7c2 Coal Economics CO2
7c2 Coal Economics CO2
7c2 Coal Economics CO2
444 Castro Street, Suite 720 Mountain View, California 94041 Telephone: (650) 969-8876 Fax: (650) 969-1317 Email: [email protected]
CO2 MITIGATION ECONOMICS FOR EXISTING COAL-FIRED POWER PLANTS Presented at the U.S. Dept. of Energy National Energy Technology Laboratory (NETL) First National Conference on Carbon Sequestration May 14-17, 2001 Washington, DC by Dale R. Simbeck Vice President Technology SFA Pacific, Inc. Mountain View, CA
ABSTRACT Electric power generation represents one of the largest sources of CO2 emissions in North America. A major issue in the analysis of CO2 mitigation options is the fact that over 45% of total electric power generation in North America is from coal. These existing coal-based power plants have the highest CO2 emissions of any power systems yet are the lowest cost electric generators. Retrofit CO2 reduction or recovery of existing coal-based power plants has definite advantagesusing the existing site infrastructure, having facilities that are mostly paid-off or However, retrofits also have amortized, and having high baseline CO2 emissions. disadvantagessignificant capacity and efficiency losses that require replacement capacity addition, and increased fuel use depending on the choice of CO2 mitigation technology. TransAlta is a major coal-based electric power generator in Canada and the United States. As discussed at www.transalta.com in the Sustainable Development section under Our Actions, TransAlta has a goal of zero net greenhouse gas emission (including trading and offsets) for its Canadian operations by 2024. As part of this ambitious goal, TransAlta funded site-specific analysis by engineering vendors of two noteworthy PC retrofit CO2 capture options: flue gas CO2 scrubbing (amine) and oxygen combustion with flue gas recycle. SFA Pacific standardized and summarized these two analyses into single-page evaluation spreadsheets that include mass and energy balances, capital cost buildups, and economics. Additional options are developed in this simplified format for easy comparison on a consistent and transparent basis. This approach facilitates the objective identification of specific situations, innovative options, and R&D opportunities that could significantly improve CO2 reduction, capture, separation, and utilization.
ECONOMIC BASIS FOR COMPARISON OF CO2 EMISSIONS AVOIDANCE COST Calculating the cost of CO2 emissions avoidance options for an existing PC power plant first requires baseline CO2 emissions and a baseline cost of electricity. Figure 1 is the single-page spreadsheet developed for the existing PC power plant baseline. The technical performance is from ABB Combustion Engineering, the original PC boiler power plant vendor that was also utilized by TransAlta for the oxygen combustion retrofit analysis. SFA Pacific then developed capital and operating costs (current dollars). A key economic issue involves the remaining capital of the existing power plant yet to be amortized and how to treat this old capital in a way that is consistent with the new capital for CO2 retrofits. We chose the approach of refinancing the old capital that is not yet amortized along with the new capital to keep it simple, consistent, and transparent. Therefore, the existing PC baseline economics in Figure 1 include fuel, operating and maintenance (O&M), and only a fraction of the original power plant capital at current dollar value that is refinanced based on a simple annualized capital charge rate. Figures 2 4 are examples of the single-page spreadsheet developed for several of the many CO2 reduction options. Figure 2 is for conversion of the existing PC baseline power plant to oxygen combustion with flue gas recycle and CO2 recovery/compression. The performance is from the original TransAlta analysis. Capital costs were only slightly modified to reflect on-site oxygen manufacturing, power purchased during the retrofit tie-in shutdown time, and the remaining capital yet to be amortized for the original power plant. For effective CO2 transport and utilization or disposal, all CO2 recovery options include CO2 drying and compression to 135 atmospheres pressure (2,000 psig). Non-condensable gases such as N2, O2, SO2 and NOx are stripped from the liquid CO2 during compression. Additional power generation capacity is added in all CO2 recovery options to maintain the same net power output as the original PC power plant. This is quite important due to the large power requirements associated with oxygen manufacturing and CO2 compression to high pressure. The additional power generation capacity is based on natural gas combined cycle (NGCC), as this is currently the option of choice for most new power plants. Furthermore, the capacity addition is too small for coal technology and the NGCC capital cost and emissions are much lower. Figure 3 summarizes CO2 recovery by a retrofit amine scrubber on the PC boiler flue gas. A small natural gas boiler with low-pressure extraction steam turbine generator is added to meet the additional power of CO2 compression and large stripping steam needs of the CO2 amine stripper. This avoids major retrofit costs to the existing PC boiler and steam turbine generator. A high efficiency FGD system is added to protect the amine from degradation by SO2. High efficiency NOx removal was not required based on discussion with the Fluor Daniel, which has commercial experience with flue gas CO2 amine scrubbers. Figure 4 summarizes CO2 recovery by conversion of the PC boiler to hydrogen fired coal gasification combined cycle (H2-CGCC) power plant. This design assumes minimal reuse of the
RESULTS A number of additional single-page spreadsheet cases were added to the two modified TransAlta cases. This expanded model enables direct comparison of various fuel and technology options on a consistent economic basis. There are three general groupings of retrofit options presented in this analysis: 1. Conversions to lower CO2 emission technologies without CO2 recovery. This includes total coal replacement with: 100% natural gas (via NGCC), natural gas with coal (via gas turbine hot windbox repowering), biomass with coal (via cofiring), continued 100% coal use with replacement high efficiency coal technology (coal gasification combined cycle, CGCC).
