linkage to in-house estimating systems and databases Cost estimating (four-dimensional direct connection between cost data and material quantities improves quality of estimates) Construction scheduling / coordination (fivedimensional improved construction staging and sequencing planning) Construction stage information shop review, creation of record documents Prefabrication (use of model for off- or on-site prefabrication improves quality and efficiency and reduces material waste) Automation
13
Monitoring Metrics
Decide how often and when you will assess performance
of the projects team. Establish metrics for measuring project success during the project pre-planning stage. Monitor regularly against project goals and traditional delivery methods. Suggested metrics include milestone dates, improved safety, performance goals, sustainability outcomes, RFIs,change orders, value, schedule, budget, and other measures deemed valuable to the project team.
14
15
AGC ConsensusDOCS 301, BIM Addendum www.agc.org/galleries/contracts/ConsensusDOCS%2520301%2520BIM%2520Addendum%2520Article.pdf 9AIA E202, BIM Protocol Exhibit http://info.aia.org/aia/form_free_bim.cfm
8
16
o o
reflect the selected teams strengths and skill sets and confirm with the selected team. Confirm with your internal legal staff the proposed BIM process and the requisite information flow to achieve its benefits. Ensure there are resources available to your legal staff to address concerns and seek clarifications as necessary. Do your existing Contract Form(s) allow for implementing the principles set forth in this document, and are they aligned with your BIM tactical and strategic goals? Are you modifying forms for this contact? If so, do you have a process in place to solicit feedback and implement concurrent change if appropriate? If you are using specialized procurement processes such as Design Assist, do you have contractual language to address the nuances of process and information flow from the model? Are all parties to the project aligned? Clearly outline your BIM strategy for this particular project in the contract. Include a background note on your corporate BIM strategy and a list of potential targets of opportunity. Once established, how does the contract address the need to grow and / or expand the team? How do you bring on new members? Does the project team understand this? Who has a say in this action? Is there a process set up to make this a seamless action? Consider incentives tied to achieving BIM development milestones and goals. Upon successful negotiations, execute the contract.
17
o o o
18
in development of shop-drawing level of detail models during the traditional design phases of the project. Make decisions earlier in the process to allow timely completion of design with spatial coordination. Milestones for major materials and equipment o selections and manufacturer-specific components should occur early in the deliverables schedule to allow propagation of the information model with dimensionally accurate components. This will also facilitate early order of long lead-time materials. o All parties must agree in advance on how to handle field changes. Incorporate all field changes into the BIM before project completion and include with the project turnover package. Establish specific performance metrics for the o project that are consistent with those outlined in the RFP and the capabilities of the team players. Define exactly how success is measured.
Concurrent Learning
BIM is an evolving tool. It is paramount to have a process in place to capture lessons learned during and upon completion of the project. Open communication is essential. Strive for concurrent learning akin to a research and development environment, and continuously feed this information back into the system. 72% of [BIM] users who formally measure their ROI report positive returns compared to 53% of users who estimate 10
10
19
20
Building Information Modeling achieves best outcomes through a collaborative process between owners, designers, and contractors (both general and specialty.) If a traditional Design, Bid, Build form of contracting is required, contract language should include a requirement that parties collaborate.
11
BIM Handbook: A Guide to Building Information Modeling (Eastman, Teicholz, Sacks, and Liston) ISBN: 978-0-470-18528-5
21
Monitoring Consultants
Consultants (both design and pre-construction) should be bound by metrics established in the BIM Execution Plan and monitored closely to avoid unexpected cost overruns or delays due to indecisiveness about design changes. Establish measurable accountability and defined calendar deadlines as early as possible. Freeze points for decisions and deliverables assist in timely design completion and reduce the tendency to polish the apple. Solicit budgetary feedback from the affected installing contractors at each major design decision to review for cost implications.
