NATIONAL POWER CORPORATION, Petitioner vs. LUCMAN G. IBRAHIM, OMAR, G. MARUHOM, ELIAS G. MARUHOM, BUCAY G. MARUHOM, FAROUK G.

MARUHOM, HIDJARA G. MARUHOM, ROCANIA G. MARUHOM, POTRISAM G. MARUHOM, LUMBA G. MARUHOM, SINAB G. MARUHOM, ACMAD G. MARUHOM, SOLAYMAN G. MARUHOM G.R. No. 168732, June 29, 2007 Facts: Respondent Lucman G. Ibrahim, in his personal capacity and in behalf of his co-heirs instituted an action against petitioner National Power Corporation (NAPOCOR) for recovery of possession of land and damages before the Regional Trial Court (RTC) of Lanao del Sur. In their complaint, Ibrahim and his co-heirs claimed that they were owners of several parcels of land. Sometime in 1978, NAPOCOR, through alleged stealth and without respondents knowledge and prior consent, took possession of the sub-terrain area of their lands and constructed therein underground tunnels. The existence of the tunnels was only discovered sometime in July 1992 by respondents and then later confirmed on November 13, 1992 by NAPOCOR itself through a memorandum issued by the latters Acting Assistant Project Manager. The tunnels were apparently being used by NAPOCOR in siphoning the water of Lake Lanao and in the operation of NAPOCOR. Respondent Omar G. Maruhom requested the Marawi City Water District for a permit to construct and/or install a motorized deep well in Lot 3 located in Saduc, Marawi City but his request was turned down because the construction of the deep well would cause danger to lives and property. On October 7, 1992, respondents demanded that NAPOCOR pay damages and vacate the sub-terrain portion of their lands but the latter refused to vacate much less pay damages. Respondents further averred that the construction of the underground tunnels has endangered their lives and properties as Marawi City lies in an area of local volcanic and tectonic activity. Further, these illegally constructed tunnels caused them sleepless nights, serious anxiety and shock thereby entitling them to recover moral damages and that by way of example for the public good, NAPOCOR must be held liable for exemplary damages. Disputing respondents claim, NAPOCOR filed an answer with counterclaim denying the material allegations of the complaint and interposing affirmative and special defenses, namely that (1) there is a failure to state a cause of action since respondents seek possession of the subterrain portion when they were never in possession of the same, (2) respondents have no cause of action because they failed to show proof that they were the owners of the property, and (3) the tunnels are a government project for the benefit of all and all private lands are subject to such easement as may be necessary for the same. Ibrahim, joined by his co-heirs, filed an Urgent Motion for Execution of Judgment Pending Appeal. On the other hand, NAPOCOR filed a Notice of Appeal. Thereafter, NAPOCOR filed a vigorous opposition to the motion for execution of judgment pending appeal with a motion for reconsideration of the Decision. NAPOCOR filed a Manifestation and Motion withdrawing its Notice of Appeal purposely to give way to the hearing of its motion for reconsideration. The RTC issued an Order granting execution pending appeal and denying NAPOCORs motion for reconsideration.

NAPOCOR filed its Notice of Appeal by registered mail which was denied by the RTC on the ground of having been filed out of time. Meanwhile, the Decision of the RTC was executed pending appeal and funds of NAPOCOR were garnished by respondents Ibrahim and his co-heirs.

The RTC granted the petition and rendered a modified judgment.


Subsequently, both respondent Ibrahim and NAPOCOR appealed to the CA. The CA set aside the modified judgment and reinstated the original decision amending it further by deleting the award of moral damages and reducing the amount of rentals and attorneys fees, Issue: Whether respondents are entitled to just compensation hinges upon who owns the sub-terrain area occupied by petitioner.