The results in Table 1 can be varied significantly with the key economic input assumptions. Nevertheless, we found the following results of most use: 1. Only moderate CO2 credits make the continued use of coal-based power with CO2 recovery significantly more economic than renewables and even more economical than the conversion to NGCC when natural gas prices are greater than about $3 per million Btu. However, if there is a moderate ($10/mt) CO2 disposal charge (added to the plant-gate highpressure CO2), natural gas conversion is more economical until natural gas prices reach about $6 per million Btu. Co-firing natural gas or biomass with coal adds only moderately to costs but also provides only moderate CO2 reductions. Coal with CO2 capture or conversions to 100% natural gas or 100% renewables represent much larger CO2 reductions. Assuming continued coal use with CO2 recovery for both cases, replacement or repowering with a new H2-fired CGCC was more attractive than an existing PC retrofit with amine CO2 flue gas scrubbing or oxygen combustion. This is due to the large capacity and efficiency losses of PC retrofits, whereas H2-CGCC increases both capacity and efficiency relative to the original PC unit. In addition, the gasification option is essentially an all new power plant and the traditional emissions (SOx, NOx, Hg and fine particulates) are all reduced to near zero. The challenge of gasification is the larger first costs and fundamental suspicion of this complex chemical process by traditional coal boiler utilities. Nevertheless, we expect that more power generators will consider gasification repowering for existing coal power plant upgrades in the future, forced by the increased competition of deregulation. In addition, the dominant gasification vendor, Texaco, has already made equity investments in five of their last 12 commercial gasification projects [6]. Partial CO2 reduction of an existing coal power plant to the same CO2 emissions level as a new NGCC system (65% reduction) helps the retrofit fuel gas amine CO2 scrubber option the most.
2.
3.
4.
CONCLUSIONS AND DISCUSSION The results of this analysis are useful in illuminating important characteristics of the various options and show that retrofits of existing coal power plants must be included in any objective analysis of CO2 reduction options. The key economic issues appear to be the potential of CO2 utilization producing a byproduct value as in the case of EOR or CBM. This opportunity already exists along the eastern slopes of the Rocky Mountains and the Great Plains of North America where large commercial CO2 utilization projects already exist and new projects are being considered [4,5]. The foregoing conclusion is significant in view of the fact that only commercially available technologies were considered for this paper. Current development work by various organizations has the potential to improve both costs and performance. It is reasonable to assume that some of this development work can lead to capital cost and performance improvements of at least 10% over the next 5-10 years. Key organizations involved in this development work include: Alstom, ABB Lummus, Air Liquide, Air Products & Chemicals,
REFERENCES 1. 2. SFA Pacific, Inc., CO2 Emissions Control and Mitigation, a privately funded multisponsored analysis, Mountain View, California, to be published April 2001. D. R. Simbeck, Update of New Power Plant CO2 Control Options Analysis, presented at the Fifth International Conference on Greenhouse Gas Control Technologies (GHGT-5), Cairns, Australia, August 2000. D. R. Simbeck, A Portfolio Selection Approach for Power Plant CO2 Capture, Separation and R&D Options, presented at the Fourth International Conference on Greenhouse Gas Control Technologies (GHGT-4), Interlaken, Switzerland, September 1998. S. H. Stevens and J Gale, Geologic CO2 Sequestration, Oil & Gas Journal, May 15, 2000. Press Release by Petro Source Corporation, Houston, Texas, www.petrosourcecorp.com, November 22, 2000. W. Preston, Texaco Gasification Process Startups and Future Directions, presented at the 2000 Gasification Technologies Conference, San Francisco, California, October 2000. W. F. Fong, Texaco 550 MWe for Coal or Oil via 9H IGCC, presented at the 2000 Gasification Technologies Conference, San Francisco, California, October 2000.