Model Creation
Determine if the project will have a Federated or an
Integrated modeling approach. o The Federated Model concept requires that all component models be combined for coordination only; each model creator retains responsibility and ownership for their model and work. Component models are updated by their respective creators and combined for coordination as the project moves forward. The Integrated Model concept requires that all component models exist in one model, with one entity responsible for maintaining the integrated model. The integrated model becomes better and better defined as the project moves forward. A designated party will be responsible for the integrated model. Create a schedule for critical design decisions and establish freeze points that support construction milestones. Manage design changes and prevent unlimited scenario analysis. Determine whether third parties (end users; consultants; major suppliers; government,
22
regulatory, municipal agencies; etc.) will be engaged. Schedule when models are released for downstream use. Establish the needs for 2D paper deliverables. Require that 2D deliverables be extracted from the 3D BIM. Determine what supplemental drawings or typical details are not in the model, where they exist on the project, and how this information will be conveyed to the installation team.
Determine uses of the information in the model Who will use it and for what purpose? Where will the BIM reside? Will the model (and appropriate support) reside on the project site? Owners and the project team should decide if the BIM will be used on the job site during physical project construction. If models will be used during construction, owners should require that the BIM(s) be used throughout the design, construction, and commissioning process. Insisting on accuracy of information within the model will ensure accurate turnover data and its suitability of use for future projects, facility services, etc. Owners should decide on their final and best uses of the BIM at project inception. Graphical and non-graphical information may have equal or lesser value, depending on when the information is accessed. Do not be afraid to ask for what you think you need (in many cases, the data may be available without additional cost if requested early). Existing technology provides the end user with many means for accessing project data. Careful thought and consideration at the beginning of the project prevents excessive data entry late in the process. Decisions regarding how the end user(s) will need to interact with the information model should influence the final deliverable and formats for data access.
Levels of Detail
Copyright 2010 The Construction Users Roundtable. All rights reserved
23
Require levels of detail appropriate for the intended use of the information. A model used for square foot quantity take-offs requires much less detail than a model required for shop fabrication. o Cost andscope models Cost and scope models should include general information on big-picture items such as floor area, use designations, building volume, and building grids. These models may not necessarily need to be used throughout the entire project.
Scheduling Models
Scheduling models need enough detail and granularity to allow separation of the model into discrete construction sequences.
Bidding Models
Bidding models contain overall geometry and design requirements of systems, but may not be highly detailed.
Construction Models
Construction models have the highest level of detail on a project. They contain the means and methods to construct the systems and components of the building. Construction models are used for shop-drawing production, fabrication, submittal for compliance of design intent, permits, etc.
As-Built Models
As-built models are useful as record models of the completed structure and may be required by the operations and maintenance (O&M) staff for managing the building over its life cycle. BIM considerations during design and construction
24
Not all parties involved with the project may be willing or able to engage in the more integrated design and construction processes necessary to maximize the value of BIM. Some lesscritical participants may engage in a more traditional design and construction practice. The General Contractor or Construction Manager will coordinate this work in a way that minimizes impact to the process. One or more of the early team participants might be required to model or add information for the non-participating party. As an example, the structural steel system and mechanical, electrical, and plumbing (MEP) systems may be developed in an integrated fashion to facilitate spatial coordination, while metal stud and drywall systems may be delivered by more traditional means. In this example, one of the fully engaged team members would model components required to ensure accurate spatial coordination. Spatial coordination Accurate construction-level detail modeled by all major space consumers is required to complete spatial coordination. Early design-level attempts can allocate space for building components, but until all systems are integrated into the structure with dimensionally accurate installation level components, there is no certainty of outcome. Regardless of the models accuracy, the contractor must ensure that the building is modeled with an appropriate level of detail. It must have sufficient details for piping, ducts, structural steel and attachments, and other components (electrical systems, fire protection piping, and seismic bracing), so that clashes can be accurately detected. 12
12
BIM Handbook: A Guide to Building Information Modeling (Eastman, Teicholz, Sacks, and Liston) ISBN: 978-0-470-18528-5
25
Heating, Ventilation, and Air Conditioning (HVAC) Duct All ductwork, grilles, registers, diffusers, dampers, access panels, air-moving equipment, maintenance clearances, and any item that may impact coordination with other disciplines. HVAC Piping All overhead piping, vertical piping in shafts, connections to equipment, scheduled equipment, maintenance clearances, hangers, supports, and any item that may affect coordination with other disciplines. Plumbing All overhead piping, vertical piping between floors, connections to equipment and fixtures, maintenance clearances, hangers, supports, and any item that may affect coordination with other disciplines. Fire Protection Piping All overhead piping, branch connections, drops and heads, access panels, maintenance clearances, hangers, supports, and any item that may impact coordination with other disciplines.