Ruling:
Petitioner maintains that the sub-terrain portion where the underground tunnels were constructed does not belong to respondents because, even conceding the fact that respondents owned the property, their right to the subsoil of the same does not extend beyond what is necessary to enable them to obtain all the utility and convenience that such property can normally give. In any case, petitioner asserts that respondents were still able to use the subject property even with the existence of the tunnels, citing as an example the fact that one of the respondents, Omar G. Maruhom, had established his residence on a part of the property. Petitioner concludes that the underground tunnels 115 meters below respondents property could not have caused damage or prejudice to respondents and their claim to this effect was, therefore, purely conjectural and speculative. The contention lacks merit. In the present case, petitioner failed to point to any evidence demonstrating grave abuse of discretion on the part of the CA or to any other circumstances which would call for the application of the exceptions to the above rule. Consequently, the CAs findings which upheld those of the trial court that respondents owned and possessed the property and that its substrata was possessed by petitioner since 1978 for the underground tunnels, cannot be disturbed. Moreover, the Court sustains the finding of the lower courts that the sub-terrain portion of the property similarly belongs to respondents. This conclusion is drawn from Article 437 of the Civil Code which provides: ART. 437. The owner of a parcel of land is the owner of its surface and of everything under it, and he can construct thereon any works or make any plantations and excavations which he may deem proper, without detriment to servitudes and subject to special laws and ordinances. He cannot complain of the reasonable requirements of aerial navigation. Thus, the ownership of land extends to the surface as well as to the subsoil under it. In Republic of the Philippines v. Court of Appeals, this principle was applied to show that rights over lands are indivisible and, consequently, require a definitive and categorical classification, thus: The Court of Appeals justified this by saying there is no conflict of interest between the owners of the surface rights and the owners of the sub-surface rights. This is rather strange

doctrine, for it is a well-known principle that the owner of a piece of land has rights not only to its surface but also to everything underneath and the airspace above it up to a reasonable height. Under the aforesaid ruling, the land is classified as mineral underneath and agricultural on the surface, subject to separate claims of title. This is also difficult to understand, especially in its practical application. Under the theory of the respondent court, the surface owner will be planting on the land while the mining locator will be boring tunnels underneath. The farmer cannot dig a well because he may interfere with the mining operations below and the miner cannot blast a tunnel lest he destroy the crops above. The Court feels that the rights over the land are indivisible and that the land itself cannot be half agricultural and half mineral. The classification must be categorical; the land must be either completely mineral or completely agricultural. Registered landowners may even be ousted of ownership and possession of their properties in the event the latter are reclassified as mineral lands because real properties are characteristically indivisible. For the loss sustained by such owners, they are entitled to just compensation under the Mining Laws or in appropriate expropriation proceedings. In this regard, the trial court found that respondents could have dug upon their property motorized deep wells but were prevented from doing so by the authorities precisely because of the construction and existence of the tunnels underneath the surface of their property. Respondents, therefore, still had a legal interest in the sub-terrain portion insofar as they could have excavated the same for the construction of the deep well. The fact that they could not was appreciated by the RTC as proof that the tunnels interfered with respondents enjoyment of their property and deprived them of its full use and enjoyment. Petitioner contends that the underground tunnels in this case constitute an easement upon the property of respondents which does not involve any loss of title or possession. The manner in which the easement was created by petitioner, however, violates the due process rights of respondents as it was without notice and indemnity to them and did not go through proper expropriation proceedings. Petitioner could have, at any time, validly exercised the power of eminent domain to acquire the easement over respondents property as this power encompasses not only the taking or appropriation of title to and possession of the expropriated property but likewise covers even the imposition of a mere burden upon the owner of the condemned property. Significantly, though, landowners cannot be deprived of their right over their land until expropriation proceedings are instituted in court. The court must then see to it that the taking is for public use, that there is payment of just compensation and that there is due process of law. In disregarding this procedure and failing to recognize respondents ownership of the sub-terrain portion, petitioner took a risk and exposed itself to greater liability with the passage of time. It must be emphasized that the acquisition of the easement is not without expense. The underground tunnels impose limitations on respondents use of the property for an indefinite period and deprive them of its ordinary use. Based upon the foregoing, respondents are clearly entitled to the payment of just compensation. Notwithstanding the fact that petitioner only occupies the subterrain portion, it is liable to pay not merely an easement fee but rather the full compensation for land. This is so because in this case, the nature of the easement practically deprives the owners of its normal beneficial use. Respondents, as the owners of the property thus expropriated, are entitled to a just compensation which should be neither more nor less, whenever it is possible to make the assessment, than the money equivalent of said property.