3.
4. 5. 6. 7.
5.36 mt/hr H2O in air 23.14% wt O2 in dry air to boiler 15.0% excess air
407 MWt to cooling water superheat 308.6 MWe gross 6.62 lb/kWh misc. power 17.1 MWe 3.0%ST+1.0%coal Net Electricity 291.5 MWe 36.2% LHV 35.0% HHV 9,740 Btu HHV per kWh CO2 emissions to the atmosphere 0.971 mt/MWh 2.108 million mt/yr Flue gas 1,220 827 283 76 33 0.43 0.76 1,220 mt/hr including mt/hr N2 mt/hr CO2 mt/hr H2O mt/hr O2 mt/hr SO2 mt/hr NOx
Subcritical reheat Dry Air reheat steam ST/gen 1,080 mt/hr 250 mt/hr O2 PC Boiler 715.4 43.1% 88.8% MWt Raw Subbit. Coal 806 MWt, LHV 926 mt/hr steam 832 MWt HHV 2,041,109 lbs/h steam 2,750 MM Btu/hr, LHV Flue gas-wet 1,220 mt/hr 2,839 MM Btu/hr, HHV 152.6 mt/hr coal @ 8,435 But/lb HHV 25.0% coal N to NOx coal ash 17 mt/hr 33 mt/hr O2 2.7% wt.O2
ESP
wt.% 67.80% 23.20% kg/MWh 1.5 2.6 6.26% 2.67% 0.04% 0.06% 100.02%
Capital Costs if new key unit costs Solids handling/prep 8,000 $/mt/d raw coal PC boiler 60 $/lb/hr reheat steam ST/gen & water sys 200 $/kWe gross ESP 4,000 $/mt/hr raw flue gas Subtotal of process units captial cost General facilities 20% of process units capital Eng. fees & contingencies 10% of process units capital Total capital cost of original new plant 10% of original capital Partially paid-off existing PC remaining to be amortized Inputs for summary 85% ann. capacity factor 15% of capital per yr 4% of capital per yr $ per mt CO2 $ 0.52 per MM Btu LHV
US dollars $ MM $/kW net 29 101 122 420 62 212 5 17 218 749 44 150 22 75 284 28 974 97
Notes
New PC Plant Electricity Cost Capital charges O&M CO2 emissions tax Coal
US dollars $ MM/yr $/MWh 43 19.6 11 5.2 11 4.9 65 29.7 Power Costs 12.1 CO2 Emissions mt/MWh 0.971
New PC Power Plant Partially paid-off PC costs 15% /yr of remaining capital + fuel, O&M & CO2 costs Marginal load dispatch costs Source: SFA Pacific, Inc. 50% of O&M + fuel & CO2 costs
26
Existing PC baseline
7.5 $/MWh
77 mt/hr H2O
126 MM scf/d 146 MM scf/d Additional power for O2 & CO2 compression 94.2 MWe 0.9 GE 6FA key unit costs $ MM 9 106 47 47 209 42 21 271 28 7 306 Inputs for summary US dollars $ MM/yr 41 4 1 22 (21) 20 11 78 net change 85% 15% 15% 15% 4% (10) 4.43 0.52 ann. capacity factor of new capital per yr of PC capital per yr of power cost per yr of capital per yr + PC per mt CO2 per mt CO2 per MM Btu LHV per MM Btu LHV $/kW net 29 365 161 160 715 143 72 930 93 22 1,049 modify fans, air heaters, economizer & pulverizers added to above Flue Gas @ 1.0 atm
178 MWt, LHV 606 MM Btu/hr, LHV 673 MM Btu/hr, HHV 13.3 mt/hr @ 22,895 But/lb HHV Capital Costs
618 mt/hr including 36 mt/hr CO2 0.03 mt/hr NOx 0.1 lb NOx/MM Btu Notes
Existing solids handling $/mt/d coal Existing PC modification 7% of original boiler cost Existing ST/gen $/kWe gross Modified ESP? $/mt/hr flue gas 19,000 $/mt/d oxygen New ASU & LP O2 compre New small NGCC 500 $/kW net CC 1,050 $/kWe power New CO2 drying & compres Subtotal of new & retrofit process units capital cost General facilities 20% of process units capital Eng. fees & contingencies 10% of process units capital New Capital Payoff existing PC Retrofit outage power Total Capital Electricity Cost Capital charges Payoff existing PC Retrofit outage power O&M CO2 emissions tax CO2 disposal or use Natural gas Coal Baseline existing PC reference O2 retrofit of existing PC Source: SFA Pacific, Inc. relative to existing PC 10% of original capital 30 $/MWh for 0.10 year