13
AGC BIM Forum MEP Spatial Coordination Requirements for Building Information Modeling.
26
Electrical All conduits 2 inches and larger, any rack of two or more conduits regardless of size, lights and fixtures, electrical pull and circuit boxes, access clearances, all cable trays, hangers, supports, raceways, and any item that may impact coordination with other disciplines. Framing - All king studs, headers, and any item that may affect coordination with other disciplines.
After all coordinated components are in place, installation of items not included in the coordinated installation drawing may begin. Any items not in the coordinated model will be installed after coordinated items are in place. Accessibility to install non-coordinated work is not an exclusion or exception to this requirement. Each participant is required to consider sequence of work when determining the degree of detail required. This excerpt is a small example of the level of detail and complexity required to create a spatially coordinated construction model suitable for fabrication.
Information Provenance
Establishing the provenance of building information immediately raises the specter of liability for the original authors of that information, particularly for design professionals, for whom professional liability may extend far beyond their responsible control of the informatione provenance of building information must be sufficiently clear and complete to permit anyone intending to use it to judge the reliability of it for themselves the building industry as a whole is clearly moving toward a new business environment supported by new forms of legal agreements in which the burden of responsibility for relying on the building information is shifting from the original author to the person using it.14
27
Drawing Production
Shop, installation, and fabrication drawings are produced as extractions from the spatially coordinated BIM. Fully annotated and dimensioned paper sheet sets are produced and formally submitted with the digital model to the design team for review of compliance with design. As-built deliverables and turnover documents Building Information Modeling presents opportunities for digital document turnover packages far superior to traditional paperbased deliverables. When produced in an archival quality format such as the Construction Operations Building Information Exchange (COBIE), these packages offer the owner a higher assurance of the ability to retrieve usable data over time. The COBIE approach is to enter the data as it is created during design, construction, and commissioning (see Figure 1). Designers provide floor, space, and equipment layouts. Contractors provide make, model, and serial numbers of installed equipment. Much of the data provided by contractors comes directly from product manufacturers who can also participate in COBIE. 14
14Construction Operations Building Information Exchange (COBIE) by E. William East, PE, Ph.D http://www.wbdg.org/resources/cobie.php 15 Big BIM Little BIM (Finith Jernigan) ISBN: 978-0-9795699-9
28
Focusing on the integration of design with spatial coordination and installation level detail before developing construction documents will yield highest and best outcomes on a project. Incomplete or inaccurate design models and deliverables produced for the sake of permitting and bid documents require additional effort before construction, which may exceed any perceived savings from competitive bidding.
29
How are you managing your systems now? Do you want to incorporate BIM into your existing strategy? Is this an opportunity to formulate a new strategy? Is this a catalyst to review your existing technology, processes, and workflow? How large is your portfolio of assets? Are you in a position to use BIM during Operation and Maintenance of the project?
Owners who have the benefit of having intelligent models during the design and construction phase are positioned to use the model and (more importantly) the information it contains in the operation and maintenance phase of their facility. The level to which the information models are used during operations and maintenance phase is dependent upon the scope that was required during the project team assembly, the elements that were modeled, how well the model was kept current, your internal ability and willingness to embrace the technology required to access the information, and the ease of retrieval of data.
30
Structure your Requests for Proposals to identify all available data and information possible even if you do not plan to or cannot use the information today. For example, request electronic as-builts with as much information as possible. Chances are very high that you will want to use that information in the near future.
31
o o o
Which existing or new software programs do I want the information to connect? How many people are likely to use the programs? Are adequate seat licenses available? o Will this have an impact on future RFPs? o Are there interoperability issues? o Are naming conventions between the packages supportive of easy understanding and exchange? (See Figure 2, below.)