high purity to reduce N2 & Ar trace O2, N2, SO2 & NOx increase compression costs
$ $ $ $
$/MWh 18.7 2.0 0.4 10.2 (9.6) trace O2, N2, SO2 & NOx may 9.2 impact value 5.0 CO2 Emissions 36.0 $/MWh 12.1 23.9 298% $ $ 0.124 mt/MWh 0.971 -0.847 -87.2% 28 /mt CO2 avoided or 103 /mt carbon avoided
O2 retrofit of existing PC
Figure 3 Retrofit Existing PC Boiler with Amine Flue Gas CO2 Scrubber
18 mt/hr ash 15% excess air Air 1,079 mt/hr 250 Raw Coal 806 MWt, LHV 2,751 MM Btu/hr, LHV 2,840 MM Btu/hr, HHV 152.7 mt/hr coal @ 8,435 But/lb HHV 25.0% coal N to NOx or 0.59 lb/MMBtu Existing ESP new FGD/SCR flue gas 469 mt/hr 5% excess air 443 mt/hr Air Natural Gas 341 1,164 1,289 25.5 Capital Costs 5 mt/hr O2 1.0% wt O2 New SH NG steam boiler 310 91.0% MWt 248 MWt LP steam or 1.27 ton steam/ton CO2 New backpress ST/gen 20% 403 mt/hr steam (no reheat) 62 MWe added above Existing PC Boiler 88.8% SH steam 716 MWt Flue gas 1,215 mt/hr 32 mt/hr O2 2.7% wt O2 New CO2 scr/strip 90% 1.0 atm CO2 New CO2 Compres dryer 33 MWe 3.0% ST+ 2.0% coal 46 MWe Existing ST/gen 43.1% 308 MWe gross Electricity 291.5 MWe 25.4% LHV 24.1% HHV 14,169 Btu/kWh HHV CO2 emissions to the atmosphere 0.121 mt/MWh 0.262 million mt/y HP CO2 Captured 317 mt/hr 1.09 mt/MWhr 143 MM scf/d Flue gas 1,366 mt/hr total 1,172 35 124 37 1,368 $/kW net 63 46 64 144 141 159 617 123 62 802 97 22 921 $/MWh 16.2 2.0 0.5 9.5 (10.9) 17.7 4.9 39.8 12.1 net change CO2 retrofit of existing PC+ new NGB Marginal load dispatch costs relative to existing PC 50% of O&M + fuel & CO2 costs CO2 retrofit of existing PC+ new NGB Baseline existing PC reference Source: SFA Pacific, Inc. 16.5 7.5 27.7 330% $ $ CO2 Emissions mt/MWh 0.121 0.971 -0.850 -87.5% 33 /mt CO2 avoided or 120 /mt carbon avoided mt/hr N2 mt/hr CO2 mt/hr H2O mt/hr O2 mt/hr SO2 mt/hr NOx 407 MWt to cooling water 62 MWe below 1.09 mt CO2/MWh capture Net
22,895 But/lb HHV key unit costs Existing solids handling $/mt/d raw coal Existing PC boiler $/mt/hr flue gas Existing ST/gen $/kWe gross New FGD-caustic wash 15,000 $/mt/hr PC flue gas New SCR ? $/mt/hr PC flue gas Existing ESP $/mt/hr PC flue gas New NG boilers 15 $/lb/hr no RH steam boiler New extraction ST/gen 300 $/kWe ST New CO2 scrubber 25,000 $/mt/hr PC+NG flue gas New CO2 stripper 130,000 $/mt/hr CO2 New CO2 drying & compress 1,000 $/kWe power Subtotal of new & retrofit process units capital costs General facilities 20% of process units capital Eng. fees & contingencies 10% of process units capital New Capital Payoff existing PC Retrofit outage power Total Capital Inputs for summary 10% of original capital 30 $/MWhr for 0.10 year
Electricity Cost Capital charges Payoff existing PC Retrofit outage power O&M CO2 emissions tax CO2 disposal or use Natural gas Coal Baseline existing PC reference
85% ann. capacity factor 15% of capital per yr 15% of PC capital per yr 15% 4% (10) of power cost per yr of capital per yr + PC per mt CO2 per mt CO2
$ $ $ $
10
Figure 4
net water 94.5 mt/hr hot syngas 284 mt/hr-wet 981 MWt, LHV
Notes $/kW net 64 saving from existing coal systems 134 154 118 42 44 23 229 air extraction 106 95 65 1,074 215 potential saving of existing GF 107 1,396 70 1,466
$ $ $
CO2 Emissions 0.083 mt/MWh 0.971 -0.888 -91.5% 25 /mt CO2 avoided or 91 /mt carbon avoided
11
Table 1 Summary Economic for CO2 Reduction from Existing Coal Power Plants