32
Virtual Tours Capturing lessons learned Preplanning future projects Regulatory, statutory, permitting, etc. o Remote tie to other locations geographically o Emergency Response Teams
33
6.0 References
American Institute of Architects (AIA): AIA E202 BIM Protocol Exhibit http://info.aia.org/aia/form_free_bim.cfm American Institute of Architects (AIA): AIAs Technology In Architectural Practice Knowledge Community: www.aia.org/tap American Institute of Architects (AIA) Integrated Project Delivery: A Guide www.aia.org/ipdg American Institute of Architects (AIA) Resources for Integrated Project Delivery www.aia.org/ipdg Associated General Contractors of America (AGC) AGC BIM Forum MEP Spatial Coordination Requirements for Building Information Modeling Associated General Contractors of America (AGC) BIMForum www.bimforum.org Associated General Contractors of America (AGC) Contractors Guide to BIM www.agc.org Arizona Revised Statutes 34-603 http://law.justia.com/arizona/codes/title34/00603.html Big BIM Little BIM (Finith Jernigan) ISBN: 978-0-9795699-9
34
BIM Handbook A Guide to Building Information Modeling (Eastman, Teicholz, Sacks, and Liston) ISBN: 978-0-47018528-5 Building Information Modeling A Strategic Implementation Guide (Smith and Tardif) ISBN: 978-0-47025003-7 BuildingSMART Alliance www.buildingsmartalliance.org ConsensusDOCS 301 BIM Addendum http://consensusdocs.org/catalog/300-series/ Construction Operations Building Information Exchange (COBIE) By E. William East, PE, PhD http://www.wbdg.org/resources/cobie.php Construction Users Roundtable WP 1003 Construction Strategy: Optimizing the Construction Process www.curt.org Construction Users Roundtable WP 1202 Collaboration, Integrated Information and the Project Life Cycle in Building Design, Construction and Operation www.curt.org McGraw Hill 2009 SmartMarket Report The Business Value of BIM: http://www.nibs.org/index.php/bsa/newsevents/news/Entry/mcgra whillconstructionsmartmarketreport2009 National Building Information Modeling Standard (NBIMS): www.buildingsmartalliance.org/index.php/nbims
35
Project Execution Planning Guide: http://www.engr.psu.edu/ae/cic/bimex/Sustainability of Digital Formats http://www.digitalpreservation.gov/formats/sustain/sustain.shtml U.S. General Services Administration Building Information Modeling www.gsa.gov/bim
36
Examples: WP-1201: R-402: UP 801: A CURT White Paper on Reverse Auction A CURT Report on Tripartite Initiatives A CURT User Practice on Construction Safety in Contractor Prequalification
Reports
R 402 CURT Tripartite Initiative Executive Summary R 402A CURT Tripartite Study on Extended overtime on Construction Projects R 402B Reducing Absenteeism Report R-402C Tripartite Initiative Report: Eliminating Work Disruptions and Jurisdictional Disputes R405 CURT Tripartite Initiative Report: Project Stakeholder Responsibilities R411 Building Comprehensive Labor Market Information R 807 CURT Owner Safety Blueprint
User Practices
UP 101 Construction Measures: Key Performance Indicators UP 201 Construction Project Controls: Cost, Schedule, and Change Management UP 403 Construction Labor: Managing the Construction Workforce UP 601 Construction Purchasing: Capital Purchasing & Contracting UP 701 Construction Quality: Achieving Quality on Capital Projects and Craft Worker Prequalification UP 801 Construction Safety: Contractor and Craft Worker Prequalification UP 802 Construction Safety: The Owners Role UP 803 Construction Safety: Pre-Bid and Bid Clarification Meetings UP 804 Construction Safety: Contract Terms and Conditions
UP 805 Construction Safety: Monitoring Performance UP 806 Construction Safety: Improving Safety Programs UP 1001 Construction Strategy: Selecting Contracting Strategies UP 1002 Construction Strategy: Selecting the Right Contractor
Tools
T 404 Construction Labor: Craft Employee Training Evaluation Tool T 808 Construction Safety: Owner Safety Blueprint Assessment Tool
Training Modules
Survey Summaries
SS 406 CURT Tripartite Initiative: Workplace Attitudes Survey, Summary of Results SS 407 CURT Owner Survey: Impact of Gulf Coast hurricanes on Owner Projects, Summary of Results
Visit the CURT publications website, http://www.curt.org/14_0_curt_publications.html, for additional information and pricing.
4100 Executive Park Drive, Suite 210 Cincinnati, OH 45241-4023 Phone (513) 563-4131 Fax (513) 733-9551 www.CURT.org