Technical basis is explained in detail on Existing PC worksheet Recovered CO2 is dried and compressed to 135 atmospheres (2,000 psig) Simple mass and energy balances based on mt/hr and MWt(LHV)/MWe Capital cost basis is explained in detail on Existing PC worksheet In summary, all costs are constant 1999 US dollars with no escalation or interest during construction Assumed baseline is an existing PC unit that is partially paid-off & refinanced for CO2 modification Therefore, total capital includes added capital for old PC payoff & power during shutdown Consistent unit cost from mass and energy balances Key economic input variables $ $ Sub-Bituminus Coal 0.50 /MM Btu HHV 0.52 /MM Btu LHV 50.58% C by wt 2.89% H 14.32% O 0.61% N 0.14% S 11.46% ash 20.00% moisture 100.00% total shaded and located in black boxes $ $ Natural Gas 4.00 /MM Btu HHV 4.43 /MM Btu LHV 80.00% CH4 by wt 17.00% C2H6 1.00% N2 2.00% CO2 100.00% total Operating factor Capital charges Yet to amortize Non-fuel O&M Variable O&M cost Replacement power General facilities CO2 emissions tax $ CO2 disposal costs or EOR ( - credits) $ plus linked to all worksheets 85% Annual capacity factor 15% of capital per yr 10% of original capital 4% of capital per yr 50% of total O&M 30 $/MWh for retrofit shutdowns 20% of process units capital 10% of process units capital /mt CO2 or $ $ /mt carbon (10) /mt CO2 or (36.67) /mt carbon
$ (0.53) /1,000 scf Electric costs including any CO2 tax or credits Worksheet Name Description/comments If new (cost & performance reference) Existing PC NGCC NG-Repower Bio-cofire CGCC H2-NGCC H2-CGCC H2-CGCC-65% O2-PC PC-CO2 PC-CO2-65% Nuclear Wind Turbines Baseline PC assuming partially paid-off Subcritical steam cycle & no SO2 or NOx controls Replacement NGCC State-of-the-art "H" class GT Retrofit hot windbox NG-GT repowering Aero GT due to size, lower exhaust temp. Biomass cofiring in existing PC 10% biomass energy mixed with coal feeding Replacement CGCC with minimal reuse Conventional gasifier, cleanup &" H"-GT Replacement H2-CC with CO2 recovery Conventional O2-ATR with H2/N2 fired H-GT Replacement H2-CGCC with CO2 recovery Conventional O2-gasifier, shift & N2/H2 fired H-GT H2-CGCC only to same CO2 as new NGCC Conventional O2-gasifier, shift & N2/H2 fired H-GT Retrofit PC with O2 & CO2 recycle Add NGCC for O2 & CO2 power needs Retrofit PC with flue gas CO2 scrubber Added NG boiler for CO2 power & steam needs PC-CO2 only to same CO2 as new NGCC Added NG boiler for CO2 power & steam needs Replacement nuclear uranium at $ 0.40 per MM Btu 715 62.0 514% -100% $ 51 Replacement wind turbine farm 25% annual capacity factor 991 MW required for the same MWh/y as the original 292 MW PC Bio-GCC Replacement biomass GCC Delivered biomass @ $ PCFBG Based on: $ 500 $ 50.00 /bone dry ton (BDT) or based on below assumptions 5 mt carbon/yr 50% wt. carbon 8,000 Btu/lb LHV bone dry bone dry 383 sq. Miles for 292 MW existing PC 2.83 per MM LHV 1,661 63.4 525% -100% $ if replanted 53 1,977 59.2 490% -100% $ 48 744 34.2 284% -65% $ 35 921 39.8 330% -88% $ 33 1,049 36.0 298% -87% $ 28 1,374 34.4 285% -67% $ 35 1,466 34.2 284% -91% $ 25 931 49.4 410% -96% $ 40 1,171 33.2 275% 188 16.7 139% -8% $ if replanted -31% $ 70 62 324 25.2 209% -29% $ 46 523 38.2 316% -65% $ 41 Capital $/kW 974 97 $/MWh 29.7 12.1 relative to existing PC % power 246% baseline baseline baseline % CO2 $/mt CO2 avoided of baseline of baseline
/hectare per yr
gross revenues required for land + O&M costs thereby requires 340 hectares/MW or Source: SFA Pacific, Inc.
12